    <TITLE>Tendering notice and schedule.</TITLE>
    <GRANULENUM>5.19</GRANULENUM>
    <HEADING>Section 5.19</HEADING>
    <ANCESTORS>
      <PARENT HEADING="Title 18" SEQ="3">Conservation of Power and Water Resources</PARENT>
      <PARENT HEADING="CHAPTER I" SEQ="2">FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY</PARENT>
      <PARENT HEADING="SUBCHAPTER B" SEQ="1">REGULATIONS UNDER THE FEDERAL POWER ACT</PARENT>
      <PARENT HEADING="PART 5" SEQ="0">INTEGRATED LICENSE APPLICATION PROCESS</PARENT>
    </ANCESTORS>
  </FDSYS>
  <SECTION>
    <SECTNO>§ 5.19</SECTNO>
    <SUBJECT>Tendering notice and schedule.</SUBJECT>
    <P>(a) <E T="03">Notice.</E> Within 14 days of the filing date of any application for a license developed pursuant to this part, the Commission will issue public notice of the tendering for filing of the application. The tendering notice will include a preliminary schedule for expeditious processing of the application, including dates for:</P>
    <P>(1) Issuance of the acceptance for filing and ready for environmental analysis notice provided for in § 5.22.</P>
    <P>(2) Filing of recommendations, preliminary terms and conditions, and fishway prescriptions;</P>
    <P>(3) Issuance of a draft environmental assessment or environmental impact statement, or an environmental assessment not preceded by a draft.</P>
    <P>(4) Filing of comments on the draft environmental assessment or environmental impact statement, as applicable;</P>
    <P>(5) Filing of modified recommendations, mandatory terms and conditions, and fishway prescriptions in response to a draft NEPA document or Environmental Analysis, if no draft NEPA document is issued;</P>
    <P>(6) Issuance of a final NEPA document, if any;<PRTPAGE P="164"/>
    </P>
    <P>(7) In the case of a new or subsequent license application, a deadline for submission of final amendments, if any, to the application; and</P>
    <P>(8) Readiness of the application for Commission decision.</P>
    <P>(b) <E T="03">Modifications to process plan and schedule.</E> The tendering notice shall also include any known modifications to the schedules developed pursuant to § 5.8 for completion of consultation under section 7 of the Endangered Species Act and water quality certification under section 401 of the Clean Water Act.</P>
    <P>(c) <E T="03">Method of notice.</E> The public notice provided for in paragraphs (a) and (b) of this Section will be given by:</P>
    <P>(1) Publishing notice in the <E T="04">Federal Register</E>; and</P>
    <P>(2) Notifying appropriate Federal, state, and interstate resource agencies, state water quality and coastal zone management plan consistency certification agencies, Indian tribes, and non-governmental organizations by mail.</P>
    <P>(d) <E T="03">Resolution of pending information requests.</E> Within 30 days of the filing date of any application for a license developed pursuant to this part, the Director of the Office of Energy Projects will issue an order resolving any requests for additional information-gathering or studies made in comments on the preliminary licensing proposal or draft license application.</P>
    <CITA>[Order 2002, 68 FR 51121, Aug. 25, 2003; 68 FR 61742, Oct. 30, 2003; 68 FR 69957, Dec. 16, 2003]</CITA>