<?xml version="1.0"?>
<?xml-stylesheet type="text/xsl" href="cfr.xsl"?>
<CFRDOC xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="CFRMergedXML.xsd">
  <AMDDATE>July 1, 2004</AMDDATE>
  <FMTR>
    <TITLEPG>
      <CODE>CODE OF FEDERAL REGULATIONS</CODE>
      <PRTPAGE P="1"/>
      <TITLENUM>40</TITLENUM>
      <PARTS>Part 60 (§ 60.1 to End)</PARTS>
      <REVISED>Revised as of July 1, 2004</REVISED>
      <SUBJECT>Protection of Environment</SUBJECT>
      <CONTAINS>Containing a codification of documents of general applicability and future effect</CONTAINS>
      <DATE>As of July 1, 2004</DATE>
      <ANCIL>With Ancillaries</ANCIL>
      <PUB>
        <P>Published by</P>
        <P>Office of the Federal Register</P>
        <P>National Archives and Records</P>
        <P>Administration</P>
      </PUB>
      <SPECED>A Special Edition of the Federal Register</SPECED>
    </TITLEPG>
    <BTITLE>
      <PRTPAGE P="?ii"/>
      <GPO>U.S. GOVERNMENT PRINTING OFFICE</GPO>
      <CITY>WASHINGTON : 2004</CITY>
      <FORSALE>
        <P>For sale by the Superintendent of Documents, U.S. Government Printing Office</P>
        <P>Internet: bookstore.gpo.gov Phone: toll free (866) 512-1800; DC area (202) 512-1800</P>
        <P>Fax: (202) 512-2250 Mail: Stop SSOP, Washington, DC 20402-0001</P>
      </FORSALE>
    </BTITLE>
    <TOC>
      <PRTPAGE P="iii"/>
      <HD SOURCE="HED">Table of Contents</HD>
      <PGHD>Page</PGHD>
      <EXPL>
        <SUBJECT>Explanation</SUBJECT>
        <PG>v</PG>
      </EXPL>
      <TITLENO>
        <HD SOURCE="HED">Title 40:</HD>
        <CHAPTI>
          <SUBJECT>Chapter I—Environmental Protection Agency</SUBJECT>
          <PG>3</PG>
        </CHAPTI>
      </TITLENO>
      <FAIDS>
        <HD SOURCE="HED">Finding Aids:</HD>
        <SUBJECT>Material Approved for Incorporation by Reference</SUBJECT>
        <PG>719</PG>
        <SUBJECT>Table of CFR Titles and Chapters</SUBJECT>
        <PG>725</PG>
        <SUBJECT>Alphabetical List of Agencies Appearing in the CFR</SUBJECT>
        <PG>743</PG>
        <SUBJECT>List of CFR Sections Affected</SUBJECT>
        <PG>753</PG>
      </FAIDS>
    </TOC>
    <CITE>
      <PRTPAGE P="iv"/>
      <P>Cite this Code:<E T="01">CFR</E>
      </P>

      <CITEP>To cite the regulations in this volume use title, part and section number. Thus, <E T="01"> 40 CFR 60.1</E> refers to title 40, part 60, section 1.</CITEP>
    </CITE>
    <EXPLA>
      <PRTPAGE P="v"/>
      <HD SOURCE="HED">Explanation</HD>
      <P>The Code of Federal Regulations is a codification of the general and permanent rules published in the Federal Register by the Executive departments and agencies of the Federal Government. The Code is divided into 50 titles which represent broad areas subject to Federal regulation. Each title is divided into chapters which usually bear the name of the issuing agency. Each chapter is further subdivided into parts covering specific regulatory areas.</P>
      <P>Each volume of the Code is revised at least once each calendar year and issued on a quarterly basis approximately as follows:</P>
      <IPAR>
        <P SOURCE="P1">Title 1 through Title 16 </P>
        <STUB>as of January 1</STUB>
        <P SOURCE="P1">Title 17 through Title 27 </P>
        <STUB>as of April 1</STUB>
        <P SOURCE="P1">Title 28 through Title 41 </P>
        <STUB>as of July 1</STUB>
        <P SOURCE="P1">Title 42 through Title 50 </P>
        <STUB>as of October 1</STUB>
      </IPAR>
      <P>The appropriate revision date is printed on the cover of each volume.</P>
      <SIDEHED>
        <HD SOURCE="HED">LEGAL STATUS</HD>
        <P>The contents of the Federal Register are required to be judicially noticed (44 U.S.C. 1507). The Code of Federal Regulations is prima facie evidence of the text of the original documents (44 U.S.C. 1510).</P>
      </SIDEHED>
      <SIDEHED>
        <HD SOURCE="HED">HOW TO USE THE CODE OF FEDERAL REGULATIONS</HD>
        <P>The Code of Federal Regulations is kept up to date by the individual issues of the Federal Register. These two publications must be used together to determine the latest version of any given rule.</P>
        <P>To determine whether a Code volume has been amended since its revision date (in this case, July 1, 2004), consult the “List of CFR Sections Affected (LSA),” which is issued monthly, and the “Cumulative List of Parts Affected,” which appears in the Reader Aids section of the daily Federal Register. These two lists will identify the Federal Register page number of the latest amendment of any given rule.</P>
      </SIDEHED>
      <SIDEHED>
        <HD SOURCE="HED">EFFECTIVE AND EXPIRATION DATES</HD>
        <P>Each volume of the Code contains amendments published in the Federal Register since the last revision of that volume of the Code. Source citations for the regulations are referred to by volume number and page number of the Federal Register and date of publication. Publication dates and effective dates are usually not the same and care must be exercised by the user in determining the actual effective date. In instances where the effective date is beyond the cut-off date for the Code a note has been inserted to reflect the future effective date. In those instances where a regulation published in the Federal Register states a date certain for expiration, an appropriate note will be inserted following the text.</P>
      </SIDEHED>
      <SIDEHED>
        <HD SOURCE="HED">OMB CONTROL NUMBERS</HD>

        <P>The Paperwork Reduction Act of 1980 (Pub. L. 96-511) requires Federal agencies to display an OMB control number with their information collection request. <PRTPAGE P="vi"/>Many agencies have begun publishing numerous OMB control numbers as amendments to existing regulations in the CFR. These OMB numbers are placed as close as possible to the applicable recordkeeping or reporting requirements.</P>
      </SIDEHED>
      <SIDEHED>
        <HD SOURCE="HED">OBSOLETE PROVISIONS</HD>
        <P>Provisions that become obsolete before the revision date stated on the cover of each volume are not carried. Code users may find the text of provisions in effect on a given date in the past by using the appropriate numerical list of sections affected. For the period before January 1, 2001, consult either the List of CFR Sections Affected, 1949-1963, 1964-1972, 1973-1985, or 1986-2000, published in 11 separate volumes. For the period beginning January 1, 2001, a “List of CFR Sections Affected” is published at the end of each CFR volume.</P>
      </SIDEHED>
      <SIDEHED>
        <HD SOURCE="HED">INCORPORATION BY REFERENCE</HD>
        <P>
          <E T="03">What is incorporation by reference?</E> Incorporation by reference was established by statute and allows Federal agencies to meet the requirement to publish regulations in the Federal Register by referring to materials already published elsewhere. For an incorporation to be valid, the Director of the Federal Register must approve it. The legal effect of incorporation by reference is that the material is treated as if it were published in full in the Federal Register (5 U.S.C. 552(a)). This material, like any other properly issued regulation, has the force of law.</P>
        <P>
          <E T="03">What is a proper incorporation by reference?</E> The Director of the Federal Register will approve an incorporation by reference only when the requirements of 1 CFR part 51 are met. Some of the elements on which approval is based are:</P>
        <P>(a) The incorporation will substantially reduce the volume of material published in the Federal Register.</P>
        <P>(b) The matter incorporated is in fact available to the extent necessary to afford fairness and uniformity in the administrative process.</P>
        <P>(c) The incorporating document is drafted and submitted for publication in accordance with 1 CFR part 51.</P>
        <P>Properly approved incorporations by reference in this volume are listed in the Finding Aids at the end of this volume.</P>
        <P>
          <E T="03">What if the material incorporated by reference cannot be found?</E> If you have any problem locating or obtaining a copy of material listed in the Finding Aids of this volume as an approved incorporation by reference, please contact the agency that issued the regulation containing that incorporation. If, after contacting the agency, you find the material is not available, please notify the Director of the Federal Register, National Archives and Records Administration, Washington DC 20408, or call (202) 741-6010.</P>
      </SIDEHED>
      <SIDEHED>
        <HD SOURCE="HED">CFR INDEXES AND TABULAR GUIDES</HD>

        <P>A subject index to the Code of Federal Regulations is contained in a separate volume, revised annually as of January 1, entitled CFR <E T="04">Index and Finding Aids.</E> This volume contains the Parallel Table of Statutory Authorities and Agency Rules (Table I). A list of CFR titles, chapters, and parts and an alphabetical list of agencies publishing in the CFR are also included in this volume.</P>
        <P>An index to the text of “Title 3—The President” is carried within that volume.</P>
        <P>The Federal Register Index is issued monthly in cumulative form. This index is based on a consolidation of the “Contents” entries in the daily Federal Register.</P>
        <P>A List of CFR Sections Affected (LSA) is published monthly, keyed to the revision dates of the 50 CFR titles.</P>
      </SIDEHED>
      <SIDEHED>
        <PRTPAGE P="vii"/>
        <HD SOURCE="HED">REPUBLICATION OF MATERIAL</HD>
        <P>There are no restrictions on the republication of material appearing in the Code of Federal Regulations.</P>
      </SIDEHED>
      <SIDEHED>
        <HD SOURCE="HED">INQUIRIES</HD>
        <P>For a legal interpretation or explanation of any regulation in this volume, contact the issuing agency. The issuing agency's name appears at the top of odd-numbered pages.</P>
        <P>For inquiries concerning CFR reference assistance, call 202-741-6000 or write to the Director, Office of the Federal Register, National Archives and Records Administration, Washington, DC 20408 or e-mail fedreg.info@nara.gov.</P>
      </SIDEHED>
      <SIDEHED>
        <HD SOURCE="HED">SALES</HD>
        <P>The Government Printing Office (GPO) processes all sales and distribution of the CFR. For payment by credit card, call toll free, 866-512-1800 or DC area, 202-512-1800, M-F, 8 a.m. to 4 p.m. e.s.t. or fax your order to 202-512-2250, 24 hours a day. For payment by check, write to the Superintendent of Documents, Attn: New Orders, P.O. Box 371954, Pittsburgh, PA 15250-7954. For GPO Customer Service call 202-512-1803.</P>
      </SIDEHED>
      <SIDEHED>
        <HD SOURCE="HED">ELECTRONIC SERVICES</HD>
        <P>The full text of the Code of Federal Regulations, The United States Government Manual, the Federal Register, Public Laws, Public Papers, Weekly Compilation of Presidential Documents and the Privacy Act Compilation are available in electronic format at www.gpoaccess.gov/nara (“GPO Access”). For more information, contact Electronic Information Dissemination Services, U.S. Government Printing Office. Phone 202-512-1530, or 888-293-6498 (toll-free). E-mail, gpoaccess@gpo.gov.</P>
        <P>The Office of the Federal Register also offers a free service on the National Archives and Records Administration's (NARA) World Wide Web site for public law numbers, Federal Register finding aids, and related information.  Connect to NARA's web site at www.archives.gov/federal_register. The NARA site also contains links to GPO Access.</P>
      </SIDEHED>
      <SIG>
        <NAME>Raymond A. Mosley,</NAME>
        <POSITION>Director,</POSITION>
        <OFFICE>Office of the Federal Register.</OFFICE>
      </SIG>
      <DATE>July 1, 2004.</DATE>
    </EXPLA>
    <THISTITL>
      <PRTPAGE P="ix"/>
      <HD SOURCE="HED">THIS TITLE</HD>
      <P>Title 40—<E T="04">Protection of Environment</E> is composed of thirty volumes. The parts in these volumes are arranged in the following order: parts 1-49, parts 50-51, part 52 (52.01-52.1018), part 52 (52.1019-End), parts 53-59, part 60 (60.1-End), part 60 (Appendices), parts 61-62, part 63 (63.1-63.599), part 63 (63.600-1-63.1199), part 63 (63.1200-63.1439), part 63 (63.1440-63.8830), part 63 (63.8980-End) parts 64-71, parts 72-80, parts 81-85, part 86 (86.1-86.599-99) part 86 (86.600-1-End), parts 87-99, parts 100-135, parts 136-149, parts 150-189, parts 190-259, parts 260-265, parts 266-299, parts 300-399, parts 400-424, parts 425-699, parts 700-789, and part 790 to End. The contents of these volumes represent all current regulations codified under this title of the CFR as of July 1, 2004.</P>
      <P>Chapter I—Environmental Protection Agency appears in all thirty volumes. An alphabetical Listing of Pesticide Chemicals Index appears in parts 150-189. Regulations issued by the Council on Environmental Quality appear in the volume containing part 790 to End. The OMB control numbers for title 40 appear in § 9.1 of this chapter.</P>
      <P>For this volume, Ruth Green was Chief Editor. The Code of Federal Regulations publication program is under the direction of Frances D. McDonald, assisted by Alomha S. Morris.</P>
      <GPH DEEP="544" SPAN="1">
        <PRTPAGE P="x"/>
        <GID>CFRORDR.FRM</GID>
      </GPH>
    </THISTITL>
  </FMTR>
  <TITLE>
    <CFRTITLE>
      <LRH>40 CFR Ch. I (7-1-04 Edition)</LRH>
      <RRH>Environmental Protection Agency</RRH>
      <TITLEHD>
        <PRTPAGE P="1"/>
        <HD SOURCE="HED">Title 40—Protection of Environment</HD>
        <P>(This book contains part 60 (§ 60.1 to end))</P>
      </TITLEHD>
      <CFRTOC>
        <PTHD>Part</PTHD>
        <CHAPTI>
          <SUBJECT>
            <E T="04">chapter i</E>—Environmental Protection Agency (Continued)</SUBJECT>
          <PG>60</PG>
        </CHAPTI>
      </CFRTOC>
    </CFRTITLE>
    <CHAPTER>
      <TOC>
        <TOCHD>
          <PRTPAGE P="3"/>
          <HD SOURCE="HED">CHAPTER I—ENVIRONMENTAL PROTECTION AGENCY (CONTINUED)</HD>
        </TOCHD>
        <EDNOTE>
          <HD SOURCE="HED">Editorial Note:</HD>
          <P>Nomenclature changes to chapter I appear at 65 FR 47324, 47325, Aug. 2, 2000; 66 FR 34375, 34376, June 28, 2001.</P>
        </EDNOTE>
        <SUBCHAP>
          <HD SOURCE="HED">SUBCHAPTER C—AIR PROGRAMS (CONTINUED)</HD>
        </SUBCHAP>
        <PTHD>Part</PTHD>
        <PGHD>Page</PGHD>
        <CHAPTI>
          <PT>60</PT>
          <SUBJECT>Standards of performance for new stationary sources</SUBJECT>
          <PG>5</PG>
        </CHAPTI>
      </TOC>
      <SUBCHAP TYPE="N">
        <PRTPAGE P="5"/>
        <HD SOURCE="HED">SUBCHAPTER C—AIR PROGRAMS (CONTINUED)</HD>
        <PART>
          <EAR>Pt. 60</EAR>
          <HD SOURCE="HED">PART 60—STANDARDS OF PERFORMANCE FOR NEW STATIONARY SOURCES</HD>
          <CONTENTS>
            <SUBPART>
              <HD SOURCE="HED">Subpart A—General Provisions</HD>
              <SECHD>Sec.</SECHD>
              <SECTNO>60.1</SECTNO>
              <SUBJECT>Applicability.</SUBJECT>
              <SECTNO>60.2</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.3</SECTNO>
              <SUBJECT>Units and abbreviations.</SUBJECT>
              <SECTNO>60.4</SECTNO>
              <SUBJECT>Address.</SUBJECT>
              <SECTNO>60.5</SECTNO>
              <SUBJECT>Determination of construction or modification.</SUBJECT>
              <SECTNO>60.6</SECTNO>
              <SUBJECT>Review of plans.</SUBJECT>
              <SECTNO>60.7</SECTNO>
              <SUBJECT>Notification and record keeping.</SUBJECT>
              <SECTNO>60.8</SECTNO>
              <SUBJECT>Performance tests.</SUBJECT>
              <SECTNO>60.9</SECTNO>
              <SUBJECT>Availability of information.</SUBJECT>
              <SECTNO>60.10</SECTNO>
              <SUBJECT>State authority.</SUBJECT>
              <SECTNO>60.11</SECTNO>
              <SUBJECT>Compliance with standards and maintenance requirements.</SUBJECT>
              <SECTNO>60.12</SECTNO>
              <SUBJECT>Circumvention.</SUBJECT>
              <SECTNO>60.13</SECTNO>
              <SUBJECT>Monitoring requirements.</SUBJECT>
              <SECTNO>60.14</SECTNO>
              <SUBJECT>Modification.</SUBJECT>
              <SECTNO>60.15</SECTNO>
              <SUBJECT>Reconstruction.</SUBJECT>
              <SECTNO>60.16</SECTNO>
              <SUBJECT>Priority list.</SUBJECT>
              <SECTNO>60.17</SECTNO>
              <SUBJECT>Incorporations by reference.</SUBJECT>
              <SECTNO>60.18</SECTNO>
              <SUBJECT>General control device requirements.</SUBJECT>
              <SECTNO>60.19</SECTNO>
              <SUBJECT>General notification and reporting requirements.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart B—Adoption and Submittal of State Plans for Designated Facilities</HD>
              <SECTNO>60.20</SECTNO>
              <SUBJECT>Applicability.</SUBJECT>
              <SECTNO>60.21</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.22</SECTNO>
              <SUBJECT>Publication of guideline documents, emission guidelines, and final compliance times.</SUBJECT>
              <SECTNO>60.23</SECTNO>
              <SUBJECT>Adoption and submittal of State plans; public hearings.</SUBJECT>
              <SECTNO>60.24</SECTNO>
              <SUBJECT>Emission standards and compliance schedules.</SUBJECT>
              <SECTNO>60.25</SECTNO>
              <SUBJECT>Emission inventories, source surveillance, reports.</SUBJECT>
              <SECTNO>60.26</SECTNO>
              <SUBJECT>Legal authority.</SUBJECT>
              <SECTNO>60.27</SECTNO>
              <SUBJECT>Actions by the Administrator.</SUBJECT>
              <SECTNO>60.28</SECTNO>
              <SUBJECT>Plan revisions by the State.</SUBJECT>
              <SECTNO>60.29</SECTNO>
              <SUBJECT>Plan revisions by the Administrator.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart C—Emission Guidelines and Compliance Times</HD>
              <SECTNO>60.30</SECTNO>
              <SUBJECT>Scope.</SUBJECT>
              <SECTNO>60.31</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <RESERVED>Subpart Ca [Reserved]</RESERVED>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart Cb—Emissions Guidelines and Compliance Times for Large Municipal Waste Combustors That Are Constructed on or Before September 20, 1994</HD>
              <SECTNO>60.30b</SECTNO>
              <SUBJECT>Scope.</SUBJECT>
              <SECTNO>60.31b</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.32b</SECTNO>
              <SUBJECT>Designated facilities.</SUBJECT>
              <SECTNO>60.33b</SECTNO>
              <SUBJECT>Emission guidelines for municipal waste combustor metals, acid gases, organics, and nitrogen oxides.</SUBJECT>
              <SECTNO>60.34b</SECTNO>
              <SUBJECT>Emission guidelines for municipal waste combustor operating practices.</SUBJECT>
              <SECTNO>60.35b</SECTNO>
              <SUBJECT>Emission guidelines for municipal waste combustor operator training and certification.</SUBJECT>
              <SECTNO>60.36b</SECTNO>
              <SUBJECT>Emission guidelines for municipal waste combustor fugitive ash emissions.</SUBJECT>
              <SECTNO>60.37b</SECTNO>
              <SUBJECT>Emission guidelines for air curtain incinerators.</SUBJECT>
              <SECTNO>60.38b</SECTNO>
              <SUBJECT>Compliance and performance testing.</SUBJECT>
              <SECTNO>60.39b</SECTNO>
              <SUBJECT>Reporting and recordkeeping guidelines and compliance schedules.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart Cc—Emission Guidelines and Compliance Times for Municipal Solid Waste Landfills</HD>
              <SECTNO>60.30c</SECTNO>
              <SUBJECT>Scope.</SUBJECT>
              <SECTNO>60.31c</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.32c</SECTNO>
              <SUBJECT>Designated facilities.</SUBJECT>
              <SECTNO>60.33c</SECTNO>
              <SUBJECT>Emission guidelines for municipal solid waste landfill emissions.</SUBJECT>
              <SECTNO>60.34c</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.35c</SECTNO>
              <SUBJECT>Reporting and recordkeeping guidelines.</SUBJECT>
              <SECTNO>60.36c</SECTNO>
              <SUBJECT>Compliance times.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart Cd—Emissions Guidelines and Compliance Times for Sulfuric Acid Production Units</HD>
              <SECTNO>60.30d</SECTNO>
              <SUBJECT>Designated facilities.</SUBJECT>
              <SECTNO>60.31d</SECTNO>
              <SUBJECT>Emissions guidelines.</SUBJECT>
              <SECTNO>60.32d</SECTNO>
              <SUBJECT>Compliance times.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart Ce—Emission Guidelines and Compliance Times for Hospital/Medical/Infectious Waste Incinerators</HD>
              <SECTNO>60.30e</SECTNO>
              <SUBJECT>Scope.</SUBJECT>
              <SECTNO>60.31e</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.32e</SECTNO>
              <SUBJECT>Designated facilities.</SUBJECT>
              <SECTNO>60.33e</SECTNO>
              <SUBJECT>Emission guidelines.</SUBJECT>
              <SECTNO>60.34e</SECTNO>
              <SUBJECT>Operator training and qualification guidelines.</SUBJECT>
              <SECTNO>60.35e</SECTNO>
              <SUBJECT>Waste management guidelines.</SUBJECT>
              <SECTNO>60.36e</SECTNO>
              <SUBJECT>Inspection guidelines.</SUBJECT>
              <SECTNO>60.37e</SECTNO>

              <SUBJECT>Compliance, performance testing, and monitoring guidelines.<PRTPAGE P="6"/>
              </SUBJECT>
              <SECTNO>60.38e</SECTNO>
              <SUBJECT>Reporting and recordkeeping guidelines.</SUBJECT>
              <SECTNO>60.39e</SECTNO>
              <SUBJECT>Compliance times.</SUBJECT>
              <APP>Table 1 to Subpart Ce—Emission Limits for Small, Medium, and Large HMIWI</APP>
              <APP>Table 2 to Subpart Ce—Emission Limits for Small HMIWI which meet the criteria under § 60.33e(b)</APP>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart D—Standards of Performance for Fossil-Fuel-Fired Steam Generators for Which Construction is Commenced After August 17, 1971</HD>
              <SECTNO>60.40</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.41</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.42</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.43</SECTNO>
              <SUBJECT>Standard for sulfur dioxide.</SUBJECT>
              <SECTNO>60.44</SECTNO>
              <SUBJECT>Standard for nitrogen oxides.</SUBJECT>
              <SECTNO>60.45</SECTNO>
              <SUBJECT>Emission and fuel monitoring.</SUBJECT>
              <SECTNO>60.46</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart Da—Standards of Performance for Electric Utility Steam Generating Units for Which Construction is Commenced After September 18, 1978</HD>
              <SECTNO>60.40a</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.41a</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.42a</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.43a</SECTNO>
              <SUBJECT>Standard for sulfur dioxide.</SUBJECT>
              <SECTNO>60.44a</SECTNO>
              <SUBJECT>Standard for nitrogen oxides.</SUBJECT>
              <SECTNO>60.45a</SECTNO>
              <SUBJECT>Commercial demonstration permit.</SUBJECT>
              <SECTNO>60.46a</SECTNO>
              <SUBJECT>Compliance provisions.</SUBJECT>
              <SECTNO>60.47a</SECTNO>
              <SUBJECT>Emission monitoring.</SUBJECT>
              <SECTNO>60.48a</SECTNO>
              <SUBJECT>Compliance determination procedures and methods.</SUBJECT>
              <SECTNO>60.49a</SECTNO>
              <SUBJECT>Reporting requirements.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart Db—Standards of Performance for Industrial-Commercial-Institutional Steam Generating Units</HD>
              <SECTNO>60.40b</SECTNO>
              <SUBJECT>Applicability and delegation of authority.</SUBJECT>
              <SECTNO>60.41b</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.42b</SECTNO>
              <SUBJECT>Standard for sulfur dioxide.</SUBJECT>
              <SECTNO>60.43b</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.44b</SECTNO>
              <SUBJECT>Standard for nitrogen oxides.</SUBJECT>
              <SECTNO>60.45b</SECTNO>
              <SUBJECT>Compliance and performance test methods and procedures for sulfur dioxide.</SUBJECT>
              <SECTNO>60.46b</SECTNO>
              <SUBJECT>Compliance and performance test methods and procedures for particulate matter and nitrogen oxides.</SUBJECT>
              <SECTNO>60.47b</SECTNO>
              <SUBJECT>Emission monitoring for sulfur dioxide.</SUBJECT>
              <SECTNO>60.48b</SECTNO>
              <SUBJECT>Emission monitoring for particulate matter and nitrogen oxides.</SUBJECT>
              <SECTNO>60.49b</SECTNO>
              <SUBJECT>Reporting and recordkeeping requirements.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart Dc—Standards of Performance for Small Industrial-Commercial-Institutional Steam Generating Units</HD>
              <SECTNO>60.40c</SECTNO>
              <SUBJECT>Applicability and delegation of authority.</SUBJECT>
              <SECTNO>60.41c</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.42c</SECTNO>
              <SUBJECT>Standard for sulfur dioxide.</SUBJECT>
              <SECTNO>60.43c</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.44c</SECTNO>
              <SUBJECT>Compliance and performance test methods and procedures for sulfur dioxide.</SUBJECT>
              <SECTNO>60.45c</SECTNO>
              <SUBJECT>Compliance and performance test methods and procedures for particulate matter.</SUBJECT>
              <SECTNO>60.46c</SECTNO>
              <SUBJECT>Emission monitoring for sulfur dioxide.</SUBJECT>
              <SECTNO>60.47c</SECTNO>
              <SUBJECT>Emission monitoring for particulate matter.</SUBJECT>
              <SECTNO>60.48c</SECTNO>
              <SUBJECT>Reporting and recordkeeping requirements.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart E—Standards of Performance for Incinerators</HD>
              <SECTNO>60.50</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.51</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.52</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.53</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.54</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart Ea—Standards of Performance for Municipal Waste Combustors for Which Construction is Commenced After December 20, 1989 and on or Before September 20, 1994</HD>
              <SECTNO>60.50a</SECTNO>
              <SUBJECT>Applicability and delegation of authority.</SUBJECT>
              <SECTNO>60.51a</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.52a</SECTNO>
              <SUBJECT>Standard for municipal waste combustor metals.</SUBJECT>
              <SECTNO>60.53a</SECTNO>
              <SUBJECT>Standard for municipal waste combustor organics.</SUBJECT>
              <SECTNO>60.54a</SECTNO>
              <SUBJECT>Standard for municipal waste combustor acid gases.</SUBJECT>
              <SECTNO>60.55a</SECTNO>
              <SUBJECT>Standard for nitrogen oxides.</SUBJECT>
              <SECTNO>60.56a</SECTNO>
              <SUBJECT>Standard for municipal waste combustor operating practices.</SUBJECT>
              <SECTNO>60.57a</SECTNO>
              <SUBJECT>[Reserved]</SUBJECT>
              <SECTNO>60.58a</SECTNO>
              <SUBJECT>Compliance and performance testing.<PRTPAGE P="7"/>
              </SUBJECT>
              <SECTNO>60.59a</SECTNO>
              <SUBJECT>Reporting and recordkeeping requirements.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart Eb—Standards of Performance for Large Municipal Waste Combustors for Which Construction is Commenced After September 20, 1994 or for Which Modification or Reconstruction is Commenced After June 19, 1996</HD>
              <SECTNO>60.50b</SECTNO>
              <SUBJECT>Applicability and delegation of authority.</SUBJECT>
              <SECTNO>60.51b</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.52b</SECTNO>
              <SUBJECT>Standards for municipal waste combustor metals, acid gases, organics, and nitrogen oxides.</SUBJECT>
              <SECTNO>60.53b</SECTNO>
              <SUBJECT>Standards for municipal waste combustor operating practices.</SUBJECT>
              <SECTNO>60.54b</SECTNO>
              <SUBJECT>Standards for municipal waste combustor operator training and certification.</SUBJECT>
              <SECTNO>60.55b</SECTNO>
              <SUBJECT>Standards for municipal waste combustor fugitive ash emissions.</SUBJECT>
              <SECTNO>60.56b</SECTNO>
              <SUBJECT>Standards for air curtain incinerators.</SUBJECT>
              <SECTNO>60.57b</SECTNO>
              <SUBJECT>Siting requirements.</SUBJECT>
              <SECTNO>60.58b</SECTNO>
              <SUBJECT>Compliance and performance testing.</SUBJECT>
              <SECTNO>60.59b</SECTNO>
              <SUBJECT>Reporting and recordkeeping requirements.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart Ec—Standards of Performance for Hospital/Medical/Infectious Waste Incinerators for Which Construction is Commenced After June 20, 1996</HD>
              <SECTNO>60.50c</SECTNO>
              <SUBJECT>Applicability and delegation of authority.</SUBJECT>
              <SECTNO>60.51c</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.52c</SECTNO>
              <SUBJECT>Emission limits.</SUBJECT>
              <SECTNO>60.53c</SECTNO>
              <SUBJECT>Operator training and qualification requirements.</SUBJECT>
              <SECTNO>60.54c</SECTNO>
              <SUBJECT>Siting requirements.</SUBJECT>
              <SECTNO>60.55c</SECTNO>
              <SUBJECT>Waste management plan.</SUBJECT>
              <SECTNO>60.56c</SECTNO>
              <SUBJECT>Compliance and performance testing.</SUBJECT>
              <SECTNO>60.57c</SECTNO>
              <SUBJECT>Monitoring requirements.</SUBJECT>
              <SECTNO>60.58c</SECTNO>
              <SUBJECT>Reporting and recordkeeping requirements.</SUBJECT>
              <APP>Table 1 to Subpart Ec—Emission Limits for Small, Medium, and Large HMIWI</APP>
              <APP>Table 2 to Subpart Ec—Toxic Equivalency Factors</APP>
              <APP>Table 3 to Subpart Ec—Operating Parameters to be Monitored and Minimum Measurement and Recording Frequencies</APP>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart F—Standards of Performance for Portland Cement Plants</HD>
              <SECTNO>60.60</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.61</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.62</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.63</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.64</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.65</SECTNO>
              <SUBJECT>Recordkeeping and reporting requirements.</SUBJECT>
              <SECTNO>60.66</SECTNO>
              <SUBJECT>Delegation of authority.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart G—Standards of Performance for Nitric Acid Plants</HD>
              <SECTNO>60.70</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.71</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.72</SECTNO>
              <SUBJECT>Standard for nitrogen oxides.</SUBJECT>
              <SECTNO>60.73</SECTNO>
              <SUBJECT>Emission monitoring.</SUBJECT>
              <SECTNO>60.74</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart H—Standards of Performance for Sulfuric Acid Plants</HD>
              <SECTNO>60.80</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.81</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.82</SECTNO>
              <SUBJECT>Standard for sulfur dioxide.</SUBJECT>
              <SECTNO>60.83</SECTNO>
              <SUBJECT>Standard for acid mist.</SUBJECT>
              <SECTNO>60.84</SECTNO>
              <SUBJECT>Emission monitoring.</SUBJECT>
              <SECTNO>60.85</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart I—Standards of Performance for Hot Mix Asphalt Facilities</HD>
              <SECTNO>60.90</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.91</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.92</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.93</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart J—Standards of Performance for Petroleum Refineries</HD>
              <SECTNO>60.100</SECTNO>
              <SUBJECT>Applicability, designation of affected facility, and reconstruction.</SUBJECT>
              <SECTNO>60.101</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.102</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.103</SECTNO>
              <SUBJECT>Standard for carbon monoxide.</SUBJECT>
              <SECTNO>60.104</SECTNO>
              <SUBJECT>Standards for sulfur oxides.</SUBJECT>
              <SECTNO>60.105</SECTNO>
              <SUBJECT>Monitoring of emissions and operations.</SUBJECT>
              <SECTNO>60.106</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.107</SECTNO>
              <SUBJECT>Reporting and recordkeeping requirements.</SUBJECT>
              <SECTNO>60.108</SECTNO>
              <SUBJECT>Performance test and compliance provisions.</SUBJECT>
              <SECTNO>60.109</SECTNO>
              <SUBJECT>Delegation of authority.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart K—Standards of Performance for Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification Commenced After June 11, 1973, and Prior to May 19, 1978</HD>
              <SECTNO>60.110</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.111</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.112</SECTNO>

              <SUBJECT>Standard for volatile organic compounds (VOC).<PRTPAGE P="8"/>
              </SUBJECT>
              <SECTNO>60.113</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart Ka—Standards of Performance for Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification Commenced After May 18, 1978, and Prior to July 23, 1984</HD>
              <SECTNO>60.110a</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.111a</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.112a</SECTNO>
              <SUBJECT>Standard for volatile organic compounds (VOC).</SUBJECT>
              <SECTNO>60.113a</SECTNO>
              <SUBJECT>Testing and procedures.</SUBJECT>
              <SECTNO>60.114a</SECTNO>
              <SUBJECT>Alternative means of emission limitation.</SUBJECT>
              <SECTNO>60.115a</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart Kb—Standards of Performance for Volatile Organic Liquid Storage Vessels (Including Petroleum Liquid Storage Vessels) for Which Construction, Reconstruction, or Modification Commenced After July 23, 1984</HD>
              <SECTNO>60.110b</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.111b</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.112b</SECTNO>
              <SUBJECT>Standard for volatile organic compounds (VOC).</SUBJECT>
              <SECTNO>60.113b</SECTNO>
              <SUBJECT>Testing and procedures.</SUBJECT>
              <SECTNO>60.114b</SECTNO>
              <SUBJECT>Alternative means of emission limitation.</SUBJECT>
              <SECTNO>60.115b</SECTNO>
              <SUBJECT>Reporting and recordkeeping requirements.</SUBJECT>
              <SECTNO>60.116b</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.117b</SECTNO>
              <SUBJECT>Delegation of authority.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart L—Standards of Performance for Secondary Lead Smelters</HD>
              <SECTNO>60.120</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.121</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.122</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.123</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart M—Standards of Performance for Secondary Brass and Bronze Production Plants</HD>
              <SECTNO>60.130</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.131</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.132</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.133</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart N—Standards of Performance for Primary Emissions from Basic Oxygen Process Furnances for Which Construction is Commenced After June 11, 1973</HD>
              <SECTNO>60.140</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.141</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.142</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.143</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.144</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart Na—Standards of Performance for Secondary Emissions from Basic Oxygen Process Steelmaking Facilities for Which Construction is Commenced After January 20, 1983</HD>
              <SECTNO>60.140a</SECTNO>
              <SUBJECT>Applicability and designation of affected facilities.</SUBJECT>
              <SECTNO>60.141a</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.142a</SECTNO>
              <SUBJECT>Standards for particulate matter.</SUBJECT>
              <SECTNO>60.143a</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.144a</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.145a</SECTNO>
              <SUBJECT>Compliance provisions.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart O—Standards of Performance for Sewage Treatment Plants</HD>
              <SECTNO>60.150</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.151</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.152</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.153</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.154</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.155</SECTNO>
              <SUBJECT>Reporting.</SUBJECT>
              <SECTNO>60.156</SECTNO>
              <SUBJECT>Delegation of authority.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart P—Standards of Performance for Primary Copper Smelters</HD>
              <SECTNO>60.160</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.161</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.162</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.163</SECTNO>
              <SUBJECT>Standard for sulfur dioxide.</SUBJECT>
              <SECTNO>60.164</SECTNO>
              <SUBJECT>Standard for visible emissions.</SUBJECT>
              <SECTNO>60.165</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.166</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart Q—Standards of Performance for Primary Zinc Smelters</HD>
              <SECTNO>60.170</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.171</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.172</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.173</SECTNO>
              <SUBJECT>Standard for sulfur dioxide.</SUBJECT>
              <SECTNO>60.174</SECTNO>
              <SUBJECT>Standard for visible emissions.</SUBJECT>
              <SECTNO>60.175</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.176</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart R—Standards of Performance for Primary Lead Smelters</HD>
              <SECTNO>60.180</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.181</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.182</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.183</SECTNO>
              <SUBJECT>Standard for sulfur dioxide.</SUBJECT>
              <SECTNO>60.184</SECTNO>
              <SUBJECT>Standard for visible emissions.</SUBJECT>
              <SECTNO>60.185</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.186</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <PRTPAGE P="9"/>
              <HD SOURCE="HED">Subpart S—Standards of Performance for Primary Aluminum Reduction Plants</HD>
              <SECTNO>60.190</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.191</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.192</SECTNO>
              <SUBJECT>Standard for fluorides.</SUBJECT>
              <SECTNO>60.193</SECTNO>
              <SUBJECT>Standard for visible emissions.</SUBJECT>
              <SECTNO>60.194</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.195</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart T—Standards of Performance for the Phosphate Fertilizer Industry: Wet-Process Phosphoric Acid Plants</HD>
              <SECTNO>60.200</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.201</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.202</SECTNO>
              <SUBJECT>Standard for fluorides.</SUBJECT>
              <SECTNO>60.203</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.204</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart U—Standards of Performance for the Phosphate Fertilizer Industry: Superphosphoric Acid Plants</HD>
              <SECTNO>60.210</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.211</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.212</SECTNO>
              <SUBJECT>Standard for fluorides.</SUBJECT>
              <SECTNO>60.213</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.214</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart V—Standards of Performance for the Phosphate Fertilizer Industry: Diammonium Phosphate Plants</HD>
              <SECTNO>60.220</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.221</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.222</SECTNO>
              <SUBJECT>Standard for fluorides.</SUBJECT>
              <SECTNO>60.223</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.224</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart W—Standards of Performance for the Phosphate Fertilizer Industry: Triple Superphosphate Plants</HD>
              <SECTNO>60.230</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.231</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.232</SECTNO>
              <SUBJECT>Standard for fluorides.</SUBJECT>
              <SECTNO>60.233</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.234</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart X—Standards of Performance for the Phosphate Fertilizer Industry: Granular Triple Superphosphate Storage Facilities</HD>
              <SECTNO>60.240</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.241</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.242</SECTNO>
              <SUBJECT>Standard for fluorides.</SUBJECT>
              <SECTNO>60.243</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.244</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart Y—Standards of Performance for Coal Preparation Plants</HD>
              <SECTNO>60.250</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.251</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.252</SECTNO>
              <SUBJECT>Standards for particulate matter.</SUBJECT>
              <SECTNO>60.253</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.254</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart Z—Standards of Performance for Ferroalloy Production Facilities</HD>
              <SECTNO>60.260</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.261</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.262</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.263</SECTNO>
              <SUBJECT>Standard for carbon monoxide.</SUBJECT>
              <SECTNO>60.264</SECTNO>
              <SUBJECT>Emission monitoring.</SUBJECT>
              <SECTNO>60.265</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.266</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart AA—Standards of Performance for Steel Plants: Electric Arc Furnaces Constructed After October 21, 1974 and On or Before August 17, 1983</HD>
              <SECTNO>60.270</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.271</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.272</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.273</SECTNO>
              <SUBJECT>Emission monitoring.</SUBJECT>
              <SECTNO>60.274</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.275</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.276</SECTNO>
              <SUBJECT>Recordkeeping and reporting requirements.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart AAa—Standards of Performance for Steel Plants: Electric Arc Furnaces and Argon-Oxygen Decarburization Vessels Constructed After August 7, 1983</HD>
              <SECTNO>60.270a</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.271a</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.272a</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.273a</SECTNO>
              <SUBJECT>Emission monitoring.</SUBJECT>
              <SECTNO>60.274a</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.275a</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.276a</SECTNO>
              <SUBJECT>Recordkeeping and reporting requirements.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart BB—Standards of Performance for Kraft Pulp Mills</HD>
              <SECTNO>60.280</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.281</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.282</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.283</SECTNO>
              <SUBJECT>Standard for total reduced sulfur (TRS).</SUBJECT>
              <SECTNO>60.284</SECTNO>
              <SUBJECT>Monitoring of emissions and operations.</SUBJECT>
              <SECTNO>60.285</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <PRTPAGE P="10"/>
              <HD SOURCE="HED">Subpart CC—Standards of Performance for Glass Manufacturing Plants</HD>
              <SECTNO>60.290</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.291</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.292</SECTNO>
              <SUBJECT>Standards for particulate matter.</SUBJECT>
              <SECTNO>60.293</SECTNO>
              <SUBJECT>Standards for particulate matter from glass melting furnace with modified-processes.</SUBJECT>
              <SECTNO>60.294-60.295</SECTNO>
              <SUBJECT>[Reserved]</SUBJECT>
              <SECTNO>60.296</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart DD—Standards of Performance for Grain Elevators</HD>
              <SECTNO>60.300</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.301</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.302</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.303</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.304</SECTNO>
              <SUBJECT>Modifications.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart EE—Standards of Performance for Surface Coating of Metal Furniture</HD>
              <SECTNO>60.310</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.311</SECTNO>
              <SUBJECT>Definitions and symbols.</SUBJECT>
              <SECTNO>60.312</SECTNO>
              <SUBJECT>Standard for volatile organic compounds (VOC).</SUBJECT>
              <SECTNO>60.313</SECTNO>
              <SUBJECT>Performance tests and compliance provisions.</SUBJECT>
              <SECTNO>60.314</SECTNO>
              <SUBJECT>Monitoring of emissions and operations.</SUBJECT>
              <SECTNO>60.315</SECTNO>
              <SUBJECT>Reporting and recordkeeping requirements.</SUBJECT>
              <SECTNO>60.316</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <RESERVED>Subpart FF [Reserved]</RESERVED>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart GG—Standards of Performance for Stationary Gas Turbines</HD>
              <SECTNO>60.330</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.331</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.332</SECTNO>
              <SUBJECT>Standard for nitrogen oxides.</SUBJECT>
              <SECTNO>60.333</SECTNO>
              <SUBJECT>Standard for sulfur dioxide.</SUBJECT>
              <SECTNO>60.334</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.335</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart HH—Standards of Performance for Lime Manufacturing Plants</HD>
              <SECTNO>60.340</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.341</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.342</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.343</SECTNO>
              <SUBJECT>Monitoring of emissions and operations.</SUBJECT>
              <SECTNO>60.344</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart KK—Standards of Performance for Lead-Acid Battery Manufacturing Plants</HD>
              <SECTNO>60.370</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.371</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.372</SECTNO>
              <SUBJECT>Standards for lead.</SUBJECT>
              <SECTNO>60.373</SECTNO>
              <SUBJECT>Monitoring of emissions and operations.</SUBJECT>
              <SECTNO>60.374</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart LL—Standards of Performance for Metallic Mineral Processing Plants</HD>
              <SECTNO>60.380</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.381</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.382</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.383</SECTNO>
              <SUBJECT>Reconstruction.</SUBJECT>
              <SECTNO>60.384</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.385</SECTNO>
              <SUBJECT>Recordkeeping and reporting requirements.</SUBJECT>
              <SECTNO>60.386</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart MM—Standards of Performance for Automobile and Light Duty Truck Surface Coating Operations</HD>
              <SECTNO>60.390</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.391</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.392</SECTNO>
              <SUBJECT>Standards for volatile organic compounds.</SUBJECT>
              <SECTNO>60.393</SECTNO>
              <SUBJECT>Performance test and compliance provisions.</SUBJECT>
              <SECTNO>60.394</SECTNO>
              <SUBJECT>Monitoring of emissions and operations.</SUBJECT>
              <SECTNO>60.395</SECTNO>
              <SUBJECT>Reporting and recordkeeping requirements.</SUBJECT>
              <SECTNO>60.396</SECTNO>
              <SUBJECT>Reference methods and procedures.</SUBJECT>
              <SECTNO>60.397</SECTNO>
              <SUBJECT>Modifications.</SUBJECT>
              <SECTNO>60.398</SECTNO>
              <SUBJECT>Innovative technology waivers.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart NN—Standards of Performance for Phosphate Rock Plants</HD>
              <SECTNO>60.400</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.401</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.402</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.403</SECTNO>
              <SUBJECT>Monitoring of emissions and operations.</SUBJECT>
              <SECTNO>60.404</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart PP—Standards of Performance for Ammonium Sulfate Manufacture</HD>
              <SECTNO>60.420</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.421</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.422</SECTNO>
              <SUBJECT>Standards for particulate matter.</SUBJECT>
              <SECTNO>60.423</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.424</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart QQ—Standards of Performance for the Graphic Arts Industry: Publication Rotogravure Printing</HD>
              <SECTNO>60.430</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.431</SECTNO>
              <SUBJECT>Definitions and notations.<PRTPAGE P="11"/>
              </SUBJECT>
              <SECTNO>60.432</SECTNO>
              <SUBJECT>Standard for volatile organic compounds.</SUBJECT>
              <SECTNO>60.433</SECTNO>
              <SUBJECT>Performance test and compliance provisions.</SUBJECT>
              <SECTNO>60.434</SECTNO>
              <SUBJECT>Monitoring of operations and recordkeeping.</SUBJECT>
              <SECTNO>60.435</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart RR—Standards of Performance for Pressure Sensitive Tape and Label Surface Coating Operations</HD>
              <SECTNO>60.440</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.441</SECTNO>
              <SUBJECT>Definitions and symbols.</SUBJECT>
              <SECTNO>60.442</SECTNO>
              <SUBJECT>Standard for volatile organic compounds.</SUBJECT>
              <SECTNO>60.443</SECTNO>
              <SUBJECT>Compliance provisions.</SUBJECT>
              <SECTNO>60.444</SECTNO>
              <SUBJECT>Performance test procedures.</SUBJECT>
              <SECTNO>60.445</SECTNO>
              <SUBJECT>Monitoring of operations and recordkeeping.</SUBJECT>
              <SECTNO>60.446</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.447</SECTNO>
              <SUBJECT>Reporting requirements.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart SS—Standards of Performance for Industrial Surface Coating: Large Appliances</HD>
              <SECTNO>60.450</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.451</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.452</SECTNO>
              <SUBJECT>Standard for volatile organic compounds.</SUBJECT>
              <SECTNO>60.453</SECTNO>
              <SUBJECT>Performance test and compliance provisions.</SUBJECT>
              <SECTNO>60.454</SECTNO>
              <SUBJECT>Monitoring of emissions and operations.</SUBJECT>
              <SECTNO>60.455</SECTNO>
              <SUBJECT>Reporting and recordkeeping requirements.</SUBJECT>
              <SECTNO>60.456</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart TT—Standards of Performance for Metal Coil Surface Coating</HD>
              <SECTNO>60.460</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.461</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.462</SECTNO>
              <SUBJECT>Standards for volatile organic compounds.</SUBJECT>
              <SECTNO>60.463</SECTNO>
              <SUBJECT>Performance test and compliance provisions.</SUBJECT>
              <SECTNO>60.464</SECTNO>
              <SUBJECT>Monitoring of emissions and operations.</SUBJECT>
              <SECTNO>60.465</SECTNO>
              <SUBJECT>Reporting and recordkeeping requirements.</SUBJECT>
              <SECTNO>60.466</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart UU—Standards of Performance for Asphalt Processing and Asphalt Roofing Manufacture</HD>
              <SECTNO>60.470</SECTNO>
              <SUBJECT>Applicability and designation of affected facilities.</SUBJECT>
              <SECTNO>60.471</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.472</SECTNO>
              <SUBJECT>Standards for particulate matter.</SUBJECT>
              <SECTNO>60.473</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.474</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart VV—Standards of Performance for Equipment Leaks of VOC in the Synthetic Organic Chemicals Manufacturing Industry</HD>
              <SECTNO>60.480</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.481</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.482-1</SECTNO>
              <SUBJECT>Standards: General.</SUBJECT>
              <SECTNO>60.482-2</SECTNO>
              <SUBJECT>Standards: Pumps in light liquid service.</SUBJECT>
              <SECTNO>60.482-3</SECTNO>
              <SUBJECT>Standards: Compressors.</SUBJECT>
              <SECTNO>60.482-4</SECTNO>
              <SUBJECT>Standards: Pressure relief devices in gas/vapor service.</SUBJECT>
              <SECTNO>60.482-5</SECTNO>
              <SUBJECT>Standards: Sampling connection systems.</SUBJECT>
              <SECTNO>60.482-6</SECTNO>
              <SUBJECT>Standards: Open-ended valves or lines.</SUBJECT>
              <SECTNO>60.482-7</SECTNO>
              <SUBJECT>Standards: Valves in gas/vapor service and in light liquid service.</SUBJECT>
              <SECTNO>60.482-8</SECTNO>
              <SUBJECT>Standards: Pumps and valves in heavy liquid service, pressure relief devices in light liquid or heavy liquid service, and connectors. </SUBJECT>
              <SECTNO>60.482-9</SECTNO>
              <SUBJECT>Standards: Delay of repair.</SUBJECT>
              <SECTNO>60.482-10</SECTNO>
              <SUBJECT>Standards: Closed vent systems and control devices.</SUBJECT>
              <SECTNO>60.483-1</SECTNO>
              <SUBJECT>Alternative standards for valves—allowable percentage of valves leaking.</SUBJECT>
              <SECTNO>60.483-2</SECTNO>
              <SUBJECT>Alternative standards for valves—skip period leak detection and repair.</SUBJECT>
              <SECTNO>60.484</SECTNO>
              <SUBJECT>Equivalence of means of emission limitation.</SUBJECT>
              <SECTNO>60.485</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.486</SECTNO>
              <SUBJECT>Recordkeeping requirements.</SUBJECT>
              <SECTNO>60.487</SECTNO>
              <SUBJECT>Reporting requirements.</SUBJECT>
              <SECTNO>60.488</SECTNO>
              <SUBJECT>Reconstruction.</SUBJECT>
              <SECTNO>60.489</SECTNO>
              <SUBJECT>List of chemicals produced by affected facilities.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart WW—Standards of Performance for the Beverage Can Surface Coating Industry</HD>
              <SECTNO>60.490</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.491</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.492</SECTNO>
              <SUBJECT>Standards for volatile organic compounds.</SUBJECT>
              <SECTNO>60.493</SECTNO>
              <SUBJECT>Performance test and compliance provisions.</SUBJECT>
              <SECTNO>60.494</SECTNO>
              <SUBJECT>Monitoring of emissions and operations.</SUBJECT>
              <SECTNO>60.495</SECTNO>
              <SUBJECT>Reporting and recordkeeping requirements.</SUBJECT>
              <SECTNO>60.496</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart XX—Standards of Performance for Bulk Gasoline Terminals</HD>
              <SECTNO>60.500</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.501</SECTNO>
              <SUBJECT>Definitions.<PRTPAGE P="12"/>
              </SUBJECT>
              <SECTNO>60.502</SECTNO>
              <SUBJECT>Standards for Volatile Organic Compound (VOC) emissions from bulk gasoline terminals.</SUBJECT>
              <SECTNO>60.503</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.504</SECTNO>
              <SUBJECT>[Reserved]</SUBJECT>
              <SECTNO>60.505</SECTNO>
              <SUBJECT>Reporting and recordkeeping.</SUBJECT>
              <SECTNO>60.506</SECTNO>
              <SUBJECT>Reconstruction.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart AAA—Standards of Performance for New Residential Wood Heaters</HD>
              <SECTNO>60.530</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.531</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.532</SECTNO>
              <SUBJECT>Standards for particulate matter.</SUBJECT>
              <SECTNO>60.533</SECTNO>
              <SUBJECT>Compliance and certification.</SUBJECT>
              <SECTNO>60.534</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.535</SECTNO>
              <SUBJECT>Laboratory accreditation.</SUBJECT>
              <SECTNO>60.536</SECTNO>
              <SUBJECT>Permanent label, temporary label, and owner's manual.</SUBJECT>
              <SECTNO>60.537</SECTNO>
              <SUBJECT>Reporting and recordkeeping.</SUBJECT>
              <SECTNO>60.538</SECTNO>
              <SUBJECT>Prohibitions.</SUBJECT>
              <SECTNO>60.539</SECTNO>
              <SUBJECT>Hearing and appeal procedures.</SUBJECT>
              <SECTNO>60.539a</SECTNO>
              <SUBJECT>Delegation of authority.</SUBJECT>
              <SECTNO>60.539b</SECTNO>
              <SUBJECT>General provisions exclusions.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart BBB—Standards of Performance for the Rubber Tire Manufacturing Industry</HD>
              <SECTNO>60.540</SECTNO>
              <SUBJECT>Applicability and designation of affected facilities.</SUBJECT>
              <SECTNO>60.541</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.542</SECTNO>
              <SUBJECT>Standards for volatile organic compounds.</SUBJECT>
              <SECTNO>60.542a</SECTNO>
              <SUBJECT>Alternate standard for volatile organic compounds.</SUBJECT>
              <SECTNO>60.543</SECTNO>
              <SUBJECT>Performance test and compliance provisions.</SUBJECT>
              <SECTNO>60.544</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.545</SECTNO>
              <SUBJECT>Recordkeeping requirements.</SUBJECT>
              <SECTNO>60.546</SECTNO>
              <SUBJECT>Reporting requirements.</SUBJECT>
              <SECTNO>60.547</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.548</SECTNO>
              <SUBJECT>Delegation of authority.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <RESERVED>Subpart CCC [Reserved]</RESERVED>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart DDD—Standards of Performance for Volatile Organic Compound (VOC) Emissions from the Polymer Manufacturing Industry</HD>
              <SECTNO>60.560</SECTNO>
              <SUBJECT>Applicability and designation of affected facilities.</SUBJECT>
              <SECTNO>60.561</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.562-1</SECTNO>
              <SUBJECT>Standards: Process emissions.</SUBJECT>
              <SECTNO>60.562-2</SECTNO>
              <SUBJECT>Standards: Equipment leaks of VOC.</SUBJECT>
              <SECTNO>60.563</SECTNO>
              <SUBJECT>Monitoring requirements.</SUBJECT>
              <SECTNO>60.564</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.565</SECTNO>
              <SUBJECT>Reporting and recordkeeping requirements.</SUBJECT>
              <SECTNO>60.566</SECTNO>
              <SUBJECT>Delegation of authority.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <RESERVED>Subpart EEE [Reserved]</RESERVED>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart FFF—Standards of Performance for Flexible Vinyl and Urethane Coating and Printing</HD>
              <SECTNO>60.580</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.581</SECTNO>
              <SUBJECT>Definitions and symbols.</SUBJECT>
              <SECTNO>60.582</SECTNO>
              <SUBJECT>Standard for volatile organic compounds.</SUBJECT>
              <SECTNO>60.583</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.584</SECTNO>
              <SUBJECT>Monitoring of operations and recordkeeping requirements.</SUBJECT>
              <SECTNO>60.585</SECTNO>
              <SUBJECT>Reporting requirements.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart GGG—Standards of Performance for Equipment Leaks of VOC in Petroleum Refineries</HD>
              <SECTNO>60.590</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.591</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.592</SECTNO>
              <SUBJECT>Standards.</SUBJECT>
              <SECTNO>60.593</SECTNO>
              <SUBJECT>Exceptions.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart HHH—Standards of Performance for Synthetic Fiber Production Facilities</HD>
              <SECTNO>60.600</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.601</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.602</SECTNO>
              <SUBJECT>Standard for volatile organic compounds.</SUBJECT>
              <SECTNO>60.603</SECTNO>
              <SUBJECT>Performance test and compliance provisions.</SUBJECT>
              <SECTNO>60.604</SECTNO>
              <SUBJECT>Reporting requirements.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart III—Standards of Performance for Volatile Organic Compound (VOC) Emissions From the Synthetic Organic Chemical Manufacturing Industry (SOCMI) Air Oxidation Unit Processes</HD>
              <SECTNO>60.610</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.611</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.612</SECTNO>
              <SUBJECT>Standards.</SUBJECT>
              <SECTNO>60.613</SECTNO>
              <SUBJECT>Monitoring of emissions and operations.</SUBJECT>
              <SECTNO>60.614</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.615</SECTNO>
              <SUBJECT>Reporting and recordkeeping requirements.</SUBJECT>
              <SECTNO>60.616</SECTNO>
              <SUBJECT>Reconstruction.</SUBJECT>
              <SECTNO>60.617</SECTNO>
              <SUBJECT>Chemicals affected by subpart III.</SUBJECT>
              <SECTNO>60.618</SECTNO>
              <SUBJECT>Delegation of authority.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart JJJ—Standards of Performance for Petroleum Dry Cleaners</HD>
              <SECTNO>60.620</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.621</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.622</SECTNO>
              <SUBJECT>Standards for volatile organic compounds.</SUBJECT>
              <SECTNO>60.623</SECTNO>
              <SUBJECT>Equivalent equipment and procedures.<PRTPAGE P="13"/>
              </SUBJECT>
              <SECTNO>60.624</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.625</SECTNO>
              <SUBJECT>Recordkeeping requirements.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart KKK—Standards of Performance for Equipment Leaks of VOC From Onshore Natural Gas Processing Plants</HD>
              <SECTNO>60.630</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.631</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.632</SECTNO>
              <SUBJECT>Standards.</SUBJECT>
              <SECTNO>60.633</SECTNO>
              <SUBJECT>Exceptions.</SUBJECT>
              <SECTNO>60.634</SECTNO>
              <SUBJECT>Alternative means of emission limitation.</SUBJECT>
              <SECTNO>60.635</SECTNO>
              <SUBJECT>Recordkeeping requirements.</SUBJECT>
              <SECTNO>60.636</SECTNO>
              <SUBJECT>Reporting requirements.</SUBJECT>
            </SUBPART>
            <SUBPART>

              <HD SOURCE="HED">Subpart LLL—Standards of Performance for Onshore Natural Gas Processing: SO<E T="52">2</E> Emissions</HD>
              <SECTNO>60.640</SECTNO>
              <SUBJECT>Applicability and designation of affected facilities.</SUBJECT>
              <SECTNO>60.641</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.642</SECTNO>
              <SUBJECT>Standards for sulfur dioxide.</SUBJECT>
              <SECTNO>60.643</SECTNO>
              <SUBJECT>Compliance provisions.</SUBJECT>
              <SECTNO>60.644</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.645</SECTNO>
              <SUBJECT>[Reserved]</SUBJECT>
              <SECTNO>60.646</SECTNO>
              <SUBJECT>Monitoring of emissions and operations.</SUBJECT>
              <SECTNO>60.647</SECTNO>
              <SUBJECT>Recordkeeping and reporting requirements.</SUBJECT>
              <SECTNO>60.648</SECTNO>
              <SUBJECT>Optional procedure for measuring hydrogen sulfide in acid gas—Tutwiler Procedure.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <RESERVED>Subpart MMM [Reserved]</RESERVED>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart NNN—Standards of Performance for Volatile Organic Compound (VOC) Emissions From Synthetic Organic Chemical Manufacturing Industry (SOCMI) Distillation Operations</HD>
              <SECTNO>60.660</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.661</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.662</SECTNO>
              <SUBJECT>Standards.</SUBJECT>
              <SECTNO>60.663</SECTNO>
              <SUBJECT>Monitoring of emissions and operations.</SUBJECT>
              <SECTNO>60.664</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.665</SECTNO>
              <SUBJECT>Reporting and recordkeeping requirements.</SUBJECT>
              <SECTNO>60.666</SECTNO>
              <SUBJECT>Reconstruction.</SUBJECT>
              <SECTNO>60.667</SECTNO>
              <SUBJECT>Chemicals affected by subpart NNN.</SUBJECT>
              <SECTNO>60.668</SECTNO>
              <SUBJECT>Delegation of authority.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart OOO—Standards of Performance for Nonmetallic Mineral Processing Plants</HD>
              <SECTNO>60.670</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.671</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.672</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.673</SECTNO>
              <SUBJECT>Reconstruction.</SUBJECT>
              <SECTNO>60.674</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.675</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.676</SECTNO>
              <SUBJECT>Reporting and recordkeeping.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart PPP—Standard of Performance for Wool Fiberglass Insulation Manufacturing Plants</HD>
              <SECTNO>60.680</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.681</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.682</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <SECTNO>60.683</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.684</SECTNO>
              <SUBJECT>Recordkeeping and reporting requirements.</SUBJECT>
              <SECTNO>60.685</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart QQQ—Standards of Performance for VOC Emissions From Petroleum Refinery Wastewater Systems</HD>
              <SECTNO>60.690</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.691</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.692-1</SECTNO>
              <SUBJECT>Standards: General.</SUBJECT>
              <SECTNO>60.692-2</SECTNO>
              <SUBJECT>Standards: Individual drain systems.</SUBJECT>
              <SECTNO>60.692-3</SECTNO>
              <SUBJECT>Standards: Oil-water separators.</SUBJECT>
              <SECTNO>60.692-4</SECTNO>
              <SUBJECT>Standards: Aggregate facility.</SUBJECT>
              <SECTNO>60.692-5</SECTNO>
              <SUBJECT>Standards: Closed vent systems and control devices.</SUBJECT>
              <SECTNO>60.692-6</SECTNO>
              <SUBJECT>Standards: Delay of repair.</SUBJECT>
              <SECTNO>60.692-7</SECTNO>
              <SUBJECT>Standards: Delay of compliance.</SUBJECT>
              <SECTNO>60.693-1</SECTNO>
              <SUBJECT>Alternative standards for individual drain systems.</SUBJECT>
              <SECTNO>60.693-2</SECTNO>
              <SUBJECT>Alternative standards for oil-water separators.</SUBJECT>
              <SECTNO>60.694</SECTNO>
              <SUBJECT>Permission to use alternative means of emission limitation.</SUBJECT>
              <SECTNO>60.695</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.696</SECTNO>
              <SUBJECT>Performance test methods and procedures and compliance provisions.</SUBJECT>
              <SECTNO>60.697</SECTNO>
              <SUBJECT>Recordkeeping requirements.</SUBJECT>
              <SECTNO>60.698</SECTNO>
              <SUBJECT>Reporting requirements.</SUBJECT>
              <SECTNO>60.699</SECTNO>
              <SUBJECT>Delegation of authority.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart RRR—Standards of Performance for Volatile Organic Compound Emissions from Synthetic Organic Chemical Manufacturing Industry (SOCMI) Reactor Processes</HD>
              <SECTNO>60.700</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.701</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.702</SECTNO>
              <SUBJECT>Standards.</SUBJECT>
              <SECTNO>60.703</SECTNO>
              <SUBJECT>Monitoring of emissions and operations.</SUBJECT>
              <SECTNO>60.704</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.705</SECTNO>
              <SUBJECT>Reporting and recordkeeping requirements.</SUBJECT>
              <SECTNO>60.706</SECTNO>
              <SUBJECT>Reconstruction.</SUBJECT>
              <SECTNO>60.707</SECTNO>
              <SUBJECT>Chemicals affected by subpart RRR.</SUBJECT>
              <SECTNO>60.708</SECTNO>
              <SUBJECT>Delegation of authority.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <PRTPAGE P="14"/>
              <HD SOURCE="HED">Subpart SSS—Standards of Performance for Magnetic Tape Coating Facilities</HD>
              <SECTNO>60.710</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.711</SECTNO>
              <SUBJECT>Definitions, symbols, and cross-reference tables.</SUBJECT>
              <SECTNO>60.712</SECTNO>
              <SUBJECT>Standards for volatile organic compounds.</SUBJECT>
              <SECTNO>60.713</SECTNO>
              <SUBJECT>Compliance provisions.</SUBJECT>
              <SECTNO>60.714</SECTNO>
              <SUBJECT>Installation of monitoring devices and recordkeeping.</SUBJECT>
              <SECTNO>60.715</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.716</SECTNO>
              <SUBJECT>Permission to use alternative means of emission limitation.</SUBJECT>
              <SECTNO>60.717</SECTNO>
              <SUBJECT>Reporting and monitoring requirements.</SUBJECT>
              <SECTNO>60.718</SECTNO>
              <SUBJECT>Delegation of authority.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart TTT—Standards of Performance for Industrial Surface Coating: Surface Coating of Plastic Parts for Business Machines</HD>
              <SECTNO>60.720</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.721</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.722</SECTNO>
              <SUBJECT>Standards for volatile organic compounds.</SUBJECT>
              <SECTNO>60.723</SECTNO>
              <SUBJECT>Performance test and compliance provisions.</SUBJECT>
              <SECTNO>60.724</SECTNO>
              <SUBJECT>Reporting and recordkeeping requirements.</SUBJECT>
              <SECTNO>60.725</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.726</SECTNO>
              <SUBJECT>Delegation of authority.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart UUU—Standards of Performance for Calciners and Dryers in Mineral Industries</HD>
              <SECTNO>60.730</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.731</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.732</SECTNO>
              <SUBJECT>Standards for particulate matter.</SUBJECT>
              <SECTNO>60.733</SECTNO>
              <SUBJECT>Reconstruction.</SUBJECT>
              <SECTNO>60.734</SECTNO>
              <SUBJECT>Monitoring of emissions and operations.</SUBJECT>
              <SECTNO>60.735</SECTNO>
              <SUBJECT>Recordkeeping and reporting requirements.</SUBJECT>
              <SECTNO>60.736</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.737</SECTNO>
              <SUBJECT>Delegation of authority.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart VVV—Standards of Performance for Polymeric Coating of Supporting Substrates Facilities</HD>
              <SECTNO>60.740</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <SECTNO>60.741</SECTNO>
              <SUBJECT>Definitions, symbols, and cross-reference tables.</SUBJECT>
              <SECTNO>60.742</SECTNO>
              <SUBJECT>Standards for violatile organic compounds.</SUBJECT>
              <SECTNO>60.743</SECTNO>
              <SUBJECT>Compliance provisions.</SUBJECT>
              <SECTNO>60.744</SECTNO>
              <SUBJECT>Monitoring requirements.</SUBJECT>
              <SECTNO>60.745</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.746</SECTNO>
              <SUBJECT>Permission to use alternative means of emission limitation.</SUBJECT>
              <SECTNO>60.747</SECTNO>
              <SUBJECT>Reporting and recordkeeping requirements.</SUBJECT>
              <SECTNO>60.748</SECTNO>
              <SUBJECT>Delegation of authority.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart WWW—Standards of Performance for Municipal Solid Waste Landfills</HD>
              <SECTNO>60.750</SECTNO>
              <SUBJECT>Applicability, designation of affected facility, and delegation of authority.</SUBJECT>
              <SECTNO>60.751</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <SECTNO>60.752</SECTNO>
              <SUBJECT>Standards for air emissions from municipal solid waste landfills.</SUBJECT>
              <SECTNO>60.753</SECTNO>
              <SUBJECT>Operational standards for collection and control systems.</SUBJECT>
              <SECTNO>60.754</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <SECTNO>60.755</SECTNO>
              <SUBJECT>Compliance provisions.</SUBJECT>
              <SECTNO>60.756</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <SECTNO>60.757</SECTNO>
              <SUBJECT>Reporting requirements.</SUBJECT>
              <SECTNO>60.758</SECTNO>
              <SUBJECT>Recordkeeping requirements.</SUBJECT>
              <SECTNO>60.759</SECTNO>
              <SUBJECT>Specifications for active collection systems.</SUBJECT>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart AAAA—Standards of Performance for Small Municipal Waste Combustion Units for Which Construction is Commenced After August 30, 1999 or for Which Modification or Reconstruction is Commenced After June 6, 2001</HD>
              <SUBJGRP>
                <HD SOURCE="HED">Introduction</HD>
                <SECTNO>60.1000</SECTNO>
                <SUBJECT>What does this subpart do?</SUBJECT>
                <SECTNO>60.1005</SECTNO>
                <SUBJECT>When does this subpart become effective?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Applicability</HD>
                <SECTNO>60.1010</SECTNO>
                <SUBJECT>Does this subpart apply to my municipal waste combustion unit?</SUBJECT>
                <SECTNO>60.1015</SECTNO>
                <SUBJECT>What is a new municipal waste combustion unit?</SUBJECT>
                <SECTNO>60.1020</SECTNO>
                <SUBJECT>Does this subpart allow any exemptions?</SUBJECT>
                <SECTNO>60.1025</SECTNO>
                <SUBJECT>Do subpart E new source performance standards also apply to my municipal waste combustion unit?</SUBJECT>
                <SECTNO>60.1030</SECTNO>
                <SUBJECT>Can the Administrator delegate authority to enforce these Federal new source performance standards to a State agency?</SUBJECT>
                <SECTNO>60.1035</SECTNO>
                <SUBJECT>How are these new source performance standards structured?</SUBJECT>
                <SECTNO>60.1040</SECTNO>
                <SUBJECT>Do all five components of these new source performance standards apply at the same time?</SUBJECT>
                <SECTNO>60.1045</SECTNO>
                <SUBJECT>Are there different subcategories of small municipal waste combustion units within this subpart?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Preconstruction Requirements: Materials Separation Plan</HD>
                <SECTNO>60.1050</SECTNO>
                <SUBJECT>Who must submit a materials separation plan?</SUBJECT>
                <SECTNO>60.1055</SECTNO>
                <SUBJECT>What is a materials separation plan?</SUBJECT>
                <SECTNO>60.1060</SECTNO>
                <SUBJECT>What steps must I complete for my materials separation plan?</SUBJECT>
                <SECTNO>60.1065</SECTNO>

                <SUBJECT>What must I include in my draft materials separation plan?<PRTPAGE P="15"/>
                </SUBJECT>
                <SECTNO>60.1070</SECTNO>
                <SUBJECT>How do I make my draft materials separation plan available to the public?</SUBJECT>
                <SECTNO>60.1075</SECTNO>
                <SUBJECT>When must I accept comments on the materials separation plan?</SUBJECT>
                <SECTNO>60.1080</SECTNO>
                <SUBJECT>Where and when must I hold a public meeting on my draft materials separation plan?</SUBJECT>
                <SECTNO>60.1085</SECTNO>
                <SUBJECT>What must I do with any public comments I receive during the public comment period on my draft materials separation plan?</SUBJECT>
                <SECTNO>60.1090</SECTNO>
                <SUBJECT>What must I do with my revised materials separation plan?</SUBJECT>
                <SECTNO>60.1095</SECTNO>
                <SUBJECT>What must I include in the public meeting on my revised materials separation plan?</SUBJECT>
                <SECTNO>60.1100</SECTNO>
                <SUBJECT>What must I do with any public comments I receive on my revised materials separation plan?</SUBJECT>
                <SECTNO>60.1105</SECTNO>
                <SUBJECT>How do I submit my final materials separation plan?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Preconstruction Requirements: Siting Analysis</HD>
                <SECTNO>60.1110</SECTNO>
                <SUBJECT>Who must submit a siting analysis?</SUBJECT>
                <SECTNO>60.1115</SECTNO>
                <SUBJECT>What is a siting analysis?</SUBJECT>
                <SECTNO>60.1120</SECTNO>
                <SUBJECT>What steps must I complete for my siting analysis?</SUBJECT>
                <SECTNO>60.1125</SECTNO>
                <SUBJECT>What must I include in my siting analysis?</SUBJECT>
                <SECTNO>60.1130</SECTNO>
                <SUBJECT>How do I make my siting analysis available to the public?</SUBJECT>
                <SECTNO>60.1135</SECTNO>
                <SUBJECT>When must I accept comments on the siting analysis and revised materials separation plan?</SUBJECT>
                <SECTNO>60.1140</SECTNO>
                <SUBJECT>Where and when must I hold a public meeting on the siting analysis?</SUBJECT>
                <SECTNO>60.1145</SECTNO>
                <SUBJECT>What must I do with any public comments I receive during the public comment period on my siting analysis?</SUBJECT>
                <SECTNO>60.1150</SECTNO>
                <SUBJECT>How do I submit my siting analysis?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Good Combustion Practices: Operator Training</HD>
                <SECTNO>60.1155</SECTNO>
                <SUBJECT>What types of training must I do?</SUBJECT>
                <SECTNO>60.1160</SECTNO>
                <SUBJECT>Who must complete the operator training course? By when?</SUBJECT>
                <SECTNO>60.1165</SECTNO>
                <SUBJECT>Who must complete the plant-specific training course?</SUBJECT>
                <SECTNO>60.1170</SECTNO>
                <SUBJECT>What plant-specific training must I provide?</SUBJECT>
                <SECTNO>60.1175</SECTNO>
                <SUBJECT>What information must I include in the plant-specific operating manual?</SUBJECT>
                <SECTNO>60.1180</SECTNO>
                <SUBJECT>Where must I keep the plant-specific operating manual?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Good Combustion Practices: Operator Certification</HD>
                <SECTNO>60.1185</SECTNO>
                <SUBJECT>What types of operator certification must the chief facility operator and shift supervisor obtain and by when must they obtain it?</SUBJECT>
                <SECTNO>60.1190</SECTNO>
                <SUBJECT>After the required date for operator certification, who may operate the municipal waste combustion unit?</SUBJECT>
                <SECTNO>60.1195</SECTNO>
                <SUBJECT>What if all the certified operators must be temporarily offsite?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Good Combustion Practices: Operating Requirements</HD>
                <SECTNO>60.1200</SECTNO>
                <SUBJECT>What are the operating practice requirements for my municipal waste combustion unit?</SUBJECT>
                <SECTNO>60.1205</SECTNO>
                <SUBJECT>What happens to the operating requirements during periods of startup, shutdown, and malfunction?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Emission Limits</HD>
                <SECTNO>60.1210</SECTNO>
                <SUBJECT>What pollutants are regulated by this subpart?</SUBJECT>
                <SECTNO>60.1215</SECTNO>
                <SUBJECT>What emission limits must I meet? By when?</SUBJECT>
                <SECTNO>60.1220</SECTNO>
                <SUBJECT>What happens to the emission limits during periods of startup, shutdown, and malfunction?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Continuous Emission Monitoring</HD>
                <SECTNO>60.1225</SECTNO>
                <SUBJECT>What types of continuous emission monitoring must I perform?</SUBJECT>
                <SECTNO>60.1230</SECTNO>
                <SUBJECT>What continuous emission monitoring systems must I install for gaseous pollutants?</SUBJECT>
                <SECTNO>60.1235</SECTNO>
                <SUBJECT>How are the data from the continuous emission monitoring systems used?</SUBJECT>
                <SECTNO>60.1240</SECTNO>
                <SUBJECT>How do I make sure my continuous emission monitoring systems are operating correctly?</SUBJECT>
                <SECTNO>60.1245</SECTNO>
                <SUBJECT>Am I exempt from any appendix B or appendix F requirements to evaluate continuous emission monitoring systems?</SUBJECT>
                <SECTNO>60.1250</SECTNO>
                <SUBJECT>What is my schedule for evaluating continuous emission monitoring systems?</SUBJECT>
                <SECTNO>60.1255</SECTNO>
                <SUBJECT>What must I do if I choose to monitor carbon dioxide instead of oxygen as a diluent gas?</SUBJECT>
                <SECTNO>60.1260</SECTNO>
                <SUBJECT>What is the minimum amount of monitoring data I must collect with my continuous emission monitoring systems and is the data collection requirement enforceable?</SUBJECT>
                <SECTNO>60.1265</SECTNO>
                <SUBJECT>How do I convert my 1-hour arithmetic averages into the appropriate averaging times and units?</SUBJECT>
                <SECTNO>60.1270</SECTNO>
                <SUBJECT>What is required for my continuous opacity monitoring system and how are the data used?</SUBJECT>
                <SECTNO>60.1275</SECTNO>
                <SUBJECT>What additional requirements must I meet for the operation of my continuous emission monitoring systems and continuous opacity monitoring system?</SUBJECT>
                <SECTNO>60.1280</SECTNO>
                <SUBJECT>What must I do if any of my continuous emission monitoring systems are temporarily unavailable to meet the data collection requirements?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Stack Testing</HD>
                <SECTNO>60.1285</SECTNO>
                <SUBJECT>What types of stack tests must I conduct?</SUBJECT>
                <SECTNO>60.1290</SECTNO>
                <SUBJECT>How are the stack test data used?<PRTPAGE P="16"/>
                </SUBJECT>
                <SECTNO>60.1295</SECTNO>
                <SUBJECT>What schedule must I follow for the stack testing?</SUBJECT>
                <SECTNO>60.1300</SECTNO>
                <SUBJECT>What test methods must I use to stack test?</SUBJECT>
                <SECTNO>60.1305</SECTNO>
                <SUBJECT>May I conduct stack testing less often?</SUBJECT>
                <SECTNO>60.1310</SECTNO>
                <SUBJECT>May I deviate from the 13-month testing schedule if unforeseen circumstances arise?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Other Monitoring Requirements</HD>
                <SECTNO>60.1315</SECTNO>
                <SUBJECT>Must I meet other requirements for continuous monitoring?</SUBJECT>
                <SECTNO>60.1320</SECTNO>
                <SUBJECT>How do I monitor the load of my municipal waste combustion unit?</SUBJECT>
                <SECTNO>60.1325</SECTNO>
                <SUBJECT>How do I monitor the temperature of flue gases at the inlet of my particulate matter control device?</SUBJECT>
                <SECTNO>60.1330</SECTNO>
                <SUBJECT>How do I monitor the injection rate of activated carbon?</SUBJECT>
                <SECTNO>60.1335</SECTNO>
                <SUBJECT>What is the minimum amount of monitoring data I must collect with my continuous parameter monitoring systems and is the data collection requirement enforceable?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Recordkeeping</HD>
                <SECTNO>60.1340</SECTNO>
                <SUBJECT>What records must I keep?</SUBJECT>
                <SECTNO>60.1345</SECTNO>
                <SUBJECT>Where must I keep my records and for how long?</SUBJECT>
                <SECTNO>60.1350</SECTNO>
                <SUBJECT>What records must I keep for the materials separation plan and siting analysis?</SUBJECT>
                <SECTNO>60.1355</SECTNO>
                <SUBJECT>What records must I keep for operator training and certification?</SUBJECT>
                <SECTNO>60.1360</SECTNO>
                <SUBJECT>What records must I keep for stack tests?</SUBJECT>
                <SECTNO>60.1365</SECTNO>
                <SUBJECT>What records must I keep for continuously monitored pollutants or parameters?</SUBJECT>
                <SECTNO>60.1370</SECTNO>
                <SUBJECT>What records must I keep for municipal waste combustion units that use activated carbon?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Reporting</HD>
                <SECTNO>60.1375</SECTNO>
                <SUBJECT>What reports must I submit before I submit my notice of construction?</SUBJECT>
                <SECTNO>60.1380</SECTNO>
                <SUBJECT>What must I include in my notice of construction?</SUBJECT>
                <SECTNO>60.1385</SECTNO>
                <SUBJECT>What reports must I submit after I submit my notice of construction and in what form?</SUBJECT>
                <SECTNO>60.1390</SECTNO>
                <SUBJECT>What are the appropriate units of measurement for reporting my data?</SUBJECT>
                <SECTNO>60.1395</SECTNO>
                <SUBJECT>When must I submit the initial report?</SUBJECT>
                <SECTNO>60.1400</SECTNO>
                <SUBJECT>What must I include in my initial report?</SUBJECT>
                <SECTNO>60.1405</SECTNO>
                <SUBJECT>When must I submit the annual report?</SUBJECT>
                <SECTNO>60.1410</SECTNO>
                <SUBJECT>What must I include in my annual report?</SUBJECT>
                <SECTNO>60.1415</SECTNO>
                <SUBJECT>What must I do if I am out of compliance with the requirements of this subpart?</SUBJECT>
                <SECTNO>60.1420</SECTNO>
                <SUBJECT>If a semiannual report is required, when must I submit it?</SUBJECT>
                <SECTNO>60.1425</SECTNO>
                <SUBJECT>What must I include in the semiannual out-of-compliance reports?</SUBJECT>
                <SECTNO>60.1430</SECTNO>
                <SUBJECT>Can reporting dates be changed?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Air Curtain Incinerators That Burn 100 Percent Yard Waste</HD>
                <SECTNO>60.1435</SECTNO>
                <SUBJECT>What is an air curtain incinerator?</SUBJECT>
                <SECTNO>60.1440</SECTNO>
                <SUBJECT>What is yard waste?</SUBJECT>
                <SECTNO>60.1445</SECTNO>
                <SUBJECT>What are the emission limits for air curtain incinerators that burn 100 percent yard waste?</SUBJECT>
                <SECTNO>60.1450</SECTNO>
                <SUBJECT>How must I monitor opacity for air curtain incinerators that burn 100 percent yard waste?</SUBJECT>
                <SECTNO>60.1455</SECTNO>
                <SUBJECT>What are the recordkeeping and reporting requirements for air curtain incinerators that burn 100 percent yard waste?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Equations</HD>
                <SECTNO>60.1460</SECTNO>
                <SUBJECT>What equations must I use?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Definitions</HD>
                <SECTNO>60.1465</SECTNO>
                <SUBJECT>What definitions must I know?</SUBJECT>
                <APP>Table 1 of Subpart AAAA—Emission Limits For New Small Municipal Waste Combustion Units</APP>
                <APP>Table 2 of Subpart AAAA—Carbon Monoxide Emission Limits For New Small Municipal Waste Combustion Units</APP>
                <APP>Table 3 of Subpart AAAA—Requirements For Validating Continuous Emission Monitoring Systems (CEMS)</APP>
                <APP>Table 4 of Subpart AAAA—Requirements For Continuous Emission Monitoring Systems (CEMS)</APP>
                <APP>Table 5 of Subpart AAAA—Requirements For Stack Tests</APP>
              </SUBJGRP>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart BBBB—Emission Guidelines and Compliance Times for Small Municipal Waste Combustion Units Constructed on or Before August 30, 1999</HD>
              <SUBJGRP>
                <HD SOURCE="HED">Introduction</HD>
                <SECTNO>60.1500</SECTNO>
                <SUBJECT>What is the purpose of this subpart?</SUBJECT>
                <SECTNO>60.1505</SECTNO>
                <SUBJECT>Am I affected by this subpart?</SUBJECT>
                <SECTNO>60.1510</SECTNO>
                <SUBJECT>Is a State plan required for all States?</SUBJECT>
                <SECTNO>60.1515</SECTNO>
                <SUBJECT>What must I include in my State plan?</SUBJECT>
                <SECTNO>60.1520</SECTNO>
                <SUBJECT>Is there an approval process for my State plan?</SUBJECT>
                <SECTNO>60.1525</SECTNO>
                <SUBJECT>What if my State plan is not approvable?</SUBJECT>
                <SECTNO>60.1530</SECTNO>
                <SUBJECT>Is there an approval process for a negative declaration letter?</SUBJECT>
                <SECTNO>60.1535</SECTNO>
                <SUBJECT>What compliance schedule must I include in my State plan?</SUBJECT>
                <SECTNO>60.1540</SECTNO>

                <SUBJECT>Are there any State plan requirements for this subpart that supersede the requirements specified in subpart B?<PRTPAGE P="17"/>
                </SUBJECT>
                <SECTNO>60.1545</SECTNO>
                <SUBJECT>Does this subpart directly affect municipal waste combustion unit owners and operators in my State?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Applicability of State Plans</HD>
                <SECTNO>60.1550</SECTNO>
                <SUBJECT>What municipal waste combustion units must I address in my State plan?</SUBJECT>
                <SECTNO>60.1555</SECTNO>
                <SUBJECT>Are any small municipal waste combustion units exempt from my State plan?</SUBJECT>
                <SECTNO>60.1560</SECTNO>
                <SUBJECT>Can an affected municipal waste combustion unit reduce its capacity to less than 35 tons per day rather than comply with my State plan?</SUBJECT>
                <SECTNO>60.1565</SECTNO>
                <SUBJECT>What subcategories of small municipal waste combustion units must I include in my State plan?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Use of Model Rule</HD>
                <SECTNO>60.1570</SECTNO>
                <SUBJECT>What is the “model rule” in this subpart?</SUBJECT>
                <SECTNO>60.1575</SECTNO>
                <SUBJECT>How does the model rule relate to the required elements of my State plan?</SUBJECT>
                <SECTNO>60.1580</SECTNO>
                <SUBJECT>What are the principal components of the model rule?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Model Rule—Increments of Progress</HD>
                <SECTNO>60.1585</SECTNO>
                <SUBJECT>What are my requirements for meeting increments of progress and achieving final compliance?</SUBJECT>
                <SECTNO>60.1590</SECTNO>
                <SUBJECT>When must I complete each increment of progress?</SUBJECT>
                <SECTNO>60.1595</SECTNO>
                <SUBJECT>What must I include in the notifications of achievement of my increments of progress?</SUBJECT>
                <SECTNO>60.1600</SECTNO>
                <SUBJECT>When must I submit the notifications of achievement of increments of progress?</SUBJECT>
                <SECTNO>60.1605</SECTNO>
                <SUBJECT>What if I do not meet an increment of progress?</SUBJECT>
                <SECTNO>60.1610</SECTNO>
                <SUBJECT>How do I comply with the increment of progress for submittal of a control plan?</SUBJECT>
                <SECTNO>60.1615</SECTNO>
                <SUBJECT>How do I comply with the increment of progress for awarding contracts?</SUBJECT>
                <SECTNO>60.1620</SECTNO>
                <SUBJECT>How do I comply with the increment of progress for initiating onsite construction?</SUBJECT>
                <SECTNO>60.1625</SECTNO>
                <SUBJECT>How do I comply with the increment of progress for completing onsite construction?</SUBJECT>
                <SECTNO>60.1630</SECTNO>
                <SUBJECT>How do I comply with the increment of progress for achieving final compliance?</SUBJECT>
                <SECTNO>60.1635</SECTNO>
                <SUBJECT>What must I do if I close my municipal waste combustion unit and then restart my municipal waste combustion unit?</SUBJECT>
                <SECTNO>60.1640</SECTNO>
                <SUBJECT>What must I do if I plan to permanently close my municipal waste combustion unit and not restart it?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Model Rule—Good Combustion Practices: Operator Training</HD>
                <SECTNO>60.1645</SECTNO>
                <SUBJECT>What types of training must I do?</SUBJECT>
                <SECTNO>60.1650</SECTNO>
                <SUBJECT>Who must complete the operator training course? By when?</SUBJECT>
                <SECTNO>60.1655</SECTNO>
                <SUBJECT>Who must complete the plant-specific training course?</SUBJECT>
                <SECTNO>60.1660</SECTNO>
                <SUBJECT>What plant-specific training must I provide?</SUBJECT>
                <SECTNO>60.1665</SECTNO>
                <SUBJECT>What information must I include in the plant-specific operating manual?</SUBJECT>
                <SECTNO>60.1670</SECTNO>
                <SUBJECT>Where must I keep the plant-specific operating manual?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Model Rule—Good Combustion Practices: Operator Certification</HD>
                <SECTNO>60.1675</SECTNO>
                <SUBJECT>What types of operator certification must the chief facility operator and shift supervisor obtain and by when must they obtain it?</SUBJECT>
                <SECTNO>60.1680</SECTNO>
                <SUBJECT>After the required date for operator certification, who may operate the municipal waste combustion unit?</SUBJECT>
                <SECTNO>60.1685</SECTNO>
                <SUBJECT>What if all the certified operators must be temporarily offsite?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Model Rule—Good Combustion Practices: Operating Requirements</HD>
                <SECTNO>60.1690</SECTNO>
                <SUBJECT>What are the operating practice requirements for my municipal waste combustion unit?</SUBJECT>
                <SECTNO>60.1695</SECTNO>
                <SUBJECT>What happens to the operating requirements during periods of startup, shutdown, and malfunction?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Model Rule—Emission Limits</HD>
                <SECTNO>60.1700</SECTNO>
                <SUBJECT>What pollutants are regulated by this subpart?</SUBJECT>
                <SECTNO>60.1705</SECTNO>
                <SUBJECT>What emission limits must I meet? By when?</SUBJECT>
                <SECTNO>60.1710</SECTNO>
                <SUBJECT>What happens to the emission limits during periods of startup, shutdown, and malfunction?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Model Rule—Continuous Emission Monitoring</HD>
                <SECTNO>60.1715</SECTNO>
                <SUBJECT>What types of continuous emission monitoring must I perform?</SUBJECT>
                <SECTNO>60.1720</SECTNO>
                <SUBJECT>What continuous emission monitoring systems must I install for gaseous pollutants?</SUBJECT>
                <SECTNO>60.1725</SECTNO>
                <SUBJECT>How are the data from the continuous emission monitoring systems used?</SUBJECT>
                <SECTNO>60.1730</SECTNO>
                <SUBJECT>How do I make sure my continuous emission monitoring systems are operating correctly?</SUBJECT>
                <SECTNO>60.1735</SECTNO>
                <SUBJECT>Am I exempt from any appendix B or appendix F requirements to evaluate continuous emission monitoring systems?</SUBJECT>
                <SECTNO>60.1740</SECTNO>
                <SUBJECT>What is my schedule for evaluating continuous emission monitoring systems?</SUBJECT>
                <SECTNO>60.1745</SECTNO>
                <SUBJECT>What must I do if I choose to monitor carbon dioxide instead of oxygen as a diluent gas?</SUBJECT>
                <SECTNO>60.1750</SECTNO>

                <SUBJECT>What is the minimum amount of monitoring data I must collect with my continuous emission monitoring systems <PRTPAGE P="18"/>and is the data collection requirement enforceable?</SUBJECT>
                <SECTNO>60.1755</SECTNO>
                <SUBJECT>How do I convert my 1-hour arithmetic averages into appropriate averaging times and units?</SUBJECT>
                <SECTNO>60.1760</SECTNO>
                <SUBJECT>What is required for my continuous opacity monitoring system and how are the data used?</SUBJECT>
                <SECTNO>60.1765</SECTNO>
                <SUBJECT>What additional requirements must I meet for the operation of my continuous emission monitoring systems and continuous opacity monitoring system?</SUBJECT>
                <SECTNO>60.1770</SECTNO>
                <SUBJECT>What must I do if any of my continuous emission monitoring systems are temporarily unavailable to meet the data collection requirements?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Model Rule—Stack Testing</HD>
                <SECTNO>60.1775</SECTNO>
                <SUBJECT>What types of stack tests must I conduct?</SUBJECT>
                <SECTNO>60.1780</SECTNO>
                <SUBJECT>How are the stack test data used?</SUBJECT>
                <SECTNO>60.1785</SECTNO>
                <SUBJECT>What schedule must I follow for the stack testing?</SUBJECT>
                <SECTNO>60.1790</SECTNO>
                <SUBJECT>What test methods must I use to stack test?</SUBJECT>
                <SECTNO>60.1795</SECTNO>
                <SUBJECT>May I conduct stack testing less often?</SUBJECT>
                <SECTNO>60.1800</SECTNO>
                <SUBJECT>May I deviate from the 13-month testing schedule if unforeseen circumstances arise?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Model Rule—Other Monitoring Requirements</HD>
                <SECTNO>60.1805</SECTNO>
                <SUBJECT>Must I meet other requirements for continuous monitoring?</SUBJECT>
                <SECTNO>60.1810</SECTNO>
                <SUBJECT>How do I monitor the load of my municipal waste combustion unit?</SUBJECT>
                <SECTNO>60.1815</SECTNO>
                <SUBJECT>How do I monitor the temperature of flue gases at the inlet of my particulate matter control device?</SUBJECT>
                <SECTNO>60.1820</SECTNO>
                <SUBJECT>How do I monitor the injection rate of activated carbon?</SUBJECT>
                <SECTNO>60.1825</SECTNO>
                <SUBJECT>What is the minimum amount of monitoring data I must collect with my continuous parameter monitoring systems and is the data collection requirement enforceable?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Model Rule—Recordkeeping</HD>
                <SECTNO>60.1830</SECTNO>
                <SUBJECT>What records must I keep?</SUBJECT>
                <SECTNO>60.1835</SECTNO>
                <SUBJECT>Where must I keep my records and for how long?</SUBJECT>
                <SECTNO>60.1840</SECTNO>
                <SUBJECT>What records must I keep for operator training and certification?</SUBJECT>
                <SECTNO>60.1845</SECTNO>
                <SUBJECT>What records must I keep for stack tests?</SUBJECT>
                <SECTNO>60.1850</SECTNO>
                <SUBJECT>What records must I keep for continuously monitored pollutants or parameters?</SUBJECT>
                <SECTNO>60.1855</SECTNO>
                <SUBJECT>What records must I keep for municipal waste combustion units that use activated carbon?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Model Rule—Reporting</HD>
                <SECTNO>60.1860</SECTNO>
                <SUBJECT>What reports must I submit and in what form?</SUBJECT>
                <SECTNO>60.1865</SECTNO>
                <SUBJECT>What are the appropriate units of measurement for reporting my data?</SUBJECT>
                <SECTNO>60.1870</SECTNO>
                <SUBJECT>When must I submit the initial report?</SUBJECT>
                <SECTNO>60.1875</SECTNO>
                <SUBJECT>What must I include in my initial report?</SUBJECT>
                <SECTNO>60.1880</SECTNO>
                <SUBJECT>When must I submit the annual report?</SUBJECT>
                <SECTNO>60.1885</SECTNO>
                <SUBJECT>What must I include in my annual report?</SUBJECT>
                <SECTNO>60.1890</SECTNO>
                <SUBJECT>What must I do if I am out of compliance with the requirements of this subpart?</SUBJECT>
                <SECTNO>60.1895</SECTNO>
                <SUBJECT>If a semiannual report is required, when must I submit it?</SUBJECT>
                <SECTNO>60.1900</SECTNO>
                <SUBJECT>What must I include in the semiannual out-of-compliance reports?</SUBJECT>
                <SECTNO>60.1905</SECTNO>
                <SUBJECT>Can reporting dates be changed?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Model Rule—Air Curtain Incinerators That Burn 100 Percent Yard Waste</HD>
                <SECTNO>60.1910</SECTNO>
                <SUBJECT>What is an air curtain incinerator?</SUBJECT>
                <SECTNO>60.1915</SECTNO>
                <SUBJECT>What is yard waste?</SUBJECT>
                <SECTNO>60.1920</SECTNO>
                <SUBJECT>What are the emission limits for air curtain incinerators that burn 100 percent yard waste?</SUBJECT>
                <SECTNO>60.1925</SECTNO>
                <SUBJECT>How must I monitor opacity for air curtain incinerators that burn 100 percent yard waste?</SUBJECT>
                <SECTNO>60.1930</SECTNO>
                <SUBJECT>What are the recordkeeping and reporting requirements for air curtain incinerators that burn 100 percent yard waste?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Equations</HD>
                <SECTNO>60.1935</SECTNO>
                <SUBJECT>What equations must I use?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Definitions</HD>
                <SECTNO>60.1940</SECTNO>
                <SUBJECT>What definitions must I know?</SUBJECT>
                <APP>Table 1 of Subpart BBBB—Model Rule—Compliance Schedules and Increments of Progress</APP>
                <APP>Table 2 of Subpart BBBB—Model Rule—Class I Emission Limits For Existing Small Municipal Waste Combustion Units</APP>
                <APP>Table 3 of Subpart BBBB—Model Rule—Class I Nitrogen Oxides Emission Limits For Existing Small Municipal Waste Combustion Units</APP>
                <APP>Table 4 of Subpart BBBB—Model Rule—Class II Emission Limits For Existing Small Municipal Waste Combustion Units</APP>
                <APP>Table 5 of Subpart BBBB—Model Rule—Carbon Monoxide Emission Limits For Existing Small Municipal Waste Combustion Units</APP>
                <APP>Table 6 of Subpart BBBB—Model Rule—Requirements for Validating Continuous Emission Monitoring Systems (CEMS)</APP>

                <APP>Table 7 of Subpart BBBB—Model Rule—Requirements for Continuous Emission Monitoring Systems (CEMS)<PRTPAGE P="19"/>
                </APP>
                <APP>Table 8 of Subpart BBBB—Model Rule—Requirements for Stack Tests</APP>
              </SUBJGRP>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart CCCC—Standards of Performance for Commercial and Industrial Solid Waste Incineration Units for Which Construction Is Commenced After November 30, 1999 or for Which Modification or Reconstruction Is Commenced on or After June 1, 2001</HD>
              <SUBJGRP>
                <HD SOURCE="HED">Introduction</HD>
                <SECTNO>60.2000</SECTNO>
                <SUBJECT>What does this subpart do?</SUBJECT>
                <SECTNO>60.2005</SECTNO>
                <SUBJECT>When does this subpart become effective?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Applicability</HD>
                <SECTNO>60.2010</SECTNO>
                <SUBJECT>Does this subpart apply to my incineration unit?</SUBJECT>
                <SECTNO>60.2015</SECTNO>
                <SUBJECT>What is a new incineration unit?</SUBJECT>
                <SECTNO>60.2020</SECTNO>
                <SUBJECT>What combustion units are exempt from this subpart?</SUBJECT>
                <SECTNO>60.2025</SECTNO>
                <SUBJECT>What if my chemical recovery unit is not listed in § 60.2020(n)?</SUBJECT>
                <SECTNO>60.2030</SECTNO>
                <SUBJECT>Who implements and enforces this subpart?</SUBJECT>
                <SECTNO>60.2035</SECTNO>
                <SUBJECT>How are these new source performance standards structured?</SUBJECT>
                <SECTNO>60.2040</SECTNO>
                <SUBJECT>Do all eleven components of the new source performance standards apply at the same time?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Preconstruction Siting Analysis</HD>
                <SECTNO>60.2045</SECTNO>
                <SUBJECT>Who must prepare a siting analysis?</SUBJECT>
                <SECTNO>60.2050</SECTNO>
                <SUBJECT>What is a siting analysis?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Waste Management Plan</HD>
                <SECTNO>60.2055</SECTNO>
                <SUBJECT>What is a waste management plan?</SUBJECT>
                <SECTNO>60.2060</SECTNO>
                <SUBJECT>When must I submit my waste management plan?</SUBJECT>
                <SECTNO>60.2065</SECTNO>
                <SUBJECT>What should I include in my waste management plan?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Operator Training and Qualification</HD>
                <SECTNO>60.2070</SECTNO>
                <SUBJECT>What are the operator training and qualification requirements?</SUBJECT>
                <SECTNO>60.2075</SECTNO>
                <SUBJECT>When must the operator training course be completed?</SUBJECT>
                <SECTNO>60.2080</SECTNO>
                <SUBJECT>How do I obtain my operator qualification?</SUBJECT>
                <SECTNO>60.2085</SECTNO>
                <SUBJECT>How do I maintain my operator qualification?</SUBJECT>
                <SECTNO>60.2090</SECTNO>
                <SUBJECT>How do I renew my lapsed operator qualification?</SUBJECT>
                <SECTNO>60.2095</SECTNO>
                <SUBJECT>What site-specific documentation is required?</SUBJECT>
                <SECTNO>60.2100</SECTNO>
                <SUBJECT>What if all the qualified operators are temporarily not accessible?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Emission Limitations and Operating Limits</HD>
                <SECTNO>60.2105</SECTNO>
                <SUBJECT>What emission limitations must I meet and by when?</SUBJECT>
                <SECTNO>60.2110</SECTNO>
                <SUBJECT>What operating limits must I meet and by when?</SUBJECT>
                <SECTNO>60.2115</SECTNO>
                <SUBJECT>What if I do not use a wet scrubber to comply with the emission limitations?</SUBJECT>
                <SECTNO>60.2120</SECTNO>
                <SUBJECT>What happens during periods of startup, shutdown, and malfunction?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Performance Testing</HD>
                <SECTNO>60.2125</SECTNO>
                <SUBJECT>How do I conduct the initial and annual performance test?</SUBJECT>
                <SECTNO>60.2130</SECTNO>
                <SUBJECT>How are the performance test data used?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Initial Compliance Requirements</HD>
                <SECTNO>60.2135</SECTNO>
                <SUBJECT>How do I demonstrate initial compliance with the emission limitations and establish the operating limits?</SUBJECT>
                <SECTNO>60.2140</SECTNO>
                <SUBJECT>By what date must I conduct the initial performance test?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Continuous Compliance Requirements</HD>
                <SECTNO>60.2145</SECTNO>
                <SUBJECT>How do I demonstrate continuous compliance with the emission limitations and the operating limits?</SUBJECT>
                <SECTNO>60.2150</SECTNO>
                <SUBJECT>By what date must I conduct the annual performance test?</SUBJECT>
                <SECTNO>60.2155</SECTNO>
                <SUBJECT>May I conduct performance testing less often?</SUBJECT>
                <SECTNO>60.2160</SECTNO>
                <SUBJECT>May I conduct a repeat performance test to establish new operating limits?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Monitoring</HD>
                <SECTNO>60.2165</SECTNO>
                <SUBJECT>What monitoring equipment must I install and what parameters must I monitor?</SUBJECT>
                <SECTNO>60.2170</SECTNO>
                <SUBJECT>Is there a minimum amount of monitoring data I must obtain?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Recordkeeping and Reporting</HD>
                <SECTNO>60.2175</SECTNO>
                <SUBJECT>What records must I keep?</SUBJECT>
                <SECTNO>60.2180</SECTNO>
                <SUBJECT>Where and in what format must I keep my records?</SUBJECT>
                <SECTNO>60.2185</SECTNO>
                <SUBJECT>What reports must I submit?</SUBJECT>
                <SECTNO>60.2190</SECTNO>
                <SUBJECT>What must I submit prior to commencing construction?</SUBJECT>
                <SECTNO>60.2195</SECTNO>
                <SUBJECT>What information must I submit prior to initial startup?</SUBJECT>
                <SECTNO>60.2200</SECTNO>
                <SUBJECT>What information must I submit following my initial performance test?</SUBJECT>
                <SECTNO>60.2205</SECTNO>
                <SUBJECT>When must I submit my annual report?</SUBJECT>
                <SECTNO>60.2210</SECTNO>
                <SUBJECT>What information must I include in my annual report?</SUBJECT>
                <SECTNO>60.2215</SECTNO>
                <SUBJECT>What else must I report if I have a deviation from the operating limits or the emission limitations?</SUBJECT>
                <SECTNO>60.2220</SECTNO>
                <SUBJECT>What must I include in the deviation report?</SUBJECT>
                <SECTNO>60.2225</SECTNO>
                <SUBJECT>What else must I report if I have a deviation from the requirement to have a qualified operator accessible?</SUBJECT>
                <SECTNO>60.2230</SECTNO>
                <SUBJECT>Are there any other notifications or reports that I must submit?</SUBJECT>
                <SECTNO>60.2235</SECTNO>
                <SUBJECT>In what form can I submit my reports?</SUBJECT>
                <SECTNO>60.2240</SECTNO>
                <SUBJECT>Can reporting dates be changed?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <PRTPAGE P="20"/>
                <HD SOURCE="HED">Title V Operating Permits</HD>
                <SECTNO>60.2242</SECTNO>
                <SUBJECT>Am I required to apply for and obtain a title V operating permit for my unit?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Air Curtain Incinerators</HD>
                <SECTNO>60.2245</SECTNO>
                <SUBJECT>What is an air curtain incinerator?</SUBJECT>
                <SECTNO>60.2250</SECTNO>
                <SUBJECT>What are the emission limitations for air curtain incinerators?</SUBJECT>
                <SECTNO>60.2255</SECTNO>
                <SUBJECT>How must I monitor opacity for air curtain incinerators?</SUBJECT>
                <SECTNO>60.2260</SECTNO>
                <SUBJECT>What are the recordkeeping and reporting requirements for air curtain incinerators?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Definitions</HD>
                <SECTNO>60.2265</SECTNO>
                <SUBJECT>What definitions must I know?</SUBJECT>
                <APP>Table 1 to Subpart CCCC—Emission Limitations</APP>
                <APP>Table 2 to Subpart CCCC—Operating Limits for Wet Scrubbers</APP>
                <APP>Table 3 to Subpart CCCC—Toxic Equivalency Factors</APP>
                <APP>Table 4 to Subpart CCCC—Summary of Reporting Requirements</APP>
              </SUBJGRP>
            </SUBPART>
            <SUBPART>
              <HD SOURCE="HED">Subpart DDDD—Emissions Guidelines and Compliance Times for Commercial and Industrial Solid Waste Incineration Units that Commenced Construction On or Before November 30, 1999</HD>
              <SUBJGRP>
                <HD SOURCE="HED">Introduction</HD>
                <SECTNO>60.2500</SECTNO>
                <SUBJECT>What is the purpose of this subpart?</SUBJECT>
                <SECTNO>60.2505</SECTNO>
                <SUBJECT>Am I affected by this subpart?</SUBJECT>
                <SECTNO>60.2510</SECTNO>
                <SUBJECT>Is a State plan required for all States?</SUBJECT>
                <SECTNO>60.2515</SECTNO>
                <SUBJECT>What must I include in my State plan?</SUBJECT>
                <SECTNO>60.2520</SECTNO>
                <SUBJECT>Is there an approval process for my State plan?</SUBJECT>
                <SECTNO>60.2525</SECTNO>
                <SUBJECT>What if my State plan is not approvable?</SUBJECT>
                <SECTNO>60.2530</SECTNO>
                <SUBJECT>Is there an approval process for a negative declaration letter?</SUBJECT>
                <SECTNO>60.2535</SECTNO>
                <SUBJECT>What compliance schedule must I include in my State plan?</SUBJECT>
                <SECTNO>60.2540</SECTNO>
                <SUBJECT>Are there any State plan requirements for this subpart that apply instead of the requirements specified in subpart B?</SUBJECT>
                <SECTNO>60.2545</SECTNO>
                <SUBJECT>Does this subpart directly affect CISWI unit owners and operators in my State?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Applicability of State Plans</HD>
                <SECTNO>60.2550</SECTNO>
                <SUBJECT>What CISWI units must I address in my State plan?</SUBJECT>
                <SECTNO>60.2555</SECTNO>
                <SUBJECT>What combustion units are exempt from my State plan?</SUBJECT>
                <SECTNO>60.2558</SECTNO>
                <SUBJECT>What if a chemical recovery unit is not listed in § 60.2555(n)?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Use of Model Rule</HD>
                <SECTNO>60.2560</SECTNO>
                <SUBJECT>What is the “model rule” in this subpart?</SUBJECT>
                <SECTNO>60.2565</SECTNO>
                <SUBJECT>How does the model rule relate to the required elements of my State plan?</SUBJECT>
                <SECTNO>60.2570</SECTNO>
                <SUBJECT>What are the principal components of the model rule?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Model Rule—Increments of Progress</HD>
                <SECTNO>60.2575</SECTNO>
                <SUBJECT>What are my requirements for meeting increments of progress and achieving final compliance?</SUBJECT>
                <SECTNO>60.2580</SECTNO>
                <SUBJECT>When must I complete each increment of progress?</SUBJECT>
                <SECTNO>60.2585</SECTNO>
                <SUBJECT>What must I include in the notifications of achievement of increments of progress?</SUBJECT>
                <SECTNO>60.2590</SECTNO>
                <SUBJECT>When must I submit the notifications of achievement of increments of progress?</SUBJECT>
                <SECTNO>60.2595</SECTNO>
                <SUBJECT>What if I do not meet an increment of progress?</SUBJECT>
                <SECTNO>60.2600</SECTNO>
                <SUBJECT>How do I comply with the increment of progress for submittal of a control plan?</SUBJECT>
                <SECTNO>60.2605</SECTNO>
                <SUBJECT>How do I comply with the increment of progress for achieving final compliance?</SUBJECT>
                <SECTNO>60.2610</SECTNO>
                <SUBJECT>What must I do if I close my CISWI unit and then restart it?</SUBJECT>
                <SECTNO>60.2615</SECTNO>
                <SUBJECT>What must I do if I plan to permanently close my CISWI unit and not restart it?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Model Rule—Waste Management Plan</HD>
                <SECTNO>60.2620</SECTNO>
                <SUBJECT>What is a waste management plan?</SUBJECT>
                <SECTNO>60.2625</SECTNO>
                <SUBJECT>When must I submit my waste management plan?</SUBJECT>
                <SECTNO>60.2630</SECTNO>
                <SUBJECT>What should I include in my waste management plan?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Model Rule—Operator Training and Qualification</HD>
                <SECTNO>60.2635</SECTNO>
                <SUBJECT>What are the operator training and qualification requirements?</SUBJECT>
                <SECTNO>60.2640</SECTNO>
                <SUBJECT>When must the operator training course be completed?</SUBJECT>
                <SECTNO>60.2645</SECTNO>
                <SUBJECT>How do I obtain my operator qualification?</SUBJECT>
                <SECTNO>60.2650</SECTNO>
                <SUBJECT>How do I maintain my operator qualification?</SUBJECT>
                <SECTNO>60.2655</SECTNO>
                <SUBJECT>How do I renew my lapsed operator qualification?</SUBJECT>
                <SECTNO>60.2660</SECTNO>
                <SUBJECT>What site-specific documentation is required?</SUBJECT>
                <SECTNO>60.2665</SECTNO>
                <SUBJECT>What if all the qualified operators are temporarily not accessible?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Model Rule—Emission Limitations and Operating Limits</HD>
                <SECTNO>60.2670</SECTNO>
                <SUBJECT>What emission limitations must I meet and by when?</SUBJECT>
                <SECTNO>60.2675</SECTNO>
                <SUBJECT>What operating limits must I meet and by when?</SUBJECT>
                <SECTNO>60.2680</SECTNO>

                <SUBJECT>What if I do not use a wet scrubber to comply with the emission limitations?<PRTPAGE P="21"/>
                </SUBJECT>
                <SECTNO>60.2685</SECTNO>
                <SUBJECT>What happens during periods of startup, shutdown, and malfunction?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Model Rule—Performance Testing</HD>
                <SECTNO>60.2690</SECTNO>
                <SUBJECT>How do I conduct the initial and annual performance test?</SUBJECT>
                <SECTNO>60.2695</SECTNO>
                <SUBJECT>How are the performance test data used?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Model Rule—Initial Compliance Requirements</HD>
                <SECTNO>60.2700</SECTNO>
                <SUBJECT>How do I demonstrate initial compliance with the emission limitations and establish the operating limits?</SUBJECT>
                <SECTNO>60.2705</SECTNO>
                <SUBJECT>By what date must I conduct the initial performance test?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Model Rule—Continuous Compliance Requirements</HD>
                <SECTNO>60.2710</SECTNO>
                <SUBJECT>How do I demonstrate continuous compliance with the emission limitations and the operating limits?</SUBJECT>
                <SECTNO>60.2715</SECTNO>
                <SUBJECT>By what date must I conduct the annual performance test?</SUBJECT>
                <SECTNO>60.2720</SECTNO>
                <SUBJECT>May I conduct performance testing less often?</SUBJECT>
                <SECTNO>60.2725</SECTNO>
                <SUBJECT>May I conduct a repeat performance test to establish new operating limits?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Model Rule—Monitoring</HD>
                <SECTNO>60.2730</SECTNO>
                <SUBJECT>What monitoring equipment must I install and what parameters must I monitor?</SUBJECT>
                <SECTNO>60.2735</SECTNO>
                <SUBJECT>Is there a minimum amount of monitoring data I must obtain?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Model Rule—Recordkeeping and Reporting</HD>
                <SECTNO>60.2740</SECTNO>
                <SUBJECT>What records must I keep?</SUBJECT>
                <SECTNO>60.2745</SECTNO>
                <SUBJECT>Where and in what format must I keep my records?</SUBJECT>
                <SECTNO>60.2750</SECTNO>
                <SUBJECT>What reports must I submit?</SUBJECT>
                <SECTNO>60.2755</SECTNO>
                <SUBJECT>When must I submit my waste management plan?</SUBJECT>
                <SECTNO>60.2760</SECTNO>
                <SUBJECT>What information must I submit following my initial performance test?</SUBJECT>
                <SECTNO>60.2765</SECTNO>
                <SUBJECT>When must I submit my annual report?</SUBJECT>
                <SECTNO>60.2770</SECTNO>
                <SUBJECT>What information must I include in my annual report?</SUBJECT>
                <SECTNO>60.2775</SECTNO>
                <SUBJECT>What else must I report if I have a deviation from the operating limits or the emission limitations?</SUBJECT>
                <SECTNO>60.2780</SECTNO>
                <SUBJECT>What must I include in the deviation report?</SUBJECT>
                <SECTNO>60.2785</SECTNO>
                <SUBJECT>What else must I report if I have a deviation from the requirement to have a qualified operator accessible?</SUBJECT>
                <SECTNO>60.2790</SECTNO>
                <SUBJECT>Are there any other notifications or reports that I must submit?</SUBJECT>
                <SECTNO>60.2795</SECTNO>
                <SUBJECT>In what form can I submit my reports?</SUBJECT>
                <SECTNO>60.2800</SECTNO>
                <SUBJECT>Can reporting dates be changed?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Model Rule—Title V Operating Permits</HD>
                <SECTNO>60.2805</SECTNO>
                <SUBJECT>Am I required to apply for and obtain a title V operating permit for my unit?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Model Rule—Air Curtain Incinerators</HD>
                <SECTNO>60.2810</SECTNO>
                <SUBJECT>What is an air curtain incinerator?</SUBJECT>
                <SECTNO>60.2815</SECTNO>
                <SUBJECT>What are my requirements for meeting increments of progress and achieving final compliance?</SUBJECT>
                <SECTNO>60.2820</SECTNO>
                <SUBJECT>When must I complete each increment of progress?</SUBJECT>
                <SECTNO>60.2825</SECTNO>
                <SUBJECT>What must I include in the notifications of achievement of increments of progress?</SUBJECT>
                <SECTNO>60.2830</SECTNO>
                <SUBJECT>When must I submit the notifications of achievement of increments of progress?</SUBJECT>
                <SECTNO>60.2835</SECTNO>
                <SUBJECT>What if I do not meet an increment of progress?</SUBJECT>
                <SECTNO>60.2840</SECTNO>
                <SUBJECT>How do I comply with the increment of progress for submittal of a control plan?</SUBJECT>
                <SECTNO>60.2845</SECTNO>
                <SUBJECT>How do I comply with the increment of progress for achieving final compliance?</SUBJECT>
                <SECTNO>60.2850</SECTNO>
                <SUBJECT>What must I do if I close my air curtain incinerator and then restart it?</SUBJECT>
                <SECTNO>60.2855</SECTNO>
                <SUBJECT>What must I do if I plan to permanently close my air curtain incinerator and not restart it?</SUBJECT>
                <SECTNO>60.2860</SECTNO>
                <SUBJECT>What are the emission limitations for air curtain incinerators?</SUBJECT>
                <SECTNO>60.2865</SECTNO>
                <SUBJECT>How must I monitor opacity for air curtain incinerators?</SUBJECT>
                <SECTNO>60.2870</SECTNO>
                <SUBJECT>What are the recordkeeping and reporting requirements for air curtain incinerators?</SUBJECT>
              </SUBJGRP>
              <SUBJGRP>
                <HD SOURCE="HED">Model Rule—Definitions</HD>
                <SECTNO>60.2875</SECTNO>
                <SUBJECT>What definitions must I know?</SUBJECT>
                <APP>Table 1 to Subpart DDDD—Model Rule—Increments of Progress and Compliance Schedules</APP>
                <APP>Table 2 to Subpart DDDD—Model Rule—Emission Limitations</APP>
                <APP>Table 3 to Subpart DDDD—Model Rule—Operating Limits for Wet Scrubbers</APP>
                <APP>Table 4 to Subpart DDDD—Model Rule—Toxic Equivalency Factors</APP>
                <APP>Table 5 to Subpart DDDD—Model Rule—Summary of Reporting Requirements</APP>
              </SUBJGRP>
            </SUBPART>
          </CONTENTS>
          <AUTH>
            <HD SOURCE="HED">Authority:</HD>
            <P>42 U.S.C. 7401 <E T="03">et seq.</E>
            </P>
          </AUTH>
          <SOURCE>
            <HD SOURCE="HED">Source:</HD>
            <P>36 FR 24877, Dec. 23, 1971, unless otherwise noted.</P>
          </SOURCE>
          <SUBPART>
            <HD SOURCE="HED">Subpart A—General Provisions</HD>
            <SECTION>
              <SECTNO>§ 60.1</SECTNO>
              <SUBJECT>Applicability.</SUBJECT>

              <P>(a) Except as provided in subparts B and C, the provisions of this part apply <PRTPAGE P="22"/>to the owner or operator of any stationary source which contains an affected facility, the construction or modification of which is commenced after the date of publication in this part of any standard (or, if earlier, the date of publication of any proposed standard) applicable to that facility.</P>
              <P>(b) Any new or revised standard of performance promulgated pursuant to section 111(b) of the Act shall apply to the owner or operator of any stationary source which contains an affected facility, the construction or modification of which is commenced after the date of publication in this part of such new or revised standard (or, if earlier, the date of publication of any proposed standard) applicable to that facility.</P>
              <P>(c) In addition to complying with the provisions of this part, the owner or operator of an affected facility may be required to obtain an operating permit issued to stationary sources by an authorized State air pollution control agency or by the Administrator of the U.S. Environmental Protection Agency (EPA) pursuant to Title V of the Clean Air Act (Act) as amended November 15, 1990 (42 U.S.C. 7661). For more information about obtaining an operating permit see part 70 of this chapter.</P>
              <P>(d) <E T="03">Site-specific standard for Merck &amp; Co., Inc.'s Stonewall Plant in Elkton, Virginia.</E> (1) This paragraph applies only to the pharmaceutical manufacturing facility, commonly referred to as the Stonewall Plant, located at Route 340 South, in Elkton, Virginia (“site”).</P>
              <P>(2) Except for compliance with 40 CFR 60.49b(u), the site shall have the option of either complying directly with the requirements of this part, or reducing the site-wide emissions caps in accordance with the procedures set forth in a permit issued pursuant to 40 CFR 52.2454. If the site chooses the option of reducing the site-wide emissions caps in accordance with the procedures set forth in such permit, the requirements of such permit shall apply in lieu of the otherwise applicable requirements of this part.</P>
              <P>(3) Notwithstanding the provisions of paragraph (d)(2) of this section, for any provisions of this part except for Subpart Kb, the owner/operator of the site shall comply with the applicable provisions of this part if the Administrator determines that compliance with the provisions of this part is necessary for achieving the objectives of the regulation and the Administrator notifies the site in accordance with the provisions of the permit issued pursuant to 40 CFR 52.2454.</P>
              <CITA>[40 FR 53346, Nov. 17, 1975, as amended at 55 FR 51382, Dec. 13, 1990; 59 FR 12427, Mar. 16, 1994; 62 FR 52641, Oct. 8, 1997]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.2</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <P>The terms used in this part are defined in the Act or in this section as follows:</P>
              <P>
                <E T="03">Act</E> means the Clean Air Act (42 U.S.C. 7401 <E T="03">et seq.</E>)</P>
              <P>
                <E T="03">Administrator</E> means the Administrator of the Environmental Protection Agency or his authorized representative.</P>
              <P>
                <E T="03">Affected facility</E> means, with reference to a stationary source, any apparatus to which a standard is applicable.</P>
              <P>
                <E T="03">Alternative method</E> means any method of sampling and analyzing for an air pollutant which is not a reference or equivalent method but which has been demonstrated to the Administrator's satisfaction to, in specific cases, produce results adequate for his determination of compliance.</P>
              <P>
                <E T="03">Approved permit program</E> means a State permit program approved by the Administrator as meeting the requirements of part 70 of this chapter or a Federal permit program established in this chapter pursuant to Title V of the Act (42 U.S.C. 7661).</P>
              <P>
                <E T="03">Capital expenditure</E> means an expenditure for a physical or operational change to an existing facility which exceeds the product of the applicable “annual asset guideline repair allowance percentage” specified in the latest edition of Internal Revenue Service (IRS) Publication 534 and the existing facility's basis, as defined by section 1012 of the Internal Revenue Code. However, the total expenditure for a physical or operational change to an existing facility must not be reduced by any “excluded additions” as defined in IRS Publication 534, as would be done for tax purposes.<PRTPAGE P="23"/>
              </P>
              <P>
                <E T="03">Clean coal technology demonstration project</E> means a project using funds appropriated under the heading ‘Department of Energy-Clean Coal Technology’, up to a total amount of $2,500,000,000 for commercial demonstrations of clean coal technology, or similar projects funded through appropriations for the Environmental Protection Agency.</P>
              <P>
                <E T="03">Commenced</E> means, with respect to the definition of <E T="03">new source</E> in section 111(a)(2) of the Act, that an owner or operator has undertaken a continuous program of construction or modification or that an owner or operator has entered into a contractual obligation to undertake and complete, within a reasonable time, a continuous program of construction or modification.</P>
              <P>
                <E T="03">Construction</E> means fabrication, erection, or installation of an affected facility.</P>
              <P>
                <E T="03">Continuous monitoring system</E> means the total equipment, required under the emission monitoring sections in applicable subparts, used to sample and condition (if applicable), to analyze, and to provide a permanent record of emissions or process parameters.</P>
              <P>
                <E T="03">Electric utility steam generating unit</E> means any steam electric generating unit that is constructed for the purpose of supplying more than one-third of its potential electric output capacity and more than 25 MW electrical output to any utility power distribution system for sale. Any steam supplied to a steam distribution system for the purpose of providing steam to a steam-electric generator that would produce electrical energy for sale is also considered in determining the electrical energy output capacity of the affected facility.</P>
              <P>
                <E T="03">Equivalent method</E> means any method of sampling and analyzing for an air pollutant which has been demonstrated to the Administrator's satisfaction to have a consistent and quantitatively known relationship to the reference method, under specified conditions.</P>
              <P>
                <E T="03">Excess Emissions and Monitoring Systems Performance Report</E> is a report that must be submitted periodically by a source in order to provide data on its compliance with stated emission limits and operating parameters, and on the performance of its monitoring systems.</P>
              <P>
                <E T="03">Existing facility</E> means, with reference to a stationary source, any apparatus of the type for which a standard is promulgated in this part, and the construction or modification of which was commenced before the date of proposal of that standard; or any apparatus which could be altered in such a way as to be of that type.</P>
              <P>
                <E T="03">Isokinetic sampling</E> means sampling in which the linear velocity of the gas entering the sampling nozzle is equal to that of the undisturbed gas stream at the sample point.</P>
              <P>
                <E T="03">Issuance</E> of a part 70 permit will occur, if the State is the permitting authority, in accordance with the requirements of part 70 of this chapter and the applicable, approved State permit program. When the EPA is the permitting authority, issuance of a Title V permit occurs immediately after the EPA takes final action on the final permit.</P>
              <P>
                <E T="03">Malfunction</E> means any sudden, infrequent, and not reasonably preventable failure of air pollution control equipment, process equipment, or a process to operate in a normal or usual manner. Failures that are caused in part by poor maintenance or careless operation are not malfunctions.</P>
              <P>
                <E T="03">Modification</E> means any physical change in, or change in the method of operation of, an existing facility which increases the amount of any air pollutant (to which a standard applies) emitted into the atmosphere by that facility or which results in the emission of any air pollutant (to which a standard applies) into the atmosphere not previously emitted.</P>
              <P>
                <E T="03">Monitoring device</E> means the total equipment, required under the monitoring of operations sections in applicable subparts, used to measure and record (if applicable) process parameters.</P>
              <P>
                <E T="03">Nitrogen oxides</E> means all oxides of nitrogen except nitrous oxide, as measured by test methods set forth in this part.</P>
              <P>
                <E T="03">One-hour period</E> means any 60-minute period commencing on the hour.</P>
              <P>
                <E T="03">Opacity</E> means the degree to which emissions reduce the transmission of light and obscure the view of an object in the background.<PRTPAGE P="24"/>
              </P>
              <P>
                <E T="03">Owner or operator</E> means any person who owns, leases, operates, controls, or supervises an affected facility or a stationary source of which an affected facility is a part.</P>
              <P>
                <E T="03">Part 70 permit</E> means any permit issued, renewed, or revised pursuant to part 70 of this chapter.</P>
              <P>
                <E T="03">Particulate matter</E> means any finely divided solid or liquid material, other than uncombined water, as measured by the reference methods specified under each applicable subpart, or an equivalent or alternative method.</P>
              <P>
                <E T="03">Permit program</E> means a comprehensive State operating permit system established pursuant to title V of the Act (42 U.S.C. 7661) and regulations codified in part 70 of this chapter and applicable State regulations, or a comprehensive Federal operating permit system established pursuant to title V of the Act and regulations codified in this chapter.</P>
              <P>
                <E T="03">Permitting authority</E> means:</P>
              <P>(1) The State air pollution control agency, local agency, other State agency, or other agency authorized by the Administrator to carry out a permit program under part 70 of this chapter; or</P>
              <P>(2) The Administrator, in the case of EPA-implemented permit programs under title V of the Act (42 U.S.C. 7661).</P>
              <P>
                <E T="03">Proportional sampling</E> means sampling at a rate that produces a constant ratio of sampling rate to stack gas flow rate.</P>
              <P>
                <E T="03">Reactivation of a very clean coal-fired electric utility steam generating unit</E> means any physical change or change in the method of operation associated with the commencement of commercial operations by a coal-fired utility unit after a period of discontinued operation where the unit:</P>
              <P>(1) Has not been in operation for the two-year period prior to the enactment of the Clean Air Act Amendments of 1990, and the emissions from such unit continue to be carried in the permitting authority's emissions inventory at the time of enactment;</P>
              <P>(2) Was equipped prior to shut-down with a continuous system of emissions control that achieves a removal efficiency for sulfur dioxide of no less than 85 percent and a removal efficiency for particulates of no less than 98 percent;</P>
              <P>(3) Is equipped with low-NO<E T="52">X</E> burners prior to the time of commencement of operations following reactivation; and</P>
              <P>(4) Is otherwise in compliance with the requirements of the Clean Air Act.</P>
              <P>
                <E T="03">Reference method</E> means any method of sampling and analyzing for an air pollutant as specified in the applicable subpart.</P>
              <P>
                <E T="03">Repowering</E> means replacement of an existing coal-fired boiler with one of the following clean coal technologies: atmospheric or pressurized fluidized bed combustion, integrated gasification combined cycle, magnetohydrodynamics, direct and indirect coal-fired turbines, integrated gasification fuel cells, or as determined by the Administrator, in consultation with the Secretary of Energy, a derivative of one or more of these technologies, and any other technology capable of controlling multiple combustion emissions simultaneously with improved boiler or generation efficiency and with significantly greater waste reduction relative to the performance of technology in widespread commercial use as of November 15, 1990. Repowering shall also include any oil and/or gas-fired unit which has been awarded clean coal technology demonstration funding as of January 1, 1991, by the Department of Energy.</P>
              <P>
                <E T="03">Run</E> means the net period of time during which an emission sample is collected. Unless otherwise specified, a run may be either intermittent or continuous within the limits of good engineering practice.</P>
              <P>
                <E T="03">Shutdown</E> means the cessation of operation of an affected facility for any purpose.</P>
              <P>
                <E T="03">Six-minute period</E> means any one of the 10 equal parts of a one-hour period.</P>
              <P>
                <E T="03">Standard</E> means a standard of performance proposed or promulgated under this part.</P>
              <P>
                <E T="03">Standard conditions</E> means a temperature of 293 K (68F) and a pressure of 101.3 kilopascals (29.92 in Hg).</P>
              <P>
                <E T="03">Startup</E> means the setting in operation of an affected facility for any purpose.</P>
              <P>
                <E T="03">State</E> means all non-Federal authorities, including local agencies, interstate associations, and State-wide programs, that have delegated authority to implement: (1) The provisions of this <PRTPAGE P="25"/>part; and/or (2) the permit program established under part 70 of this chapter. The term State shall have its conventional meaning where clear from the context.</P>
              <P>
                <E T="03">Stationary source</E> means any building, structure, facility, or installation which emits or may emit any air pollutant.</P>
              <P>
                <E T="03">Title V permit</E> means any permit issued, renewed, or revised pursuant to Federal or State regulations established to implement title V of the Act (42 U.S.C. 7661). A title V permit issued by a State permitting authority is called a part 70 permit in this part.</P>
              <P>
                <E T="03">Volatile Organic Compound</E> means any organic compound which participates in atmospheric photochemical reactions; or which is measured by a reference method, an equivalent method, an alternative method, or which is determined by procedures specified under any subpart.</P>
              <CITA>[44 FR 55173, Sept. 25, 1979, as amended at 45 FR 5617, Jan. 23, 1980; 45 FR 85415, Dec. 24, 1980; 54 FR 6662, Feb. 14, 1989; 55 FR 51382, Dec. 13, 1990; 57 FR 32338, July 21, 1992; 59 FR 12427, Mar. 16, 1994]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.3</SECTNO>
              <SUBJECT>Units and abbreviations.</SUBJECT>
              <P>Used in this part are abbreviations and symbols of units of measure. These are defined as follows:</P>
              <P>(a) System International (SI) units of measure:
              </P>
              <EXTRACT>
                <FP SOURCE="FP-1">A—ampere</FP>
                <FP SOURCE="FP-1">g—gram</FP>
                <FP SOURCE="FP-1">Hz—hertz</FP>
                <FP SOURCE="FP-1">J—joule</FP>
                <FP SOURCE="FP-1">K—degree Kelvin</FP>
                <FP SOURCE="FP-1">kg—kilogram</FP>
                <FP SOURCE="FP-1">m—meter</FP>
                <FP SOURCE="FP-1">m <E T="51">3</E>—cubic meter</FP>
                <FP SOURCE="FP-1">mg—milligram—10 <E T="51">−3</E> gram</FP>
                <FP SOURCE="FP-1">mm—millimeter—10 <E T="51">−3</E> meter</FP>
                <FP SOURCE="FP-1">Mg—megagram—10 <E T="51">6</E> gram</FP>
                <FP SOURCE="FP-1">mol—mole</FP>
                <FP SOURCE="FP-1">N—newton</FP>
                <FP SOURCE="FP-1">ng—nanogram—10 <E T="51">−9</E> gram</FP>
                <FP SOURCE="FP-1">nm—nanometer—10 <E T="51">−9</E> meter</FP>
                <FP SOURCE="FP-1">Pa—pascal</FP>
                <FP SOURCE="FP-1">s—second</FP>
                <FP SOURCE="FP-1">V—volt</FP>
                <FP SOURCE="FP-1">W—watt</FP>
                <FP SOURCE="FP-1">Ω—ohm</FP>
                <FP SOURCE="FP-1">μg—microgram—10 <E T="51">−6</E> gram</FP>
              </EXTRACT>
              
              <P>(b) Other units of measure:
              </P>
              <EXTRACT>
                <FP SOURCE="FP-1">Btu—British thermal unit</FP>
                <FP SOURCE="FP-1"> °C—degree Celsius (centigrade)</FP>
                <FP SOURCE="FP-1">cal—calorie</FP>
                <FP SOURCE="FP-1">cfm—cubic feet per minute</FP>
                <FP SOURCE="FP-1">cu ft—cubic feet</FP>
                <FP SOURCE="FP-1">dcf—dry cubic feet</FP>
                <FP SOURCE="FP-1">dcm—dry cubic meter</FP>
                <FP SOURCE="FP-1">dscf—dry cubic feet at standard conditions</FP>
                <FP SOURCE="FP-1">dscm—dry cubic meter at standard conditions</FP>
                <FP SOURCE="FP-1">eq—equivalent</FP>
                <FP SOURCE="FP-1">°F—degree Fahrenheit</FP>
                <FP SOURCE="FP-1">ft—feet</FP>
                <FP SOURCE="FP-1">gal—gallon</FP>
                <FP SOURCE="FP-1">gr—grain</FP>
                <FP SOURCE="FP-1">g-eq—gram equivalent</FP>
                <FP SOURCE="FP-1">hr—hour</FP>
                <FP SOURCE="FP-1">in—inch</FP>
                <FP SOURCE="FP-1">k—1,000</FP>
                <FP SOURCE="FP-1">l—liter</FP>
                <FP SOURCE="FP-1">lpm—liter per minute</FP>
                <FP SOURCE="FP-1">lb—pound</FP>
                <FP SOURCE="FP-1">meq—milliequivalent</FP>
                <FP SOURCE="FP-1">min—minute</FP>
                <FP SOURCE="FP-1">ml—milliliter</FP>
                <FP SOURCE="FP-1">mol. wt.—molecular weight</FP>
                <FP SOURCE="FP-1">ppb—parts per billion</FP>
                <FP SOURCE="FP-1">ppm—parts per million</FP>
                <FP SOURCE="FP-1">psia—pounds per square inch absolute</FP>
                <FP SOURCE="FP-1">psig—pounds per square inch gage</FP>
                <FP SOURCE="FP-1">°R—degree Rankine</FP>
                <FP SOURCE="FP-1">scf—cubic feet at standard conditions</FP>
                <FP SOURCE="FP-1">scfh—cubic feet per hour at standard conditions</FP>
                <FP SOURCE="FP-1">scm—cubic meter at standard conditions</FP>
                <FP SOURCE="FP-1">sec—second</FP>
                <FP SOURCE="FP-1">sq ft—square feet</FP>
                <FP SOURCE="FP-1">std—at standard conditions</FP>
              </EXTRACT>
              
              <P>(c) Chemical nomenclature:
              </P>
              <EXTRACT>
                <FP SOURCE="FP-1">CdS—cadmium sulfide</FP>
                <FP SOURCE="FP-1">CO—carbon monoxide</FP>
                <FP SOURCE="FP-1">CO<E T="52">2</E>—carbon dioxide</FP>
                <FP SOURCE="FP-1">HCl—hydrochloric acid</FP>
                <FP SOURCE="FP-1">Hg—mercury</FP>
                <FP SOURCE="FP-1">H<E T="52">2</E>O—water</FP>
                <FP SOURCE="FP-1">H<E T="52">2</E>S—hydrogen sulfide</FP>
                <FP SOURCE="FP-1">H<E T="52">2</E>SO<E T="52">4</E>—sulfuric acid</FP>
                <FP SOURCE="FP-1">N<E T="52">2</E>—nitrogen</FP>
                <FP SOURCE="FP-1">NO—nitric oxide</FP>
                <FP SOURCE="FP-1">NO<E T="52">2</E>—nitrogen dioxide</FP>
                <FP SOURCE="FP-1">NO<E T="52">X</E>—nitrogen oxides</FP>
                <FP SOURCE="FP-1">O<E T="52">2</E>—oxygen</FP>
                <FP SOURCE="FP-1">SO<E T="52">2</E>—sulfur dioxide</FP>
                <FP SOURCE="FP-1">SO<E T="52">3</E>—sulfur trioxide</FP>
                <FP SOURCE="FP-1">SO<E T="52">X</E>—sulfur oxides</FP>
              </EXTRACT>
              
              <P>(d) Miscellaneous:
              </P>
              <EXTRACT>
                <FP SOURCE="FP-1">A.S.T.M.—American Society for Testing and Materials</FP>
              </EXTRACT>
              <CITA>[42 FR 37000, July 19, 1977; 42 FR 38178, July 27, 1977]</CITA>
            </SECTION>
            <SECTION>
              <PRTPAGE P="26"/>
              <SECTNO>§ 60.4</SECTNO>
              <SUBJECT>Address.</SUBJECT>

              <P>(a) All requests, reports, applications, submittals, and other communications to the Administrator pursuant to this part shall be submitted in duplicate to the appropriate Regional Office of the U.S. Environmental Protection Agency to the attention of the Director of the Division indicated in the following list of EPA Regional Offices.
              </P>
              <EXTRACT>
                <FP SOURCE="FP-1">Region I (Connecticut, Maine, Massachusetts, New Hampshire, Rhode Island, Vermont), Director, Air Management Division, U.S. Environmental Protection Agency, John F. Kennedy Federal Building, Boston, MA 02203.</FP>
                <FP SOURCE="FP-1">Region II (New Jersey, New York, Puerto Rico, Virgin Islands), Director, Air and Waste Management Division, U.S. Environmental Protection Agency, Federal Office Building, 26 Federal Plaza (Foley Square), New York, NY 10278.</FP>
                <FP SOURCE="FP-1">Region III (Delaware, District of Columbia, Maryland, Pennsylvania, Virginia, West Virginia), Director, Air and Waste Management Division, U.S. Environmental Protection Agency, Curtis Building, Sixth and Walnut Streets, Philadelphia, PA 19106.</FP>
                <FP SOURCE="FP-1">Region IV (Alabama, Florida, Georgia, Kentucky, Mississippi, North Carolina, South Carolina, Tennessee), Director, Air and Waste Management Division, U.S. Environmental Protection Agency, 345 Courtland Street, NE., Atlanta, GA 30365.</FP>
                <FP SOURCE="FP-1">Region V (Illinois, Indiana, Michigan, Minnesota, Ohio, Wisconsin), Director, Air and Radiation Division, U.S. Environmental Protection Agency, 77 West Jackson Boulevard, Chicago, IL 60604-3590.</FP>
                <FP SOURCE="FP-1">Region VI (Arkansas, Louisiana, New Mexico, Oklahoma, Texas); Director; Air, Pesticides, and Toxics Division; U.S. Environmental Protection Agency, 1445 Ross Avenue, Dallas, TX 75202.</FP>
                <FP SOURCE="FP-1">Region VII (Iowa, Kansas, Missouri, Nebraska), Director, Air, RCRA, and Toxics Division, U.S. Environmental Protection Agency, 901 N. 5th Street, Kansas City, KS 66101.</FP>
                <FP SOURCE="FP-1">Region VIII (Colorado, Montana, North Dakota, South Dakota, Utah, Wyoming) Assistant Regional Administrator, Office of Enforcement, Compliance and Environmental Justice, 999 18th Street, Suite 300, Denver, CO 80202-2466.</FP>
                <FP SOURCE="FP-1">Region IX (American Samoa, Arizona, California, Guam, Hawaii, Nevada, Northern Mariana Islands), Director, Air Division, U.S. Environmental Protection Agency, 75 Hawthorne Street, San Francisco, CA 94105.</FP>
                <FP SOURCE="FP-1">Region X (Alaska, Oregon, Idaho, Washington), Director, Air and Waste Management Division, U.S. Environmental Protection Agency, 1200 Sixth Avenue, Seattle, WA 98101.</FP>
              </EXTRACT>
              
              <P>(b) Section 111(c) directs the Administrator to delegate to each State, when appropriate, the authority to implement and enforce standards of performance for new stationary sources located in such State. All information required to be submitted to EPA under paragraph (a) of this section, must also be submitted to the appropriate State Agency of any State to which this authority has been delegated (provided, that each specific delegation may except sources from a certain Federal or State reporting requirement). The appropriate mailing address for those States whose delegation request has been approved is as follows:</P>
              <EXTRACT>
                <P>(A) [Reserved]</P>
                <P>(B) State of Alabama, Air Pollution Control Division, Air Pollution Control Commission, 645 S. McDonough Street, Montgomery, AL 36104.</P>
                <P>(C) State of Alaska, Department of Environmental Conservation, Pouch O, Juneau, AK 99811.</P>
                <P>(D) Arizona:</P>
                <FP SOURCE="FP-1">Arizona Department of Environmental Quality, Office of Air Quality, P.O. Box 600, Phoenix, AZ 85001-0600.</FP>
                <FP SOURCE="FP-1">Maricopa County Air Pollution Control, 2406 S. 24th Street, Suite E-214, Phoenix, AZ 85034.</FP>
                <FP SOURCE="FP-1">Pima County Department of Environmental Quality, 130 West Congress Street, 3rd Floor, Tucson, AZ 85701-1317.</FP>
                <FP SOURCE="FP-1">Pinal County Air Quality Control District, Building F, 31 North Pinal Street, Florence, AZ 85232.</FP>
                
                <NOTE>
                  <HD SOURCE="HED">Note:</HD>
                  <P>For tables listing the delegation status of agencies in Region IX, see paragraph (d) of this section.</P>
                </NOTE>
                
                <P>(E) State of Arkansas: Chief, Division of Air Pollution Control, Arkansas Department of Pollution Control and Ecology, 8001 National Drive, P.O. Box 9583, Little Rock, AR 72209.</P>
                <P>(F) California:</P>
                <FP SOURCE="FP-1">Amador County Air Pollution Control District, 500 Argonaut Lane, Jackson, CA 95642.</FP>
                <FP SOURCE="FP-1">Antelope Valley Air Pollution Control District, 43301 Division Street, Suite 206, P.O. Box 4409, Lancaster, CA 93539-4409.</FP>
                <FP SOURCE="FP-1">Bay Area Air Quality Management District, 939 Ellis Street, San Francisco, CA 94109.</FP>

                <FP SOURCE="FP-1">Butte County Air Pollution Control District, 2525 Dominic Drive, Suite J, Chico, CA 95928-7184.<PRTPAGE P="27"/>
                </FP>
                <FP SOURCE="FP-1">Calaveras County Air Pollution Control District, 891 Mountain Ranch Rd., San Andreas, CA 95249.</FP>
                <FP SOURCE="FP-1">Colusa County Air Pollution Control District, 100 Sunrise Blvd., Suite F, Colusa, CA 95932-3246.</FP>
                <FP SOURCE="FP-1">El Dorado County Air Pollution Control District, 2850 Fairlane Court, Bldg. C, Placerville, CA 95667-4100.</FP>
                <FP SOURCE="FP-1">Feather River Air Quality Management District, 938 14th Street, Marysville, CA 95901-4149.</FP>
                <FP SOURCE="FP-1">Glenn County Air Pollution Control District, 720 N. Colusa Street, P.O. Box 351, Willows, CA 95988-0351.</FP>
                <FP SOURCE="FP-1">Great Basin Unified Air Pollution Control District, 157 Short Street, Suite 6, Bishop, CA 93514-3537.</FP>
                <FP SOURCE="FP-1">Imperial County Air Pollution Control District, 150 South Ninth Street, El Centro, CA 92243-2801.</FP>
                <FP SOURCE="FP-1">Kern County Air Pollution Control District (Southeast Desert), 2700 M. Street, Suite 302, Bakersfield, CA 93301-2370.</FP>
                <FP SOURCE="FP-1">Lake County Air Quality Management District, 885 Lakeport Blvd., Lakeport, CA 95453-5405.</FP>
                <FP SOURCE="FP-1">Lassen County Air Pollution Control District, 175 Russell Avenue, Susanville, CA 96130-4215.</FP>
                <FP SOURCE="FP-1">Mariposa County Air Pollution Control District, P.O. Box 5, Mariposa, CA 95338.</FP>
                <FP SOURCE="FP-1">Mendocino County Air Pollution Control District, 306 E. Gobbi Street, Ukiah, CA 95482-5511.</FP>
                <FP SOURCE="FP-1">Modoc County Air Pollution Control District, 202 W. 4th Street, Alturas, CA 96101-3915.</FP>
                <FP SOURCE="FP-1">Mojave Desert Air Quality Management District, 14306 Part Avenue, Victorville, CA 92392-2310.</FP>
                <FP SOURCE="FP-1">Monterey Bay Unified Air Pollution Control District, 24580 Silver Cloud Ct., Monterey, CA 93940-6536.</FP>
                <FP SOURCE="FP-1">North Coast Unified Air Pollution Control District, 2300 Myrtle Avenue, Eureka, CA 95501-3327.</FP>
                <FP SOURCE="FP-1">Northern Sierra Air Quality Management District, 200 Litton Drive, P.O. Box 2509, Grass Valley, CA 95945-2509.</FP>
                <FP SOURCE="FP-1">Northern Sonoma County Air Pollution Control District, 150 Matheson Street, Healdsburg, CA 95448-4908.</FP>
                <FP SOURCE="FP-1">Placer County Air Pollution Control District, DeWitt Center, 11464 “B” Avenue, Auburn, CA 95603-2603.</FP>
                <FP SOURCE="FP-1">Sacramento Metropolitan Air Quality Management District, 777 12th Street, Third Floor, Sacramento, CA 95814-1908.</FP>
                <FP SOURCE="FP-1">San Diego County Air Pollution Control District, 9150 Chesapeake Drive, San Diego, CA 92123-1096.</FP>
                <FP SOURCE="FP-1">San Joaquin Valley Unified Air Pollution Control District, 1999 Tuolumne Street, 1990 E. Gettysburg, Fresno, CA 93726.</FP>
                <FP SOURCE="FP-1">San Luis Obispo County Air Pollution Control District, 3433 Roberto Court, San Luis Obispo, CA 93401-7126.</FP>
                <FP SOURCE="FP-1">Santa Barbara County Air Pollution Control District, 26 Castilian Drive, B-23, Goleta, CA 93117-3027.</FP>
                <FP SOURCE="FP-1">Shasta County Air Quality Management District, 1855 Placer Street, Suite 101, Redding, CA 96001-1759.</FP>
                <FP SOURCE="FP-1">Siskiyou County Air Pollution Control District, 525 So. Foothill Drive, Yreka, CA 96097-3036.</FP>
                <FP SOURCE="FP-1">South Coast Air Quality Management District, 21865 E. Copley Drive, Diamond Bar, CA 91765-4182.</FP>
                <FP SOURCE="FP-1">Tehama County Air Pollution Control District, P.O. Box 38 (1750 Walnut Street), Red Bluff, CA 96080-0038.</FP>
                <FP SOURCE="FP-1">Tuolumne County Air Pollution Control District, 2 South Green Street, Sonora, CA 95370-4618.</FP>
                <FP SOURCE="FP-1">Ventura County Air Pollution Control District, 669 County Square Drive, Ventura, CA 93003-5417.</FP>
                <FP SOURCE="FP-1">Yolo-Solano Air Quality Management District, 1947 Galileo Ct., Suite 103, Davis, CA 95616-4882.</FP>
                
                <NOTE>
                  <HD SOURCE="HED">Note:</HD>
                  <P>For tables listing the delegation status of agencies in Region IX, see paragraph (d) of this section.</P>
                </NOTE>
                

                <P>(G) State of Colorado, Department of Public Health and Environment, 4300 Cherry Creek Drive South, Denver, CO 80222-1530.
                </P>
                <NOTE>
                  <HD SOURCE="HED">Note:</HD>
                  <P>For a table listing Region VIII's NSPS delegation status, see paragraph (c) of this section.</P>
                </NOTE>
                
                <P>(H) State of Connecticut, Bureau of Air Management, Department of Environmental Protection, State Office Building, 165 Capitol Avenue, Hartford, CT 06106.</P>
                <P>(I) State of Delaware, Delaware Department of Natural Resources and Environmental Control, 89 Kings Highway, P.O. Box 1401, Dover, DE 19901</P>
                <P>(J) District of Columbia, Department of Consumer and Regulatory Affairs, 5000 Overlook Avenue SW., Washington DC 20032.</P>
                <P>(K) Bureau of Air Quality Management, Department of Environmental Regulation, Twin Towers Office Building, 2600 Blair Stone Road, Tallahassee, FL 32301.</P>
                <P>(L) State of Georgia, Environmental Protection Division, Department of Natural Resources, 270 Washington Street, SW., Atlanta, GA 30334.</P>
                <P>(M) Hawaii:</P>
                <FP SOURCE="FP-1">Hawaii State Agency, Clean Air Branch, 919 Ala Moana Blvd., 3rd Floor, Post Office Box 3378, Honolulu, HI 96814.</FP>
                
                <NOTE>
                  <HD SOURCE="HED">Note:</HD>
                  <P>For tables listing the delegation status of agencies in Region IX, see paragraph (d) of this section.</P>
                </NOTE>
                

                <P>(N) State of Idaho, Department of Health and Welfare, Statehouse, Boise, ID 83701.<PRTPAGE P="28"/>
                </P>
                <P>(O) State of Illinois, Bureau of Air, Division of Air Pollution Control, Illinois Environmental Protection Agency, 2200 Churchill Road, Springfield, IL 62794-9276.</P>
                <P>(P) State of Indiana, Indiana Department of Environmental Management, 100 North Senate Avenue, P.O. Box 6015, Indianapolis, Indiana 46206-6015.</P>
                <P>(Q) State of Iowa: Iowa Department of Natural Resources, Environmental Protection Division, Air Quality Bureau, 7900 Hickman Road, Suite 1, Urbandale, IA 50322.</P>
                <P>(R) State of Kansas: Kansas Department of Health and Environment, Bureau of Air and Radiation, 1000 S.W. Jackson, Suite 310, Topeka, KS 66612-1366.</P>
                <P>(S) Division of Air Pollution Control, Department for Natural Resources and Environmental Protection, U.S. 127, Frankfort, KY 40601.</P>
                <P>(T) State of Louisiana: Louisiana Department of Environmental Quality, Office of Environmental Assessment, P.O. Box 4314, Baton Rouge, LA 70821-4314. For a list of delegated standards for Louisiana (excluding Indian country), see paragraph (e)(1) of this section.</P>
                <P>(U) State of Maine, Bureau of Air Quality Control, Department of Environmental Protection, State House, Station No. 17, Augusta, ME 04333.</P>
                <P>(V) State of Maryland: Bureau of Air Quality and Noise Control, Maryland State Department of Health and Mental Hygiene, 201 West Preston Street, Baltimore, MD 21201.</P>
                <P>(W) Commonwealth of Massachusetts, Division of Air Quality Control, Department of Environmental Protection, One Winter Street, 7th floor, Boston, MA 02108.</P>
                <P>(X) State of Michigan, Air Quality Division, Michigan Department of Environmental Quality, P.O. Box 30260, Lansing, Michigan 48909.</P>
                <P>(Y) Minnesota Pollution Control Agency, Division of Air Quality, 520 Lafayette Road, St. Paul, MN 55155.</P>
                <P>(Z) Bureau of Pollution Control, Department of Natural Resources, P.O. Box 10385, Jackson, MS 39209.</P>
                <P>(AA) State of Missouri: Missouri Department of Natural Resources, Division of Environmental Quality, P.O. Box 176, Jefferson City, MO 65102.</P>

                <P>(BB) State of Montana, Department of Environmental Quality, 1520 E. 6th Ave., PO Box 200901, Helena, MT 59620-0901.
                </P>
                <NOTE>
                  <HD SOURCE="HED">Note:</HD>
                  <P>For a table listing Region VIII's NSPS delegation status, see paragraph (c) of this section.</P>
                </NOTE>
                
                <P>(CC) State of Nebraska, Nebraska Department of Environmental Control, P.O. Box 94877, State House Station, Lincoln, NE 68509.</P>
                <FP SOURCE="FP-1">Lincoln-Lancaster County Health Department, Division of Environmental Health, 2200 St. Marys Avenue, Lincoln, NE 68502</FP>
                <P>(DD) Nevada:</P>
                <FP SOURCE="FP-1">Nevada State Agency, Air Pollution Control, Bureau of Air Quality/Division of Environmental Protection, 333 West Nye Lane, Carson City, NV 89710.</FP>
                <FP SOURCE="FP-1">Clark County Department of Air Quality Management, 500 S. Grand Central Parkway, First floor, Las Vegas, NV 89155-1776.</FP>
                <FP SOURCE="FP-1">Washoe County Air Pollution Control, Washoe County District Air Quality Management, P.O. Box 11130, 1001 E. Ninth Street, Reno, NV 89520.</FP>
              </EXTRACT>
              
              <NOTE>
                <HD SOURCE="HED">Note:</HD>
                <P>For tables listing the delegation status of agencies in Region IX, see paragraph (d) of this section.</P>
              </NOTE>
              
              <P>(EE) State of New Hampshire, Air Resources Division, Department of Environmental Services, 64 North Main Street, Caller Box 2033, Concord, NH 03302-2033.</P>
              <P>(FF) State of New Jersey: New Jersey Department of Environmental Protection, Division of Environmental Quality, Enforcement Element, John Fitch Plaza, CN-027, Trenton, NJ 08625.</P>
              <P>(1) The following table lists the specific source and pollutant categories that have been delegated to the states in Region II. The (X) symbol is used to indicate each category that has been delegated.</P>
              <GPOTABLE CDEF="xls15,r100,xs32,xs32,xs32,xs32" COLS="6" OPTS="L2">
                <BOXHD>
                  <CHED H="1"/>
                  <CHED H="1">Subpart</CHED>
                  <CHED H="1">State</CHED>
                  <CHED H="2">New Jersey</CHED>
                  <CHED H="2">New York</CHED>
                  <CHED H="2">Puerto Rico</CHED>
                  <CHED H="2">Virgin Islands</CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">D</ENT>
                  <ENT>Fossil-Fuel Fired Steam Generators for Which Construction Commenced After August 17, 1971 (Steam Generators and Lignite Fired Steam Generators)</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Da</ENT>
                  <ENT>Electric Utility Steam Generating Units for Which Construction Commenced After September 18, 1978</ENT>
                  <ENT>X</ENT>
                  <ENT O="xl"/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Db</ENT>
                  <ENT>Industrial-Commercial-Institutional Steam Generating Units</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">E</ENT>
                  <ENT>Incinerators</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">F</ENT>
                  <ENT>Portland Cement Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">G</ENT>
                  <ENT>Nitric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">H</ENT>
                  <ENT>Sulfuric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">I</ENT>
                  <ENT>Asphalt Concrete Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">J</ENT>
                  <ENT>Petroleum Refineries—(All Categories)</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <PRTPAGE P="29"/>
                  <ENT I="01">K</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids Constructed After June 11, 1973, and prior to May 19, 1978</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Ka</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids Constructed After May 18, 1978</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">L</ENT>
                  <ENT>Secondary Lead Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">M</ENT>
                  <ENT>Secondary Brass and Bronze Ingot Production Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">N</ENT>
                  <ENT>Iron and Steel Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">O</ENT>
                  <ENT>Sewage Treatment Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">P</ENT>
                  <ENT>Primary Copper Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Q</ENT>
                  <ENT>Primary Zinc Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">R</ENT>
                  <ENT>Primary Lead Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">S</ENT>
                  <ENT>Primary Aluminum Reduction Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">T</ENT>
                  <ENT>Phosphate Fertilizer Industry: Wet Process Phosphoric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">U</ENT>
                  <ENT>Phosphate Fertilizer Industry: Superphosphoric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">V</ENT>
                  <ENT>Phosphate Fertilizer Industry: Diammonium Phosphate Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">W</ENT>
                  <ENT>Phosphate Fertilizer Industry: Triple Superphosphate Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">X</ENT>
                  <ENT>Phosphate Fertilizer Industry: Granular Triple Superphosphate</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Y</ENT>
                  <ENT>Coal Preparation Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Z</ENT>
                  <ENT>Ferroally Production Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AA</ENT>
                  <ENT>Steel Plants: Electric Arc Furnaces</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AAa</ENT>
                  <ENT>Electric Arc Furnaces and Argon-Oxygen Decarburization Vessels in Steel Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">BB</ENT>
                  <ENT>Kraft Pulp Mills</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">CC</ENT>
                  <ENT>Glass Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">DD</ENT>
                  <ENT>Grain Elevators</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">EE</ENT>
                  <ENT>Surface Coating of Metal Furniture</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">GG</ENT>
                  <ENT>Stationary Gas Turbines</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">HH</ENT>
                  <ENT>Lime Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">KK</ENT>
                  <ENT>Lead Acid Battery Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT O="xl"/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">LL</ENT>
                  <ENT>Metallic Mineral Processing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">MM</ENT>
                  <ENT>Automobile and Light-Duty Truck Surface Coating Operations</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">NN</ENT>
                  <ENT>Phosphate Rock Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT O="xl"/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">PP</ENT>
                  <ENT>Ammonium Sulfate Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT O="xl"/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">QQ</ENT>
                  <ENT>Graphic Art Industry Publication Rotogravure Printing</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">RR</ENT>
                  <ENT>Pressure Sensitive Tape and Label Surface Coating Operations</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">SS</ENT>
                  <ENT>Industrial Surface Coating: Large Appliances</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">TT</ENT>
                  <ENT>Metal Coil Surface Coating</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">UU</ENT>
                  <ENT>Asphalt Processing and Asphalt Roofing Manufacture</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">VV</ENT>
                  <ENT>Equipment Leaks of Volatile Organic Compounds in Synthetic Organic Chemical Manufacturing Industry</ENT>
                  <ENT>X</ENT>
                  <ENT O="xl"/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">WW</ENT>
                  <ENT>Beverage Can Surface Coating Industry</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">XX</ENT>
                  <ENT>Bulk Gasoline Terminals</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">FFF</ENT>
                  <ENT>Flexible Vinyl and Urethane Coating and Printing</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">GGG</ENT>
                  <ENT>Equipment Leaks of VOC in Petroleum Refineries</ENT>
                  <ENT>X</ENT>
                  <ENT O="xl"/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">HHH</ENT>
                  <ENT>Synthetic Fiber Production Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT O="xl"/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">JJJ</ENT>
                  <ENT>Petroleum Dry Clearners</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">KKK</ENT>
                  <ENT>Equipment Leaks of VOC from Onshore Natural Gas Processing Plants</ENT>
                  <ENT O="xl"/>
                  <ENT O="xl"/>
                  <ENT O="xl"/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">LLL</ENT>
                  <ENT>Onshore Natural Gas Processing Plants; SO<E T="52">2</E> Emissions</ENT>
                  <ENT O="xl"/>
                  <ENT>X</ENT>
                  <ENT O="xl"/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">OOO</ENT>
                  <ENT>Nonmetallic Mineral Processing Plants</ENT>
                  <ENT O="xl"/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">PPP</ENT>
                  <ENT>Wool Fiberglass Insulation Manufacturing Plants</ENT>
                  <ENT O="xl"/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
              </GPOTABLE>
              <P>(GG) State of New Mexico: New Mexico Environment Department, 1190 St. Francis Drive, P.O. Box 26110, Santa Fe, New Mexico 87502. Note: For a list of delegated standards for New Mexico (excluding Bernalillo County and Indian country), see paragraph (e)(1) of this section.</P>
              <P>(HH) New York: New York State Department of Environmental Conservation, 50 Wolf Road Albany, New York 12233, attention: Division of Air Resources.</P>

              <P>(II) North Carolina Environmental Management Commission, Department of Natural and Economic Resources, Division of Environmental Management, P.O. Box 27687, Raleigh, NC 27611. Attention: Air Quality Section.<PRTPAGE P="30"/>
              </P>

              <P>(JJ) State of North Dakota, Division of Air Quality, North Dakota Department of Health, P.O. Box 5520, Bismarck, ND 58506-5520.
              </P>
              <NOTE>
                <HD SOURCE="HED">Note:</HD>
                <P>For a table listing Region VIII's NSPS delegation status, see paragraph (c) of this section.</P>
              </NOTE>
              
              <P>(KK) State of Ohio:</P>
              <P>(i) Medina, Summit and Portage Counties; Director, Akron Regional Air Quality Management District, 177 South Broadway, Akron, OH 44308.</P>
              <P>(ii) Stark County: Air Pollution Control Division, 420 Market Avenue North, Canton, Ohio 44702-3335.</P>
              <P>(iii) Butler, Clermont, Hamilton, and Warren Counties: Air Program Manager, Hamilton County Department of Environmental Services, 1632 Central Parkway, Cincinnati, Ohio 45210.</P>
              <P>(iv) Cuyahoga County: Commissioner, Department of Public Health &amp; Welfare, Division of Air Pollution Control, 1925 Saint Clair, Cleveland, Ohio 44114.</P>
              <P>(v) Belmont, Carroll, Columbiana, Harrison, Jefferson, and Monroe Counties: Director, North Ohio Valley Air Authority (NOVAA), 814 Adams Street, Steubenville, OH 43952.</P>
              <P>(vi) Clark, Darke, Greene, Miami, Montgomery, and Preble Counties: Director, Regional Air Pollution Control Agency (RAPCA) 451 West Third Street, Dayton, Ohio 45402.</P>
              <P>(vii) Lucas County and the City of Rossford (in Wood County): Director, Toledo Environmental Services Agency, 26 Main Street, Toledo, OH 43605.</P>
              <P>(viii) Adams, Brown, Lawrence, and Scioto Counties; Engineer-Director, Air Division, Portsmouth City Health Department, 740 Second Street, Portsmouth, OH 45662.</P>
              <P>(ix) Allen, Ashland, Auglaize, Crawford, Defiance, Erie, Fulton, Hancock, Hardin, Henry, Huron, Marion, Mercer, Ottawa, Paulding, Putnam, Richland, Sandusky, Seneca, Van Wert, Williams, Wood (except City of Rossford), and Wyandot Counties: Ohio Environmental Protection Agency, Northwest District Office, Air Pollution Control, 347 Dunbridge Rd., Bowling Green, Ohio 43402.</P>
              <P>(x) Ashtabula, Holmes, Lorain, and Wayne Counties: Ohio Environmental Protection Agency, Northeast District Office, Air Pollution Unit, 2110 East Aurora Road, Twinsburg, OH 44087.</P>
              <P>(xi) Athens, Coshocton, Gallia, Guernsey, Hocking, Jackson, Meigs, Morgan, Muskingum, Noble, Perry, Pike, Ross, Tuscarawas, Vinton, and Washington Counties: Ohio Environmental Protection Agency, Southeast District Office, Air Pollution Unit, 2195 Front Street, Logan, OH 43138.</P>
              <P>(xii) Champaign, Clinton, Highland, Logan, and Shelby Counties: Ohio Environmental Protection Agency, Southwest District Office, Air Pollution Unit, 401 East Fifth Street, Dayton, Ohio 45402-2911.</P>
              <P>(xiii) Delaware, Fairfield, Fayette, Franklin, Knox, Licking, Madison, Morrow, Pickaway, and Union Counties: Ohio Environmental Protection Agency, Central District Office, Air Pollution Control, 3232 Alum Creek Drive, Columbus, Ohio, 43207-3417.</P>
              <P>(xiv) Geauga and Lake Counties: Lake County General Health District, Air Pollution Control, 105 Main Street, Painesville, OH 44077.</P>
              <P>(xv) Mahoning and Trumbull Counties: Mahoning-Trumbull Air Pollution Control Agency, 9 West Front Street, Youngstown, OH 44503.</P>
              <P>(LL) State of Oklahoma, Oklahoma State Department of Health, Air Quality Service, P.O. Box 53551, Oklahoma City, OK 73152.</P>
              <P>(i) Oklahoma City and County: Director, Oklahoma City-County Health Department, 921 Northeast 23rd Street, Oklahoma City, OK 73105.</P>
              <P>(ii) Tulsa County: Tulsa City-County Health Department, 4616 East Fifteenth Street, Tulsa, OK 74112.</P>

              <P>(MM) State of Oregon. (i) Oregon Department of Environmental Quality (ODEQ), 811 SW Sixth Avenue, Portland, OR 97204-1390, <E T="03">http://www.deq.state.or.us.</E>
              </P>

              <P>(ii) Lane Regional Air Pollution Authority (LRAPA), 1010 Main Street, Springfield, Oregon 97477, <E T="03">http://www.lrapa.org.</E>
              </P>
              <P>(NN)(a) City of Philadelphia: Philadelphia Department of Public Health, Air Management Services, 500 S. Broad Street, Philadelphia, PA 19146.</P>
              <P>(b) Commonwealth of Pennsylvania: Department of Environmental Resources, Post Office Box 2063, Harrisburg, PA 17120.</P>

              <P>(c) Allegheny County: Allegheny County Health Department, Bureau of <PRTPAGE P="31"/>Air Pollution Control, 301 Thirty-ninth Street, Pittsburgh, PA 15201.</P>
              <P>(OO) State of Rhode Island, Division of Air and Hazardous Materials, Department of Environmental Management, 291 Promenade Street, Providence, RI 02908.</P>
              <P>(PP) State of South Carolina, Office of Environmental Quality Control, Department of Health and Environmental Control, 2600 Bull Street, Columbia, SC 29201.</P>

              <P>(QQ) State of South Dakota, Air Quality Program, Department of Environment and Natural Resources, Joe Foss Building, 523 East Capitol, Pierre, SD 57501-3181.
              </P>
              <NOTE>
                <HD SOURCE="HED">Note:</HD>
                <P>For a table listing Region VIII's NSPS delegation status, see paragragh (c) of this section.</P>
              </NOTE>
              
              <P>(RR) Division of Air Pollution Control, Tennessee Department of Public Health, 256 Capitol Hill Building, Nashville, TN 37219.</P>
              <FP SOURCE="FP-1">Knox County Department of Air Pollution, City/County Building, Room L222, 400 Main Avenue, Knoxville, TN 37902.</FP>
              <FP SOURCE="FP-1">Air Pollution Control Bureau, Metropolitan Health Department, 311 23rd Avenue North, Nashville, TN 37203.</FP>
              <P>(SS) State of Texas, Texas Air Control Board, 6330 Highway 290 East, Austin, TX 78723.</P>

              <P>(TT) State of Utah, Division of Air Quality, Department of Environmental Quality, P.O. Box 144820, Salt Lake City, UT 84114-4820.
              </P>
              <NOTE>
                <HD SOURCE="HED">Note:</HD>
                <P>For a table listing Region VIII's NSPS delegation status, see paragraph (c) of this section.</P>
              </NOTE>
              
              <P>(UU) State of Vermont, Air Pollution Control Division, Agency of Natural Resources, Building 3 South, 103 South Main Street, Waterbury, VT 05676.</P>
              <P>(VV) Commonwealth of Virginia, Virginia State Air Pollution Control Board, Room 1106, Ninth Street Office Building, Richmond, VA 23219.</P>
              <P>(WW) <E T="03">State of Washington.</E> (i) Washington State Department of Ecology (Ecology), P.O. Box 47600, Olympia, WA 98504-7600, <E T="03">http://www.ecy.wa.gov/</E>
              </P>

              <P>(ii) Benton Clean Air Authority (BCAA), 650 George Washington Way, Richland, WA 99352-4289, <E T="03">http://www.bcaa.net/</E>
              </P>

              <P>(iii) Northwest Air Pollution Control Authority (NWAPA), 1600 South Second St., Mount Vernon, WA 98273-5202, <E T="03">http://www.nwair.org/</E>
              </P>

              <P>(iv) Olympic Regional Clean Air Agency (ORCAA), 909 Sleater-Kinney Road S.E., Suite 1, Lacey, WA 98503-1128, <E T="03">http://www.orcaa.org/</E>
              </P>

              <P>(v) Puget Sound Clean Air Agency (PSCAA), 110 Union Street, Suite 500, Seattle, WA 98101-2038, <E T="03">http://www.pscleanair.org/</E>
              </P>

              <P>(vi) Spokane County Air Pollution Control Authority (SCAPCA), West 1101 College, Suite 403, Spokane, WA 99201, <E T="03">http://www.scapca.org/</E>
              </P>

              <P>(vii) Southwest Clean Air Agency (SWCAA), 1308 NE. 134th St., Vancouver, WA 98685-2747, <E T="03">http://www.swcleanair.org/</E>
              </P>

              <P>(viii) Yakima Regional Clean Air Authority (YRCAA), 6 South 2nd Street, Suite 1016, Yakima, WA 98901, <E T="03">http://co.yakima.wa.us/cleanair/default.htm</E>
              </P>
              <P>(ix) The following table lists the delegation status of the New Source Performance Standards for the State of Washington. An “X” indicates the subpart has been delegated, subject to all the conditions and limitations set forth in Federal law and the letters granting delegation. Some authorities cannot be delegated and are retained by EPA. Refer to the letters granting delegation for a discussion of these retained authorities. The dates noted at the end of the table indicate the effective dates of Federal rules that have been delegated. Authority for implementing and enforcing any amendments made to these rules after these effective dates are not delegated.</P>
              <GPOTABLE CDEF="s50,8C,8C,8C,8C,8C,8C,8C,8C" COLS="9" OPTS="L2">
                <TTITLE>NSPS Subparts Delegated to Washington Air Agencies</TTITLE>
                <BOXHD>
                  <CHED H="1">Subpart <SU>1</SU>
                  </CHED>
                  <CHED H="1">Washington</CHED>
                  <CHED H="2">Ecology <SU>2</SU>
                  </CHED>
                  <CHED H="2">BCAA <SU>3</SU>
                  </CHED>
                  <CHED H="2">NWAPA <SU>4</SU>
                  </CHED>
                  <CHED H="2">ORCAA <SU>5</SU>
                  </CHED>
                  <CHED H="2">PSCAA <SU>6</SU>
                  </CHED>
                  <CHED H="2">SCAPCA <SU>7</SU>
                  </CHED>
                  <CHED H="2">SWCAA <SU>8</SU>
                  </CHED>
                  <CHED H="2">YRCAA <SU>9</SU>
                  </CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">AGeneral Provisions</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">BAdoption and Submittal of State Plans for Designated Facilities</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <PRTPAGE P="32"/>
                  <ENT I="01">CEmission Guidelines and Compliance Times</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">CbLarge Municipal Waste Combustors that are Constructed on or before September 20, 1994 (Emission Guidelines and Compliance Times)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">CcMunicipal Solid Waste Landfills (Emission Guidelines and Compliance Times)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">CdSulfuric Acid Production Units (Emission Guidelines and Compliance Times)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">CeHospital/Medical/Infectious Waste Incinerators (Emission Guidelines and Compliance Times)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">DFossil-Fuel-Fired Steam Generators for which Construction is Commenced after August 17, 1971</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">DaElectric Utility Steam Generating Units for which Construction is Commenced after September 18, 1978</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">DbIndustrial-Commercial-Institutional Steam Generating Units</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">DcSmall Industrial-Commercial-Institutional Steam Generating Units</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">EIncinerators</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">EaMunicipal Waste Combustors for which Construction is Commenced after December 20, 1989 and on or before September 20, 1994</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">EbLarge Municipal Waste Combustors for which Construction is Commenced after September 20, 1994 or for which Modification or Reconstruction is Commenced after June 19, 1996</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">EcHospital/Medical/Infectious Waste Incinerators for which Construction is Commenced after June 20, 1996</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">FPortland Cement Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">GNitric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">HSulfuric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">IHot Mix Asphalt Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">JPetroleum Refineries</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">KStorage Vessels for Petroleum Liquids for which Construction, Reconstruction, or Modification Commenced after June 11, 1973 and prior to May 19, 1978</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <PRTPAGE P="33"/>
                  <ENT I="01">KaStorage Vessels for Petroleum Liquids for which Construction, Reconstruction, or Modification Commenced after May 18, 1978 and prior to July 23, 1984</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">KbVOC Liquid Storage Vessels (including Petroleum Liquid Storage Vessels) for which Construction, Reconstruction, or Modification Commenced after July 23, 1984</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">LSecondary Lead Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">MSecondary Brass and Bronze Production Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">NPrimary Emissions from Basic Oxygen Process Furnaces for which Construction is Commenced after June 11, 1973</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">NaSecondary Emissions from Basic Oxygen ProcessSteel-making Facilities for which Construction is Commenced afterJanuary 20, 1983</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">OSewage Treatment Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">PPrimary Copper Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">QPrimary Zinc Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">RPrimary Lead Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">SPrimary AluminumReduction Plants <SU>10</SU>
                  </ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">TPhosphate Fertilizer Industry: Wet ProcessPhosphoric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">UPhosphate Fertilizer Industry:Superphosphoric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">VPhosphate FertilizerIndustry: Diammonium Phosphate Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">WPhosphate Fertilizer Industry: TripleSuperphosphate Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">XPhosphate Fertilizer Industry: Granular Triple SuperphosphateStorage Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">YCoal Preparation Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">ZFerroalloy Production Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AASteel Plants: ElectricArc Furnaces Constructed after October 21, 1974 and on or before August17, 1983</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AAaSteel Plants: Electric Arc Furnaces and Argon-Oxygen DecarburizationVessels Constructed after August 7, 1983</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">BBKraft Pulp Mills <SU>11</SU>
                  </ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">CCGlass Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">DDGrain Elevators</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <PRTPAGE P="34"/>
                  <ENT I="01">EESurface Coating of Metal Furniture</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">GGStationary Gas Turbines</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">HHLime Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">KKLead-Acid Battery Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">LLMetallic Mineral Processing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">MMAutomobile and Light Duty Truck SurfaceCoating Operations</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">NNPhosphate Rock Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">PPAmmonium Sulfate Manufacture</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">QQGraphic Arts Industry:Publication Rotogravure Printing</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">RRPressure Sensitive Tape and Label SurfaceCoating Standards</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">SSIndustrial SurfaceCoating: Large Appliances</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">TTMetal Coil Surface Coating</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">UUAsphalt Processing andAsphalt Roof Manufacture</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">VVEquipment Leaks of VOC in Synthetic OrganicChemical Manufacturing Industry</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">WWBeverage Can SurfaceCoating Industry</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">XXBulk Gasoline Terminals</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AAANew Residential Wood Heaters</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">BBBRubber TireManufacturing Industry</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">DDDVOC Emissions fromPolymer Manufacturing Industry</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">FFFFlexible Vinyl andUrethane Coating and Printing</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">GGGEquipment Leaks of VOC in Petroleum Refineries</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">HHHSynthetic FiberProduction Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">IIIVOC Emissions from Synthetic Organic Chemical Manufacturing Industry Air Oxidation Unit Processes</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">JJJPetroleum Dry Cleaners</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">KKKEquipment Leaks of VOC from Onshore Natural Gas Processing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">LLLOnshore Natural Gas Processing: SO<E T="52">2</E> Emissions</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">NNNVOC Emissions from Synthetic Organic Chemical Manufacturing Industry Distillation Operations</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <PRTPAGE P="35"/>
                  <ENT I="01">OOONonmetallic Mineral Processing Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">PPPWool Fiberglass Insulation Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">QQQVOC Emissions from Petroleum Refinery Wastewater Systems</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">RRRVOCs from Synthetic Organic Chemical Manufacturing Industry Reactor Processes</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">SSSMagnetic Tape Coating Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">TTTIndustrial Surface Coating: Surface Coating of Plastic Parts for Business Machines</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">UUUCalciners and Dryers in Mineral Industries</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">VVVPolymeric Coating of Supporting Substrates Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">WWWMunicipal Solid Waste Landfills</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AAAASmall Municipal Waste Combustion Units for which Construction is Commenced after August 30, 1999 or for which Modification or Reconstruction isCommenced after June 6, 2001</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">BBBBSmall Municipal Waste Combustion Units Constructed on or before August 30, 1999 (Emission Guidelines and Compliance Times)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">CCCCCommercial and Industrial Solid Waste Incineration Units for which Construction is Commenced after November, 30, 1999 or for which Modification or Reconstruction is Commenced on or after June 1, 2001</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">DDDDCommercial and Industrial Solid Waste Incineration Units thatCommenced Construction on or before November 30, 1999 (Emission Guidelines and Compliance Times)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <TNOTE>
                  <SU>1</SU> Any authority within any subpart of this part that is not delegable, is not delegated. Please refer to Attachment B to the delegation letters for a listing of the NSPS authorities excluded from delegation.</TNOTE>
                <TNOTE>
                  <SU>2</SU> Washington State Department of Ecology, for 40 CFR 60.17(h)(1), (h)(2), (h)(3) and 40 CFR part 60, subpart AAAA, as in effect on June 6, 2001; for 40 CFR part 60, subpart CCCC, as in effect on June 1, 2001; and for all other NSPS delegated, as in effect February 20, 2001.</TNOTE>
                <TNOTE>
                  <SU>3</SU> Benton Clean Air Authority, for 40 CFR 60.17(h)(1), (h)(2), (h)(3) and 40 CFR part 60, subpart AAAA, as in effect on June 6, 2001; for 40 CFR part 60, subpart CCCC, as in effect on June 1, 2001; and for all other NSPS delegated, as in effect February 20, 2001.</TNOTE>
                <TNOTE>
                  <SU>4</SU> Northwest Air Pollution Authority, for all NSPS delegated, as in effect on July 1, 2000.</TNOTE>
                <TNOTE>
                  <SU>5</SU> Olympic Regional Clean Air Authority, for 40 CFR 60.17(h)(1), (h)(2), (h)(3) and 40 CFR part 60, subpart AAAA, as in effect on June 6, 2001; for 40 CFR part 60, subpart CCCC, as in effect on June 1, 2001; and for all other NSPS delegated, as in effect February 20, 2001.</TNOTE>
                <TNOTE>
                  <SU>6</SU> Puget Sound Clean Air Authority, for all NSPS delegated, as in effect on July 1, 2002.</TNOTE>
                <TNOTE>
                  <SU>7</SU> Spokane County Air Pollution Control Authority, for 40 CFR 60.17(h)(1), (h)(2), (h)(3) and 40 CFR part 60, subpart AAAA, as in effect on June 6, 2001; for 40 CFR part 60, subpart CCCC, as in effect on June 1, 2001; and for all other NSPS delegated, as in effect February 20, 2001.</TNOTE>
                <TNOTE>

                  <SU>8</SU> Southwest Clean Air Agency, for all NSPS delegated, as in effect on July 1, 2000.<PRTPAGE P="36"/>
                </TNOTE>
                <TNOTE>
                  <SU>9</SU> Yakima Regional Clean Air Authority, for 40 CFR 60.17(h)(1), (h)(2), (h)(3) and 40 CFR part 60, subpart AAAA, as in effect on June 6, 2001; for 40 CFR part 60, subpart CCCC, as in effect on June 1, 2001; and for all other NSPS delegated, as in effect February 20, 2001.</TNOTE>
                <TNOTE>
                  <SU>10</SU> Subpart S of this part is not delegated to local agencies in Washington because the Washington State Department of Ecology retains sole authority to regulate Primary Aluminum Plants, pursuant to Washington Administrative Code 173-415-010.</TNOTE>
                <TNOTE>
                  <SU>11</SU> Subpart BB of this part is not delegated to local agencies in Washington because the Washington State Department of Ecology retains sole authority to regulate Kraft and Sulfite Pulping Mills, pursuant to Washington State Administrative Code 173-405-012 and 173-410-012.</TNOTE>
              </GPOTABLE>
              <P>(XX) State of West Virginia: Air Pollution Control Commission, 1558 Washington Street East, Charleston, WV 25311.</P>
              <P>(YY) Wisconsin—Wisconsin Department of Natural Resources, P.O. Box 7921, Madison, WI 53707.</P>

              <P>(ZZ) State of Wyoming, Department of Environmental Quality, Air Quality Division, Herschler Building, 122 West 25th Street, Cheyenne, WY 82002.
              </P>
              <NOTE>
                <HD SOURCE="HED">Note:</HD>
                <P>For a table listing Region VIII's NSPS delegation status, see paragraph (c) of this section.</P>
              </NOTE>
              

              <P>(AAA) Territory of Guam: Guam Environmental Protection Agency, Post Office Box 2999, Agana, Guam 96910.
              </P>
              <NOTE>
                <HD SOURCE="HED">Note:</HD>
                <P>For tables listing the delegation status of agencies in Region IX, see paragraph (d) of this section.</P>
              </NOTE>
              
              <P>(BBB) Commonwealth of Puerto Rico: Commonwealth of Puerto Rico Environmental Quality Board, P.O. Box 11488, Santurce, PR 00910,  Attention: Air Quality Area Director (see table under § 60.4(b)(FF)(1)).</P>
              <P>(CCC) U.S. Virgin Islands: U.S. Virgin Islands Department of Conservation and Cultural Affairs, P.O. Box 578, Charlotte Amalie, St. Thomas, VI 00801.</P>

              <P>(DDD) American Samoa Environmental Protection Agency, Pago Pago, American Samoa 96799.
              </P>
              <NOTE>
                <HD SOURCE="HED">Note:</HD>
                <P>For tables listing the delegation status of agencies in Region IX, see paragraph (d) of this section.</P>
              </NOTE>
              

              <P>(EEE) Commonwealth of the Northern Mariana Islands, Division of Environmental Quality, P.O. Box 1304, Saipan, MP 96950.
              </P>
              <NOTE>
                <HD SOURCE="HED">Note:</HD>
                <P>For tables listing the delegation status of agencies in Region IX, see paragraph (d) of this section.</P>
              </NOTE>
              
              <P>(c) The following is a table indicating the delegation status of New Source Performance Standards for Region VIII.</P>
              <GPOTABLE CDEF="s100,8,8,8,8,8,8" COLS="7" OPTS="L2">
                <TTITLE>Delegation Status of New Source Performance Standards</TTITLE>
                <TDESC>[(NSPS) for Region VIII]</TDESC>
                <BOXHD>
                  <CHED H="1">Subpart</CHED>
                  <CHED H="1">CO</CHED>
                  <CHED H="1">MT</CHED>
                  <CHED H="1">ND</CHED>
                  <CHED H="1">SD</CHED>
                  <CHED H="1">UT</CHED>
                  <CHED H="1">WY</CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">A—General Provisions</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">D—Fossil Fuel Fired Steam Generators</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Da—Electric Utility Steam Generators</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Db—Industrial-Commercial—Institutional Steam Generators</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Dc—Industrial-Commercial—Institutional Steam Generators</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">E—Incinerators</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Ea—Municipal Waste Combustors</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Eb-Large Municipal Waste Combustors</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Ec-Hospital/Medical/Infectious Waste Incinerators</ENT>
                  <ENT>(*)</ENT>
                  <ENT/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">F—Portland Cement Plants</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">G—Nitric Acid Plants</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">H—Sulfuric Acid Plants</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">I—Asphalt Concrete Plants</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">J—Petroleum Refineries</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">K—Petroleum Storage Vessels (after 6/11/73 &amp; prior to <LI>5/19/78)</LI>
                  </ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Ka—Petroleum Storage Vessels (after 5/18/78 &amp; prior to <LI>7/23/84)</LI>
                  </ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Kb—Petroleum Storage Vessels (after 7/23/84)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">L—Secondary Lead Smelters</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">M—Secondary Brass &amp; Bronze Production Plants</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">N—Primary Emissions from Basic Oxygen Process Furnaces (after 6/11/73)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <PRTPAGE P="37"/>
                  <ENT I="01">Na—Secondary Emissions from Basic Oxygen Process Furnaces (after 1/20/83)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">O—Sewage Treatment Plants</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">P—Primary Copper Smelters</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Q—Primary Zinc Smelters</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">R—Primary Lead Smelters</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">S—Primary Aluminum Reduction Plants</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">T—Phosphate Fertilizer Industry: Wet Process Phosphoric Plants</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">U—Phosphate Fertilizer Industry: Superphosphoric Acid Plants</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">V—Phosphate Fertilizer Industry: Diammonium Phosphate Plants</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">W—Phosphate Fertilizer Industry: Triple Superphosphate Plants</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">X—Phosphate Fertilizer Industry: Granular Triple Superphosphate Storage Facilities</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Y—Coal Preparation Plants</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Z—Ferroalloy Production Facilities</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AA—Steel Plants: Electric Arc Furnaces (10/21/74-8/17/83)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AAa—Steel Plants: Electric Arc Furnaces and Argon-Oxygen Decarburization Vessels (after 8/7/83)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">BB—Kraft Pulp Mills</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">CC—Glass Manufacturing Plants</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">DD—Grain Elevator</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">EE—Surface Coating of Metal Furniture</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">GG—Stationary Gas Turbines</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">HH—Lime Manufacturing Plants</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">KK—Lead-Acid Battery Manufacturing Plants</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">LL—Metallic Mineral Processing Plants</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">MM—Automobile &amp; Light Duty Truck Surface Coating Operations</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">NN—Phosphate Rock Plants</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">PP—Ammonium Sulfate Manufacturing</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">QQ—Graphic Arts Industry: Publication Rotogravure Printing</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">RR—Pressure Sensitive Tape &amp; Label Surface Coating</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">SS—Industrial Surface Coating: Large Applications</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">TT—Metal Coil Surface Coating</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">UU—Asphalt Processing &amp; Asphalt Roofing Manufacture</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">VV—Synthetic Organic Chemicals Manufacturing: Equipment Leaks of VOC</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">WW—Beverage Can Surface Coating Industry</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">XX—Bulk Gasoline Terminals</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AAA—Residential Wood Heaters</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">BBB—Rubber Tires</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">DDD—VOC Emissions from Polymer Manufacturing Industry</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">FFF—Flexible Vinyl &amp; Urethane Coating &amp; Printing</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">GGG—Equipment Leaks of VOC in Petroleum Refineries</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">HHH—Synthetic Fiber Production</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">III—VOC Emissions from the Synthetic Organic Chemical Manufacturing Industry Air Oxidation Unit Processes</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">JJJ—Petroleum Dry Cleaners</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">KKK—Equipment Leaks of VOC from Onshore Natural Gas Processing Plants</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">LLL—Onshore Natural Gas Processing: SO<E T="52">2</E> Emissions</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">NNN—VOC Emissions from the Synthetic Organic Chemical Manufacturing Industry Distillation Operations</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">OOO—Nonmetallic Mineral Processing Plants</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">PPP—Wool Fiberglass Insulation Manufacturing Plants</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">QQQ—VOC Emissions from Petroleum Refinery Wastewater Systems</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT O="xl"/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <PRTPAGE P="38"/>
                  <ENT I="01">RRR—VOC Emissions from Synthetic Organic Chemistry Manufacturing Industry (SOCMI) Reactor Processes</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">SSS—Magnetic Tape Industry</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">TTT—Plastic Parts for Business Machine Coatings</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">UUU—Calciners and Dryers in Mineral Industries</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">VVV—Polymeric Coating of Supporting Substrates</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT/>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">WWW—Municipal Solid Waste Landfills</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AAAA—Small Municipal Waste Combustors</ENT>
                  <ENT/>
                  <ENT> (*)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>(*)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">CCCC—Commercial and Industrial Solid Waste Incineration Units</ENT>
                  <ENT/>
                  <ENT>(*)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>(*)</ENT>
                </ROW>
                <TNOTE>(*) Indicates approval of state regulation.</TNOTE>
                <TNOTE>
                  <SU>1</SU> Indicates approval of New Source Performance Standards as part of the State Implementation Plan (SIP).</TNOTE>
              </GPOTABLE>
              <P>(d) The following tables list the specific Part 60 standards that have been delegated unchanged to the air pollution control agencies in Region IX. The (X) symbol is used to indicate each standard that has been delegated. The following provisions of this subpart are not delegated: §§ 60.4(b), 60.8(b), 60.9, 60.11(b), 60.11(e), 60.13(a), 60.13(d)(2), 60.13(g), 60.13(i).</P>
              <P>(1) <E T="03">Arizona.</E> The following table identifies delegations as of June 15, 2001:</P>
              <GPOTABLE CDEF="xls24,r50,8C,8C,8C,8C" COLS="6" OPTS="L2">
                <TTITLE>Delegation Status for New Source Performance Standards for Arizona</TTITLE>
                <BOXHD>
                  <CHED H="1"/>
                  <CHED H="1">Subpart</CHED>
                  <CHED H="1">Air pollution control agency</CHED>
                  <CHED H="2">Arizona DEQ</CHED>
                  <CHED H="2">Maricopa County</CHED>
                  <CHED H="2">Pima County</CHED>
                  <CHED H="2">Pinal County</CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">A</ENT>
                  <ENT>General Provisions</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">D</ENT>
                  <ENT>Fossil-Fuel Fired Steam Generators Constructed After August 17, 1971</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Da</ENT>
                  <ENT>Electric Utility Steam Generating Units Constructed After September 18, 1978</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Db</ENT>
                  <ENT>Industrial-Commercial-Institutional Steam Generating Units</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Dc</ENT>
                  <ENT>Small Industrial Steam Generating Units</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">E</ENT>
                  <ENT>Incinerators</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Ea</ENT>
                  <ENT>Municipal Waste Combustors Constructed After December 20, 1989 and On or Before September 20, 1994</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Eb</ENT>
                  <ENT>Municipal Waste Combustors Constructed After September 20, 1994</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Ec</ENT>
                  <ENT>Hospital/Medical/Infectious Waste Incinerators for Which Construction is Commenced After June 20, 1996</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">F</ENT>
                  <ENT>Portland Cement Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">G</ENT>
                  <ENT>Nitric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">H</ENT>
                  <ENT>Sulfuric Acid Plant</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">I</ENT>
                  <ENT>Hot Mix Asphalt Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">J</ENT>
                  <ENT>Petroleum Refineries</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">K</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification Commenced After June 11, 1973, and Prior to May 19, 1978</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Ka</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification Commenced After May 18, 1978, and Prior to July 23, 1984</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Kb</ENT>
                  <ENT>Volatile Organic Liquid Storage Vessels (Including Petroleum Liquid Storage Vessels) for Which Construction, Reconstruction, or Modification Commenced After July 23, 1984</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">L</ENT>
                  <ENT>Secondary Lead Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">M</ENT>
                  <ENT>Secondary Brass and Bronze Production Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">N</ENT>
                  <ENT>Primary Emissions from Basic Oxygen Process Furnaces for Which Construction is Commenced After June 11, 1973</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Na</ENT>
                  <ENT>Secondary Emissions from Basic Oxygen Process Steelmaking Facilities for Which Construction is Commenced After January 20, 1983</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">O</ENT>
                  <ENT>Sewage Treatment Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">P</ENT>
                  <ENT>Primary Copper Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Q</ENT>
                  <ENT>Primary Zinc Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">R</ENT>
                  <ENT>Primary Lead Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <PRTPAGE P="39"/>
                  <ENT I="01">S</ENT>
                  <ENT>Primary Aluminum Reduction Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">T</ENT>
                  <ENT>Phosphate Fertilizer Industry: Wet Process Phosphoric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">U</ENT>
                  <ENT>Phosphate Fertilizer Industry: Superphosphoric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">V</ENT>
                  <ENT>Phosphate Fertilizer Industry: Diammonium Phosphate Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">W</ENT>
                  <ENT>Phosphate Fertilizer Industry: Triple Superphosphate Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">X</ENT>
                  <ENT>Phosphate Fertilizer Industry: Granular Triple Superphosphate Storage Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Y</ENT>
                  <ENT>Coal Preparation Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Z</ENT>
                  <ENT>Ferroalloy Production Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AA</ENT>
                  <ENT>Steel Plants: Electric Arc Furnaces Constructed After October 21, 1974 and On or Before August 17, 1983</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AAa</ENT>
                  <ENT>Steel Plants: Electric Arc Furnaces and Argon-Oxygen Decarburization Vessels Constructed After August 7, 1983</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">BB</ENT>
                  <ENT>Kraft pulp Mills</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">CC</ENT>
                  <ENT>Glass Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">DD</ENT>
                  <ENT>Grain Elevators</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">EE</ENT>
                  <ENT>Surface Coating of Metal Furniture</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">FF</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">GG</ENT>
                  <ENT>Stationary Gas Turbines</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">HH</ENT>
                  <ENT>Lime Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">KK</ENT>
                  <ENT>Lead-Acid Battery Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">LL</ENT>
                  <ENT>Metallic Mineral Processing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">MM</ENT>
                  <ENT>Automobile and Light Duty Trucks Surface Coating Operations</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">NN</ENT>
                  <ENT>Phosphate Rock Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">PP</ENT>
                  <ENT>Ammonium Sulfate Manufacture</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">QQ</ENT>
                  <ENT>Graphic Arts Industry: Publication Rotogravure Printing</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">RR</ENT>
                  <ENT>Pressure Sensitive Tape and Label Surface Coating Operations</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">SS</ENT>
                  <ENT>Industrial Surface Coating: Large Appliances</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">TT</ENT>
                  <ENT>Metal Coil Surface Coating</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">UU</ENT>
                  <ENT>Asphalt Processing and Asphalt Roofing Manufacture</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">VV</ENT>
                  <ENT>Equipment Leaks of VOC in the Synthetic Organic Chemicals Manufacturing Industry</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">WW</ENT>
                  <ENT>Beverage Can Surface Coating Industry</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">XX</ENT>
                  <ENT>Bulk Gasoline Terminals</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AAA</ENT>
                  <ENT>New Residential Wool Heaters</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">BBB</ENT>
                  <ENT>Rubber Tire Manufacturing Industry</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">CCC</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">DDD</ENT>
                  <ENT>Volatile Organic Compounds (VOC) Emissions from the Polymer Manufacturing Industry</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">EEE</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">FFF</ENT>
                  <ENT>Flexible Vinyl and Urethane Coating and Printing</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">GGG</ENT>
                  <ENT>Equipment Leaks of VOC in Petroleum Refineries</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">HHH</ENT>
                  <ENT>Synthetic Fiber Production Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">III</ENT>
                  <ENT>Volatile Organic Compound (VOC) Emissions From the Synthetic Organic Chemical Manufacturing Industry (SOCMI) Air Oxidation Unit Processes</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">JJJ</ENT>
                  <ENT>Petroleum Dry Cleaners</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">KKK</ENT>
                  <ENT>Equipment Leaks of VOC From Onshore Natural Gas Processing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">LLL</ENT>
                  <ENT>Onshore Natural Gas Processing: SO2 Emissions</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">MMM</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">NNN</ENT>
                  <ENT>Volatile Organic Compound (VOC) Emissions From Synthetic Organic Chemical Manufacturing Industry (SOCMI) Distillation Operations</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">OOO</ENT>
                  <ENT>Nonmetallic Mineral Processing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">PPP</ENT>
                  <ENT>Wool Fiberglass Insulation Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">QQQ</ENT>
                  <ENT>VOC Emissions From Petroleum Refinery Wastewater Systems</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">RRR</ENT>
                  <ENT>Volatile Organic Compound Emissions from Synthetic Organic Chemical Manufacturing Industry (SOCMI) Reactor Processes</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">SSS</ENT>
                  <ENT>Magnetic Tape Coating Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">TTT</ENT>
                  <ENT>Industrial Surface Coating: Surface Coating of Plastic Parts for Business Machines</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">UUU</ENT>
                  <ENT>Calciners and Dryers in Mineral Industries</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">VVV</ENT>
                  <ENT>Polymeric Coating of Supporting Substrates Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">WWW</ENT>
                  <ENT>Municipal Solid Waste Landfills</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
              </GPOTABLE>
              <PRTPAGE P="40"/>
              <P>(2) <E T="03">California.</E> The following tables identify delegations for each of the local air pollution control agencies of California.</P>
              <P>(i) Delegations for Amador County Air Pollution Control District, Antelope Valley Air Pollution Control District, Bay Area Air Quality Management District, and Butte County Air Pollution Control District are shown in the following table:</P>
              <GPOTABLE CDEF="xls24,r100,8C,8C,8C,8C" COLS="6" OPTS="L2">
                <TTITLE>Delegation Status for New Source Performance Standards for Amador County APCD, Antelope Valley APCD, Bay Area AQMD, and Butte County AQMD</TTITLE>
                <BOXHD>
                  <CHED H="1"/>
                  <CHED H="1">Subpart</CHED>
                  <CHED H="1">Air pollution control agency</CHED>
                  <CHED H="2">Amador County APCD</CHED>
                  <CHED H="2">Antelope Valley APCD</CHED>
                  <CHED H="2">Bay Area AQMD</CHED>
                  <CHED H="2">Butte County APCD</CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">A</ENT>
                  <ENT>General Provisions</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">D</ENT>
                  <ENT>Fossil-Fuel Fired Steam Generators Constructed After August 17, 1971</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Da</ENT>
                  <ENT>Electric Utility Steam Generating Units Constructed After September 18, 1978</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Db</ENT>
                  <ENT>Industrial-Commercial-Institutional Steam Generating Units</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Dc</ENT>
                  <ENT>Small Industrial Steam Generating Units</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">E</ENT>
                  <ENT>Incinerators</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Ea</ENT>
                  <ENT>Municipal Waste Combustors Constructed After December 20,1989 and On or Before September 20, 1994</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Eb</ENT>
                  <ENT>Municipal Waste Combustors Constructed After September 20,1994</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Ec</ENT>
                  <ENT>Hospital/Medical/Infectious Waste Incinerators for Which Construction is Commenced After June 20, 1996</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">F</ENT>
                  <ENT>Portland Cement Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">G</ENT>
                  <ENT>Nitric Acid Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">H</ENT>
                  <ENT>Sulfuric Acid Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">I</ENT>
                  <ENT>Hot Mix Asphalt Facilities</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">J</ENT>
                  <ENT>Petroleum Refineries</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">K</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification Commenced After June 11, 1973, and Prior to May 19, 1978</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Ka</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification Commenced After May 18, 1978, and Prior to July 23, 1984</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Kb</ENT>
                  <ENT>Volatile Organic Liquid Storage Vessels (Including Petroleum Liquid Storage Vessels) for Which Construction, Reconstruction, or Modification Commenced After July 23,1984</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">L</ENT>
                  <ENT>Secondary Lead Smelters</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">M</ENT>
                  <ENT>Secondary Brass and Bronze Production Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">N</ENT>
                  <ENT>Primary Emissions from Basic Oxygen Process Furnaces for Which Construction is Commenced After June 11, 1973</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Na</ENT>
                  <ENT>Secondary Emissions from Basic Oxygen Process Steelmaking Facilities for Which Construction is Commenced After January 20, 1983</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">O</ENT>
                  <ENT>Sewage Treatment Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">P</ENT>
                  <ENT>Primary Copper Smelters</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Q</ENT>
                  <ENT>Primary Zinc Smelters</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">R</ENT>
                  <ENT>Primary Lead Smelters</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">S</ENT>
                  <ENT>Primary Aluminum Reduction Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">T</ENT>
                  <ENT>Phosphate Fertilizer Industry: Wet Process Phosphoric Acid Plants</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">U</ENT>
                  <ENT>Phosphate Fertilizer Industry: Superphosphoric Acid Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">V</ENT>
                  <ENT>Phosphate Fertilizer Industry: Diammonium Phosphate Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">W</ENT>
                  <ENT>Phosphate Fertilizer Industry: Triple Superphosphate Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">X</ENT>
                  <ENT>Phosphate Fertilizer Industry: Granular Triple Superphosphate Storage Facilities</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Y</ENT>
                  <ENT>Coal Preparation Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Z</ENT>
                  <ENT>Ferroalloy Production Facilities</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">AA</ENT>
                  <ENT>Steel Plants: Electric Arc Furnaces Constructed After October 21, 1974 and On or Before August 17, 1983</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">AAa</ENT>
                  <ENT>Steel Plants: Electric Arc Furnaces and Argon-Oxygen Decarburization Vessels Constructed After August 7, 1983</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">BB</ENT>
                  <ENT>Kraft pulp Mills</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">CC</ENT>
                  <ENT>Glass Manufacturing Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">DD</ENT>
                  <ENT>Grain Elevators</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">EE</ENT>
                  <ENT>Surface Coating of Metal Furniture</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">FF</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">GG</ENT>
                  <ENT>Stationary Gas Turbines</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">HH</ENT>
                  <ENT>Lime Manufacturing Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <PRTPAGE P="41"/>
                  <ENT I="01">KK</ENT>
                  <ENT>Lead-Acid Battery Manufacturing Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">LL</ENT>
                  <ENT>Metallic Mineral Processing Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">MM</ENT>
                  <ENT>Automobile and Light Duty Trucks Surface Coating Operations</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">NN</ENT>
                  <ENT>Phosphate Rock Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">PP</ENT>
                  <ENT>Ammonium Sulfate Manufacture</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">QQ</ENT>
                  <ENT>Graphic Arts Industry: Publication Rotogravure Printing</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">RR</ENT>
                  <ENT>Pressure Sensitive Tape and Label Surface Coating Operations</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">SS</ENT>
                  <ENT>Industrial Surface Coating: Large Appliances</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">TT</ENT>
                  <ENT>Metal Coil Surface Coating</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">UU</ENT>
                  <ENT>Asphalt Processing and Asphalt Roofing Manufacture</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">VV</ENT>
                  <ENT>Equipment Leaks of VOC in the Synthetic Organic Chemicals Manufacturing Industry</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">WW</ENT>
                  <ENT>Beverage Can Surface Coating Industry</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">XX</ENT>
                  <ENT>Bulk Gasoline Terminals</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">AAA</ENT>
                  <ENT>New Residential Wool Heaters</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">BBB</ENT>
                  <ENT>Rubber Tire Manufacturing Industry</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">CCC</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">DDD</ENT>
                  <ENT>Volatile Organic Compounds (VOC) Emissions from the Polymer Manufacturing Industry</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">EEE</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">FFF</ENT>
                  <ENT>Flexible Vinyl and Urethane Coating and Printing</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">GGG</ENT>
                  <ENT>Equipment Leaks of VOC in Petroleum Refineries</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">HHH</ENT>
                  <ENT>Synthetic Fiber Production Facilities</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">III</ENT>
                  <ENT>Volatile Organic Compound (VOC) Emissions From the Synthetic Organic Chemical Manufacturing Industry (SOCMI) Air Oxidation Unit Processes</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">JJJ</ENT>
                  <ENT>Petroleum Dry Cleaners</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">KKK</ENT>
                  <ENT>Equipment Leaks of VOC From Onshore Natural Gas Processing Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">LLL</ENT>
                  <ENT>Onshore Natural Gas Processing: SO2 Emissions</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">MMM</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">NNN</ENT>
                  <ENT>Volatile Organic Compound (VOC) Emissions From Synthetic Organic Chemical Manufacturing Industry (SOCMI) Distillation Operations</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">OOO</ENT>
                  <ENT>Nonmetallic Mineral Processing Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">PPP</ENT>
                  <ENT>Wool Fiberglass Insulation Manufacturing Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">QQQ</ENT>
                  <ENT>VOC Emissions From Petroleum Refinery Wastewater Systems</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">RRR</ENT>
                  <ENT>Volatile Organic Compound Emissions from Synthetic Organic Chemical Manufacturing Industry (SOCMI) Reactor Processes</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">SSS</ENT>
                  <ENT>Magnetic Tape Coating Facilities</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">TTT</ENT>
                  <ENT>Industrial Surface Coating: Surface Coating of Plastic Parts for Business Machines</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">UUU</ENT>
                  <ENT>Calciners and Dryers in Mineral Industries</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">VVV</ENT>
                  <ENT>Polymeric Coating of Supporting Substrates Facilities</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">WWW</ENT>
                  <ENT>Municipal Solid Waste Landfills</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
              </GPOTABLE>
              <P>(ii) [Reserved]</P>
              <P>(iii) Delegations for Glenn County Air Pollution Control District, Great Basin Unified Air Pollution Control District, Imperial County Air Pollution Control District, and Kern County Air Pollution Control District are shown in the following table:</P>
              <GPOTABLE CDEF="xls24,r50,8C,8C,8C,8C" COLS="6" OPTS="L2">
                <TTITLE>Delegation Status for New Source Performance Standards for Glenn County APCD, Great Basin Unified APCD, Imperial County APCD, and Kern County APCD</TTITLE>
                <BOXHD>
                  <CHED H="1"/>
                  <CHED H="1">Subpart</CHED>
                  <CHED H="1">Air pollution control agency</CHED>
                  <CHED H="2">Glenn<LI>County APCD</LI>
                  </CHED>
                  <CHED H="2">Great Basin Unified APCD</CHED>
                  <CHED H="2">Imperial County APCD</CHED>
                  <CHED H="2">Kern County APCD</CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">A</ENT>
                  <ENT>General Provisions</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">D</ENT>
                  <ENT>Fossil-Fuel Fired Steam Generators Constructed After August 17, 1971</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <PRTPAGE P="42"/>
                  <ENT I="01">Da</ENT>
                  <ENT>Electric Utility Steam Generating Units Constructed AfterSeptember 18, 1978</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Db</ENT>
                  <ENT>Industrial-Commercial-Institutional Steam Generating Units</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Dc</ENT>
                  <ENT>Small Industrial Steam Generating Units</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">E</ENT>
                  <ENT>Incinerators</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Ea</ENT>
                  <ENT>Municipal Waste Combustors Constructed After December 20, 1989 and On or Before September 20, 1994</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Eb</ENT>
                  <ENT>Municipal Waste Combustors Constructed After September 20,1994</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Ec</ENT>
                  <ENT>Hospital/Medical/Infectious Waste Incinerators for Which Construction is Commenced After June 20, 1996</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">F</ENT>
                  <ENT>Portland Cement Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">G</ENT>
                  <ENT>Nitric Acid Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">H</ENT>
                  <ENT>Sulfuric Acid Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">I</ENT>
                  <ENT>Hot Mix Asphalt Facilities</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">J</ENT>
                  <ENT>Petroleum Refineries</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">K</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification Commenced After June 11, 1973, and Prior to May 19, 1978</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Ka</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification Commenced After May 18, 1978, and Prior to July 23, 1984</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Kb</ENT>
                  <ENT>Volatile Organic Liquid Storage Vessels (Including Petroleum Liquid Storage Vessels) for Which Construction, Reconstruction, or Modification Commenced After July 23, 1984</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">L</ENT>
                  <ENT>Secondary Lead Smelters</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">M</ENT>
                  <ENT>Secondary Brass and Bronze Production Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">N</ENT>
                  <ENT>Primary Emissions from Basic Oxygen Process Furnaces forWhich Construction is Commenced After June 11, 1973</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Na</ENT>
                  <ENT>Secondary Emissions from Basic Oxygen Process Steelmaking Facilities for Which Construction is Commenced After January 20, 1983</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">O</ENT>
                  <ENT>Sewage Treatment Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">P</ENT>
                  <ENT>Primary Copper Smelters</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Q</ENT>
                  <ENT>Primary Zinc Smelters</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">R</ENT>
                  <ENT>Primary Lead Smelters</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">S</ENT>
                  <ENT>Primary Aluminum Reduction Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">T</ENT>
                  <ENT>Phosphate Fertilizer Industry: Wet Process Phosphoric AcidPlants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">U</ENT>
                  <ENT>Phosphate Fertilizer Industry: Superphosphoric Acid Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">V</ENT>
                  <ENT>Phosphate Fertilizer Industry: Diammonium Phosphate Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">W</ENT>
                  <ENT>Phosphate Fertilizer Industry: Triple Superphosphate Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">X</ENT>
                  <ENT>Phosphate Fertilizer Industry: Granular Triple Superphosphate Storage Facilities</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Y</ENT>
                  <ENT>Coal Preparation Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Z</ENT>
                  <ENT>Ferroalloy Production Facilities</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AA</ENT>
                  <ENT>Steel Plants: Electric Arc Furnaces Constructed After October 21, 1974 and On or Before August 17, 1983</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AAa</ENT>
                  <ENT>Steel Plants: Electric Arc Furnaces and Argon-Oxygen Decarburization Vessels Constructed After August 7, 1983</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">BB</ENT>
                  <ENT>Kraft pulp Mills</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">CC</ENT>
                  <ENT>Glass Manufacturing Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">DD</ENT>
                  <ENT>Grain Elevators</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">EE</ENT>
                  <ENT>Surface Coating of Metal Furniture</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">FF</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">GG</ENT>
                  <ENT>Stationary Gas Turbines</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">HH</ENT>
                  <ENT>Lime Manufacturing Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">KK</ENT>
                  <ENT>Lead-Acid Battery Manufacturing Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">LL</ENT>
                  <ENT>Metallic Mineral Processing Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">MM</ENT>
                  <ENT>Automobile and Light Duty Trucks Surface Coating Operations</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">NN</ENT>
                  <ENT>Phosphate Rock Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">PP</ENT>
                  <ENT>Ammonium Sulfate Manufacture</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">QQ</ENT>
                  <ENT>Graphic Arts Industry: Publication Rotogravure Printing</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">RR</ENT>
                  <ENT>Pressure Sensitive Tape and Label Surface Coating Operations</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">SS</ENT>
                  <ENT>Industrial Surface Coating: Large Appliances</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">TT</ENT>
                  <ENT>Metal Coil Surface Coating</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">UU</ENT>
                  <ENT>Asphalt Processing and Asphalt Roofing Manufacture</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <PRTPAGE P="43"/>
                  <ENT I="01">VV</ENT>
                  <ENT>Equipment Leaks of VOC in the Synthetic Organic Chemicals Manufacturing Industry</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">WW</ENT>
                  <ENT>Beverage Can Surface Coating Industry</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">XX</ENT>
                  <ENT>Bulk Gasoline Terminals</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">AAA</ENT>
                  <ENT>New Residential Wool Heaters</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">BBB</ENT>
                  <ENT>Rubber Tire Manufacturing Industry</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">CCC</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">DDD</ENT>
                  <ENT>Volatile Organic Compounds (VOC) Emissions from the Polymer Manufacturing Industry</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">EEE</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">FFF</ENT>
                  <ENT>Flexible Vinyl and Urethane Coating and Printing</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">GGG</ENT>
                  <ENT>Equipment Leaks of VOC in Petroleum Refineries</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">HHH</ENT>
                  <ENT>Synthetic Fiber Production Facilities</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">III</ENT>
                  <ENT>Volatile Organic Compound (VOC) Emissions From the Synthetic Organic Chemical Manufacturing Industry (SOCMI)Air Oxidation Unit Processes</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">JJJ</ENT>
                  <ENT>Petroleum Dry Cleaners</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">KKK</ENT>
                  <ENT>Equipment Leaks of VOC From Onshore Natural Gas ProcessingPlants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">LLL</ENT>
                  <ENT>Onshore Natural Gas Processing: SO2 Emissions</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">MMM</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">NNN</ENT>
                  <ENT>Volatile Organic Compound (VOC) Emissions From Synthetic Organic Chemical Manufacturing Industry (SOCMI)Distillation Operations</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">OOO</ENT>
                  <ENT>Nonmetallic Mineral Processing Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">PPP</ENT>
                  <ENT>Wool Fiberglass Insulation Manufacturing Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">QQQ</ENT>
                  <ENT>VOC Emissions From Petroleum Refinery Wastewater Systems</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">RRR</ENT>
                  <ENT>Volatile Organic Compound Emissions from Synthetic Organic Chemical Manufacturing Industry (SOCMI) Reactor Processes</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">SSS</ENT>
                  <ENT>Magnetic Tape Coating Facilities</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">TTT</ENT>
                  <ENT>Industrial Surface Coating: Surface Coating of Plastic Parts for Business Machines</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">UUU</ENT>
                  <ENT>Calciners and Dryers in Mineral Industries</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">VVV</ENT>
                  <ENT>Polymeric Coating of Supporting Substrates Facilities</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">WWW</ENT>
                  <ENT>Municipal Solid Waste Landfills</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
              </GPOTABLE>
              <P>(iv) Delegations for Lake County Air Quality Management District, Lassen County Air Pollution Control District, Mariposa County Air Pollution Control District, and Mendocino County Air Pollution Control District are shown in the following table:</P>
              <GPOTABLE CDEF="xls24,r50,8C,8C,8C,8C" COLS="6" OPTS="L2">
                <TTITLE>Delegation Status for New Source Performance Standards for Lake County Air Quality Management District, Lassen County Air Pollution Control District, Mariposa County Air Pollution Control District, and Mendocino County Air Pollution Control District</TTITLE>
                <BOXHD>
                  <CHED H="1"/>
                  <CHED H="1">Subpart</CHED>
                  <CHED H="1">Air pollution control agency</CHED>
                  <CHED H="2">Lake County AQMD</CHED>
                  <CHED H="2">Lassen County APCD</CHED>
                  <CHED H="2">Mariposa County AQMD</CHED>
                  <CHED H="2">Mendocino County AQMD</CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">A</ENT>
                  <ENT>General Provisions</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">D</ENT>
                  <ENT>Fossil-Fuel Fired Steam Generators Constructed After August 17, 1971</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Da</ENT>
                  <ENT>Electric Utility Steam Generating Units Constructed After September 18, 1978</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Db</ENT>
                  <ENT>Industrial-Commercial-Institutional Steam Generating Units</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Dc</ENT>
                  <ENT>Small Industrial Steam Generating Units</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">E</ENT>
                  <ENT>Incinerators</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Ea</ENT>
                  <ENT>Municipal Waste Combustors Constructed After December 20, 1989 and On or Before September 20, 1994</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Eb</ENT>
                  <ENT>Municipal Waste Combustors Constructed After September 20,1994</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <PRTPAGE P="44"/>
                  <ENT I="01">Ec</ENT>
                  <ENT>Hospital/Medical/Infectious Waste Incinerators for Which Construction is Commenced After June 20, 1996</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">F</ENT>
                  <ENT>Portland Cement Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">G</ENT>
                  <ENT>Nitric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">H</ENT>
                  <ENT>Sulfuric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">I</ENT>
                  <ENT>Hot Mix Asphalt Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">J</ENT>
                  <ENT>Petroleum Refineries</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">K</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification Commenced After June 11, 1973, and Prior to May 19, 1978</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Ka</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification CommencedAfter May 18, 1978, and Prior to July 23, 1984</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Kb</ENT>
                  <ENT>Volatile Organic Liquid Storage Vessels (Including Petroleum Liquid Storage Vessels) for Which Construction, Reconstruction, or Modification Commenced After July 23,1984</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">L</ENT>
                  <ENT>Secondary Lead Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">M</ENT>
                  <ENT>Secondary Brass and Bronze Production Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">N</ENT>
                  <ENT>Primary Emissions from Basic Oxygen Process Furnaces for Which Construction is Commenced After June 11, 1973</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Na</ENT>
                  <ENT>Secondary Emissions from Basic Oxygen Process Steelmaking Facilities for Which Construction is Commenced AfterJanuary 20, 1983</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">O</ENT>
                  <ENT>Sewage Treatment Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">P</ENT>
                  <ENT>Primary Copper Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Q</ENT>
                  <ENT>Primary Zinc Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">R</ENT>
                  <ENT>Primary Lead Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">S</ENT>
                  <ENT>Primary Aluminum Reduction Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">T</ENT>
                  <ENT>Phosphate Fertilizer Industry: Wet Process Phosphoric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">U</ENT>
                  <ENT>Phosphate Fertilizer Industry: Superphosphoric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">V</ENT>
                  <ENT>Phosphate Fertilizer Industry: Diammonium Phosphate Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">W</ENT>
                  <ENT>Phosphate Fertilizer Industry: Triple Superphosphate Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">X</ENT>
                  <ENT>Phosphate Fertilizer Industry: Granular Triple Superphosphate Storage Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Y</ENT>
                  <ENT>Coal Preparation Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Z</ENT>
                  <ENT>Ferroalloy Production Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AA</ENT>
                  <ENT>Steel Plants: Electric Arc Furnaces Constructed After October 21, 1974 and On or Before August 17, 1983</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AAa</ENT>
                  <ENT>Steel Plants: Electric Arc Furnaces and Argon-Oxygen Decarburization Vessels Constructed After August 7, 1983</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">BB</ENT>
                  <ENT>Kraft Pulp Mills</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">CC</ENT>
                  <ENT>Glass Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">DD</ENT>
                  <ENT>Grain Elevators</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">EE</ENT>
                  <ENT>Surface Coating of Metal Furniture</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">FF</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">GG</ENT>
                  <ENT>Stationary Gas Turbines</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">HH</ENT>
                  <ENT>Lime Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">KK</ENT>
                  <ENT>Lead-Acid Battery Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">LL</ENT>
                  <ENT>Metallic Mineral Processing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">MM</ENT>
                  <ENT>Automobile and Light Duty Trucks Surface Coating Operations</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">NN</ENT>
                  <ENT>Phosphate Rock Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">PP</ENT>
                  <ENT>Ammonium Sulfate Manufacture</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">QQ</ENT>
                  <ENT>Graphic Arts Industry: Publication Rotogravure Printing</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">RR</ENT>
                  <ENT>Pressure Sensitive Tape and Label Surface Coating Operations</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">SS</ENT>
                  <ENT>Industrial Surface Coating: Large Appliances</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">TT</ENT>
                  <ENT>Metal Coil Surface Coating</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">UU</ENT>
                  <ENT>Asphalt Processing and Asphalt Roofing Manufacture</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">VV</ENT>
                  <ENT>Equipment Leaks of VOC in the Synthetic Organic Chemicals Manufacturing Industry</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">WW</ENT>
                  <ENT>Beverage Can Surface Coating Industry</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">XX</ENT>
                  <ENT>Bulk Gasoline Terminals</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">AAA</ENT>
                  <ENT>New Residential Wool Heaters</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">BBB</ENT>
                  <ENT>Rubber Tire Manufacturing Industry</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">CCC</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <PRTPAGE P="45"/>
                  <ENT I="01">DDD</ENT>
                  <ENT>Volatile Organic Compounds (VOC) Emissions from the Polymer Manufacturing Industry</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">EEE</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">FFF</ENT>
                  <ENT>Flexible Vinyl and Urethane Coating and Printing</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">GGG</ENT>
                  <ENT>Equipment Leaks of VOC in Petroleum Refineries</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">HHH</ENT>
                  <ENT>Synthetic Fiber Production Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">III</ENT>
                  <ENT>Volatile Organic Compound (VOC) Emissions From the Synthetic Organic Chemical Manufacturing Industry (SOCMI)Air Oxidation Unit Processes</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">JJJ</ENT>
                  <ENT>Petroleum Dry Cleaners</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">KKK</ENT>
                  <ENT>Equipment Leaks of VOC From Onshore Natural Gas Processing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">LLL</ENT>
                  <ENT>Onshore Natural Gas Processing: SO2 Emissions</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">MMM</ENT>
                  <ENT>(Reserve)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">NNN</ENT>
                  <ENT>Volatile Organic Compound (VOC) Emissions From Synthetic Organic Chemical Manufacturing Industry (SOCMI) Distillation Operations</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">OOO</ENT>
                  <ENT>Nonmetallic Mineral Processing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">PPP</ENT>
                  <ENT>Wool Fiberglass Insulation Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">QQQ</ENT>
                  <ENT>VOC Emissions From Petroleum Refinery Wastewater Systems</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">RRR</ENT>
                  <ENT>Volatile Organic Compound Emissions from Synthetic Organic Chemical Manufacturing Industry (SOCMI) Reactor Processes</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">SSS</ENT>
                  <ENT>Magnetic Tape Coating Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">TTT</ENT>
                  <ENT>Industrial Surface Coating: Surface Coating of Plastic Parts for Business Machines</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">UUU</ENT>
                  <ENT>Calciners and Dryers in Mineral Industries</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">VVV</ENT>
                  <ENT>Polymeric Coating of Supporting Substrates Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">WWW</ENT>
                  <ENT>Municipal Solid Waste Landfills</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
              </GPOTABLE>
              <P>(v) Delegations for Modoc County Air Pollution Control District, Mojave Desert Air Quality Management District, Monterey Bay Unified Air Pollution Control District, and North Coast Unified Air Pollution Control District are shown in the following table:</P>
              <GPOTABLE CDEF="xls24,r100,8C,8C,8C,8C" COLS="6" OPTS="L2">
                <TTITLE>Delegation Status for New Source Performance Standards for Modoc County Air Pollution Control District, Mojave Desert Air Quality Management District, Monterey Bay Unified Air Pollution Control District, and North Coast Unified Air Pollution Control District</TTITLE>
                <BOXHD>
                  <CHED H="1"/>
                  <CHED H="1">Subpart</CHED>
                  <CHED H="1">Air pollution control agency</CHED>
                  <CHED H="2">Modoc County APCD</CHED>
                  <CHED H="2">Mojave Desert AQMD</CHED>
                  <CHED H="2">Monterey Bay Unified APCD</CHED>
                  <CHED H="2">North Coast Unified AQMD</CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">A</ENT>
                  <ENT>General Provisions</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">D</ENT>
                  <ENT>Fossil-Fuel Fired Steam Generators Constructed After August 17, 1971</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Da</ENT>
                  <ENT>Electric Utility Steam Generating Units Constructed After September 18, 1978</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Db</ENT>
                  <ENT>Industrial-Commercial-Institutional Steam Generating Units</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Dc</ENT>
                  <ENT>Small Industrial Steam Generating Units</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">E</ENT>
                  <ENT>Incinerators</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Ea</ENT>
                  <ENT>Municipal Waste Combustors Constructed After December 20, 1989 and On or Before September 20, 1994</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Eb</ENT>
                  <ENT>Municipal Waste Combustors Constructed After September 20,1994</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Ec</ENT>
                  <ENT>Hospital/Medical/Infectious Waste Incinerators for Which Construction is Commenced After June 20, 1996</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">F</ENT>
                  <ENT>Portland Cement Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <PRTPAGE P="46"/>
                  <ENT I="01">G</ENT>
                  <ENT>Nitric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">H</ENT>
                  <ENT>Sulfuric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">I</ENT>
                  <ENT>Hot Mix Asphalt Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">J</ENT>
                  <ENT>Petroleum Refineries</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">K</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification Commenced After June 11, 1973, and Prior to May 19, 1978</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Ka</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification Commenced After May 18, 1978, and Prior to July 23, 1984</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Kb</ENT>
                  <ENT>Volatile Organic Liquid Storage Vessels (Including Petroleum Liquid Storage Vessels) for Which Construction, Reconstruction, or Modification Commenced After July 23, 1984</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">L</ENT>
                  <ENT>Secondary Lead Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">M</ENT>
                  <ENT>Secondary Brass and Bronze Production Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">N</ENT>
                  <ENT>Primary Emissions from Basic Oxygen Process Furnaces for Which Construction is Commenced After June 11, 1973</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Na</ENT>
                  <ENT>Secondary Emissions from Basic Oxygen Process Steelmaking Facilities for Which Construction is Commenced After January 20, 1983</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">O</ENT>
                  <ENT>Sewage Treatment Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">P</ENT>
                  <ENT>Primary Copper Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Q</ENT>
                  <ENT>Primary Zinc Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">R</ENT>
                  <ENT>Primary Lead Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">S</ENT>
                  <ENT>Primary Aluminum Reduction Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">T</ENT>
                  <ENT>Phosphate Fertilizer Industry: Wet Process Phosphoric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">U</ENT>
                  <ENT>Phosphate Fertilizer Industry: Superphosphoric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">V</ENT>
                  <ENT>Phosphate Fertilizer Industry: Diammonium Phosphate Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">W</ENT>
                  <ENT>Phosphate Fertilizer Industry: Triple Superphosphate Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">X</ENT>
                  <ENT>Phosphate Fertilizer Industry: Granular Triple Superphosphate Storage Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Y</ENT>
                  <ENT>Coal Preparation Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Z</ENT>
                  <ENT>Ferroalloy Production Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AA</ENT>
                  <ENT>Steel Plants: Electric Arc Furnaces Constructed After October 21, 1974 and On or Before August 17, 1983</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AAa</ENT>
                  <ENT>Steel Plants: Electric Arc Furnaces and Argon-Oxygen Decarburization Vessels Constructed After August 7, 1983</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">BB</ENT>
                  <ENT>Kraft pulp Mills</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">CC</ENT>
                  <ENT>Glass Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">DD</ENT>
                  <ENT>Grain Elevators</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">EE</ENT>
                  <ENT>Surface Coating of Metal Furniture</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">FF</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">GG</ENT>
                  <ENT>Stationary Gas Turbines</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">HH</ENT>
                  <ENT>Lime Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">KK</ENT>
                  <ENT>Lead-Acid Battery Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">LL</ENT>
                  <ENT>Metallic Mineral Processing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">MM</ENT>
                  <ENT>Automobile and Light Duty Trucks Surface Coating Operations</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">NN</ENT>
                  <ENT>Phosphate Rock Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">PP</ENT>
                  <ENT>Ammonium Sulfate Manufacture</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">QQ</ENT>
                  <ENT>Graphic Arts Industry: Publication Rotogravure Printing</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">RR</ENT>
                  <ENT>Pressure Sensitive Tape and Label Surface Coating Operations</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">SS</ENT>
                  <ENT>Industrial Surface Coating: Large Appliances</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">TT</ENT>
                  <ENT>Metal Coil Surface Coating</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">UU</ENT>
                  <ENT>Asphalt Processing and Asphalt Roofing Manufacture</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">VV</ENT>
                  <ENT>Equipment Leaks of VOC in the Synthetic Organic Chemicals Manufacturing Industry</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">WW</ENT>
                  <ENT>Beverage Can Surface Coating Industry</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">XX</ENT>
                  <ENT>Bulk Gasoline Terminals</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">AAA</ENT>
                  <ENT>New Residential Wool Heaters</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">BBB</ENT>
                  <ENT>Rubber Tire Manufacturing Industry</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">CCC</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">DDD</ENT>
                  <ENT>Volatile Organic Compounds (VOC) Emissions from the Polymer manufacturing Industry</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">EEE</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <PRTPAGE P="47"/>
                  <ENT I="01">FFF</ENT>
                  <ENT>Flexible Vinyl and Urethane Coating and Printing</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">GGG</ENT>
                  <ENT>Equipment Leaks of VOC in Petroleum Refineries</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">HHH</ENT>
                  <ENT>Synthetic Fiber Production Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">III</ENT>
                  <ENT>Volatile Organic Compound (VOC) Emissions From the Synthetic Organic Chemical Manufacturing Industry (SOCMI) Air Oxidation Unit Processes</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">JJJ</ENT>
                  <ENT>Petroleum Dry Cleaners</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">KKK</ENT>
                  <ENT>Equipment Leaks of VOC From Onshore Natural Gas Processing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">LLL</ENT>
                  <ENT>Onshore Natural Gas Processing: SO2 Emissions</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">MMM</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">NNN</ENT>
                  <ENT>Volatile Organic Compound (VOC) Emissions From Synthetic Organic Chemical Manufacturing Industry (SOCMI) Distillation Operations</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">OOO</ENT>
                  <ENT>Nonmetallic Mineral Processing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">PPP</ENT>
                  <ENT>Wool Fiberglass Insulation Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">QQQ</ENT>
                  <ENT>VOC Emissions From Petroleum Refinery Wastewater Systems</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">RRR</ENT>
                  <ENT>Volatile Organic Compound Emissions from Synthetic Organic Chemical Manufacturing Industry (SOCMI) Reactor Processes</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">SSS</ENT>
                  <ENT>Magnetic Tape Coating Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">TTT</ENT>
                  <ENT>Industrial Surface Coating: Surface Coating of Plastic Parts for Business Machines</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">UUU</ENT>
                  <ENT>Calciners and Dryers in Mineral Industries</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">VVV</ENT>
                  <ENT>Polymeric Coating of Supporting Substrates Facilities</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">WWW</ENT>
                  <ENT>Municipal Solid Waste Landfills</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
              </GPOTABLE>
              <P>(vi) Delegations for Northern Sierra Air Quality Management District, Northern Sonoma County Air Pollution Control District, Placer County Air Pollution Control District, and Sacramento Metropolitan Air Quality Management District are shown in the following table:</P>
              <GPOTABLE CDEF="xls24,r100,8C,8C,8C,8C" COLS="6" OPTS="L2">
                <TTITLE>Delegation Status for New Source Performance Standards for Northern Sierra Air Quality Management District, Northern Sonoma County Air Pollution Control District, Placer County Air Pollution Control District, and Sacramento Metropolitan Air Quality Management District</TTITLE>
                <BOXHD>
                  <CHED H="1"/>
                  <CHED H="1">Subpart</CHED>
                  <CHED H="1">Air pollution control agency</CHED>
                  <CHED H="2">Northern Sierra AQMD</CHED>
                  <CHED H="2">Northern Sonoma County APCD</CHED>
                  <CHED H="2">Placer County APCD</CHED>
                  <CHED H="2">Sacramento Metropolitan AQMD</CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">A</ENT>
                  <ENT>General Provisions</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">D</ENT>
                  <ENT>Fossil-Fuel Fired Steam Generators Constructed After August 17, 1971</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Da</ENT>
                  <ENT>Electric Utility Steam Generating Units Constructed After September 18, 1978</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Db</ENT>
                  <ENT>Industrial-Commercial-Institutional Steam Generating Units</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Dc</ENT>
                  <ENT>Small Industrial Steam Generating Units</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">E</ENT>
                  <ENT>Incinerators</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Ea</ENT>
                  <ENT>Municipal Waste Combustors Constructed After December 20, 1989 and On or Before September 20, 1994</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Eb</ENT>
                  <ENT>Municipal Waste Combustors Constructed After September 20, 1994</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Ec</ENT>
                  <ENT>Hospital/Medical/Infectious Waste Incinerators for Which Construction is Commenced After June 20, 1996</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">F</ENT>
                  <ENT>Portland Cement Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">G</ENT>
                  <ENT>Nitric Acid Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <PRTPAGE P="48"/>
                  <ENT I="01">H</ENT>
                  <ENT>Sulfuric Acid Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">I</ENT>
                  <ENT>Hot Mix Asphalt Facilities</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">J</ENT>
                  <ENT>Petroleum Refineries</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">K</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification Commenced After June 11, 1973, and Prior to May 19, 1978</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Ka</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification Commenced After May 18, 1978, and Prior to July 23, 1984</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Kb</ENT>
                  <ENT>Volatile Organic Liquid Storage Vessels (Including Petroleum Liquid Storage Vessels) for Which Construction, Reconstruction, or Modification Commenced After July 23, 1984</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">L</ENT>
                  <ENT>Secondary Lead Smelters</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">M</ENT>
                  <ENT>Secondary Brass and Bronze Production Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">N</ENT>
                  <ENT>Primary Emissions from Basic Oxygen Process Furnaces for Which Construction is Commenced After June 11, 1973</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Na</ENT>
                  <ENT>Secondary Emissions from Basic Oxygen Process Steelmaking Facilities for Which Construction is Commenced After January 20, 1983</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">O</ENT>
                  <ENT>Sewage Treatment Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">P</ENT>
                  <ENT>Primary Copper Smelters</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Q</ENT>
                  <ENT>Primary Zinc Smelters</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">R</ENT>
                  <ENT>Primary Lead Smelters</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">S</ENT>
                  <ENT>Primary Aluminum Reduction Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">T</ENT>
                  <ENT>Phosphate Fertilizer Industry: Wet Process Phosphoric Acid Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">U</ENT>
                  <ENT>Phosphate Fertilizer Industry: Superphosphoric Acid Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">V</ENT>
                  <ENT>Phosphate Fertilizer Industry: Diammonium Phosphate Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">W</ENT>
                  <ENT>Phosphate Fertilizer Industry: Triple Superphosphate Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">X</ENT>
                  <ENT>Phosphate Fertilizer Industry: Granular Triple Superphosphate Storage Facilities</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Y</ENT>
                  <ENT>Coal Preparation Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Z</ENT>
                  <ENT>Ferroalloy Production Facilities</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AA</ENT>
                  <ENT>Steel Plants: Electric Arc Furnaces Constructed After October 21, 1974 and On or Before August 17, 1983</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AAa</ENT>
                  <ENT>Steel Plants: Electric Arc Furnaces and Argon-Oxygen Decarburization Vessels Constructed After August 7, 1983</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">BB</ENT>
                  <ENT>Kraft pulp Mills</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">CC</ENT>
                  <ENT>Glass Manufacturing Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">DD</ENT>
                  <ENT>Grain Elevators</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">EE</ENT>
                  <ENT>Surface Coating of Metal Furniture</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">FF</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">GG</ENT>
                  <ENT>Stationary Gas Turbines</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">HH</ENT>
                  <ENT>Lime Manufacturing Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">KK</ENT>
                  <ENT>Lead-Acid Battery Manufacturing Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">LL</ENT>
                  <ENT>Metallic Mineral Processing Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">MM</ENT>
                  <ENT>Automobile and Light Duty Trucks Surface Coating Operations</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">NN</ENT>
                  <ENT>Phosphate Rock Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">PP</ENT>
                  <ENT>Ammonium Sulfate Manufacture</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">QQ</ENT>
                  <ENT>Graphic Arts Industry: Publication Rotogravure Printing</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">RR</ENT>
                  <ENT>Pressure Sensitive Tape and Label Surface Coating Operations</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">SS</ENT>
                  <ENT>Industrial Surface Coating: Large Appliances</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">TT</ENT>
                  <ENT>Metal Coil Surface Coating</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">UU</ENT>
                  <ENT>Asphalt Processing and Asphalt Roofing Manufacture</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">VV</ENT>
                  <ENT>Equipment Leaks of VOC in the Synthetic Organic Chemicals Manufacturing Industry</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">WW</ENT>
                  <ENT>Beverage Can Surface Coating Industry</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">XX</ENT>
                  <ENT>Bulk Gasoline Terminals</ENT>
                  <ENT>....</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">AAA</ENT>
                  <ENT>New Residential Wool Heaters</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">BBB</ENT>
                  <ENT>Rubber Tire Manufacturing Industry</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">CCC</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">DDD</ENT>
                  <ENT>Volatile Organic Compounds (VOC) Emissions from the Polymer Manufacturing Industry</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">EEE</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <PRTPAGE P="49"/>
                  <ENT I="01">FFF</ENT>
                  <ENT>Flexible Vinyl and Urethane Coating and Printing</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">GGG</ENT>
                  <ENT>Equipment Leaks of VOC in Petroleum Refineries</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">HHH</ENT>
                  <ENT>Synthetic Fiber Production Facilities</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">III</ENT>
                  <ENT>Volatile Organic Compound (VOC) Emissions From the Synthetic Organic Chemical Manufacturing Industry (SOCMI) Air Oxidation Unit Processes</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">JJJ</ENT>
                  <ENT>Petroleum Dry Cleaners</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">KKK</ENT>
                  <ENT>Equipment Leaks of VOC From Onshore Natural Gas Processing Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">LLL</ENT>
                  <ENT>Onshore Natural Gas Processing: SO2 Emissions</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">MMM</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">NNN</ENT>
                  <ENT>Volatile Organic Compound (VOC) Emissions From Synthetic Organic Chemical Manufacturing Industry (SOCMI) Distillation Operations</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">OOO</ENT>
                  <ENT>Nonmetallic Mineral Processing Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">PPP</ENT>
                  <ENT>Wool Fiberglass Insulation Manufacturing Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">QQQ</ENT>
                  <ENT>VOC Emissions From Petroleum Refinery Wastewater Systems</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">RRR</ENT>
                  <ENT>Volatile Organic Compound Emissions from Synthetic Organic Chemical Manufacturing Industry (SOCMI) Reactor Processes</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">SSS</ENT>
                  <ENT>Magnetic Tape Coating Facilities</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">TTT</ENT>
                  <ENT>Industrial Surface Coating: Surface Coating of Plastic Parts for Business Machines</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">UUU</ENT>
                  <ENT>Calciners and Dryers in Mineral Industries</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">VVV</ENT>
                  <ENT>Polymeric Coating of Supporting Substrates Facilities</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">WWW</ENT>
                  <ENT>Municipal Solid Waste Landfills</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
              </GPOTABLE>
              <P>(vii) Delegations for San Diego County Air Pollution Control District, San Joaquin Valley Unified Air Pollution Control District, San Luis Obispo County Air Pollution Control District, and Santa Barbara County Air Pollution Control District are shown in the following table:</P>
              <GPOTABLE CDEF="xls24,r50,8C,8C,8C,8C" COLS="6" OPTS="L2">
                <TTITLE>Delegation Status for New Source Performance Standards for San Diego County Air Pollution Control District, San Joaquin Valley Unified Air Pollution Control District, San Luis Obispo County Air Pollution Control District, and Santa Barbara County Air Pollution Control District</TTITLE>
                <BOXHD>
                  <CHED H="1"/>
                  <CHED H="1">Subpart</CHED>
                  <CHED H="1">Air pollution control agency</CHED>
                  <CHED H="2">San Diego County APCD</CHED>
                  <CHED H="2">San Joaquin Valley United APCD</CHED>
                  <CHED H="2">San Luis Obispo County APCD</CHED>
                  <CHED H="2">Santa Barbara County APCD</CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">A</ENT>
                  <ENT>General Provisions</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">D</ENT>
                  <ENT>Fossil-Fuel Fired Steam Generators Constructed After August 17, 1971</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Da</ENT>
                  <ENT>Electric Utility Steam Generating Units Constructed After September 18, 1978</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Db</ENT>
                  <ENT>Industrial-Commercial-Institutional Steam Generating Units</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Dc</ENT>
                  <ENT>Small Industrial Steam Generating Units</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">E</ENT>
                  <ENT>Incinerators</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Ea</ENT>
                  <ENT>Municipal Waste Combustors Constructed After December 20, 1989 and On or Before September 20, 1994</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Eb</ENT>
                  <ENT>Municipal Waste Combustors Constructed After September 20, 1994</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Ec</ENT>
                  <ENT>Hospital/Medical/Infectious Waste Incinerators for Which Construction is Commenced After June 20, 1996</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">F</ENT>
                  <ENT>Portland Cement Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">G</ENT>
                  <ENT>Nitric Acid Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <PRTPAGE P="50"/>
                  <ENT I="01">H</ENT>
                  <ENT>Sulfuric Acid Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">I</ENT>
                  <ENT>Hot Mix Asphalt Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">J</ENT>
                  <ENT>Petroleum Refineries</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">K</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification Commenced Ater June 11, 1973, and Prior to May 19, 1978</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Ka</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification Commenced After May 18, 1978, and Prior to July 23, 1984</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Kb</ENT>
                  <ENT>Volatile Organic Liquid Storage Vessels (Including Petroleum Liquid Storage Vessels) for Which Construction, Reconstruction, or Modification Commenced After July 23, 1984</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">L</ENT>
                  <ENT>Secondary Lead Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">M</ENT>
                  <ENT>Secondary Brass and Bronze Production Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">N</ENT>
                  <ENT>Primary Emissions from Basic Oxygen Process Furnaces for Which Construction is Commenced After June 11, 1973</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Na</ENT>
                  <ENT>Secondary Emissions from Basic Oxygen Process Steelmaking Facilities for Which Construction is Commenced After January 20, 1983</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">O</ENT>
                  <ENT>Sewage Treatment Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">P</ENT>
                  <ENT>Primary Copper Smelters</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Q</ENT>
                  <ENT>Primary Zinc Smelters</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">R</ENT>
                  <ENT>Primary Lead Smelters</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">S</ENT>
                  <ENT>Primary Aluminum Reduction Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">T</ENT>
                  <ENT>Phosphate Fertilizer Industry: Wet Process Phosphoric Acid Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">U</ENT>
                  <ENT>Phosphate Fertilizer Industry: Superphosphoric Acid Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">V</ENT>
                  <ENT>Phosphate Fertilizer Industry: Diammonium Phosphate Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">W</ENT>
                  <ENT>Phosphate Fertilizer Industry: Triple Superphosphate Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">X</ENT>
                  <ENT>Phosphate Fertilizer Industry: Granular Triple Superphosphate Storage Facilities</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Y</ENT>
                  <ENT>Coal Preparation Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Z</ENT>
                  <ENT>Ferroalloy Production Facilities</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AA</ENT>
                  <ENT>Steel Plants: Electric Arc Furnaces Constructed After October 21, 1974 and On or Before August 17, 1983</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AAa</ENT>
                  <ENT>Steel Plants: Electric Arc Furnaces and Argon-Oxygen Decarburization Vessels Constructed After August 7, 1983</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">BB</ENT>
                  <ENT>Kraft pulp Mills</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">CC</ENT>
                  <ENT>Glass Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">DD</ENT>
                  <ENT>Grain Elevators</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">EE</ENT>
                  <ENT>Surface Coating of Metal Furniture</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">FF</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">GG</ENT>
                  <ENT>Stationary Gas Turbines</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">HH</ENT>
                  <ENT>Lime Manufacturing Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">KK</ENT>
                  <ENT>Lead-Acid Battery Manufacturing Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">LL</ENT>
                  <ENT>Metallic Mineral Processing Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">MM</ENT>
                  <ENT>Automobile and Light Duty Trucks Surface Coating Operations</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">NN</ENT>
                  <ENT>Phosphate Rock Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">PP</ENT>
                  <ENT>Ammonium Sulfate Manufacture</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">QQ</ENT>
                  <ENT>Graphic Arts Industry: Publication Rotogravure Printing</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">RR</ENT>
                  <ENT>Pressure Sensitive Tape and Label Surface Coating Operations</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">SS</ENT>
                  <ENT>Industrial Surface Coating: Large Appliances</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">TT</ENT>
                  <ENT>Metal Coil Surface Coating</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">UU</ENT>
                  <ENT>Asphalt Processing and Asphalt Roofing Manufacture</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">VV</ENT>
                  <ENT>Equipment Leaks of VOC in the Synthetic Organic Chemicals Manufacturing Industry</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">WW</ENT>
                  <ENT>Beverage Can Surface Coating Industry</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">XX</ENT>
                  <ENT>Bulk Gasoline Terminals</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">AAA</ENT>
                  <ENT>New Residential Wool Heaters</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">BBB</ENT>
                  <ENT>Rubber Tire Manufacturing Industry</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">CCC</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">DDD</ENT>
                  <ENT>Volatile Organic Compounds (VOC) Emissions from the Polymer Manufacturing Industry</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">EEE</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">FFF</ENT>
                  <ENT>Flexible Vinyl and Urethane Coating and Printing</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <PRTPAGE P="51"/>
                  <ENT I="01">GGG</ENT>
                  <ENT>Equipment Leaks of VOC in Petroleum Refineries</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">HHH</ENT>
                  <ENT>Synthetic Fiber Production Facilities</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">III</ENT>
                  <ENT>Volatile Organic Compound (VOC) Emissions From the Synthetic Organic Chemical Manufacturing Industry (SOCMI) Air Oxidation Unit Processes</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">JJJ</ENT>
                  <ENT>Petroleum Dry Cleaners</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">KKK</ENT>
                  <ENT>Equipment Leaks of VOC From Onshore Natural Gas Processing Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">LLL</ENT>
                  <ENT>Onshore Natural Gas Processing: SO2 Emissions</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">MMM</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">NNN</ENT>
                  <ENT>Volatile Organic Compound (VOC) Emissions From Synthetic Organic Chemical Manufacturing Industry (SOCMI) Distillation Operations</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">OOO</ENT>
                  <ENT>Nonmetallic Mineral Processing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">PPP</ENT>
                  <ENT>Wool Fiberglass Insulation Manufacturing Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">QQQ</ENT>
                  <ENT>VOC Emissions From Petroleum Refinery Wastewater Systems</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">RRR</ENT>
                  <ENT>Volatile Organic Compound Emissions from Synthetic Organic Chemical Manufacturing Industry (SOCMI) Reactor Processes</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">SSS</ENT>
                  <ENT>Magnetic Tape Coating Facilities</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">TTT</ENT>
                  <ENT>Industrial Surface Coating: Surface Coating of Plastic Parts for Business Machines</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">UUU</ENT>
                  <ENT>Calciners and Dryers in Mineral Industries</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">VVV</ENT>
                  <ENT>Polymeric Coating of Supporting Substrates Facilities</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">WWW</ENT>
                  <ENT>Municipal Solid Waste Landfills</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
              </GPOTABLE>
              <P>(viii) Delegations for Shasta County Air Quality Management District, Siskiyou County Air Pollution Control District, South Coast Air Quality Management District, and Tehama County Air Pollution Control District are shown in the following table:</P>
              <GPOTABLE CDEF="xls24,r100,8C,8C,8C,8C" COLS="6" OPTS="L2">
                <TTITLE>Delegation Status for New Source Performance Standards for Shasta County Air Quality Management District, Siskiyou County Air Pollution Control District, South Coast Air Quality Management District, and Tehama County Air Pollution Control District</TTITLE>
                <BOXHD>
                  <CHED H="1"/>
                  <CHED H="1">Subpart</CHED>
                  <CHED H="1">Air pollution control agency</CHED>
                  <CHED H="2">Shasta County AQMD</CHED>
                  <CHED H="2">Siskiyou County APCD</CHED>
                  <CHED H="2">South Coast AQMD</CHED>
                  <CHED H="2">Tehama County APCD</CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">A</ENT>
                  <ENT>General Provisions</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">D</ENT>
                  <ENT>Fossil-Fuel Fired Steam Generators Constructed After August 17, 1971</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Da</ENT>
                  <ENT>Electric Utility Steam Generating Units Constructed After September 18, 1978</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Db</ENT>
                  <ENT>Industrial-Commercial-Institutional Steam Generating Units</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Dc</ENT>
                  <ENT>Small Industrial Steam Generating Units</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">E</ENT>
                  <ENT>Incinerators</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Ea</ENT>
                  <ENT>Municipal Waste Combustors Constructed After December 20, 1989 and On or Before September 20, 1994</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Eb</ENT>
                  <ENT>Municipal Waste Combustors Constructed After September 20, 1994</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Ec</ENT>
                  <ENT>Hospital/Medical/Infectious Waste Incinerators for Which Construction is Commenced After June 20, 1996</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">F</ENT>
                  <ENT>Portland Cement Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">G</ENT>
                  <ENT>Nitric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">H</ENT>
                  <ENT>Sulfuric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">I</ENT>
                  <ENT>Hot Mix Asphalt Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">J</ENT>
                  <ENT>Petroleum Refineries</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <PRTPAGE P="52"/>
                  <ENT I="01">K</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification Commenced After June 11, 1973, and Prior to May 19, 1978</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Ka</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification Commenced After May 18, 1978, and Prior to July 23, 1984</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Kb</ENT>
                  <ENT>Volatile Organic Liquid Storage Vessels (Including Petroleum Liquid Storage Vessels) for Which Construction, Reconstruction, or Modification Commenced After July 23, 1984</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">L</ENT>
                  <ENT>Secondary Lead Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">M</ENT>
                  <ENT>Secondary Brass and Bronze Production Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">N</ENT>
                  <ENT>Primary Emissions from Basic Oxygen Process Furnaces for Which Construction is Commenced After June 11, 1973</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Na</ENT>
                  <ENT>Secondary Emissions from Basic Oxygen Process Steelmaking Facilities for Which Construction is Commenced After January 20, 1983</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">O</ENT>
                  <ENT>Sewage Treatment Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">P</ENT>
                  <ENT>Primary Copper Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Q</ENT>
                  <ENT>Primary Zinc Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">R</ENT>
                  <ENT>Primary Lead Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">S</ENT>
                  <ENT>Primary Aluminum Reduction Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">T</ENT>
                  <ENT>Phosphate Fertilizer Industry: Wet Process Phosphoric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">U</ENT>
                  <ENT>Phosphate Fertilizer Industry: Superphosphoric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">V</ENT>
                  <ENT>Phosphate Fertilizer Industry: Diammonium Phosphate Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">W</ENT>
                  <ENT>Phosphate Fertilizer Industry: Triple Superphosphate Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">X</ENT>
                  <ENT>Phosphate Fertilizer Industry: Granular Triple Superphosphate Storage Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Y</ENT>
                  <ENT>Coal Preparation Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Z</ENT>
                  <ENT>Ferroalloy Production Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01"> AA</ENT>
                  <ENT>Steel Plants: Electric Arc Furnaces Constructed After October 21, 1974 and On or Before August 17, 1983</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">AAa</ENT>
                  <ENT>Steel Plants: Electric Arc Furnaces and Argon-Oxygen Decarburization Vessels Constructed After August 7, 1983</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">BB</ENT>
                  <ENT>Kraft pulp Mills</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">CC</ENT>
                  <ENT>Glass Manufacturing Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">DD</ENT>
                  <ENT>Grain Elevators</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">EE</ENT>
                  <ENT>Surface Coating of Metal Furniture</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">FF</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">GG</ENT>
                  <ENT>Stationary Gas Turbines</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">HH</ENT>
                  <ENT>Lime Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">KK</ENT>
                  <ENT>Lead-Acid Battery Manufacturing Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">LL</ENT>
                  <ENT>Metallic Mineral Processing Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">MM</ENT>
                  <ENT>Automobile and Light Duty Trucks Surface Coating Operations</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">NN</ENT>
                  <ENT>Phosphate Rock Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">PP</ENT>
                  <ENT>Ammonium Sulfate Manufacture</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01"> QQ</ENT>
                  <ENT>Graphic Arts Industry: Publication Rotogravure Printing</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">RR</ENT>
                  <ENT>Pressure Sensitive Tape and Label Surface Coating Operations</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">SS</ENT>
                  <ENT>Industrial Surface Coating: Large Appliances</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">TT</ENT>
                  <ENT>Metal Coil Surface Coating</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">UU</ENT>
                  <ENT>Asphalt Processing and Asphalt Roofing Manufacture</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">VV</ENT>
                  <ENT>Equipment Leaks of VOC in the Synthetic Organic Chemicals Manufacturing Industry</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">WW</ENT>
                  <ENT>Beverage Can Surface Coating Industry</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">XX</ENT>
                  <ENT>Bulk Gasoline Terminals</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">AAA</ENT>
                  <ENT>New Residential Wool Heaters</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">BBB</ENT>
                  <ENT>Rubber Tire Manufacturing Industry</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">CCC</ENT>
                  <ENT>(Reserved)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">DDD</ENT>
                  <ENT>Volatile Organic Compounds (VOC) Emissions from the Polymer Manufacturing Industry</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">EEE</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">FFF</ENT>
                  <ENT>Flexible Vinyl and Urethane Coating and Printing</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">GGG</ENT>
                  <ENT>Equipment Leaks of VOC in Petroleum Refineries</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">HHH</ENT>
                  <ENT>Synthetic Fiber Production Facilities</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <PRTPAGE P="53"/>
                  <ENT I="01">III</ENT>
                  <ENT>Volatile Organic Compound (VOC) Emissions From the Synthetic Organic Chemical Manufacturing Industry (SOCMI) Air Oxidation Unit Processes</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">JJJ</ENT>
                  <ENT>Petroleum Dry Cleaners</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">KKK</ENT>
                  <ENT>Equipment Leaks of VOC From Onshore Natural Gas Processing Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">LLL</ENT>
                  <ENT>Onshore Natural Gas Processing: SO2 Emissions</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">MMM</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">NNN</ENT>
                  <ENT>Volatile Organic Compound (VOC) Emissions From Synthetic Organic Chemical Manufacturing Industry (SOCMI) Distillation Operations</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">OOO</ENT>
                  <ENT>Nonmetallic Mineral Processing Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">PPP</ENT>
                  <ENT>Wool Fiberglass Insulation Manufacturing Plants</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">QQQ</ENT>
                  <ENT>VOC Emissions From Petroleum Refinery Wastewater Systems</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">RRR</ENT>
                  <ENT>Volatile Organic Compound Emissions from Synthetic Organic Chemical Manufacturing Industry (SOCMI) Reactor Processes</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">SSS</ENT>
                  <ENT>Magnetic Tape Coating Facilities</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01"> TTT</ENT>
                  <ENT>Industrial Surface Coating: Surface Coating of Plastic Parts for Business Machines</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">UUU</ENT>
                  <ENT>Calciners and Dryers in Mineral Industries</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">VVV</ENT>
                  <ENT>Polymeric Coating of Supporting Substrates Facilities</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">WWW</ENT>
                  <ENT>Municipal Solid Waste Landfills</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
              </GPOTABLE>
              <P>(ix) Delegations for Tuolumne County Air Pollution Control District, Ventura County Air Pollution Control District, and Yolo-Solano Air Quality Management District are shown in the following table:</P>
              <GPOTABLE CDEF="xls24,r50,12C,12C,12C" COLS="5" OPTS="L2">
                <TTITLE>Delegation Status for New Source Performance Standards for Tuolumne County Air Pollution Control District, Ventura County Air Pollution Control District, and Yolo-Solano Air Quality Management District</TTITLE>
                <BOXHD>
                  <CHED H="1"/>
                  <CHED H="1">Subpart</CHED>
                  <CHED H="1">Air pollution control agency</CHED>
                  <CHED H="2">Tuolumne County APCD</CHED>
                  <CHED H="2">Ventura<LI>County APCD</LI>
                  </CHED>
                  <CHED H="2">Yolo-Solano AQMD</CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">A</ENT>
                  <ENT>General Provisions</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">D</ENT>
                  <ENT>Fossil-Fuel Fired Steam Generators Constructed After August 17, 1971</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Da</ENT>
                  <ENT>Electric Utility Steam Generating Units Constructed After September 18, 1978</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Db</ENT>
                  <ENT>Industrial-Commercial-Institutional Steam Generating Units</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Dc</ENT>
                  <ENT>Small Industrial Steam Generating Units</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">E</ENT>
                  <ENT>Incinerators</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Ea</ENT>
                  <ENT>Municipal Waste Combustors Constructed After December 20, 1989 and On or Before September 20, 1994</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Eb</ENT>
                  <ENT>Municipal Waste Combustors Constructed After September 20, 1994</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Ec</ENT>
                  <ENT>Hospital/Medical/Infectious Waste Incinerators for Which Construction is Commenced After June 20, 1996</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">F</ENT>
                  <ENT>Portland Cement Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">G</ENT>
                  <ENT>Nitric Acid Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">H</ENT>
                  <ENT>Sulfuric Acid Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">I</ENT>
                  <ENT>Hot Mix Asphalt Facilities</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">J</ENT>
                  <ENT>Petroleum Refineries</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">K</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification Commenced After June 11, 1973, and Prior to May 19, 1978</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Ka</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification Commenced After May 18, 1978, and Prior to July 23, 1984</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <PRTPAGE P="54"/>
                  <ENT I="01">Kb</ENT>
                  <ENT>Volatile Organic Liquid Storage Vessels (Including Petroleum Liquid Storage Vessels) for Which Construction, Reconstruction, or Modification Commenced After July 23, 1984</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">L</ENT>
                  <ENT>Secondary Lead Smelters</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">M</ENT>
                  <ENT>Secondary Brass and Bronze Production Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">N</ENT>
                  <ENT>Primary Emissions from Basic Oxygen Process Furnaces for Which Construction is Commenced After June 11, 1973</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Na</ENT>
                  <ENT>Secondary Emissions from Basic Oxygen Process Steelmaking Facilities for Which Construction is Commenced AfterJanuary 20, 1983</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">O</ENT>
                  <ENT>Sewage Treatment Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">P</ENT>
                  <ENT>Primary Copper Smelters</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Q</ENT>
                  <ENT>Primary Zinc Smelters</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">R</ENT>
                  <ENT>Primary Lead Smelters</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">S</ENT>
                  <ENT>Primary Aluminum Reduction Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">T</ENT>
                  <ENT>Phosphate Fertilizer Industry: Wet Process Phosphoric Acid Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">U</ENT>
                  <ENT>Phosphate Fertilizer Industry: Superphosphoric Acid Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">V</ENT>
                  <ENT>Phosphate Fertilizer Industry: Diammonium Phosphate Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">W</ENT>
                  <ENT>Phosphate Fertilizer Industry: Triple Superphosphate Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">X</ENT>
                  <ENT>Phosphate Fertilizer Industry: Granular Triple Superphosphate Storage Facilities</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Y</ENT>
                  <ENT>Coal Preparation Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Z</ENT>
                  <ENT>Ferroalloy Production Facilities</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">AA</ENT>
                  <ENT>Steel Plants: Electric Arc Furnaces Constructed After October 21, 1974 and On or Before August 17, 1983</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AAa</ENT>
                  <ENT>Steel Plants: Electric Arc Furnaces and Argon-Oxygen Decarburization Vessels Constructed After August 7, 1983</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">BB</ENT>
                  <ENT>Kraft pulp Mills</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">CC</ENT>
                  <ENT>Glass Manufacturing Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">DD</ENT>
                  <ENT>Grain Elevators</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">EE</ENT>
                  <ENT>Surface Coating of Metal Furniture</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">FF</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">GG</ENT>
                  <ENT>Stationary Gas Turbines</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">HH</ENT>
                  <ENT>Lime Manufacturing Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">KK</ENT>
                  <ENT>Lead-Acid Battery Manufacturing Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">LL</ENT>
                  <ENT>Metallic Mineral Processing Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">MM</ENT>
                  <ENT>Automobile and Light Duty Trucks Surface Coating Operations</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">NN</ENT>
                  <ENT>Phosphate Rock Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">PP</ENT>
                  <ENT>Ammonium Sulfate Manufacture</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">QQ</ENT>
                  <ENT>Graphic Arts Industry: Publication Rotogravure Printing</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">RR</ENT>
                  <ENT>Pressure Sensitive Tape and Label Surface Coating Operations</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">SS</ENT>
                  <ENT>Industrial Surface Coating: Large Appliances</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">TT</ENT>
                  <ENT>Metal Coil Surface Coating</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">UU</ENT>
                  <ENT>Asphalt Processing and Asphalt Roofing Manufacture</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">VV</ENT>
                  <ENT>Equipment Leaks of VOC in the Synthetic Organic Chemicals Manufacturing Industry</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">WW</ENT>
                  <ENT>Beverage Can Surface Coating Industry</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">XX</ENT>
                  <ENT>Bulk Gasoline Terminals</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">AAA</ENT>
                  <ENT>New Residential Wool Heaters</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">BBB</ENT>
                  <ENT>Rubber Tire Manufacturing Industry</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">CCC</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">DDD</ENT>
                  <ENT>Volatile Organic Compounds (VOC) Emissions from the Polymer Manufacturing Industry</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">EEE</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">FFF</ENT>
                  <ENT>Flexible Vinyl and Urethane Coating and Printing</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">GGG</ENT>
                  <ENT>Equipment Leaks of VOC in Petroleum Refineries</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">HHH</ENT>
                  <ENT>Synthetic Fiber Production Facilities</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">III</ENT>
                  <ENT>Volatile Organic Compound (VOC) Emissions From the Synthetic Organic Chemical Manufacturing Industry (SOCMI) Air Oxidation Unit Processes</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">JJJ</ENT>
                  <ENT>Petroleum Dry Cleaners</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">KKK</ENT>
                  <ENT>Equipment Leaks of VOC From Onshore Natural Gas Processing Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">LLL</ENT>
                  <ENT>Onshore Natural Gas Processing: SO2 Emissions</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">MMM</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <PRTPAGE P="55"/>
                  <ENT I="01">NNN</ENT>
                  <ENT>Volatile Organic Compound (VOC) Emissions From Synthetic Organic Chemical Manufacturing Industry (SOCMI) Distillation Operations</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">OOO</ENT>
                  <ENT>Nonmetallic Mineral Processing Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">PPP</ENT>
                  <ENT>Wool Fiberglass Insulation Manufacturing Plants</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">QQQ</ENT>
                  <ENT>VOC Emissions From Petroleum Refinery Wastewater Systems</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">RRR</ENT>
                  <ENT>Volatile Organic Compound Emissions from Synthetic Organic Chemical Manufacturing Industry (SOCMI) Reactor Processes</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">SSS</ENT>
                  <ENT>Magnetic Tape Coating Facilities</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">TTT</ENT>
                  <ENT>Industrial Surface Coating: Surface Coating of Plastic Parts for Business Machines</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">UUU</ENT>
                  <ENT>Calciners and Dryers in Mineral Industries</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">VVV</ENT>
                  <ENT>Polymeric Coating of Supporting Substrates Facilities</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">WWW</ENT>
                  <ENT>Municipal Solid Waste Landfills</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
              </GPOTABLE>
              <P>(3) <E T="03">Hawaii.</E> The following table identifies delegations as of June 15, 2001:</P>
              <GPOTABLE CDEF="xls24,r100,12C" COLS="3" OPTS="L2">
                <TTITLE>Delegation Status for New Source Performance Standards for Hawaii</TTITLE>
                <BOXHD>
                  <CHED H="1"/>
                  <CHED H="1">Subpart</CHED>
                  <CHED H="1">Hawaii</CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">A</ENT>
                  <ENT>General Provisions</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">D</ENT>
                  <ENT>Fossil-Fuel Fired Steam Generators Constructed After August 17, 1971</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Da</ENT>
                  <ENT>Electric Utility Steam Generating Units Constructed After September 18, 1978</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Db</ENT>
                  <ENT>Industrial-Commercial-Institutional Steam Generating Units</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Dc</ENT>
                  <ENT>Small Industrial Steam Generating Units</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">E</ENT>
                  <ENT>Incinerators</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Ea</ENT>
                  <ENT>Municipal Waste Combustors Constructed After December 20, 1989 and On or Before September 20, 1994</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Eb</ENT>
                  <ENT>Municipal Waste Combustors Constructed After September 20, 1994</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Ec</ENT>
                  <ENT>Hospital/Medical/Infectious Waste Incinerators for Which Construction is Commenced After June 20, 1996</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">F</ENT>
                  <ENT>Portland Cement Plants</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">G</ENT>
                  <ENT>Nitric Acid Plants</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">H</ENT>
                  <ENT>Sulfuric Acid Plants</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">I</ENT>
                  <ENT>Hot Mix Asphalt Facilities</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">J</ENT>
                  <ENT>Petroleum Refineries</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">K</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification Commenced After June 11, 1973, and Prior to May 19, 1978</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Ka</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification Commenced After May 18, 1978, and Prior to July 23, 1984</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Kb</ENT>
                  <ENT>Volatile Organic Liquid Storage Vessels (Including Petroleum Liquid Storage Vessels) for Which Construction, Reconstruction, or Modification Commenced After July 23, 1984</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">L</ENT>
                  <ENT>Secondary Lead Smelters</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">M</ENT>
                  <ENT>Secondary Brass and Bronze Production Plants</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">N</ENT>
                  <ENT>Primary Emissions from Basic Oxygen Process Furnaces for Which Construction is Commenced After June 11, 1973</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Na</ENT>
                  <ENT>Secondary Emissions from Basic Oxygen Process Steelmaking Facilities for Which Construction is Commenced After January 20, 1983</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">O</ENT>
                  <ENT>Sewage Treatment Plants</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">P</ENT>
                  <ENT>Primary Copper Smelters</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Q</ENT>
                  <ENT>Primary Zinc Smelters</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">R</ENT>
                  <ENT>Primary Lead Smelters</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">S</ENT>
                  <ENT>Primary Aluminum Reduction Plants</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">T</ENT>
                  <ENT>Phosphate Fertilizer Industry: Wet Process Phosphoric Acid Plants</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">U</ENT>
                  <ENT>Phosphate Fertilizer Industry: Superphosphoric Acid Plants</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">V</ENT>
                  <ENT>Phosphate Fertilizer Industry: Diammonium Phosphate Plants</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">W</ENT>
                  <ENT>Phosphate Fertilizer Industry: Triple Superphosphate Plants</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">X</ENT>
                  <ENT>Phosphate Fertilizer Industry: Granular Triple Superphosphate Storage Facilities</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Y</ENT>
                  <ENT>Coal Preparation Plants</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Z</ENT>
                  <ENT>Ferroalloy Production Facilities</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">AA</ENT>
                  <ENT>Steel Plants: Electric Arc Furnaces Constructed After October 21, 1974 and On or Before August 17, 1983</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <PRTPAGE P="56"/>
                  <ENT I="01">AAa</ENT>
                  <ENT>Steel Plants: Electric Arc Furnaces and Argon-Oxygen Decarburization Vessels Constructed After August 7, 1983</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">BB</ENT>
                  <ENT>Kraft pulp Mills</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">CC</ENT>
                  <ENT>Glass Manufacturing Plants</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">DD</ENT>
                  <ENT>Grain Elevators</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">EE</ENT>
                  <ENT>Surface Coating of Metal Furniture</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">FF</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">GG</ENT>
                  <ENT>Stationary Gas Turbines</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">HH</ENT>
                  <ENT>Lime Manufacturing Plants</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">KK</ENT>
                  <ENT>Lead-Acid Battery Manufacturing Plants</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">LL</ENT>
                  <ENT>Metallic Mineral Processing Plants</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">MM</ENT>
                  <ENT>Automobile and Light Duty Trucks Surface Coating Operations</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">NN</ENT>
                  <ENT>Phosphate Rock Plants</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">PP</ENT>
                  <ENT>Ammonium Sulfate Manufacture</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">QQ</ENT>
                  <ENT>Graphic Arts Industry: Publication Rotogravure Printing</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">RR</ENT>
                  <ENT>Pressure Sensitive Tape and Label Surface Coating Operations</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">SS</ENT>
                  <ENT>Industrial Surface Coating: Large Appliances</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">TT</ENT>
                  <ENT>Metal Coil Surface Coating</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">UU</ENT>
                  <ENT>Asphalt Processing and Asphalt Roofing Manufacture</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">VV</ENT>
                  <ENT>Equipment Leaks of VOC in the Synthetic Organic Chemicals Manufacturing Industry</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">WW</ENT>
                  <ENT>Beverage Can Surface Coating Industry</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">XX</ENT>
                  <ENT>Bulk Gasoline Terminals</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AAA</ENT>
                  <ENT>New Residential Wool Heaters</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">BBB</ENT>
                  <ENT>Rubber Tire Manufacturing Industry</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">CCC</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">DDD</ENT>
                  <ENT>Volatile Organic Compounds (VOC) Emissions from the Polymer Manufacturing Industry</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">EEE</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">FFF</ENT>
                  <ENT>Flexible Vinyl and Urethane Coating and Printing</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">GGG</ENT>
                  <ENT>Equipment Leaks of VOC in Petroleum Refineries</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">HHH</ENT>
                  <ENT>Synthetic Fiber Production Facilities</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">III</ENT>
                  <ENT>Volatile Organic Compound (VOC) Emissions From the Synthetic Organic Chemical Manufacturing Industry (SOCMI) Air Oxidation Unit Processes</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">JJJ</ENT>
                  <ENT>Petroleum Dry Cleaners</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">KKK</ENT>
                  <ENT>Equipment Leaks of VOC From Onshore Natural Gas Processing Plants</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">LLL</ENT>
                  <ENT>Onshore Natural Gas Processing: SO2 Emissions</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">MMM</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">NNN</ENT>
                  <ENT>Volatile Organic Compound (VOC) Emissions From Synthetic Organic Chemical Manufacturing Industry (SOCMI) Distillation Operations</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">OOO</ENT>
                  <ENT>Nonmetallic Mineral Processing Plants</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">PPP</ENT>
                  <ENT>Wool Fiberglass Insulation Manufacturing Plants</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">QQQ</ENT>
                  <ENT>VOC Emissions From Petroleum Refinery Wastewater Systems</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">RRR</ENT>
                  <ENT>Volatile Organic Compound Emissions from Synthetic Organic Chemical Manufacturing Industry (SOCMI) Reactor Processes</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">SSS</ENT>
                  <ENT>Magnetic Tape Coating Facilities</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">TTT</ENT>
                  <ENT>Industrial Surface Coating: Surface Coating of Plastic Parts for Business Machines</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">UUU</ENT>
                  <ENT>Calciners and Dryers in Mineral Industries</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">VVV</ENT>
                  <ENT>Polymeric Coating of Supporting Substrates Facilities</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">WWW</ENT>
                  <ENT>Municipal Solid Waste Landfills</ENT>
                  <ENT/>
                </ROW>
              </GPOTABLE>
              <P>(4) <E T="03">Nevada.</E> The following table identifies delegations as of June 15, 2001:</P>
              <GPOTABLE CDEF="xls24,r100,8C,8C,8C" COLS="5" OPTS="L2">
                <TTITLE>Delegation Status for New Source Performance Standards for Nevada</TTITLE>
                <BOXHD>
                  <CHED H="1"/>
                  <CHED H="1">Subpart</CHED>
                  <CHED H="1">Air pollution control agency</CHED>
                  <CHED H="2">Nevada DEP</CHED>
                  <CHED H="2">Clark County</CHED>
                  <CHED H="2">Washoe County</CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">A</ENT>
                  <ENT>General Provisions</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">D</ENT>
                  <ENT>Fossil-Fuel Fired Steam Generators Constructed After August 17, 1971</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Da</ENT>
                  <ENT>Electric Utility Steam Generating Units Constructed After September 18, 1978</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Db</ENT>
                  <ENT>Industrial-Commercial-Institutional Steam Generating Units</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Dc</ENT>
                  <ENT>Small Industrial Steam Generating Units</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">E</ENT>
                  <ENT>Incinerators</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Ea</ENT>
                  <ENT>Municipal Waste Combustors Constructed After December 20, 1989 and On or Before September 20, 1994</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Eb</ENT>
                  <ENT>Municipal Waste Combustors Constructed After September 20, 1994</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <PRTPAGE P="57"/>
                  <ENT I="01">Ec</ENT>
                  <ENT>Hospital/Medical/Infectious Waste Incinerators for Which Construction is Commenced After June 20, 1996</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">F</ENT>
                  <ENT>Portland Cement Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">G</ENT>
                  <ENT>Nitric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">H</ENT>
                  <ENT>Sulfuric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">I</ENT>
                  <ENT>Hot Mix Asphalt Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">J</ENT>
                  <ENT>Petroleum Refineries</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">K</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification Commenced After June 11, 1973, and Prior to May 19, 1978</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Ka</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification Commenced After May 18, 1978, and Prior to July 23, 1984</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Kb</ENT>
                  <ENT>Volatile Organic Liquid Storage Vessels (Including Petroleum Liquid Storage Vessels) for Which Construction, Reconstruction, or Modification Commenced After July 23, 1984</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">L</ENT>
                  <ENT>Secondary Lead Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">M</ENT>
                  <ENT>Secondary Brass and Bronze Production Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">N</ENT>
                  <ENT>Primary Emissions from Basic Oxygen Process Furnaces for Which Construction is Commenced After June 11, 1973</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Na</ENT>
                  <ENT>Secondary Emissions from Basic Oxygen Process Steelmaking Facilities for Which Construction is Commenced After January 20, 1983</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">O</ENT>
                  <ENT>Sewage Treatment Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">P</ENT>
                  <ENT>Primary Copper Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Q</ENT>
                  <ENT>Primary Zinc Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">R</ENT>
                  <ENT>Primary Lead Smelters</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">S</ENT>
                  <ENT>Primary Aluminum Reduction Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">T</ENT>
                  <ENT>Phosphate Fertilizer Industry: Wet Process Phosphoric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">U</ENT>
                  <ENT>Phosphate Fertilizer Industry: Superphosphoric Acid Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">V</ENT>
                  <ENT>Phosphate Fertilizer Industry: Diammonium Phosphate Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">W</ENT>
                  <ENT>Phosphate Fertilizer Industry: Triple Superphosphate Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">X</ENT>
                  <ENT>Phosphate Fertilizer Industry: Granular Triple Superphosphate Storage Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Y</ENT>
                  <ENT>Coal Preparation Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Z</ENT>
                  <ENT>Ferroalloy Production Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AA</ENT>
                  <ENT>Steel Plants: Electric Arc Furnaces Constructed After October 21, 1974 and On or Before August 17, 1983</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AAa</ENT>
                  <ENT>Steel Plants: Electric Arc Furnaces and Argon-Oxygen Decarburization Vessels Constructed After August 7, 1983</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">BB</ENT>
                  <ENT>Kraft pulp Mills</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">CC</ENT>
                  <ENT>Glass Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">DD</ENT>
                  <ENT>Grain Elevators</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">EE</ENT>
                  <ENT>Surface Coating of Metal Furniture</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">FF</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">GG</ENT>
                  <ENT>Stationary Gas Turbines</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">HH</ENT>
                  <ENT>Lime Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">KK</ENT>
                  <ENT>Lead-Acid Battery Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">LL</ENT>
                  <ENT>Metallic Mineral Processing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">MM</ENT>
                  <ENT>Automobile and Light Duty Trucks Surface Coating Operations</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">NN</ENT>
                  <ENT>Phosphate Rock Plants</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">PP</ENT>
                  <ENT>Ammonium Sulfate Manufacture</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">QQ</ENT>
                  <ENT>Graphic Arts Industry: Publication Rotogravure Printing</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">RR</ENT>
                  <ENT>Pressure Sensitive Tape and Label Surface Coating Operations</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">SS</ENT>
                  <ENT>Industrial Surface Coating: Large Appliances</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">TT</ENT>
                  <ENT>Metal Coil Surface Coating</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">UU</ENT>
                  <ENT>Asphalt Processing and Asphalt Roofing Manufacture</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">VV</ENT>
                  <ENT>Equipment Leaks of VOC in the Synthetic Organic Chemicals Manufacturing Industry</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">WW</ENT>
                  <ENT>Beverage Can Surface Coating Industry</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">XX</ENT>
                  <ENT>Bulk Gasoline Terminals</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">AAA</ENT>
                  <ENT>New Residential Wool Heaters</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">BBB</ENT>
                  <ENT>Rubber Tire Manufacturing Industry</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">CCC</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">DDD</ENT>
                  <ENT>Volatile Organic Compounds (VOC) Emissions from the Polymer Manufacturing Industry</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">EEE</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">FFF</ENT>
                  <ENT>Flexible Vinyl and Urethane Coating and Printing</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">GGG</ENT>
                  <ENT>Equipment Leaks of VOC in Petroleum Refineries</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">HHH</ENT>
                  <ENT>Synthetic Fiber Production Facilities</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">III</ENT>
                  <ENT>Volatile Organic Compound (VOC) Emissions From the Synthetic Organic Chemical Manufacturing Industry (SOCMI) Air Oxidation Unit Processes</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">JJJ</ENT>
                  <ENT>Petroleum Dry Cleaners</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <PRTPAGE P="58"/>
                  <ENT I="01">KKK</ENT>
                  <ENT>Equipment Leaks of VOC From Onshore Natural Gas Processing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">LLL</ENT>
                  <ENT>Onshore Natural Gas Processing: SO2 Emissions</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">MMM</ENT>
                  <ENT>(Reserved)</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">NNN</ENT>
                  <ENT>Volatile Organic Compound (VOC) Emissions From Synthetic Organic Chemical Manufacturing Industry (SOCMI) Distillation Operations</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">OOO</ENT>
                  <ENT>Nonmetallic Mineral Processing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">PPP</ENT>
                  <ENT>Wool Fiberglass Insulation Manufacturing Plants</ENT>
                  <ENT>X</ENT>
                  <ENT/>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">QQQ</ENT>
                  <ENT>VOC Emissions From Petroleum Refinery Wastewater Systems</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">RRR</ENT>
                  <ENT>Volatile Organic Compound Emissions from Synthetic Organic Chemical Manufacturing Industry (SOCMI) Reactor Processes</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">SSS</ENT>
                  <ENT>Magnetic Tape Coating Facilities</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">TTT</ENT>
                  <ENT>Industrial Surface Coating: Surface Coating of Plastic Parts for Business Machines</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">UUU</ENT>
                  <ENT>Calciners and Dryers in Mineral Industries</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">VVV</ENT>
                  <ENT>Polymeric Coating of Supporting Substrates Facilities</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">WWW</ENT>
                  <ENT>Municipal Solid Waste Landfills</ENT>
                  <ENT/>
                  <ENT/>
                  <ENT/>
                </ROW>
              </GPOTABLE>
              <P>(5) Guam. The following table identifies delegations as of June 15, 2001:</P>
              <GPOTABLE CDEF="xls18,r100,48" COLS="3" OPTS="L2">
                <TTITLE>Delegation Status for New Source Performance Standards for Guam</TTITLE>
                <BOXHD>
                  <CHED H="1"/>
                  <CHED H="1">Subpart</CHED>
                  <CHED H="1">Guam</CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">A</ENT>
                  <ENT>General Provisions</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">D</ENT>
                  <ENT>Fossil-Fuel Fired Steam Generators Constructed After August 17, 1971</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Da</ENT>
                  <ENT>Electric Utility Steam Generating Units Constructed After September 18, 1978</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Db</ENT>
                  <ENT>Industrial-Commercial-Institutional Steam Generating Units</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Dc</ENT>
                  <ENT>Small Industrial Steam Generating Units</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">E</ENT>
                  <ENT>Incinerators</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Ea</ENT>
                  <ENT>Municipal Waste Combustors Constructed After December 20, 1989 and On or Before September 20, 1994</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Eb</ENT>
                  <ENT>Municipal Waste Combustors Constructed After September 20, 1994</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">Ec</ENT>
                  <ENT>Hospital/Medical/Infectious Waste Incinerators for Which Construction is Commenced After June 20, 1996</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">F</ENT>
                  <ENT>Portland Cement Plants</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">G</ENT>
                  <ENT>Nitric Acid Plants</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">H</ENT>
                  <ENT>Sulfuric Acid Plants</ENT>
                  <ENT/>
                </ROW>
                <ROW>
                  <ENT I="01">I</ENT>
                  <ENT>Hot Mix Asphalt Facilities</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">J</ENT>
                  <ENT>Petroleum Refineries</ENT>
                  <ENT>X</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">K</ENT>
                  <ENT>Storage Vessels for Petroleum Liquids for Which Construction, Reconstruction, or Modification Commenced After June 11, 1973, and Prior to May 19, 1978</ENT>
                  <ENT>X</ENT>
                </ROW>
              </GPOTABLE>
              <P>(e) The following lists the specific part 60 standards that have been delegated unchanged to the air pollution control agencies in Region 6.</P>
              <P>(1) <E T="03">New Mexico.</E> The New Mexico Environment Department has been delegated all part 60 standards promulgated by EPA, except subpart AAA—Standards of Performance for New Residential Wood Heaters, as amended in the <E T="04">Federal Register</E> through September 1, 2002.</P>

              <P>(2) Louisiana. The Louisiana Department of Environmental Quality has been delegated all part 60 standards promulgated by EPA, except subpart AAA—Standards of Performance for New Residential Wood Heaters, as amended in the <E T="04">Federal Register</E> through July 1, 2002.<PRTPAGE P="59"/>
              </P>
              <CITA>[40 FR 18169, Apr. 25, 1975]</CITA>
              <EDNOTE>
                <HD SOURCE="HED">Editorial Note:</HD>
                <P>For <E T="04">Federal Register</E> citations affecting § 60.4 see the List of CFR Sections Affected which appears in the Finding Aids section of the printed volume and on GPO Access.</P>
              </EDNOTE>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.5</SECTNO>
              <SUBJECT>Determination of construction or mod-i-fi-ca-tion.</SUBJECT>
              <P>(a) When requested to do so by an owner or operator, the Administrator will make a determination of whether action taken or intended to be taken by such owner or operator constitutes construction (including reconstruction) or modification or the commencement thereof within the meaning of this part.</P>
              <P>(b) The Administrator will respond to any request for a determination under paragraph (a) of this section within 30 days of receipt of such request.</P>
              <CITA>[40 FR 58418, Dec. 16, 1975]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.6</SECTNO>
              <SUBJECT>Review of plans.</SUBJECT>
              <P>(a) When requested to do so by an owner or operator, the Administrator will review plans for construction or modification for the purpose of providing technical advice to the owner or operator.</P>
              <P>(b)(1) A separate request shall be submitted for each construction or modification project.</P>
              <P>(2) Each request shall identify the location of such project, and be accompanied by technical information describing the proposed nature, size, design, and method of operation of each affected facility involved in such project, including information on any equipment to be used for measurement or control of emissions.</P>
              <P>(c) Neither a request for plans review nor advice furnished by the Administrator in response to such request shall (1) relieve an owner or operator of legal responsibility for compliance with any provision of this part or of any applicable State or local requirement, or (2) prevent the Administrator from implementing or enforcing any provision of this part or taking any other action authorized by the Act.</P>
              <CITA>[36 FR 24877, Dec. 23, 1971, as amended at 39 FR 9314, Mar. 8, 1974]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.7</SECTNO>
              <SUBJECT>Notification and record keeping.</SUBJECT>
              <P>(a) Any owner or operator subject to the provisions of this part shall furnish the Administrator written notification or, if acceptable to both the Administrator and the owner or operator of a source, electronic notification, as follows:</P>
              <P>(1) A notification of the date construction (or reconstruction as defined under § 60.15) of an affected facility is commenced postmarked no later than 30 days after such date. This requirement shall not apply in the case of mass-produced facilities which are purchased in completed form.</P>
              <P>(2) [Reserved]</P>
              <P>(3) A notification of the actual date of initial startup of an affected facility postmarked within 15 days after such date.</P>
              <P>(4) A notification of any physical or operational change to an existing facility which may increase the emission rate of any air pollutant to which a standard applies, unless that change is specifically exempted under an applicable subpart or in § 60.14(e). This notice shall be postmarked 60 days or as soon as practicable before the change is commenced and shall include information describing the precise nature of the change, present and proposed emission control systems, productive capacity of the facility before and after the change, and the expected completion date of the change. The Administrator may request additional relevant information subsequent to this notice.</P>
              <P>(5) A notification of the date upon which demonstration of the continuous monitoring system performance commences in accordance with § 60.13(c). Notification shall be postmarked not less than 30 days prior to such date.</P>

              <P>(6) A notification of the anticipated date for conducting the opacity observations required by § 60.11(e)(1) of this part. The notification shall also include, if appropriate, a request for the Administrator to provide a visible emissions reader during a performance <PRTPAGE P="60"/>test. The notification shall be postmarked not less than 30 days prior to such date.</P>
              <P>(7) A notification that continuous opacity monitoring system data results will be used to determine compliance with the applicable opacity standard during a performance test required by § 60.8 in lieu of Method 9 observation data as allowed by § 60.11(e)(5) of this part. This notification shall be postmarked not less than 30 days prior to the date of the performance test.</P>
              <P>(b) Any owner or operator subject to the provisions of this part shall maintain records of the occurrence and duration of any startup, shutdown, or malfunction in the operation of an affected facility; any malfunction of the air pollution control equipment; or any periods during which a continuous monitoring system or monitoring device is inoperative.</P>
              <P>(c) Each owner or operator required to install a continuous monitoring device shall submit excess emissions and monitoring systems performance report (excess emissions are defined in applicable subparts) and-or summary report form (see paragraph (d) of this section) to the Administrator semiannually, except when: more frequent reporting is specifically required by an applicable subpart; or the Administrator, on a case-by-case basis, determines that more frequent reporting is necessary to accurately assess the compliance status of the source. All reports shall be postmarked by the 30th day following the end of each six-month period. Written reports of excess emissions shall include the following information:</P>
              <P>(1) The magnitude of excess emissions computed in accordance with § 60.13(h), any conversion factor(s) used, and the date and time of commencement and completion of each time period of excess emissions. The process operating time during the reporting period.</P>
              <P>(2) Specific identification of each period of excess emissions that occurs during startups, shutdowns, and malfunctions of the affected facility. The nature and cause of any malfunction (if known), the corrective action taken or preventative measures adopted.</P>
              <P>(3) The date and time identifying each period during which the continuous monitoring system was inoperative except for zero and span checks and the nature of the system repairs or adjustments.</P>
              <P>(4) When no excess emissions have occurred or the continuous monitoring system(s) have not been inoperative, repaired, or adjusted, such information shall be stated in the report.</P>
              <P>(d) The summary report form shall contain the information and be in the format shown in figure 1 unless otherwise specified by the Administrator. One summary report form shall be submitted for each pollutant monitored at each affected facility.</P>
              <P>(1) If the total duration of excess emissions for the reporting period is less than 1 percent of the total operating time for the reporting period and CMS downtime for the reporting period is less than 5 percent of the total operating time for the reporting period, only the summary report form shall be submitted and the excess emission report described in § 60.7(c) need not be submitted unless requested by the Administrator.</P>
              <P>(2) If the total duration of excess emissions for the reporting period is 1 percent or greater of the total operating time for the reporting period or the total CMS downtime for the reporting period is 5 percent or greater of the total operating time for the reporting period, the summary report form and the excess emission report described in § 60.7(c) shall both be submitted.</P>
              <HD SOURCE="HD1">Figure 1—Summary Report—Gaseous and Opacity Excess Emission and Monitoring System Performance</HD>
              <EXTRACT>
                <FP SOURCE="FP-1">Pollutant (Circle One—SO<E T="52">2</E>/NO<E T="52">X</E>/TRS/H<E T="52">2</E>S/CO/Opacity)</FP>
                <FP SOURCE="FP-1">Reporting period dates: From _____ to _____</FP>
                <FP SOURCE="FP-1">Company:</FP>
                <FP SOURCE="FP-DASH">Emission Limitation</FP>
                <FP SOURCE="FP-1">Address:</FP>
                <FP SOURCE="FP-DASH">Monitor Manufacturer and Model No.</FP>
                <FP SOURCE="FP-DASH">Date of Latest CMS Certification or Audit</FP>
                <FP SOURCE="FP-1">Process Unit(s) Description:</FP>
                <FP SOURCE="FP-DASH">Total source operating time in reporting period <SU>1</SU>
                  <PRTPAGE P="61"/>
                </FP>
                <GPOTABLE CDEF="s100n,7,r100n,7" COLS="4" OPTS="L2">
                  <BOXHD>
                    <CHED H="1">Emission data summary <SU>1</SU>
                    </CHED>
                    <CHED H="1"/>
                    <CHED H="1">CMS performance summary <SU>1</SU>
                    </CHED>
                    <CHED H="1"/>
                  </BOXHD>
                  <ROW>
                    <ENT I="11">1. Duration of excess emissions in reporting period due to:</ENT>
                    <ENT/>
                    <ENT O="xl">1. CMS downtime in reporting period due to:</ENT>
                  </ROW>
                  <ROW>
                    <ENT I="02">a. Startup/shutdown</ENT>
                    <ENT/>
                    <ENT>a. Monitor equipment malfunctions</ENT>
                    <ENT/>
                  </ROW>
                  <ROW>
                    <ENT I="02">b. Control equipment problems</ENT>
                    <ENT/>
                    <ENT>b. Non-Monitor equipment malfunctions</ENT>
                    <ENT/>
                  </ROW>
                  <ROW>
                    <ENT I="02">c. Process problems</ENT>
                    <ENT/>
                    <ENT>c. Quality assurance calibration</ENT>
                    <ENT/>
                  </ROW>
                  <ROW>
                    <ENT I="02">d. Other known causes</ENT>
                    <ENT/>
                    <ENT>d. Other known causes</ENT>
                    <ENT/>
                  </ROW>
                  <ROW>
                    <ENT I="02">e. Unknown causes</ENT>
                    <ENT/>
                    <ENT>e. Unknown causes</ENT>
                    <ENT/>
                  </ROW>
                  <ROW>
                    <ENT I="01">2. Total duration of excess emission</ENT>
                    <ENT/>
                    <ENT>2. Total CMS Downtime</ENT>
                    <ENT/>
                  </ROW>
                  <ROW>
                    <ENT I="01">3. Total duration of excess emissions × (100) [Total source operating time]</ENT>
                    <ENT>% <SU>2</SU>
                    </ENT>
                    <ENT>3. [Total CMS Downtime] × (100) [Total source operating time]</ENT>
                    <ENT>% <SU>2</SU>
                    </ENT>
                  </ROW>
                  <TNOTE>
                    <SU>1</SU> For opacity, record all times in minutes. For gases, record all times in hours.</TNOTE>
                  <TNOTE>
                    <SU>2</SU> For the reporting period: If the total duration of excess emissions is 1 percent or greater of the total operating time or the total CMS downtime is 5 percent or greater of the total operating time, both the summary report form and the excess emission report described in § 60.7(c) shall be submitted.</TNOTE>
                </GPOTABLE>

                <P>On a separate page, describe any changes since last quarter in CMS, process or controls. I certify that the information contained in this report is true, accurate, and complete.
                </P>
                <FP SOURCE="FP-DASH"/>
                <FP>Name</FP>
                
                <FP SOURCE="FP-DASH"/>
                <FP>Signature</FP>
                
                <FP SOURCE="FP-DASH"/>
                <FP>Title</FP>
                
                <FP SOURCE="FP-DASH"/>
                <FP>Date</FP>
              </EXTRACT>
              
              <P>(e)(1) Notwithstanding the frequency of reporting requirements specified in paragraph (c) of this section, an owner or operator who is required by an applicable subpart to submit excess emissions and monitoring systems performance reports (and summary reports) on a quarterly (or more frequent) basis may reduce the frequency of reporting for that standard to semiannual if the following conditions are met:</P>
              <P>(i) For 1 full year (e.g., 4 quarterly or 12 monthly reporting periods) the affected facility's excess emissions and monitoring systems reports submitted to comply with a standard under this part continually demonstrate that the facility is in compliance with the applicable standard;</P>
              <P>(ii) The owner or operator continues to comply with all recordkeeping and monitoring requirements specified in this subpart and the applicable standard; and</P>
              <P>(iii) The Administrator does not object to a reduced frequency of reporting for the affected facility, as provided in paragraph (e)(2) of this section.</P>
              <P>(2) The frequency of reporting of excess emissions and monitoring systems performance (and summary) reports may be reduced only after the owner or operator notifies the Administrator in writing of his or her intention to make such a change and the Administrator does not object to the intended change. In deciding whether to approve a reduced frequency of reporting, the Administrator may review information concerning the source's entire previous performance history during the required recordkeeping period prior to the intended change, including performance test results, monitoring data, and evaluations of an owner or operator's conformance with operation and maintenance requirements. Such information may be used by the Administrator to make a judgment about the source's potential for noncompliance in the future. If the Administrator disapproves the owner or operator's request to reduce the frequency of reporting, the Administrator will notify the owner or operator in writing within 45 days after receiving notice of the owner or operator's intention. The notification from the Administrator to the owner or operator will specify the grounds on which the disapproval is based. In the absence of a notice of disapproval within 45 days, approval is automatically granted.</P>

              <P>(3) As soon as monitoring data indicate that the affected facility is not in compliance with any emission limitation or operating parameter specified in the applicable standard, the frequency of reporting shall revert to the frequency specified in the applicable standard, and the owner or operator shall submit an excess emissions and monitoring systems performance report (and summary report, if required) at the next appropriate reporting period following the noncomplying event. <PRTPAGE P="62"/>After demonstrating compliance with the applicable standard for another full year, the owner or operator may again request approval from the Administrator to reduce the frequency of reporting for that standard as provided for in paragraphs (e)(1) and (e)(2) of this section.</P>
              <P>(f) Any owner or operator subject to the provisions of this part shall maintain a file of all measurements, including continuous monitoring system, monitoring device, and performance testing measurements; all continuous monitoring system performance evaluations; all continuous monitoring system or monitoring device calibration checks; adjustments and maintenance performed on these systems or devices; and all other information required by this part recorded in a permanent form suitable for inspection. The file shall be retained for at least two years following the date of such measurements, maintenance, reports, and records, except as follows:</P>
              <P>(1) This paragraph applies to owners or operators required to install a continuous emissions monitoring system (CEMS) where the CEMS installed is automated, and where the calculated data averages do not exclude periods of CEMS breakdown or malfunction. An automated CEMS records and reduces the measured data to the form of the pollutant emission standard through the use of a computerized data acquisition system. In lieu of maintaining a file of all CEMS subhourly measurements as required under paragraph (f) of this section, the owner or operator shall retain the most recent consecutive three averaging periods of subhourly measurements and a file that contains a hard copy of the data acquisition system algorithm used to reduce the measured data into the reportable form of the standard.</P>
              <P>(2) This paragraph applies to owners or operators required to install a CEMS where the measured data is manually reduced to obtain the reportable form of the standard, and where the calculated data averages do not exclude periods of CEMS breakdown or malfunction. In lieu of maintaining a file of all CEMS subhourly measurements as required under paragraph (f) of this section, the owner or operator shall retain all subhourly measurements for the most recent reporting period. The subhourly measurements shall be retained for 120 days from the date of the most recent summary or excess emission report submitted to the Administrator.</P>
              <P>(3) The Administrator or delegated authority, upon notification to the source, may require the owner or operator to maintain all measurements as required by paragraph (f) of this section, if the Administrator or the delegated authority determines these records are required to more accurately assess the compliance status of the affected source.</P>
              <P>(g) If notification substantially similar to that in paragraph (a) of this section is required by any other State or local agency, sending the Administrator a copy of that notification will satisfy the requirements of paragraph (a) of this section.</P>
              <P>(h) Individual subparts of this part may include specific provisions which clarify or make inapplicable the provisions set forth in this section.</P>
              <CITA>[36 FR 24877, Dec. 28, 1971, as amended at 40 FR 46254, Oct. 6, 1975; 40 FR 58418, Dec. 16, 1975; 45 FR 5617, Jan. 23, 1980; 48 FR 48335, Oct. 18, 1983; 50 FR 53113, Dec. 27, 1985; 52 FR 9781, Mar. 26, 1987; 55 FR 51382, Dec. 13, 1990; 59 FR 12428, Mar. 16, 1994; 59 FR 47265, Sep. 15, 1994; 64 FR 7463, Feb. 12, 1999]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.8</SECTNO>
              <SUBJECT>Performance tests.</SUBJECT>
              <P>(a) Within 60 days after achieving the maximum production rate at which the affected facility will be operated, but not later than 180 days after initial startup of such facility and at such other times as may be required by the Administrator under section 114 of the Act, the owner or operator of such facility shall conduct performance test(s) and furnish the Administrator a written report of the results of such performance test(s).</P>

              <P>(b) Performance tests shall be conducted and data reduced in accordance with the test methods and procedures contained in each applicable subpart unless the Administrator (1) specifies or approves, in specific cases, the use of a reference method with minor changes in methodology, (2) approves the use of an equivalent method, (3) approves the <PRTPAGE P="63"/>use of an alternative method the results of which he has determined to be adequate for indicating whether a specific source is in compliance, (4) waives the requirement for performance tests because the owner or operator of a source has demonstrated by other means to the Administrator's satisfaction that the affected facility is in compliance with the standard, or (5) approves shorter sampling times and smaller sample volumes when necessitated by process variables or other factors. Nothing in this paragraph shall be construed to abrogate the Administrator's authority to require testing under section 114 of the Act.</P>
              <P>(c) Performance tests shall be conducted under such conditions as the Administrator shall specify to the plant operator based on representative performance of the affected facility. The owner or operator shall make available to the Administrator such records as may be necessary to determine the conditions of the performance tests. Operations during periods of startup, shutdown, and malfunction shall not constitute representative conditions for the purpose of a performance test nor shall emissions in excess of the level of the applicable emission limit during periods of startup, shutdown, and malfunction be considered a violation of the applicable emission limit unless otherwise specified in the applicable standard.</P>
              <P>(d) The owner or operator of an affected facility shall provide the Administrator at least 30 days prior notice of any performance test, except as specified under other subparts, to afford the Administrator the opportunity to have an observer present. If after 30 days notice for an initially scheduled performance test, there is a delay (due to operational problems, etc.) in conducting the scheduled performance test, the owner or operator of an affected facility shall notify the Administrator (or delegated State or local agency) as soon as possible of any delay in the original test date, either by providing at least 7 days prior notice of the rescheduled date of the performance test, or by arranging a rescheduled date with the Administrator (or delegated State or local agency) by mutual agreement.</P>
              <P>(e) The owner or operator of an affected facility shall provide, or cause to be provided, performance testing facilities as follows:</P>
              <P>(1) Sampling ports adequate for test methods applicable to such facility. This includes (i) constructing the air pollution control system such that volumetric flow rates and pollutant emission rates can be accurately determined by applicable test methods and procedures and (ii) providing a stack or duct free of cyclonic flow during performance tests, as demonstrated by applicable test methods and procedures.</P>
              <P>(2) Safe sampling platform(s).</P>
              <P>(3) Safe access to sampling plat-form(s).</P>
              <P>(4) Utilities for sampling and testing equipment.</P>
              <P>(f) Unless otherwise specified in the applicable subpart, each performance test shall consist of three separate runs using the applicable test method. Each run shall be conducted for the time and under the conditions specified in the applicable standard. For the purpose of determining compliance with an applicable standard, the arithmetic means of results of the three runs shall apply. In the event that a sample is accidentally lost or conditions occur in which one of the three runs must be discontinued because of forced shutdown, failure of an irreplaceable portion of the sample train, extreme meteorological conditions, or other circumstances, beyond the owner or operator's control, compliance may, upon the Administrator's approval, be determined using the arithmetic mean of the results of the two other runs.</P>
              <CITA>[36 FR 24877, Dec. 23, 1971, as amended at 39 FR 9314, Mar. 8, 1974; 42 FR 57126, Nov. 1, 1977; 44 FR 33612, June 11, 1979; 54 FR 6662, Feb. 14, 1989; 54 FR 21344, May 17, 1989; 64 FR 7463, Feb. 12, 1999]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.9</SECTNO>
              <SUBJECT>Availability of information.</SUBJECT>
              <P>The availability to the public of information provided to, or otherwise obtained by, the Administrator under this part shall be governed by part 2 of this chapter. (Information submitted voluntarily to the Administrator for the purposes of §§ 60.5 and 60.6 is governed by §§ 2.201 through 2.213 of this chapter and not by § 2.301 of this chapter.)</P>
            </SECTION>
            <SECTION>
              <PRTPAGE P="64"/>
              <SECTNO>§ 60.10</SECTNO>
              <SUBJECT>State authority.</SUBJECT>
              <P>The provisions of this part shall not be construed in any manner to preclude any State or political subdivision thereof from:</P>
              <P>(a) Adopting and enforcing any emission standard or limitation applicable to an affected facility, provided that such emission standard or limitation is not less stringent than the standard applicable to such facility.</P>
              <P>(b) Requiring the owner or operator of an affected facility to obtain permits, licenses, or approvals prior to initiating construction, modification, or operation of such facility.</P>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.11</SECTNO>
              <SUBJECT>Compliance with standards and maintenance requirements.</SUBJECT>
              <P>(a) Compliance with standards in this part, other than opacity standards, shall be determined in accordance with performance tests established by § 60.8, unless otherwise specified in the applicable standard.</P>
              <P>(b) Compliance with opacity standards in this part shall be determined by conducting observations in accordance with Method 9 in appendix A of this part, any alternative method that is approved by the Administrator, or as provided in paragraph (e)(5) of this section. For purposes of determining initial compliance, the minimum total time of observations shall be 3 hours (30 6-minute averages) for the performance test or other set of observations (meaning those fugitive-type emission sources subject only to an opacity standard).</P>
              <P>(c) The opacity standards set forth in this part shall apply at all times except during periods of startup, shutdown, malfunction, and as otherwise provided in the applicable standard.</P>
              <P>(d) At all times, including periods of startup, shutdown, and malfunction, owners and operators shall, to the extent practicable, maintain and operate any affected facility including associated air pollution control equipment in a manner consistent with good air pollution control practice for minimizing emissions. Determination of whether acceptable operating and maintenance procedures are being used will be based on information available to the Administrator which may include, but is not limited to, monitoring results, opacity observations, review of operating and maintenance procedures, and inspection of the source.</P>

              <P>(e)(1) For the purpose of demonstrating initial compliance, opacity observations shall be conducted concurrently with the initial performance test required in § 60.8 unless one of the following conditions apply. If no performance test under § 60.8 is required, then opacity observations shall be conducted within 60 days after achieving the maximum production rate at which the affected facility will be operated but no later than 180 days after initial startup of the facility. If visibility or other conditions prevent the opacity observations from being conducted concurrently with the initial performance test required under § 60.8, the source owner or operator shall reschedule the opacity observations as soon after the initial performance test as possible, but not later than 30 days thereafter, and shall advise the Administrator of the rescheduled date. In these cases, the 30-day prior notification to the Administrator required in § 60.7(a)(6) shall be waived. The rescheduled opacity observations shall be conducted (to the extent possible) under the same operating conditions that existed during the initial performance test conducted under § 60.8. The visible emissions observer shall determine whether visibility or other conditions prevent the opacity observations from being made concurrently with the initial performance test in accordance with procedures contained in Method 9 of appendix B of this part. Opacity readings of portions of plumes which contain condensed, uncombined water vapor shall not be used for purposes of determing compliance with opacity standards. The owner or operator of an affected facility shall make available, upon request by the Administrator, such records as may be necessary to determine the conditions under which the visual observations were made and shall provide evidence indicating proof of current visible observer emission certification. Except as provided in paragraph (e)(5) of this section, the results of continuous monitoring by transmissometer which indicate that the opacity at the time visual observations were made was not in excess of <PRTPAGE P="65"/>the standard are probative but not conclusive evidence of the actual opacity of an emission, provided that the source shall meet the burden of proving that the instrument used meets (at the time of the alleged violation) Performance Specification 1 in appendix B of this part, has been properly maintained and (at the time of the alleged violation) that the resulting data have not been altered in any way.</P>
              <P>(2) Except as provided in paragraph (e)(3) of this section, the owner or operator of an affected facility to which an opacity standard in this part applies shall conduct opacity observations in accordance with paragraph (b) of this section, shall record the opacity of emissions, and shall report to the Administrator the opacity results along with the results of the initial performance test required under § 60.8. The inability of an owner or operator to secure a visible emissions observer shall not be considered a reason for not conducting the opacity observations concurrent with the initial performance test.</P>
              <P>(3) The owner or operator of an affected facility to which an opacity standard in this part applies may request the Administrator to determine and to record the opacity of emissions from the affected facility during the initial performance test and at such times as may be required. The owner or operator of the affected facility shall report the opacity results. Any request to the Administrator to determine and to record the opacity of emissions from an affected facility shall be included in the notification required in § 60.7(a)(6). If, for some reason, the Administrator cannot determine and record the opacity of emissions from the affected facility during the performance test, then the provisions of paragraph (e)(1) of this section shall apply.</P>
              <P>(4) An owner or operator of an affected facility using a continuous opacity monitor (transmissometer) shall record the monitoring data produced during the initial performance test required by § 60.8 and shall furnish the Administrator a written report of the monitoring results along with Method 9 and § 60.8 performance test results.</P>
              <P>(5) An owner or operator of an affected facility subject to an opacity standard may submit, for compliance purposes, continuous opacity monitoring system (COMS) data results produced during any performance test required under § 60.8 in lieu of Method 9 observation data. If an owner or operator elects to submit COMS data for compliance with the opacity standard, he shall notify the Administrator of that decision, in writing, at least 30 days before any performance test required under § 60.8 is conducted. Once the owner or operator of an affected facility has notified the Administrator to that effect, the COMS data results will be used to determine opacity compliance during subsequent tests required under § 60.8 until the owner or operator notifies the Administrator, in writing, to the contrary. For the purpose of determining compliance with the opacity standard during a performance test required under § 60.8 using COMS data, the minimum total time of COMS data collection shall be averages of all 6-minute continuous periods within the duration of the mass emission performance test. Results of the COMS opacity determinations shall be submitted along with the results of the performance test required under § 60.8. The owner or operator of an affected facility using a COMS for compliance purposes is responsible for demonstrating that the COMS meets the requirements specified in § 60.13(c) of this part, that the COMS has been properly maintained and operated, and that the resulting data have not been altered in any way. If COMS data results are submitted for compliance with the opacity standard for a period of time during which Method 9 data indicates noncompliance, the Method 9 data will be used to determine compliance with the opacity standard.</P>

              <P>(6) Upon receipt from an owner or operator of the written reports of the results of the performance tests required by § 60.8, the opacity observation results and observer certification required by § 60.11(e)(1), and the COMS results, if applicable, the Administrator will make a finding concerning compliance with opacity and other applicable standards. If COMS data results are used to comply with an opacity standard, only those results are required to <PRTPAGE P="66"/>be submitted along with the performance test results required by § 60.8. If the Administrator finds that an affected facility is in compliance with all applicable standards for which performance tests are conducted in accordance with § 60.8 of this part but during the time such performance tests are being conducted fails to meet any applicable opacity standard, he shall notify the owner or operator and advise him that he may petition the Administrator within 10 days of receipt of notification to make appropriate adjustment to the opacity standard for the affected facility.</P>
              <P>(7) The Administrator will grant such a petition upon a demonstration by the owner or operator that the affected facility and associated air pollution control equipment was operated and maintained in a manner to minimize the opacity of emissions during the performance tests; that the performance tests were performed under the conditions established by the Administrator; and that the affected facility and associated air pollution control equipment were incapable of being adjusted or operated to meet the applicable opacity standard.</P>

              <P>(8) The Administrator will establish an opacity standard for the affected facility meeting the above requirements at a level at which the source will be able, as indicated by the performance and opacity tests, to meet the opacity standard at all times during which the source is meeting the mass or concentration emission standard. The Administrator will promulgate the new opacity standard in the <E T="04">Federal Register.</E>
              </P>
              <P>(f) Special provisions set forth under an applicable subpart shall supersede any conflicting provisions in paragraphs (a) through (e) of this section.</P>
              <P>(g) For the purpose of submitting compliance certifications or establishing whether or not a person has violated or is in violation of any standard in this part, nothing in this part shall preclude the use, including the exclusive use, of any credible evidence or information, relevant to whether a source would have been in compliance with applicable requirements if the appropriate performance or compliance test or procedure had been performed.</P>
              <CITA>[38 FR 28565, Oct. 15, 1973, as amended at 39 FR 39873, Nov. 12, 1974; 43 FR 8800, Mar. 3, 1978; 45 FR 23379, Apr. 4, 1980; 48 FR 48335, Oct. 18, 1983; 50 FR 53113, Dec. 27, 1985; 51 FR 1790, Jan. 15, 1986; 52 FR 9781, Mar. 26, 1987; 62 FR 8328, Feb. 24, 1997; 65 FR 61749, Oct. 17, 2000]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.12</SECTNO>
              <SUBJECT>Circumvention.</SUBJECT>
              <P>No owner or operator subject to the provisions of this part shall build, erect, install, or use any article, machine, equipment or process, the use of which conceals an emission which would otherwise constitute a violation of an applicable standard. Such concealment includes, but is not limited to, the use of gaseous diluents to achieve compliance with an opacity standard or with a standard which is based on the concentration of a pollutant in the gases discharged to the atmosphere.</P>
              <CITA>[39 FR 9314, Mar. 8, 1974]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.13</SECTNO>
              <SUBJECT>Monitoring requirements.</SUBJECT>
              <P>(a) For the purposes of this section, all continuous monitoring systems required under applicable subparts shall be subject to the provisions of this section upon promulgation of performance specifications for continuous monitoring systems under appendix B to this part and, if the continuous monitoring system is used to demonstrate compliance with emission limits on a continuous basis, appendix F to this part, unless otherwise specified in an applicable subpart or by the Administrator. Appendix F is applicable December 4, 1987.</P>
              <P>(b) All continuous monitoring systems and monitoring devices shall be installed and operational prior to conducting performance tests under § 60.8. Verification of operational status shall, as a minimum, include completion of the manufacturer's written requirements or recommendations for installation, operation, and calibration of the device.</P>

              <P>(c) If the owner or operator of an affected facility elects to submit continous opacity monitoring system (COMS) data for compliance with the opacity standard as provided under <PRTPAGE P="67"/>§ 60.11(e)(5), he shall conduct a performance evaluation of the COMS as specified in Performance Specification 1, appendix B, of this part before the performance test required under § 60.8 is conducted. Otherwise, the owner or operator of an affected facility shall conduct a performance evaluation of the COMS or continuous emission monitoring system (CEMS) during any performance test required under § 60.8 or within 30 days thereafter in accordance with the applicable performance specification in appendix B of this part, The owner or operator of an affected facility shall conduct COMS or CEMS performance evaluations at such other times as may be required by the Administrator under section 114 of the Act.</P>
              <P>(1) The owner or operator of an affected facility using a COMS to determine opacity compliance during any performance test required under § 60.8 and as described in § 60.11(e)(5) shall furnish the Administrator two or, upon request, more copies of a written report of the results of the COMS performance evaluation described in paragraph (c) of this section at least 10 days before the performance test required under § 60.8 is conducted.</P>
              <P>(2) Except as provided in paragraph (c)(1) of this section, the owner or operator of an affected facility shall furnish the Administrator within 60 days of completion two or, upon request, more copies of a written report of the results of the performance evaluation.</P>
              <P>(d)(1) Owners and operators of a CEMS installed in accordance with the provisions of this part, must automatically check the zero (or low level value between 0 and 20 percent of span value) and span (50 to 100 percent of span value) calibration drifts at least once daily in accordance with a written procedure. The zero and span must, as a minimum, be adjusted whenever either the 24-hour zero drift or the 24-hour span drift exceeds two times the limit of the applicable performance specification in appendix B of this part. The system must allow the amount of the excess zero and span drift to be recorded and quantified whenever specified. Owners and operators of a COMS installed in accordance with the provisions of this part, must automatically, intrinsic to the opacity monitor, check the zero and upscale (span) calibration drifts at least once daily. For a particular COMS, the acceptable range of zero and upscale calibration materials is as defined in the applicable version of PS-1 in appendix B of this part. For a COMS, the optical surfaces, exposed to the effluent gases, must be cleaned before performing the zero and upscale drift adjustments, except for systems using automatic zero adjustments. The optical surfaces must be cleaned when the cumulative automatic zero compensation exceeds 4 percent opacity.</P>
              <P>(2) Unless otherwise approved by the Administrator, the following procedures must be followed for a COMS. Minimum procedures must include an automated method for producing a simulated zero opacity condition and an upscale opacity condition using a certified neutral density filter or other related technique to produce a known obstruction of the light beam. Such procedures must provide a system check of all active analyzer internal optics with power or curvature, all active electronic circuitry including the light source and photodetector assembly, and electronic or electro-mechanical systems and hardware and or software used during normal measurement operation.</P>
              <P>(e) Except for system breakdowns, repairs, calibration checks, and zero and span adjustments required under paragraph (d) of this section, all continuous monitoring systems shall be in continuous operation and shall meet minimum frequency of operation requirements as follows:</P>
              <P>(1) All continuous monitoring systems referenced by paragraph (c) of this section for measuring opacity of emissions shall complete a minimum of one cycle of sampling and analyzing for each successive 10-second period and one cycle of data recording for each successive 6-minute period.</P>

              <P>(2) All continuous monitoring systems referenced by paragraph (c) of this section for measuring emissions, except opacity, shall complete a minimum of one cycle of operation (sampling, analyzing, and data recording) for each successive 15-minute period.<PRTPAGE P="68"/>
              </P>
              <P>(f) All continuous monitoring systems or monitoring devices shall be installed such that representative measurements of emissions or process parameters from the affected facility are obtained. Additional procedures for location of continuous monitoring systems contained in the applicable Performance Specifications of appendix B of this part shall be used.</P>
              <P>(g) When the effluents from a single affected facility or two or more affected facilities subject to the same emission standards are combined before being released to the atmosphere, the owner or operator may install applicable continuous monitoring systems on each effluent or on the combined effluent. When the affected facilities are not subject to the same emission standards, separate continuous monitoring systems shall be installed on each effluent. When the effluent from one affected facility is released to the atmosphere through more than one point, the owner or operator shall install an applicable continuous monitoring system on each separate effluent unless the installation of fewer systems is approved by the Administrator. When more than one continuous monitoring system is used to measure the emissions from one affected facility (e.g., multiple breechings, multiple outlets), the owner or operator shall report the results as required from each continuous monitoring system.</P>

              <P>(h) Owners or operators of all continuous monitoring systems for measurement of opacity shall reduce all data to 6-minute averages and for continuous monitoring systems other than opacity to 1-hour averages for time periods as defined in § 60.2. Six-minute opacity averages shall be calculated from 36 or more data points equally spaced over each 6-minute period. For continuous monitoring systems other than opacity, 1-hour averages shall be computed from four or more data points equally spaced over each 1-hour period. Data recorded during periods of continuous system breakdown, repair, calibration checks, and zero and span adjustments shall not be included in the data averages computed under this paragraph. For owners and operators complying with the requirements in § 60.7(f) (1) or (2), data averages must include any data recorded during periods of monitor breakdown or malfunction. An arithmetic or integrated average of all data may be used. The data may be recorded in reduced or nonreduced form (e.g., ppm pollutant and percent O<E T="52">2</E> or ng/J of pollutant). All excess emissions shall be converted into units of the standard using the applicable conversion procedures specified in subparts. After conversion into units of the standard, the data may be rounded to the same number of significant digits as used in the applicable subparts to specify the emission limit (e.g., rounded to the nearest 1 percent opacity).</P>
              <P>(i) After receipt and consideration of written application, the Administrator may approve alternatives to any monitoring procedures or requirements of this part including, but not limited to the following:</P>
              <P>(1) Alternative monitoring requirements when installation of a continuous monitoring system or monitoring device specified by this part would not provide accurate measurements due to liquid water or other interferences caused by substances in the effluent gases.</P>
              <P>(2) Alternative monitoring requirements when the affected facility is infrequently operated.</P>
              <P>(3) Alternative monitoring requirements to accommodate continuous monitoring systems that require additional measurements to correct for stack moisture conditions.</P>
              <P>(4) Alternative locations for installing continuous monitoring systems or monitoring devices when the owner or operator can demonstrate that installation at alternate locations will enable accurate and representative measurements.</P>
              <P>(5) Alternative methods of converting pollutant concentration measurements to units of the standards.</P>
              <P>(6) Alternative procedures for performing daily checks of zero and span drift that do not involve use of span gases or test cells.</P>
              <P>(7) Alternatives to the A.S.T.M. test methods or sampling procedures specified by any subpart.</P>

              <P>(8) Alternative continuous monitoring systems that do not meet the design or performance requirements in Performance Specification 1, appendix <PRTPAGE P="69"/>B, but adequately demonstrate a definite and consistent relationship between its measurements and the measurements of opacity by a system complying with the requirements in Performance Specification 1. The Administrator may require that such demonstration be performed for each affected facility.</P>
              <P>(9) Alternative monitoring requirements when the effluent from a single affected facility or the combined effluent from two or more affected facilities is released to the atmosphere through more than one point.</P>
              <P>(j) An alternative to the relative accuracy (RA) test specified in Performance Specification 2 of appendix B may be requested as follows:</P>
              <P>(1) An alternative to the reference method tests for determining RA is available for sources with emission rates demonstrated to be less than 50 percent of the applicable standard. A source owner or operator may petition the Administrator to waive the RA test in Section 8.4 of Performance Specification 2 and substitute the procedures in Section 16.0 if the results of a performance test conducted according to the requirements in § 60.8 of this subpart or other tests performed following the criteria in § 60.8 demonstrate that the emission rate of the pollutant of interest in the units of the applicable standard is less than 50 percent of the applicable standard. For sources subject to standards expressed as control efficiency levels, a source owner or operator may petition the Administrator to waive the RA test and substitute the procedures in Section 16.0 of Performance Specification 2 if the control device exhaust emission rate is less than 50 percent of the level needed to meet the control efficiency requirement. The alternative procedures do not apply if the continuous emission monitoring system is used to determine compliance continuously with the applicable standard. The petition to waive the RA test shall include a detailed description of the procedures to be applied. Included shall be location and procedure for conducting the alternative, the concentration or response levels of the alternative RA materials, and the other equipment checks included in the alternative procedure. The Administrator will review the petition for completeness and applicability. The determination to grant a waiver will depend on the intended use of the CEMS data (e.g., data collection purposes other than NSPS) and may require specifications more stringent than in Performance Specification 2 (e.g., the applicable emission limit is more stringent than NSPS).</P>
              <P>(2) The waiver of a CEMS RA test will be reviewed and may be rescinded at such time, following successful completion of the alternative RA procedure, that the CEMS data indicate that the source emissions are approaching the level. The criterion for reviewing the waiver is the collection of CEMS data showing that emissions have exceeded 70 percent of the applicable standard for seven, consecutive, averaging periods as specified by the applicable regulation(s). For sources subject to standards expressed as control efficiency levels, the criterion for reviewing the waiver is the collection of CEMS data showing that exhaust emissions have exceeded 70 percent of the level needed to meet the control efficiency requirement for seven, consecutive, averaging periods as specified by the applicable regulation(s) [e.g., § 60.45(g) (2) and (3), § 60.73(e), and § 60.84(e)]. It is the responsibility of the source operator to maintain records and determine the level of emissions relative to the criterion on the waiver of RA testing. If this criterion is exceeded, the owner or operator must notify the Administrator within 10 days of such occurrence and include a description of the nature and cause of the increasing emissions. The Administrator will review the notification and may rescind the waiver and require the owner or operator to conduct a RA test of the CEMS as specified in Section 8.4 of Performance Specification 2.</P>
              <CITA>[40 FR 46255, Oct. 6, 1975; 40 FR 59205, Dec. 22, 1975, as amended at 41 FR 35185, Aug. 20, 1976; 48 FR 13326, Mar. 30, 1983; 48 FR 23610, May 25, 1983; 48 FR 32986, July 20, 1983; 52 FR 9782, Mar. 26, 1987; 52 FR 17555, May 11, 1987; 52 FR 21007, June 4, 1987; 64 FR 7463, Feb. 12, 1999; 65 FR 48920, Aug. 10, 2000; 65 FR 61749, Oct. 17, 2000; 66 FR 44980, Aug. 27, 2001]</CITA>
              <EDNOTE>
                <HD SOURCE="HED">Editorial Note:</HD>

                <P>At 65 FR 61749, Oct. 17, 2000, § 60.13 was amended by revising the <PRTPAGE P="70"/>words “ng/J of pollutant” to read “ng of pollutant per J of heat input” in the sixth sentence of paragraph (h). However, the amendment could not be incorporated because the words “ng/J of pollutant” do not exist in the sixth sentence of paragraph (h).</P>
              </EDNOTE>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.14</SECTNO>
              <SUBJECT>Modification.</SUBJECT>
              <P>(a) Except as provided under paragraphs (e) and (f) of this section, any physical or operational change to an existing facility which results in an increase in the emission rate to the atmosphere of any pollutant to which a standard applies shall be considered a modification within the meaning of section 111 of the Act. Upon modification, an existing facility shall become an affected facility for each pollutant to which a standard applies and for which there is an increase in the emission rate to the atmosphere.</P>
              <P>(b) Emission rate shall be expressed as kg/hr of any pollutant discharged into the atmosphere for which a standard is applicable. The Administrator shall use the following to determine emission rate:</P>
              <P>(1) Emission factors as specified in the latest issue of “Compilation of Air Pollutant Emission Factors,” EPA Publication No. AP-42, or other emission factors determined by the Administrator to be superior to AP-42 emission factors, in cases where utilization of emission factors demonstrates that the emission level resulting from the physical or operational change will either clearly increase or clearly not increase.</P>
              <P>(2) Material balances, continuous monitor data, or manual emission tests in cases where utilization of emission factors as referenced in paragraph (b)(1) of this section does not demonstrate to the Administrator's satisfaction whether the emission level resulting from the physical or operational change will either clearly increase or clearly not increase, or where an owner or operator demonstrates to the Administrator's satisfaction that there are reasonable grounds to dispute the result obtained by the Administrator utilizing emission factors as referenced in paragraph (b)(1) of this section. When the emission rate is based on results from manual emission tests or continuous monitoring systems, the procedures specified in appendix C of this part shall be used to determine whether an increase in emission rate has occurred. Tests shall be conducted under such conditions as the Administrator shall specify to the owner or operator based on representative performance of the facility. At least three valid test runs must be conducted before and at least three after the physical or operational change. All operating parameters which may affect emissions must be held constant to the maximum feasible degree for all test runs.</P>
              <P>(c) The addition of an affected facility to a stationary source as an expansion to that source or as a replacement for an existing facility shall not by itself bring within the applicability of this part any other facility within that source.</P>
              <P>(d) [Reserved]</P>
              <P>(e) The following shall not, by themselves, be considered modifications under this part:</P>
              <P>(1) Maintenance, repair, and replacement which the Administrator determines to be routine for a source category, subject to the provisions of paragraph (c) of this section and § 60.15.</P>
              <P>(2) An increase in production rate of an existing facility, if that increase can be accomplished without a capital expenditure on that facility.</P>
              <P>(3) An increase in the hours of operation.</P>
              <P>(4) Use of an alternative fuel or raw material if, prior to the date any standard under this part becomes applicable to that source type, as provided by § 60.1, the existing facility was designed to accommodate that alternative use. A facility shall be considered to be designed to accommodate an alternative fuel or raw material if that use could be accomplished under the facility's construction specifications as amended prior to the change. Conversion to coal required for energy considerations, as specified in section 111(a)(8) of the Act, shall not be considered a modification.</P>

              <P>(5) The addition or use of any system or device whose primary function is the reduction of air pollutants, except when an emission control system is removed or is replaced by a system which the Administrator determines to be less environmentally beneficial.<PRTPAGE P="71"/>
              </P>
              <P>(6) The relocation or change in ownership of an existing facility.</P>
              <P>(f) Special provisions set forth under an applicable subpart of this part shall supersede any conflicting provisions of this section.</P>
              <P>(g) Within 180 days of the completion of any physical or operational change subject to the control measures specified in paragraph (a) of this section, compliance with all applicable standards must be achieved.</P>
              <P>(h) No physical change, or change in the method of operation, at an existing electric utility steam generating unit shall be treated as a modification for the purposes of this section provided that such change does not increase the maximum hourly emissions of any pollutant regulated under this section above the maximum hourly emissions achievable at that unit during the 5 years prior to the change.</P>
              <P>(i) Repowering projects that are awarded funding from the Department of Energy as permanent clean coal technology demonstration projects (or similar projects funded by EPA) are exempt from the requirements of this section provided that such change does not increase the maximum hourly emissions of any pollutant regulated under this section above the maximum hourly emissions achievable at that unit during the five years prior to the change.</P>
              <P>(j)(1) Repowering projects that qualify for an extension under section 409(b) of the Clean Air Act are exempt from the requirements of this section, provided that such change does not increase the actual hourly emissions of any pollutant regulated under this section above the actual hourly emissions achievable at that unit during the 5 years prior to the change.</P>
              <P>(2) This exemption shall not apply to any new unit that:</P>
              <P>(i) Is designated as a replacement for an existing unit;</P>
              <P>(ii) Qualifies under section 409(b) of the Clean Air Act for an extension of an emission limitation compliance date under section 405 of the Clean Air Act; and</P>
              <P>(iii) Is located at a different site than the existing unit.</P>

              <P>(k) The installation, operation, cessation, or removal of a temporary clean coal technology demonstration project is exempt from the requirements of this section. A <E T="03">temporary clean coal control technology demonstration project,</E> for the purposes of this section is a clean coal technology demonstration project that is operated for a period of 5 years or less, and which complies with the State implementation plan for the State in which the project is located and other requirements necessary to attain and maintain the national ambient air quality standards during the project and after it is terminated.</P>
              <P>(l) The reactivation of a very clean coal-fired electric utility steam generating unit is exempt from the requirements of this section.</P>
              <CITA>[40 FR 58419, Dec. 16, 1975, as amended at 43 FR 34347, Aug. 3, 1978; 45 FR 5617, Jan. 23, 1980; 57 FR 32339, July 21, 1992; 65 FR 61750, Oct. 17, 2000]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.15</SECTNO>
              <SUBJECT>Reconstruction.</SUBJECT>
              <P>(a) An existing facility, upon reconstruction, becomes an affected facility, irrespective of any change in emission rate.</P>
              <P>(b) “Reconstruction” means the replacement of components of an existing facility to such an extent that:</P>
              <P>(1) The fixed capital cost of the new components exceeds 50 percent of the fixed capital cost that would be required to construct a comparable entirely new facility, and</P>
              <P>(2) It is technologically and economically feasible to meet the applicable standards set forth in this part.</P>
              <P>(c) “Fixed capital cost” means the capital needed to provide all the depreciable components.</P>
              <P>(d) If an owner or operator of an existing facility proposes to replace components, and the fixed capital cost of the new components exceeds 50 percent of the fixed capital cost that would be required to construct a comparable entirely new facility, he shall notify the Administrator of the proposed replacements. The notice must be postmarked 60 days (or as soon as practicable) before construction of the replacements is commenced and must include the following information:</P>
              <P>(1) Name and address of the owner or operator.<PRTPAGE P="72"/>
              </P>
              <P>(2) The location of the existing facility.</P>
              <P>(3) A brief description of the existing facility and the components which are to be replaced.</P>
              <P>(4) A description of the existing air pollution control equipment and the proposed air pollution control equipment.</P>
              <P>(5) An estimate of the fixed capital cost of the replacements and of constructing a comparable entirely new facility.</P>
              <P>(6) The estimated life of the existing facility after the replacements.</P>
              <P>(7) A discussion of any economic or technical limitations the facility may have in complying with the applicable standards of performance after the proposed replacements.</P>
              <P>(e) The Administrator will determine, within 30 days of the receipt of the notice required by paragraph (d) of this section and any additional information he may reasonably require, whether the proposed replacement constitutes reconstruction.</P>
              <P>(f) The Administrator's determination under paragraph (e) shall be based on:</P>
              <P>(1) The fixed capital cost of the replacements in comparison to the fixed capital cost that would be required to construct a comparable entirely new facility;</P>
              <P>(2) The estimated life of the facility after the replacements compared to the life of a comparable entirely new facility;</P>
              <P>(3) The extent to which the components being replaced cause or contribute to the emissions from the facility; and</P>
              <P>(4) Any economic or technical limitations on compliance with applicable standards of performance which are inherent in the proposed replacements.</P>
              <P>(g) Individual subparts of this part may include specific provisions which refine and delimit the concept of reconstruction set forth in this section.</P>
              <CITA>[40 FR 58420, Dec. 16, 1975]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.16</SECTNO>
              <SUBJECT>Priority list.</SUBJECT>
              <GPOTABLE CDEF="xls10,r100" COLS="2" OPTS="L2">
                <TTITLE>Prioritized Major Source Categories</TTITLE>
                <BOXHD>
                  <CHED H="1">
                    <E T="03">Priority Number</E>
                    <SU>1</SU>
                  </CHED>
                  <CHED H="1">
                    <E T="03">Source Category</E>
                  </CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">1.</ENT>
                  <ENT>Synthetic Organic Chemical Manufacturing Industry (SOCMI) and Volatile Organic Liquid Storage Vessels and Handling Equipment</ENT>
                </ROW>
                <ROW>
                  <ENT I="22"/>
                  <ENT>(a) SOCMI unit processes</ENT>
                </ROW>
                <ROW>
                  <ENT I="22"/>
                  <ENT>(b) Volatile organic liquid (VOL) storage vessels and handling equipment</ENT>
                </ROW>
                <ROW>
                  <ENT I="22"/>
                  <ENT>(c) SOCMI fugitive sources</ENT>
                </ROW>
                <ROW>
                  <ENT I="22"/>
                  <ENT>(d) SOCMI secondary sources</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">2.</ENT>
                  <ENT>Industrial Surface Coating: Cans</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">3.</ENT>
                  <ENT>Petroleum Refineries: Fugitive Sources</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">4.</ENT>
                  <ENT>Industrial Surface Coating: Paper</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">5.</ENT>
                  <ENT>Dry Cleaning</ENT>
                </ROW>
                <ROW>
                  <ENT I="22"/>
                  <ENT>(a) Perchloroethylene</ENT>
                </ROW>
                <ROW>
                  <ENT I="22"/>
                  <ENT>(b) Petroleum solvent</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">6.</ENT>
                  <ENT>Graphic Arts</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">7.</ENT>
                  <ENT>Polymers and Resins: Acrylic Resins</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">8.</ENT>
                  <ENT>Mineral Wool (Deleted)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">9.</ENT>
                  <ENT>Stationary Internal Combustion Engines</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">10.</ENT>
                  <ENT>Industrial Surface Coating: Fabric</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">11.</ENT>
                  <ENT>Industrial-Commercial-Institutional Steam Generating Units.</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">12.</ENT>
                  <ENT>Incineration: Non-Municipal (Deleted)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">13.</ENT>
                  <ENT>Non-Metallic Mineral Processing</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">14.</ENT>
                  <ENT>Metallic Mineral Processing</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">15.</ENT>
                  <ENT>Secondary Copper (Deleted)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">16.</ENT>
                  <ENT>Phosphate Rock Preparation</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">17.</ENT>
                  <ENT>Foundries: Steel and Gray Iron</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">18.</ENT>
                  <ENT>Polymers and Resins: Polyethylene</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">19.</ENT>
                  <ENT>Charcoal Production</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">20.</ENT>
                  <ENT>Synthetic Rubber</ENT>
                </ROW>
                <ROW>
                  <ENT I="22"/>
                  <ENT>(a) Tire manufacture</ENT>
                </ROW>
                <ROW>
                  <ENT I="22"/>
                  <ENT>(b) SBR production</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">21.</ENT>
                  <ENT>Vegetable Oil</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">22.</ENT>
                  <ENT>Industrial Surface Coating: Metal Coil</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">23.</ENT>
                  <ENT>Petroleum Transportation and Marketing</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">24.</ENT>
                  <ENT>By-Product Coke Ovens</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">25.</ENT>
                  <ENT>Synthetic Fibers</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">26.</ENT>
                  <ENT>Plywood Manufacture</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">27.</ENT>
                  <ENT>Industrial Surface Coating: Automobiles</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">28.</ENT>
                  <ENT>Industrial Surface Coating: Large Appliances</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">29.</ENT>
                  <ENT>Crude Oil and Natural Gas Production</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">30.</ENT>
                  <ENT>Secondary Aluminum</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">31.</ENT>
                  <ENT>Potash (Deleted)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">32.</ENT>
                  <ENT>Lightweight Aggregate Industry: Clay, Shale, and Slate <SU>2</SU>
                  </ENT>
                </ROW>
                <ROW>
                  <ENT I="01">33.</ENT>
                  <ENT>Glass</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">34.</ENT>
                  <ENT>Gypsum</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">35.</ENT>
                  <ENT>Sodium Carbonate</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">36.</ENT>
                  <ENT>Secondary Zinc (Deleted)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">37.</ENT>
                  <ENT>Polymers and Resins: Phenolic</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">38.</ENT>
                  <ENT>Polymers and Resins: Urea-Melamine</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">39.</ENT>
                  <ENT>Ammonia (Deleted)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">40.</ENT>
                  <ENT>Polymers and Resins: Polystyrene</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">41.</ENT>
                  <ENT>Polymers and Resins: ABS-SAN Resins</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">42.</ENT>
                  <ENT>Fiberglass</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">43.</ENT>
                  <ENT>Polymers and Resins: Polypropylene</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">44.</ENT>
                  <ENT>Textile Processing</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">45.</ENT>
                  <ENT>Asphalt Processing and Asphalt Roofing Manufacture</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">46.</ENT>
                  <ENT>Brick and Related Clay Products</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">47.</ENT>
                  <ENT>Ceramic Clay Manufacturing (Deleted)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">48.</ENT>
                  <ENT>Ammonium Nitrate Fertilizer</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">49.</ENT>
                  <ENT>Castable Refractories (Deleted)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">50.</ENT>
                  <ENT>Borax and Boric Acid (Deleted)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">51.</ENT>
                  <ENT>Polymers and Resins: Polyester Resins</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">52.</ENT>
                  <ENT>Ammonium Sulfate</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">53.</ENT>
                  <ENT>Starch</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">54.</ENT>
                  <ENT>Perlite</ENT>
                </ROW>
                <ROW>
                  <PRTPAGE P="73"/>
                  <ENT I="01">55.</ENT>
                  <ENT>Phosphoric Acid: Thermal Process (Deleted)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">56.</ENT>
                  <ENT>Uranium Refining</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">57.</ENT>
                  <ENT>Animal Feed Defluorination (Deleted)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">58.</ENT>
                  <ENT>Urea (for fertilizer and polymers)</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">59.</ENT>
                  <ENT>Detergent (Deleted)
                  </ENT>
                </ROW>
                <ROW EXPSTB="01">
                  <ENT I="21">
                    <E T="03">Other Source Categories</E>
                    
                  </ENT>
                </ROW>
                <ROW>
                  <ENT I="22">Lead acid battery manufacture <SU>3</SU>
                  </ENT>
                </ROW>
                <ROW>
                  <ENT I="22">Organic solvent cleaning <SU>3</SU>
                  </ENT>
                </ROW>
                <ROW>
                  <ENT I="22">Industrial surface coating: metal furniture <SU>3</SU>
                  </ENT>
                </ROW>
                <ROW>
                  <ENT I="22">Stationary gas turbines <SU>4</SU>
                  </ENT>
                </ROW>
                <ROW>
                  <ENT I="22">Municipal solid waste landfills <SU>4</SU>
                  </ENT>
                </ROW>
                <TNOTE>
                  <SU>1</SU> Low numbers have highest priority, e.g., No. 1 is high priority, No. 59 is low priority.</TNOTE>
                <TNOTE>
                  <SU>2</SU> Formerly titled “Sintering: Clay and Fly Ash”.</TNOTE>
                <TNOTE>
                  <SU>3</SU> Minor source category, but included on list since an NSPS is being developed for that source category.</TNOTE>
                <TNOTE>
                  <SU>4</SU> Not prioritized, since an NSPS for this major source category has already been promulgated.</TNOTE>
              </GPOTABLE>
              <CITA>[47 FR 951, Jan. 8, 1982, as amended at 47 FR 31876, July 23, 1982; 51 FR 42796, Nov. 25, 1986; 52 FR 11428, Apr. 8, 1987; 61 FR 9919, Mar. 12, 1996]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.17</SECTNO>
              <SUBJECT>Incorporations by reference.</SUBJECT>

              <P>The materials listed below are incorporated by reference in the corresponding sections noted. These incorporations by reference were approved by the Director of the Federal Register on the date listed. These materials are incorporated as they exist on the date of the approval, and a notice of any change in these materials will be published in the <E T="04">Federal Register.</E> The materials are available for purchase at the corresponding address noted below, and all are available for inspection at the Library (MD-35), U.S. EPA, Research Triangle Park, NC or at the National Archives and Records Administration (NARA). For information on the availability of this material at NARA, call 202-741-6030, or go to: <E T="03">http://www.archives.gov/federal_register/code_of_federal_regulations/ibr_locations.html.</E>
              </P>
              <P>(a) The following materials are available for purchase from at least one of the following addresses: American Society for Testing and Materials (ASTM), 1916 Race Street, Philadelphia, PA 19103; or University Microfilms International, 300 North Zeeb Road, Ann Arbor, MI 48106.</P>
              <P>(1) ASTM A99-76, 82 (Reapproved 1987), Standard Specification for Ferromanganese, incorporation by reference (IBR) approved January 27, 1983 for § 60.261.</P>
              <P>(2) ASTM A100-69, 74, 93, Standard Specification for Ferrosilicon, IBR approved January 27, 1983 for § 60.261.</P>
              <P>(3) ASTM A101-73, 93, Standard Specification for Ferrochromium, IBR approved January 27, 1983 for § 60.261.</P>
              <P>(4) ASTM A482-76, 93, Standard Specification for Ferrochromesilicon, IBR approved January 27, 1983 for § 60.261.</P>
              <P>(5) ASTM A483-64, 74 (Reapproved 1988), Standard Specification for Silicomanganese, IBR approved January 27, 1983 for § 60.261.</P>
              <P>(6) ASTM A495-76, 94, Standard Specification for Calcium-Silicon and Calcium Manganese-Silicon, IBR approved January 27, 1983 for § 60.261.</P>
              <P>(7) ASTM D86-78, 82, 90, 93, 95, 96, Distillation of Petroleum Products, IBR approved for §§ 60.562-2(d), 60.593(d), and 60.633(h).</P>
              <P>(8) ASTM D129-64, 78, 95, Standard Test Method for Sulfur in Petroleum Products (General Bomb Method), IBR approved for Appendix A: Method 19, Section 12.5.2.2.3; and § 60.106(j)(2).</P>
              <P>(9) ASTM D240-76, 92, Standard Test Method for Heat of Combustion of Liquid Hydrocarbon Fuels by Bomb Calorimeter, IBR approved January 27, 1983 for §§ 60.46(c), 60.296(b), and Appendix A: Method 19, Section 12.5.2.2.3.</P>
              <P>(10) ASTM D270-65, 75, Standard Method of Sampling Petroleum and Petroleum Products, IBR approved January 27, 1983 for Appendix A: Method 19, Section 12.5.2.2.1.</P>
              <P>(11) ASTM D323-82, 94, Test Method for Vapor Pressure of Petroleum Products (Reid Method), IBR approved April 8, 1987 for §§ 60.111(l), 60.111a(g), 60.111b(g), and 60.116b(f)(2)(ii).</P>
              <P>(12) ASTM D388-77, 90, 91, 95, 98a, Standard Specification for Classification of Coals by Rank, IBR approved for §§ 60.41(f), 60.45(f)(4)(i), 60.45(f)(4)(ii), 60.45(f)(4)(vi), 60.41a, 60.41b, and 60.251(b) and (c).</P>
              <P>(13) ASTM D396-78, 89, 90, 92, 96, 98, Standard Specification for Fuel Oils, IBR approved for §§ 60.41b, 60.41c, 60.111(b), and 60.111a(b).</P>

              <P>(14) ASTM D975-78, 96, 98a, Standard Specification for Diesel Fuel Oils, IBR approved January 27, 1983 for §§ 60.111(b) and 60.111a(b).<PRTPAGE P="74"/>
              </P>
              <P>(15) ASTM D1072-80, 90 (Reapproved 1994), Standard Method for Total Sulfur in Fuel Gases, IBR approved July 31, 1984 for § 60.335(d).</P>
              <P>(16) ASTM D1137-53, 75, Standard Method for Analysis of Natural Gases and Related Types of Gaseous Mixtures by the Mass Spectrometer, IBR approved January 27, 1983 for § 60.45(f)(5)(i).</P>
              <P>(17) ASTM D1193-77, 91, Standard Specification for Reagent Water, IBR approved for Appendix A: Method 5, Section 7.1.3; Method 5E, Section 7.2.1; Method 5F, Section 7.2.1; Method 6, Section 7.1.1; Method 7, Section 7.1.1; Method 7C, Section 7.1.1; Method 7D, Section 7.1.1; Method 10A, Section 7.1.1; Method 11, Section 7.1.3; Method 12, Section 7.1.3; Method 13A, Section 7.1.2; Method 26, Section 7.1.2; Method 26A, Section 7.1.2; and Method 29, Section 7.2.2.</P>
              <P>(18) ASTM D1266-87, 91, 98, Standard Test Method for Sulfur in Petroleum Products (Lamp Method), IBR approved August 17, 1989 for § 60.106(j)(2).</P>
              <P>(19) ASTM D1475-60 (Reapproved 1980), 90, Standard Test Method for Density of Paint, Varnish Lacquer, and Related Products, IBR approved January 27, 1983 for § 60.435(d)(1), Appendix A: Method 24, Section 6.1; and Method 24A, Sections 6.5 and 7.1.</P>
              <P>(20) ASTM D1552-83, 95, Standard Test Method for Sulfur in Petroleum Products (High Temperature Method), IBR approved for Appendix A: Method 19, Section 12.5.2.2.3; and § 60.106(j)(2).</P>
              <P>(21) ASTM D1826-77, 94, Standard Test Method for Calorific Value of Gases in Natural Gas Range by Continuous Recording Calorimeter, IBR approved January 27, 1983 for §§ 60.45(f)(5)(ii), 60.46(c)(2), 60.296(b)(3), and Appendix A: Method 19, Section 12.3.2.4.</P>
              <P>(22) ASTM D1835-87, 91, 97, Standard Specification for Liquefied Petroleum (LP) Gases, approved for §§ 60.41b and 60.41c.</P>
              <P>(23) ASTM D1945-64, 76, 91, 96, Standard Method for Analysis of Natural Gas by Gas Chromatography, IBR approved January 27, 1983 for § 60.45(f)(5)(i).</P>
              <P>(24) ASTM D1946-77, 90 (Reapproved 1994), Standard Method for Analysis of Reformed Gas by Gas Chromatography, IBR approved for §§ 60.45(f)(5)(i), 60.18(f)(3), 60.614(e)(2)(ii), 60.614(e)(4), 60.664(e)(2)(ii), 60.664(e)(4), 60.564(f)(1), 60.704(d)(2)(ii), and 60.704(d)(4).</P>
              <P>(25) ASTM D2013-72, 86, Standard Method of Preparing Coal Samples for Analysis, IBR approved January 27, 1983, for Appendix A: Method 19, Section 12.5.2.1.3.</P>
              <P>(26) ASTM D2015-77 (Reapproved 1978), 96, Standard Test Method for Gross Calorific Value of Solid Fuel by the Adiabatic Bomb Calorimeter, IBR approved January 27, 1983 for § 60.45(f)(5)(ii), 60.46(c)(2), and Appendix A: Method 19, Section 12.5.2.1.3.</P>
              <P>(27) ASTM D2016-74, 83, Standard Test Methods for Moisture Content of Wood, IBR approved for Appendix A: Method 28, Section 16.1.1.</P>
              <P>(28) ASTM D2234-76, 96, 97b, 98, Standard Methods for Collection of a Gross Sample of Coal, IBR approved January 27, 1983 for Appendix A: Method 19, Section 12.5.2.1.1.</P>
              <P>(29) ASTM D2369-81, 87, 90, 92, 93, 95, Standard Test Method for Volatile Content of Coatings, IBR approved January 27, 1983 for Appendix A: Method 24, Section 6.2.</P>
              <P>(30) ASTM D2382-76, 88, Heat of Combustion of Hydrocarbon Fuels by Bomb Calorimeter (High-Precision Method), IBR approved for §§ 60.18(f)(3), 60.485(g)(6), 60.614(e)(4), 60.664(e)(4), 60.564(f)(3), and 60.704(d)(4).</P>

              <P>(31) ASTM D2504-67, 77, 88 (Reapproved 1993), Noncondensable Gases in C<E T="52">3</E> and Lighter Hydrocarbon Products by Gas Chromatography, IBR approved for § 60.485(g)(5).</P>
              <P>(32) ASTM D2584-68 (Reapproved 1985), 94, Standard Test Method for Ignition Loss of Cured Reinforced Resins, IBR approved February 25, 1985 for § 60.685(c)(3)(i).</P>
              <P>(33) ASTM D2622-87, 94, 98, Standard Test Method for Sulfur in Petroleum Products by X-Ray Spectrometry, IBR approved August 17, 1989 for § 60.106(j)(2).</P>
              <P>(34) ASTM D2879-83, 96, 97, Test Method for Vapor Pressure-Temperature Relationship and Initial Decomposition Temperature of Liquids by Isoteniscope, IBR approved April 8, 1987 for §§ 60.485(e)(1), 60.111b(f)(3), 60.116b(e)(3)(ii), and 60.116b(f)(2)(i).</P>

              <P>(35) ASTM D2880-78, 96, Standard Specification for Gas Turbine Fuel <PRTPAGE P="75"/>Oils, IBR approved January 27, 1983 for §§ 60.111(b), 60.111a(b), and 60.335(d).</P>
              <P>(36) ASTM D2908-74, 91, Standard Practice for Measuring Volatile Organic Matter in Water by Aqueous-Injection Gas Chromatography, IBR approved for § 60.564(j).</P>
              <P>(37) ASTM D2986-71, 78, 95a, Standard Method for Evaluation of Air, Assay Media by the Monodisperse DOP (Dioctyl Phthalate) Smoke Test, IBR approved January 27, 1983 for Appendix A: Method 5, Section 7.1.1; Method 12, Section 7.1.1; and Method 13A, Section 7.1.1.2.</P>
              <P>(38) ASTM D3031-81, Standard Test Method for Total Sulfur in Natural Gas by Hydrogenation, IBR approved July 31, 1984 for § 60.335(d).</P>
              <P>(39) ASTM D3173-73, 87, Standard Test Method for Moisture in the Analysis Sample of Coal and Coke, IBR approved January 27, 1983 for Appendix A: Method 19, Section 12.5.2.1.3.</P>
              <P>(40) ASTM D3176-74, 89, Standard Method for Ultimate Analysis of Coal and Coke, IBR approved January 27, 1983 for § 60.45(f)(5)(i) and Appendix A: Method 19, Section 12.3.2.3.</P>
              <P>(41) ASTM D3177-75, 89, Standard Test Method for Total Sulfur in the Analysis Sample of Coal and Coke, IBR approved January 27, 1983 for Appendix A: Method 19, Section 12.5.2.1.3.</P>
              <P>(42) ASTM D3178-73 (Reapproved 1979), 89, Standard Test Methods for Carbon and Hydrogen in the Analysis Sample of Coal and Coke, IBR approved January 27, 1983 for § 60.45(f)(5)(i).</P>
              <P>(43) ASTM D3246-81, 92, 96, Standard Method for Sulfur in Petroleum Gas by Oxidative Microcoulometry, IBR approved July 31, 1984 for § 60.335(d).</P>
              <P>(44) ASTM D3270-73T, 80, 91, 95, Standard Test Methods for Analysis for Fluoride Content of the Atmosphere and Plant Tissues (Semiautomated Method), IBR approved for Appendix A: Method 13A, Section 16.1.</P>
              <P>(45) ASTM D3286-85, 96, Standard Test Method for Gross Calorific Value of Coal and Coke by the Isoperibol Bomb Calorimeter, IBR approved for Appendix A: Method 19, Section 12.5.2.1.3.</P>
              <P>(46) ASTM D3370-76, 95a, Standard Practices for Sampling Water, IBR approved for § 60.564(j).</P>
              <P>(47) ASTM D3792-79, 91, Standard Test Method for Water Content of Water-Reducible Paints by Direct Injection into a Gas Chromatograph, IBR approved January 27, 1983 for Appendix A: Method 24, Section 6.3.</P>
              <P>(48) ASTM D4017-81, 90, 96a, Standard Test Method for Water in Paints and Paint Materials by the Karl Fischer Titration Method, IBR approved January 27, 1983 for Appendix A: Method 24, Section 6.4.</P>
              <P>(49) ASTM D4057-81, 95, Standard Practice for Manual Sampling of Petroleum and Petroleum Products, IBR approved for Appendix A: Method 19, Section 12.5.2.2.3.</P>
              <P>(50) ASTM D4084-82, 94, Standard Method for Analysis of Hydrogen Sulfide in Gaseous Fuels (Lead Acetate Reaction Rate Method), IBR approved July 31, 1984 for § 60.335(d).</P>
              <P>(51) ASTM D4177-95, Standard Practice for Automatic Sampling of Petroleum and Petroleum Products, IBR approved for Appendix A: Method 19, 12.5.2.2.1.</P>
              <P>(52) ASTM D4239-85, 94, 97, Standard Test Methods for Sulfur in the Analysis Sample of Coal and Coke Using High Temperature Tube Furnace Combustion Methods, IBR approved for Appendix A: Method 19, Section 12.5.2.1.3.</P>
              <P>(53) ASTM D4442-84, 92, Standard Test Methods for Direct Moisture Content Measurement in Wood and Wood-base Materials, IBR approved for Appendix A: Method 28, Section 16.1.1.</P>
              <P>(54) ASTM D4444-92, Standard Test Methods for Use and Calibration of Hand-Held Moisture Meters, IBR approved for Appendix A: Method 28, Section 16.1.1.</P>
              <P>(55) ASTM D4457-85 (Reapproved 1991), Test Method for Determination of Dichloromethane and 1, 1, 1-Trichloroethane in Paints and Coatings by Direct Injection into a Gas Chromatograph, IBR approved for Appendix A: Method 24, Section 6.5.</P>
              <P>(56) ASTM D4809-95, Standard Test Method for Heat of Combustion of Liquid Hydrocarbon Fuels by Bomb Calorimeter (Precision Method), IBR approved for §§ 60.18(f)(3), 60.485(g)(6), 60.564(f)(3), 60.614(d)(4), 60.664(e)(4), and 60.704(d)(4).</P>

              <P>(57) ASTM D5403-93, Standard Test Methods for Volatile Content of Radiation Curable Materials. IBR approved <PRTPAGE P="76"/>September 11, 1995 for Appendix A: Method 24, Section 6.6.</P>
              <P>(58) ASTM D5865-98, Standard Test Method for Gross Calorific Value of Coal and Coke. IBR approved for § 60.45(f)(5)(ii), 60.46(c)(2), and Appendix A: Method 19, Section 12.5.2.1.3.</P>
              <P>(59) ASTM E168-67, 77, 92, General Techniques of Infrared Quantitative Analysis, IBR approved for §§ 60.593(b)(2) and 60.632(f).</P>
              <P>(60) ASTM E169-63, 77, 93, General Techniques of Ultraviolet Quantitative Analysis, IBR approved for §§ 60.593(b)(2) and 60.632(f).</P>
              <P>(61) ASTM E260-73, 91, 96, General Gas Chromatography Procedures, IBR approved for §§ 60.593(b)(2) and 60.632(f).</P>
              <P>(62)-(63) [Reserved]</P>
              <P>(64) ASTM D 6216-98 Standard Practice for Opacity Monitor Manufacturers to Certify Conformance with Design and Performance Specifications, IBR approved February 6, 2001 for appendix B, PS-1.</P>
              <P>(b) The following material is available for purchase from the Association of Official Analytical Chemists, 1111 North 19th Street, Suite 210, Arlington, VA 22209.</P>
              <P>(1) AOAC Method 9, Official Methods of Analysis of the Association of Official Analytical Chemists, 11th edition, 1970, pp. 11-12, IBR approved January 27, 1983 for §§ 60.204(b)(3), 60.214(b)(3), 60.224(b)(3), 60.234(b)(3).</P>
              <P>(c) The following material is available for purchase from the American Petroleum Institute, 1220 L Street NW., Washington, DC 20005.</P>
              <P>(1) API Publication 2517, Evaporation Loss from External Floating Roof Tanks, Second Edition, February 1980, IBR approved January 27, 1983, for §§ 60.111(i), 60.111a(f), 60.111a(f)(1) and 60.116b(e)(2)(i).</P>
              <P>(d) The following material is available for purchase from the Technical Association of the Pulp and Paper Industry (TAPPI), Dunwoody Park, Atlanta, GA 30341.</P>
              <P>(1) TAPPI Method T624 os-68, IBR approved January 27, 1983 for § 60.285(d)(3).</P>
              <P>(e) The following material is available for purchase from the Water Pollution Control Federation (WPCF), 2626 Pennsylvania Avenue NW., Washington, DC 20037.</P>
              <P>(1) Method 209A, Total Residue Dried at 103-105 °C, in Standard Methods for the Examination of Water and Wastewater, 15th Edition, 1980, IBR approved February 25, 1985 for § 60.683(b).</P>
              <P>(f) The following material is available for purchase from the following address: Underwriter's Laboratories, Inc. (UL), 333 Pfingsten Road, Northbrook, IL 60062.</P>
              <P>(1) UL 103, Sixth Edition revised as of September 3, 1986, Standard for Chimneys, Factory-built, Residential Type and Building Heating Appliance.</P>
              <P>(g) The following material is available for purchase from the following address: West Coast Lumber Inspection Bureau, 6980 SW. Barnes Road, Portland, OR 97223.</P>
              <P>(1) West Coast Lumber Standard Grading Rules No. 16, pages 5-21 and 90 and 91, September 3, 1970, revised 1984.</P>
              <P>(h) The following material is available for purchase from the American Society of Mechanical Engineers (ASME), 345 East 47th Street, New York, NY 10017.</P>
              <P>(1) ASME QRO-1-1994, Standard for the Qualification and Certification of Resource Recovery Facility Operators, IBR approved for §§ 60.56a, 60.54b(a), 60.54b(b), 60.1185(a), 60.1185(c)(2), 60.1675(a), and 60.1675(c)(2).</P>
              <P>(2) ASME PTC 4.1-1964 (Reaffirmed 1991), Power Test Codes: Test Code for Steam Generating Units (with 1968 and 1969 Addenda), IBR approved for §§ 60.46b, 60.58a(h)(6)(ii), 60.58b(i)(6)(ii), 60.1320(a)(3) and 60.1810(a)(3).</P>
              <P>(3) ASME Interim Supplement 19.5 on Instruments and Apparatus: Application, Part II of Fluid Meters, 6th Edition (1971), IBR approved for §§ 60.58a(h)(6)(ii), 60.58b(i)(6)(ii), 60.1320(a)4), and 60.1810(a)(4).</P>

              <P>(i) Test Methods for Evaluating Solid Waste, Physical/Chemical Methods,” EPA Publication SW-846 Third Edition (November 1986), as amended by Updates I (July 1992), II (September 1994), IIA (August, 1993), IIB (January 1995), and III (December 1996). This document may be obtained from the U.S. EPA, Office of Solid Waste and Emergency Response, Waste Characterization Branch, Washington, DC 20460, and is incorporated by reference for appendix A to part 60, Method 29, Sections 7.5.34; <PRTPAGE P="77"/>9.2.1; 9.2.3; 10.2; 10.3; 11.1.1; 11.1.3; 13.2.1; 13.2.2; 13.3.1; and Table 29-3.</P>
              <P>(j) “Standard Methods for the Examination of Water and Wastewater,” 16th edition, 1985. Method 303F: “Determination of Mercury by the Cold Vapor Technique.” This document may be obtained from the American Public Health Association, 1015 18th Street, NW., Washington, DC 20036, and is incorporated by reference for appendix A to part 60, Method 29, Sections 9.2.3; 10.3; and 11.1.3.</P>
              <P>(k) This material is available for purchase from the American Hospital Association (AHA) Service, Inc., Post Office Box 92683, Chicago, Illinois 60675-2683. You may inspect a copy at EPA's Air and Radiation Docket and Information Center (Docket A-91-61, Item IV-J-124), Room M-1500, 1200 Pennsylvania Ave., NW., Washington, DC.</P>
              <P>(1) An Ounce of Prevention: Waste Reduction Strategies for Health Care Facilities. American Society for Health Care Environmental Services of the American Hospital Association. Chicago, Illinois. 1993. AHA Catalog No. 057007. ISBN 0-87258-673-5. IBR approved for § 60.35e and § 60.55c.</P>
              <P>(l) This material is available for purchase from the National Technical Information Services, 5285 Port Royal Road, Springfield, Virginia 22161. You may inspect a copy at EPA's Air and Radiation Docket and Information Center (Docket A-91-61, Item IV-J-125), Room M-1500, 1200 Pennsylvania Ave., NW., Washington, DC.</P>
              <P>(1) OMB Bulletin No. 93-17: Revised Statistical Definitions for Metropolitan Areas. Office of Management and Budget, June 30, 1993. NTIS No. PB 93-192-664. IBR approved for § 60.31e.</P>
              <CITA>[48 FR 3735, Jan. 27, 1983]</CITA>
              <EDNOTE>
                <HD SOURCE="HED">Editorial Note:</HD>
                <P>For <E T="04">Federal Register</E> citations affecting § 60.17, see the List of CFR Sections Affected, which appears in the Finding Aids section of the printed volume and on GPO Access.</P>
              </EDNOTE>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.18</SECTNO>
              <SUBJECT>General control device requirements.</SUBJECT>
              <P>(a) <E T="03">Introduction.</E> This section contains requirements for control devices used to comply with applicable subparts of parts 60 and 61. The requirements are placed here for administrative convenience and only apply to facilities covered by subparts referring to this section.</P>
              <P>(b) <E T="03">Flares.</E> Paragraphs (c) through (f) apply to flares.</P>
              <P>(c)(1) Flares shall be designed for and operated with no visible emissions as determined by the methods specified in paragraph (f), except for periods not to exceed a total of 5 minutes during any 2 consecutive hours.</P>
              <P>(2) Flares shall be operated with a flame present at all times, as determined by the methods specified in paragraph (f).</P>
              <P>(3) An owner/operator has the choice of adhering to either the heat content specifications in paragraph (c)(3)(ii) of this section and the maximum tip velocity specifications in paragraph (c)(4) of this section, or adhering to the requirements in paragraph (c)(3)(i) of this section.</P>

              <P>(i)(A) Flares shall be used that have a diameter of 3 inches or greater, are nonassisted, have a hydrogen content of 8.0 percent (by volume), or greater, and are designed for and operated with an exit velocity less than 37.2 m/sec (122 ft/sec) and less than the velocity, V<E T="52">max</E>, as determined by the following equation:
              </P>
              <FP SOURCE="FP-1">V<E T="52">max</E>=(X<E T="52">H2</E>−K<E T="52">1</E>)* K<E T="52">2</E>
              </FP>
              
              <EXTRACT>
                <FP>Where:</FP>
                <FP SOURCE="FP-1">V<E T="52">max</E>=Maximum permitted velocity, m/sec.</FP>
                <FP SOURCE="FP-1">K<E T="52">1</E>=Constant, 6.0 volume-percent hydrogen.</FP>
                <FP SOURCE="FP-1">K<E T="52">2</E>=Constant, 3.9(m/sec)/volume-percent hydrogen.</FP>
                <FP SOURCE="FP-1">X<E T="52">H2</E>=The volume-percent of hydrogen, on a wet basis, as calculated by using the American Society for Testing and Materials (ASTM) Method D1946-77. (Incorporated by reference as specified in § 60.17).</FP>
              </EXTRACT>
              
              <P>(B) The actual exit velocity of a flare shall be determined by the method specified in paragraph (f)(4) of this section.</P>

              <P>(ii) Flares shall be used only with the net heating value of the gas being combusted being 11.2 MJ/scm (300 Btu/scf) or greater if the flare is steam-assisted or air-assisted; or with the net heating value of the gas being combusted being 7.45 MJ/scm (200 Btu/scf) or greater if the flare is nonassisted. The net heating value of the gas being combusted shall be determined by the methods specified in paragraph (f)(3) of this section.<PRTPAGE P="78"/>
              </P>
              <P>(4)(i) Steam-assisted and nonassisted flares shall be designed for and operated with an exit velocity, as determined by the methods specified in paragraph (f)(4) of this section, less than 18.3 m/sec (60 ft/sec), except as provided in paragraphs (c)(4) (ii) and (iii) of this section.</P>
              <P>(ii) Steam-assisted and nonassisted flares designed for and operated with an exit velocity, as determined by the methods specified in paragraph (f)(4), equal to or greater than 18.3 m/sec (60 ft/sec) but less than 122 m/sec (400 ft/sec) are allowed if the net heating value of the gas being combusted is greater than 37.3 MJ/scm (1,000 Btu/scf).</P>

              <P>(iii) Steam-assisted and nonassisted flares designed for and operated with an exit velocity, as determined by the methods specified in paragraph (f)(4), less than the velocity, V<E T="52">max</E>, as determined by the method specified in paragraph (f)(5), and less than 122 m/sec (400 ft/sec) are allowed.</P>

              <P>(5) Air-assisted flares shall be designed and operated with an exit velocity less than the velocity, V<E T="52">max</E>, as determined by the method specified in paragraph (f)(6).</P>
              <P>(6) Flares used to comply with this section shall be steam-assisted, air-assisted, or nonassisted.</P>
              <P>(d) Owners or operators of flares used to comply with the provisions of this subpart shall monitor these control devices to ensure that they are operated and maintained in conformance with their designs. Applicable subparts will provide provisions stating how owners or operators of flares shall monitor these control devices.</P>
              <P>(e) Flares used to comply with provisions of this subpart shall be operated at all times when emissions may be vented to them.</P>
              <P>(f)(1) Method 22 of appendix A to this part shall be used to determine the compliance of flares with the visible emission provisions of this subpart. The observation period is 2 hours and shall be used according to Method 22.</P>
              <P>(2) The presence of a flare pilot flame shall be monitored using a thermocouple or any other equivalent device to detect the presence of a flame.</P>
              <P>(3) The net heating value of the gas being combusted in a flare shall be calculated using the following equation:</P>
              <GPH DEEP="31" SPAN="1">
                <GID>EC01JN92.008</GID>
              </GPH>
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">H<E T="52">T</E>=Net heating value of the sample, MJ/scm; where the net enthalpy per mole of offgas is based on combustion at 25 °C and 760 mm Hg, but the standard temperature for determining the volume corresponding to one mole is 20 °C;</FP>
                <GPH DEEP="58" SPAN="2">
                  <GID>EC01JN92.009</GID>
                </GPH>
                <FP SOURCE="FP-1">C<E T="52">i</E>=Concentration of sample component i in ppm on a wet basis, as measured for organics by Reference Method 18 and measured for hydrogen and carbon monoxide by ASTM D1946-77 or 90 (Reapproved 1994) (Incorporated by reference as specified in § 60.17); and</FP>
                <FP SOURCE="FP-1">H<E T="52">i</E>=Net heat of combustion of sample component i, kcal/g mole at 25 °C and 760 mm Hg. The heats of combustion may be determined using ASTM D2382-76 or 88 or D4809-95 (incorporated by reference as specified in § 60.17) if published values are not available or cannot be calculated.</FP>
              </EXTRACT>
              
              <P>(4) The actual exit velocity of a flare shall be determined by dividing the volumetric flowrate (in units of standard temperature and pressure), as determined by Reference Methods 2, 2A, 2C, or 2D as appropriate; by the unobstructed (free) cross sectional area of the flare tip.</P>
              <P>(5) The maximum permitted velocity, V<E T="52">max</E>, for flares complying with paragraph (c)(4)(iii) shall be determined by the following equation.</P>
              <EXTRACT>
                <FP>Log<E T="52">10</E> (V<E T="52">max</E>)=(H<E T="52">T</E>+28.8)/31.7</FP>
                
                <PRTPAGE P="79"/>
                <FP SOURCE="FP-1">V<E T="52">max</E>=Maximum permitted velocity, M/sec</FP>
                <FP SOURCE="FP-1">28.8=Constant</FP>
                <FP SOURCE="FP-1">31.7=Constant</FP>
                <FP SOURCE="FP-1">H<E T="52">T</E>=The net heating value as determined in paragraph (f)(3).</FP>
              </EXTRACT>
              
              <P>(6) The maximum permitted velocity, V<E T="52">max</E>, for air-assisted flares shall be determined by the following equation.</P>
              <EXTRACT>
                <FP>V<E T="52">max</E>=8.706+0.7084 (H<E T="52">T</E>)</FP>
                
                <FP SOURCE="FP-1">V<E T="52">max</E>=Maximum permitted velocity, m/sec</FP>
                <FP SOURCE="FP-1">8.706=Constant</FP>
                <FP SOURCE="FP-1">0.7084=Constant</FP>
                <FP SOURCE="FP-1">H<E T="52">T</E>=The net heating value as determined in paragraph (f)(3).</FP>
              </EXTRACT>
              <CITA>[51 FR 2701, Jan. 21, 1986, as amended at 63 FR 24444, May 4, 1998; 65 FR 61752, Oct. 17, 2000]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.19</SECTNO>
              <SUBJECT>General notification and reporting requirements.</SUBJECT>
              <P>(a) For the purposes of this part, time periods specified in days shall be measured in calendar days, even if the word “calendar” is absent, unless otherwise specified in an applicable requirement.</P>
              <P>(b) For the purposes of this part, if an explicit postmark deadline is not specified in an applicable requirement for the submittal of a notification, application, report, or other written communication to the Administrator, the owner or operator shall postmark the submittal on or before the number of days specified in the applicable requirement. For example, if a notification must be submitted 15 days before a particular event is scheduled to take place, the notification shall be postmarked on or before 15 days preceding the event; likewise, if a notification must be submitted 15 days after a particular event takes place, the notification shall be delivered or postmarked on or before 15 days following the end of the event. The use of reliable non-Government mail carriers that provide indications of verifiable delivery of information required to be submitted to the Administrator, similar to the postmark provided by the U.S. Postal Service, or alternative means of delivery, including the use of electronic media, agreed to by the permitting authority, is acceptable.</P>
              <P>(c) Notwithstanding time periods or postmark deadlines specified in this part for the submittal of information to the Administrator by an owner or operator, or the review of such information by the Administrator, such time periods or deadlines may be changed by mutual agreement between the owner or operator and the Administrator. Procedures governing the implementation of this provision are specified in paragraph (f) of this section.</P>
              <P>(d) If an owner or operator of an affected facility in a State with delegated authority is required to submit periodic reports under this part to the State, and if the State has an established timeline for the submission of periodic reports that is consistent with the reporting frequency(ies) specified for such facility under this part, the owner or operator may change the dates by which periodic reports under this part shall be submitted (without changing the frequency of reporting) to be consistent with the State's schedule by mutual agreement between the owner or operator and the State. The allowance in the previous sentence applies in each State beginning 1 year after the affected facility is required to be in compliance with the applicable subpart in this part. Procedures governing the implementation of this provision are specified in paragraph (f) of this section.</P>
              <P>(e) If an owner or operator supervises one or more stationary sources affected by standards set under this part and standards set under part 61, part 63, or both such parts of this chapter, he/she may arrange by mutual agreement between the owner or operator and the Administrator (or the State with an approved permit program) a common schedule on which periodic reports required by each applicable standard shall be submitted throughout the year. The allowance in the previous sentence applies in each State beginning 1 year after the stationary source is required to be in compliance with the applicable subpart in this part, or 1 year after the stationary source is required to be in compliance with the applicable 40 CFR part 61 or part 63 of this chapter standard, whichever is latest. Procedures governing the implementation of this provision are specified in paragraph (f) of this section.</P>

              <P>(f)(1)(i) Until an adjustment of a time period or postmark deadline has been approved by the Administrator under <PRTPAGE P="80"/>paragraphs (f)(2) and (f)(3) of this section, the owner or operator of an affected facility remains strictly subject to the requirements of this part.</P>
              <P>(ii) An owner or operator shall request the adjustment provided for in paragraphs (f)(2) and (f)(3) of this section each time he or she wishes to change an applicable time period or postmark deadline specified in this part.</P>
              <P>(2) Notwithstanding time periods or postmark deadlines specified in this part for the submittal of information to the Administrator by an owner or operator, or the review of such information by the Administrator, such time periods or deadlines may be changed by mutual agreement between the owner or operator and the Administrator. An owner or operator who wishes to request a change in a time period or postmark deadline for a particular requirement shall request the adjustment in writing as soon as practicable before the subject activity is required to take place. The owner or operator shall include in the request whatever information he or she considers useful to convince the Administrator that an adjustment is warranted.</P>
              <P>(3) If, in the Administrator's judgment, an owner or operator's request for an adjustment to a particular time period or postmark deadline is warranted, the Administrator will approve the adjustment. The Administrator will notify the owner or operator in writing of approval or disapproval of the request for an adjustment within 15 calendar days of receiving sufficient information to evaluate the request.</P>
              <P>(4) If the Administrator is unable to meet a specified deadline, he or she will notify the owner or operator of any significant delay and inform the owner or operator of the amended schedule.</P>
              <CITA>[59 FR 12428, Mar. 16, 1994, as amended at 64 FR 7463, Feb. 12, 1998]</CITA>
            </SECTION>
          </SUBPART>
          <SUBPART>
            <HD SOURCE="HED">Subpart B—Adoption and Submittal of State Plans for Designated Facilities</HD>
            <SOURCE>
              <HD SOURCE="HED">Source:</HD>
              <P>40 FR 53346, Nov. 17, 1975, unless otherwise noted.</P>
            </SOURCE>
            <SECTION>
              <SECTNO>§ 60.20</SECTNO>
              <SUBJECT>Applicability.</SUBJECT>
              <P>The provisions of this subpart apply to States upon publication of a final guideline document under § 60.22(a).</P>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.21</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <P>Terms used but not defined in this subpart shall have the meaning given them in the Act and in subpart A:</P>
              <P>(a) <E T="03">Designated pollutant</E> means any air pollutant, emissions of which are subject to a standard of performance for new stationary sources but for which air quality criteria have not been issued, and which is not included on a list published under section 108(a) or section 112(b)(1)(A) of the Act.</P>
              <P>(b) <E T="03">Designated facility</E> means any existing facility (see § 60.2(aa)) which emits a designated pollutant and which would be subject to a standard of performance for that pollutant if the existing facility were an affected facility (see § 60.2(e)).</P>
              <P>(c) <E T="03">Plan</E> means a plan under section 111(d) of the Act which establishes emission standards for designated pollutants from designated facilities and provides for the implementation and enforcement of such emission standards.</P>
              <P>(d) <E T="03">Applicable plan</E> means the plan, or most recent revision thereof, which has been approved under § 60.27(b) or promulgated under § 60.27(d).</P>
              <P>(e) <E T="03">Emission guideline</E> means a guideline set forth in subpart C of this part, or in a final guideline document published under § 60.22(a), which reflects the degree of emission reduction achievable through the application of the best system of emission reduction which (taking into account the cost of such reduction) the Administrator has determined has been adequately demonstrated for designated facilities.</P>
              <P>(f) <E T="03">Emission standard</E> means a legally enforceable regulation setting forth an allowable rate of emissions into the atmosphere, or prescribing equipment specifications for control of air pollution emissions.</P>
              <P>(g) <E T="03">Compliance schedule</E> means a legally enforceable schedule specifying a date or dates by which a source or category of sources must comply with specific emission standards contained in a plan or with any increments of progress to achieve such compliance.<PRTPAGE P="81"/>
              </P>
              <P>(h) <E T="03">Increments of progress</E> means steps to achieve compliance which must be taken by an owner or operator of a designated facility, including:</P>
              <P>(1) Submittal of a final control plan for the designated facility to the appropriate air pollution control agency;</P>
              <P>(2) Awarding of contracts for emission control systems or for process modifications, or issuance of orders for the purchase of component parts to accomplish emission control or process modification;</P>
              <P>(3) Initiation of on-site construction or installation of emission control equipment or process change;</P>
              <P>(4) Completion of on-site construction or installation of emission control equipment or process change; and</P>
              <P>(5) Final compliance.</P>
              <P>(i) <E T="03">Region</E> means an air quality control region designated under section 107 of the Act and described in part 81 of this chapter.</P>
              <P>(j) <E T="03">Local agency</E> means any local governmental agency.</P>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.22</SECTNO>
              <SUBJECT>Publication of guideline documents, emission guidelines, and final compliance times.</SUBJECT>

              <P>(a) Concurrently upon or after proposal of standards of performance for the control of a designated pollutant from affected facilities, the Administrator will publish a draft guideline document containing information pertinent to control of the designated pollutant form designated facilities. Notice of the availability of the draft guideline document will be published in the <E T="04">Federal Register</E> and public comments on its contents will be invited. After consideration of public comments and upon or after promulgation of standards of performance for control of a designated pollutant from affected facilities, a final guideline document will be published and notice of its availability will be published in the <E T="04">Federal Register.</E>
              </P>
              <P>(b) Guideline documents published under this section will provide information for the development of State plans, such as:</P>
              <P>(1) Information concerning known or suspected endangerment of public health or welfare caused, or contributed to, by the designated pollutant.</P>
              <P>(2) A description of systems of emission reduction which, in the judgment of the Administrator, have been adequately demonstrated.</P>
              <P>(3) Information on the degree of emission reduction which is achievable with each system, together with information on the costs and environmental effects of applying each system to designated facilities.</P>
              <P>(4) Incremental periods of time normally expected to be necessary for the design, installation, and startup of identified control systems.</P>
              <P>(5) An emission guideline that reflects the application of the best system of emission reduction (considering the cost of such reduction) that has been adequately demonstrated for designated facilities, and the time within which compliance with emission standards of equivalent stringency can be achieved. The Administrator will specify different emission guidelines or compliance times or both for different sizes, types, and classes of designated facilities when costs of control, physical limitations, geographical location, or similar factors make sub-cate-gor-i-za-tion appropriate. (6) Such other available information as the Administrator determines may contribute to the formulation of State plans.</P>
              <P>(c) Except as provided in paragraph (d)(1) of this section, the emission guidelines and compliance times referred to in paragraph (b)(5) of this section will be proposed for comment upon publication of the draft guideline document, and after consideration of comments will be promulgated in subpart C of this part with such modifications as may be appropriate.</P>

              <P>(d)(1) If the Administrator determines that a designated pollutant may cause or contribute to endangerment of public welfare, but that adverse effects on public health have not been demonstrated, he will include the determination in the draft guideline document and in the <E T="04">Federal Register</E> notice of its availability. Except as provided in paragraph (d)(2) of this section, paragraph (c) of this section shall be inapplicable in such cases.</P>

              <P>(2) If the Administrator determines at any time on the basis of new information that a prior determination under paragraph (d)(1) of this section is <PRTPAGE P="82"/>incorrect or no longer correct, he will publish notice of the determination in the <E T="04">Federal Register,</E> revise the guideline document as necessary under paragraph (a) of this section, and propose and promulgate emission guidelines and compliance times under paragraph (c) of this section.</P>
              <CITA>[40 FR 53346, Nov. 17, 1975, as amended at 54 FR 52189, Dec. 20, 1989]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.23</SECTNO>
              <SUBJECT>Adoption and submittal of State plans; public hearings.</SUBJECT>
              <P>(a)(1) Unless otherwise specified in the applicable subpart, within 9 months after notice of the availability of a final guideline document is published under § 60.22(a), each State shall adopt and submit to the Administrator, in accordance with § 60.4 of subpart A of this part, a plan for the control of the designated pollutant to which the guideline document applies.</P>
              <P>(2) Within nine months after notice of the availability of a final revised guideline document is published as provided in § 60.22(d)(2), each State shall adopt and submit to the Administrator any plan revision necessary to meet the requirements of this subpart.</P>
              <P>(b) If no designated facility is located within a State, the State shall submit a letter of certification to that effect to the Administrator within the time specified in paragraph (a) of this section. Such certification shall exempt the State from the requirements of this subpart for that designated pollutant.</P>
              <P>(c)(1) Except as provided in paragraphs (c)(2) and (c)(3) of this section, the State shall, prior to the adoption of any plan or revision thereof, conduct one or more public hearings within the State on such plan or plan revision.</P>
              <P>(2) No hearing shall be required for any change to an increment of progress in an approved compliance schedule unless the change is likely to cause the facility to be unable to comply with the final compliance date in the schedule.</P>
              <P>(3) No hearing shall be required on an emission standard in effect prior to the effective date of this subpart if it was adopted after a public hearing and is at least as stringent as the corresponding emission guideline specified in the applicable guideline document published under § 60.22(a).</P>
              <P>(d) Any hearing required by paragraph (c) of this section shall be held only after reasonable notice. Notice shall be given at least 30 days prior to the date of such hearing and shall include:</P>
              <P>(1) Notification to the public by prominently advertising the date, time, and place of such hearing in each region affected;</P>
              <P>(2) Availability, at the time of public announcement, of each proposed plan or revision thereof for public inspection in at least one location in each region to which it will apply;</P>
              <P>(3) Notification to the Administrator;</P>
              <P>(4) Notification to each local air pollution control agency in each region to which the plan or revision will apply; and</P>
              <P>(5) In the case of an interstate region, notification to any other State included in the region.</P>
              <P>(e) The State shall prepare and retain, for a minimum of 2 years, a record of each hearing for inspection by any interested party. The record shall contain, as a minimum, a list of witnesses together with the text of each presentation.</P>
              <P>(f) The State shall submit with the plan or revision:</P>
              <P>(1) Certification that each hearing required by paragraph (c) of this section was held in accordance with the notice required by paragraph (d) of this section; and</P>
              <P>(2) A list of witnesses and their organizational affiliations, if any, appearing at the hearing and a brief written summary of each presentation or written submission.</P>

              <P>(g) Upon written application by a State agency (through the appropriate Regional Office), the Administrator may approve State procedures designed to insure public participation in the matters for which hearings are required and public notification of the opportunity to participate if, in the judgment of the Administrator, the procedures, although different from the requirements of this subpart, in fact provide for adequate notice to and participation of the public. The Administrator may impose such conditions on his approval as he deems necessary. Procedures approved under this section <PRTPAGE P="83"/>shall be deemed to satisfy the requirements of this subpart regarding procedures for public hearings.</P>
              <CITA>[40 FR 53346, Nov. 17, 1975, as amended at 60 FR 65414, Dec. 19, 1995]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.24</SECTNO>
              <SUBJECT>Emission standards and compliance schedules.</SUBJECT>
              <P>(a) Each plan shall include emission standards and compliance schedules.</P>
              <P>(b)(1) Emission standards shall prescribe allowable rates of emissions except when it is clearly impracticable. Such cases will be identified in the guideline documents issued under § 60.22. Where emission standards prescribing equipment specifications are established, the plan shall, to the degree possible, set forth the emission reductions achievable by implementation of such specifications, and may permit compliance by the use of equipment determined by the State to be equivalent to that prescribed.</P>
              <P>(2) Test methods and procedures for determining compliance with the emission standards shall be specified in the plan. Methods other than those specified in appendix A to this part may be specified in the plan if shown to be equivalent or alternative methods as defined in § 60.2 (t) and (u).</P>
              <P>(3) Emission standards shall apply to all designated facilities within the State. A plan may contain emission standards adopted by local jurisdictions provided that the standards are enforceable by the State.</P>
              <P>(c) Except as provided in paragraph (f) of this section, where the Administrator has determined that a designated pollutant may cause or contribute to endangerment of public health, emission standards shall be no less stringent than the corresponding emission guideline(s) specified in subpart C of this part, and final compliance shall be required as expeditiously as practicable but no later than the compliance times specified in subpart C of this part.</P>
              <P>(d) Where the Administrator has determined that a designated pollutant may cause or contribute to endangerment of public welfare but that adverse effects on public health have not been demonstrated, States may balance the emission guidelines, compliance times, and other information provided in the applicable guideline document against other factors of public concern in establishing emission standards, compliance schedules, and variances. Appropriate consideration shall be given to the factors specified in § 60.22(b) and to information presented at the public hearing(s) conducted under § 60.23(c).</P>
              <P>(e)(1) Any compliance schedule extending more than 12 months from the date required for submittal of the plan must include legally enforceable increments of progress to achieve compliance for each designated facility or category of facilities. Unless otherwise specified in the applicable subpart, increments of progress must include, where practicable, each increment of progress specified in § 60.21(h) and must include such additional increments of progress as may be necessary to permit close and effective supervision of progress toward final compliance.</P>
              <P>(2) A plan may provide that compliance schedules for individual sources or categories of sources will be formulated after plan submittal. Any such schedule shall be the subject of a public hearing held according to § 60.23 and shall be submitted to the Administrator within 60 days after the date of adoption of the schedule but in no case later than the date prescribed for submittal of the first semiannual report required by § 60.25(e).</P>
              <P>(f) Unless otherwise specified in the applicable subpart on a case-by-case basis for particular designated facilities or classes of facilities, States may provide for the application of less stringent emissions standards or longer compliance schedules than those otherwise required by paragraph (c) of this section, provided that the State demonstrates with respect to each such facility (or class of facilities):</P>
              <P>(1) Unreasonable cost of control resulting from plant age, location, or basic process design;</P>
              <P>(2) Physical impossibility of installing necessary control equipment; or</P>

              <P>(3) Other factors specific to the facility (or class of facilities) that make application of a less stringent standard or final compliance time significantly more reasonable.<PRTPAGE P="84"/>
              </P>
              <P>(g) Nothing in this subpart shall be construed to preclude any State or political subdivision thereof from adopting or enforcing (1) emission standards more stringent than emission guidelines specified in subpart C of this part or in applicable guideline documents or (2) compliance schedules requiring final compliance at earlier times than those specified in subpart C or in applicable guideline documents.</P>
              <CITA>[40 FR 53346, Nov. 17, 1975, as amended at 60 FR 65414, Dec. 19, 1995; 65 FR 76384, Dec. 6, 2000]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.25</SECTNO>
              <SUBJECT>Emission inventories, source surveillance, reports.</SUBJECT>
              <P>(a) Each plan shall include an inventory of all designated facilities, including emission data for the designated pollutants and information related to emissions as specified in appendix D to this part. Such data shall be summarized in the plan, and emission rates of designated pollutants from designated facilities shall be correlated with applicable emission standards. As used in this subpart, “correlated” means presented in such a manner as to show the relationship between measured or estimated amounts of emissions and the amounts of such emissions allowable under applicable emission standards.</P>
              <P>(b) Each plan shall provide for monitoring the status of compliance with applicable emission standards. Each plan shall, as a minimum, provide for:</P>
              <P>(1) Legally enforceable procedures for requiring owners or operators of designated facilities to maintain records and periodically report to the State information on the nature and amount of emissions from such facilities, and/or such other information as may be necessary to enable the State to determine whether such facilities are in compliance with applicable portions of the plan.</P>
              <P>(2) Periodic inspection and, when applicable, testing of designated facilities.</P>
              <P>(c) Each plan shall provide that information obtained by the State under paragraph (b) of this section shall be correlated with applicable emission standards (see § 60.25(a)) and made available to the general public.</P>
              <P>(d) The provisions referred to in paragraphs (b) and (c) of this section shall be specifically identified. Copies of such provisions shall be submitted with the plan unless:</P>
              <P>(1) They have been approved as portions of a preceding plan submitted under this subpart or as portions of an implementation plan submitted under section 110 of the Act, and</P>
              <P>(2) The State demonstrates:</P>
              <P>(i) That the provisions are applicable to the designated pollutant(s) for which the plan is submitted, and</P>
              <P>(ii) That the requirements of § 60.26 are met.</P>
              <P>(e) The State shall submit reports on progress in plan enforcement to the Administrator on an annual (calendar year) basis, commencing with the first full report period after approval of a plan or after promulgation of a plan by the Administrator. Information required under this paragraph must be included in the annual report required by § 51.321 of this chapter.</P>
              <P>(f) Each progress report shall include:</P>
              <P>(1) Enforcement actions initiated against designated facilities during the reporting period, under any emission standard or compliance schedule of the plan.</P>
              <P>(2) Identification of the achievement of any increment of progress required by the applicable plan during the reporting period.</P>
              <P>(3) Identification of designated facilities that have ceased operation during the reporting period.</P>
              <P>(4) Submission of emission inventory data as described in paragraph (a) of this section for designated facilities that were not in operation at the time of plan development but began operation during the reporting period.</P>
              <P>(5) Submission of additional data as necessary to update the information submitted under paragraph (a) of this section or in previous progress reports.</P>
              <P>(6) Submission of copies of technical reports on all performance testing on designated facilities conducted under paragraph (b)(2) of this section, complete with concurrently recorded process data.</P>
              <CITA>[40 FR 53346, Nov. 17, 1975, as amended at 44 FR 65071, Nov. 9, 1979]</CITA>
            </SECTION>
            <SECTION>
              <PRTPAGE P="85"/>
              <SECTNO>§ 60.26</SECTNO>
              <SUBJECT>Legal authority.</SUBJECT>
              <P>(a) Each plan shall show that the State has legal authority to carry out the plan, including authority to:</P>
              <P>(1) Adopt emission standards and compliance schedules applicable to designated facilities.</P>
              <P>(2) Enforce applicable laws, regulations, standards, and compliance schedules, and seek injunctive relief.</P>
              <P>(3) Obtain information necessary to determine whether designated facilities are in compliance with applicable laws, regulations, standards, and compliance schedules, including authority to require recordkeeping and to make inspections and conduct tests of designated facilities.</P>
              <P>(4) Require owners or operators of designated facilities to install, maintain, and use emission monitoring devices and to make periodic reports to the State on the nature and amounts of emissions from such facilities; also authority for the State to make such data available to the public as reported and as correlated with applicable emission standards.</P>
              <P>(b) The provisions of law or regulations which the State determines provide the authorities required by this section shall be specifically identified. Copies of such laws or regulations shall be submitted with the plan unless:</P>
              <P>(1) They have been approved as portions of a preceding plan submitted under this subpart or as portions of an implementation plan submitted under section 110 of the Act, and</P>
              <P>(2) The State demonstrates that the laws or regulations are applicable to the designated pollutant(s) for which the plan is submitted.</P>
              <P>(c) The plan shall show that the legal authorities specified in this section are available to the State at the time of submission of the plan. Legal authority adequate to meet the requirements of paragraphs (a)(3) and (4) of this section may be delegated to the State under section 114 of the Act.</P>
              <P>(d) A State governmental agency other than the State air pollution control agency may be assigned responsibility for carrying out a portion of a plan if the plan demonstrates to the Administrator's satisfaction that the State governmental agency has the legal authority necessary to carry out that portion of the plan.</P>
              <P>(e) The State may authorize a local agency to carry out a plan, or portion thereof, within the local agency's jurisdiction if the plan demonstrates to the Administrator's satisfaction that the local agency has the legal authority necessary to implement the plan or portion thereof, and that the authorization does not relieve the State of responsibility under the Act for carrying out the plan or portion thereof.</P>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.27</SECTNO>
              <SUBJECT>Actions by the Administrator.</SUBJECT>
              <P>(a) The Administrator may, whenever he determines necessary, extend the period for submission of any plan or plan revision or portion thereof.</P>
              <P>(b) After receipt of a plan or plan revision, the Administrator will propose the plan or revision for approval or disapproval. The Administrator will, within four months after the date required for submission of a plan or plan revision, approve or disapprove such plan or revision or each portion thereof.</P>
              <P>(c) The Administrator will, after consideration of any State hearing record, promptly prepare and publish proposed regulations setting forth a plan, or portion thereof, for a State if:</P>
              <P>(1) The State fails to submit a plan within the time prescribed;</P>
              <P>(2) The State fails to submit a plan revision required by § 60.23(a)(2) within the time prescribed; or</P>
              <P>(3) The Administrator disapproves the State plan or plan revision or any portion thereof, as unsatisfactory because the requirements of this subpart have not been met.</P>
              <P>(d) The Administrator will, within six months after the date required for submission of a plan or plan revision, promulgate the regulations proposed under paragraph (c) of this section with such modifications as may be appropriate unless, prior to such promulgation, the State has adopted and submitted a plan or plan revision which the Administrator determines to be approvable.</P>

              <P>(e)(1) Except as provided in paragraph (e)(2) of this section, regulations proposed and promulgated by the Administrator under this section will prescribe <PRTPAGE P="86"/>emission standards of the same stringency as the corresponding emission guideline(s) specified in the final guideline document published under § 60.22(a) and will require final compliance with such standards as expeditiously as practicable but no later than the times specified in the guideline document.</P>
              <P>(2) Upon application by the owner or operator of a designated facility to which regulations proposed and promulgated under this section will apply, the Administrator may provide for the application of less stringent emission standards or longer compliance schedules than those otherwise required by this section in accordance with the criteria specified in § 60.24(f).</P>
              <P>(f) Prior to promulgation of a plan under paragraph (d) of this section, the Administrator will provide the opportunity for at least one public hearing in either:</P>
              <P>(1) Each State that failed to hold a public hearing as required by § 60.23(c); or</P>

              <P>(2) Washington, DC or an alternate location specified in the <E T="04">Federal Register</E>.</P>
              <CITA>[40 FR 53346, Nov. 17, 1975, as amended at 65 FR 76384, Dec. 6, 2000]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.28</SECTNO>
              <SUBJECT>Plan revisions by the State.</SUBJECT>
              <P>(a) Plan revisions which have the effect of delaying compliance with applicable emission standards or increments of progress or of establishing less stringent emission standards shall be submitted to the Administrator within 60 days after adoption in accordance with the procedures and requirements applicable to development and submission of the original plan.</P>
              <P>(b) More stringent emission standards, or orders which have the effect of accelerating compliance, may be submitted to the Administrator as plan revisions in accordance with the procedures and requirements applicable to development and submission of the original plan.</P>
              <P>(c) A revision of a plan, or any portion thereof, shall not be considered part of an applicable plan until approved by the Administrator in accordance with this subpart.</P>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.29</SECTNO>
              <SUBJECT>Plan revisions by the Administrator.</SUBJECT>
              <P>After notice and opportunity for public hearing in each affected State, the Administrator may revise any provision of an applicable plan if:</P>
              <P>(a) The provision was promulgated by the Administrator, and</P>
              <P>(b) The plan, as revised, will be consistent with the Act and with the requirements of this subpart.</P>
            </SECTION>
          </SUBPART>
          <SUBPART>
            <HD SOURCE="HED">Subpart C—Emission Guidelines and Compliance Times</HD>
            <SECTION>
              <SECTNO>§ 60.30</SECTNO>
              <SUBJECT>Scope.</SUBJECT>
              <P>The following subparts contain emission guidelines and compliance times for the control of certain designated pollutants in accordance with section 111(d) and section 129 of the Clean Air Act and subpart B of this part.</P>
              <P>(a) Subpart Ca [Reserved]</P>
              <P>(b) Subpart Cb—Municipal Waste Combustors.</P>
              <P>(c) Subpart Cc—Municipal Solid Waste Landfills.</P>
              <P>(d) Subpart Cd—Sulfuric Acid Production Plants.</P>
              <P>(e) Subpart Ce—Hospital/Medical/Infectious Waste Incinerators.</P>
              <CITA>[62 FR 48379, Sept. 15, 1997]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.31</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <P>Terms used but not defined in this subpart have the meaning given them in the Act and in subparts A and B of this part.</P>
              <CITA>[42 FR 55797, Oct. 18, 1977]</CITA>
            </SECTION>
          </SUBPART>
          <SUBPART>
            <RESERVED>Subpart Ca [Reserved]</RESERVED>
          </SUBPART>
          <SUBPART>
            <HD SOURCE="HED">Subpart Cb—Emissions Guidelines and Compliance Times for Large Municipal Waste Combustors That are Constructed on or Before September 20, 1994</HD>
            <SOURCE>
              <HD SOURCE="HED">Source:</HD>
              <P>60 FR 65415, Dec. 19, 1995, unless otherwise noted.</P>
            </SOURCE>
            <SECTION>
              <SECTNO>§ 60.30b</SECTNO>
              <SUBJECT>Scope.</SUBJECT>

              <P>This subpart contains emission guidelines and compliance schedules for the control of certain designated <PRTPAGE P="87"/>pollutants from certain municipal waste combustors in accordance with section 111(d) and section 129 of the Clean Air Act and subpart B of this part. The provisions in these emission guidelines supersede the provisions of § 60.24(f) of subpart B of this part.</P>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.31b</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <P>Terms used but not defined in this subpart have the meaning given them in the Clean Air Act and subparts A, B, and Eb of this part.</P>
              <P>
                <E T="03">Municipal waste combustor plant</E> means one or more designated facilities (as defined in § 60.32b) at the same location.</P>
              <CITA>[60 FR 65415, Dec. 19, 1995, as amended at 62 FR 45119, 45125, Aug. 25, 1997]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.32b</SECTNO>
              <SUBJECT>Designated facilities.</SUBJECT>
              <P>(a) The designated facility to which these guidelines apply is each municipal waste combustor unit with a combustion capacity greater than 250 tons per day of municipal solid waste for which construction was commenced on or before September 20, 1994.</P>
              <P>(b) Any municipal waste combustion unit that is capable of combusting more than 250 tons per day of municipal solid waste and is subject to a federally enforceable permit limiting the maximum amount of municipal solid waste that may be combusted in the unit to less than or equal to 11 tons per day is not subject to this subpart if the owner or operator:</P>
              <P>(1) Notifies the EPA Administrator of an exemption claim,</P>
              <P>(2) Provides a copy of the federally enforceable permit that limits the firing of municipal solid waste to less than 11 tons per day, and</P>
              <P>(3) Keeps records of the amount of municipal solid waste fired on a daily basis.</P>
              <P>(c) Physical or operational changes made to an existing municipal waste combustor unit primarily for the purpose of complying with emission guidelines under this subpart are not considered in determining whether the unit is a modified or reconstructed facility under subpart Ea or subpart Eb of this part.</P>
              <P>(d) A qualifying small power production facility, as defined in section 3(17)(C) of the Federal Power Act (16 U.S.C. 796(17)(C)), that burns homogeneous waste (such as automotive tires or used oil, but not including refuse-derived fuel) for the production of electric energy is not subject to this subpart if the owner or operator of the facility notifies the EPA Administrator of this exemption and provides data documenting that the facility qualifies for this exemption.</P>
              <P>(e) A qualifying cogeneration facility, as defined in section 3(18)(B) of the Federal Power Act (16 U.S.C. 796(18)(B)), that burns homogeneous waste (such as automotive tires or used oil, but not including refuse-derived fuel) for the production of electric energy and steam or forms of useful energy (such as heat) that are used for industrial, commercial, heating, or cooling purposes, is not subject to this subpart if the owner or operator of the facility notifies the EPA Administrator of this exemption and provides data documenting that the facility qualifies for this exemption.</P>
              <P>(f) Any unit combusting a single-item waste stream of tires is not subject to this subpart if the owner or operator of the unit:</P>
              <P>(1) Notifies the EPA Administrator of an exemption claim, and</P>
              <P>(2) Provides data documenting that the unit qualifies for this exemption.</P>
              <P>(g) Any unit required to have a permit under section 3005 of the Solid Waste Disposal Act is not subject to this subpart.</P>
              <P>(h) Any materials recovery facility (including primary or secondary smelters) that combusts waste for the primary purpose of recovering metals is not subject to this subpart.</P>
              <P>(i) Any cofired combustor, as defined under § 60.51b of subpart Eb of this part, that meets the capacity specifications in paragraph (a) of this section is not subject to this subpart if the owner or operator of the cofired combustor:</P>
              <P>(1) Notifies the EPA Administrator of an exemption claim,</P>
              <P>(2) Provides a copy of the federally enforceable permit (specified in the definition of cofired combustor in this section), and</P>

              <P>(3) Keeps a record on a calendar quarter basis of the weight of municipal solid waste combusted at the cofired combustor and the weight of all other <PRTPAGE P="88"/>fuels combusted at the cofired combustor.</P>
              <P>(j) Air curtain incinerators, as defined under § 60.51b of subpart Eb of this part, that meet the capacity specifications in paragraph (a) of this section, and that combust a fuel stream composed of 100 percent yard waste are exempt from all provisions of this subpart except the opacity standard under § 60.37b, the testing procedures under § 60.38b, and the reporting and recordkeeping provisions under § 60.39b.</P>
              <P>(k) Air curtain incinerators that meet the capacity specifications in paragraph (a) of this section and that combust municipal solid waste other than yard waste are subject to all provisions of this subpart.</P>
              <P>(l) Pyrolysis/combustion units that are an integrated part of a plastics/rubber recycling unit (as defined in § 60.51b) are not subject to this subpart if the owner or operator of the plastics/rubber recycling unit keeps records of the weight of plastics, rubber, and/or rubber tires processed on a calendar quarter basis; the weight of chemical plant feedstocks and petroleum refinery feedstocks produced and marketed on a calendar quarter basis; and the name and address of the purchaser of the feedstocks. The combustion of gasoline, diesel fuel, jet fuel, fuel oils, residual oil, refinery gas, petroleum coke, liquified petroleum gas, propane, or butane produced by chemical plants or petroleum refineries that use feedstocks produced by plastics/rubber recycling units are not subject to this subpart.</P>
              <P>(m) Cement kilns firing municipal solid waste are not subject to this subpart.</P>
              <CITA>[60 FR 65415, Dec. 19, 1995, as amended at 62 FR 45119, 45125, Aug. 25, 1997]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.33b</SECTNO>
              <SUBJECT>Emission guidelines for municipal waste combustor metals, acid gases, organics, and nitrogen oxides.</SUBJECT>
              <P>(a) The emission limits for municipal waste combustor metals are specified in paragraphs (a)(1) through (a)(3) of this section.</P>
              <P>(1) For approval, a State plan shall include emission limits for particulate matter and opacity at least as protective as the emission limits for particulate matter and opacity specified in paragraphs (a)(1)(i) through (a)(1)(iii) of this section.</P>
              <P>(i) The emission limit for particulate matter contained in the gases discharged to the atmosphere from a designated facility is 27 milligrams per dry standard cubic meter, corrected to 7 percent oxygen.</P>
              <P>(ii) [Reserved]</P>
              <P>(iii) The emission limit for opacity exhibited by the gases discharged to the atmosphere from a designated facility is 10 percent (6-minute average).</P>
              <P>(2) For approval, a State plan shall include emission limits for cadmium and lead at least as protective as the emission limits for cadmium and lead specified in paragraphs (a)(2)(i) through (a)(2)(iv) of this section.</P>
              <P>(i) The emission limit for cadmium contained in the gases discharged to the atmosphere from a designated facility is 0.040 milligrams per dry standard cubic meter, corrected to 7 percent oxygen.</P>
              <P>(ii) [Reserved]</P>
              <P>(iii) The emission limit for lead contained in the gases discharged to the atmosphere from a designated facility is 0.49 milligrams per dry standard cubic meter, corrected to 7 percent oxygen.</P>
              <P>(iv) [Reserved]</P>
              <P>(3) For approval, a State plan shall include emission limits for mercury at least as protective as the emission limits specified in this paragraph. The emission limit for mercury contained in the gases discharged to the atmosphere from a designated facility is 0.080 milligrams per dry standard cubic meter or 15 percent of the potential mercury emission concentration (85-percent reduction by weight), corrected to 7 percent oxygen, whichever is less stringent.</P>

              <P>(4) For approval, a State plan shall be submitted by August 25, 1998 and shall include an emission limit for lead at least as protective as the emission limit for lead specified in this paragraph. The emission limit for lead contained in the gases discharged to the atmosphere from a designated facility is 0.44 milligrams per dry standard cubic meter, corrected to 7 percent oxygen.<PRTPAGE P="89"/>
              </P>
              <P>(b) The emission limits for municipal waste combustor acid gases, expressed as sulfur dioxide and hydrogen chloride, are specified in paragraphs (b)(1) and (b)(2) of this section.</P>
              <P>(1) For approval, a State plan shall include emission limits for sulfur dioxide at least as protective as the emission limits for sulfur dioxide specified in paragraphs (b)(1)(i) and (b)(1)(ii) of this section.</P>
              <P>(i) The emission limit for sulfur dioxide contained in the gases discharged to the atmosphere from a designated facility is 31 parts per million by volume or 25 percent of the potential sulfur dioxide emission concentration (75-percent reduction by weight or volume), corrected to 7 percent oxygen (dry basis), whichever is less stringent. Compliance with this emission limit is based on a 24-hour daily geometric mean.</P>
              <P>(ii) [Reserved]</P>
              <P>(2) For approval, a State plan shall include emission limits for hydrogen chloride at least as protective as the emission limits for hydrogen chloride specified in paragraphs (b)(2)(i) and (b)(2)(ii) of this section.</P>
              <P>(i) The emission limit for hydrogen chloride contained in the gases discharged to the atmosphere from a designated facility is 31 parts per million by volume or 5 percent of the potential hydrogen chloride emission concentration (95-percent reduction by weight or volume), corrected to 7 percent oxygen (dry basis), whichever is less stringent.</P>
              <P>(ii) [Reserved]</P>
              <P>(3) For approval, a State plan shall be submitted by August 25, 1998 and shall include emission limits for sulfur dioxide and hydrogen chloride at least as protective as the emission limits specified in paragraphs (b)(3)(i) and (b)(3)(ii) of this section.</P>
              <P>(i) The emission limit for sulfur dioxide contained in the gases discharged to the atmosphere from a designated facility is 29 parts per million by volume or 25 percent of the potential sulfur dioxide emission concentration (75-percent reduction by weight or volume), corrected to 7 percent oxygen (dry basis), whichever is less stringent. Compliance with this emission limit is based on a 24-hour daily geometric mean.</P>
              <P>(ii) The emission limit for hydrogen chloride contained in the gases discharged to the atmosphere from a designated facility is 29 parts per million by volume or 5 percent of the potential hydrogen chloride emission concentration (95-percent reduction by weight or volume), corrected to 7 percent oxygen (dry basis), whichever is less stringent.</P>
              <P>(c) The emission limits for municipal waste combustor organics, expressed as total mass dioxins/furans, are specified in paragraphs (c)(1) and (c)(2) of this section.</P>
              <P>(1) For approval, a State plan shall include an emission limit for dioxins/furans contained in the gases discharged to the atmosphere from a designated facility at least as protective as the emission limit for dioxins/furans specified in either paragraph (c)(1)(i) or (c)(1)(ii) of this section, as applicable.</P>
              <P>(i) The emission limit for designated facilities that employ an electrostatic precipitator-based emission control system is 60 nanograms per dry standard cubic meter (total mass), corrected to 7 percent oxygen.</P>
              <P>(ii) The emission limit for designated facilities that do not employ an electrostatic precipitator-based emission control system is 30 nanograms per dry standard cubic meter (total mass), corrected to 7 percent oxygen.</P>
              <P>(2) [Reserved]</P>
              <P>(d) For approval, a State plan shall include emission limits for nitrogen oxides at least as protective as the emission limits listed in table 1 of this subpart for designated facilities. Table 1 provides emission limits for the nitrogen oxides concentration level for each type of designated facility.</P>
              <GPOTABLE CDEF="s25,10C" COLS="2" OPTS="L2">
                <TTITLE>Table 1—Nitrogen Oxides Guidelines for Designated Facilities</TTITLE>
                <BOXHD>
                  <CHED H="1">Municipal waste combustor technology</CHED>
                  <CHED H="1">Nitrogen oxides emission limit (parts per million by volume) <SU>a</SU>
                  </CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">Mass burn waterwall</ENT>
                  <ENT>205</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Mass burn rotary waterwall</ENT>
                  <ENT>250</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Refuse-derived fuel combustor</ENT>
                  <ENT>250</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Fluidized bed combustor</ENT>
                  <ENT>240</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Mass burn refractory combustors</ENT>
                  <ENT>no limit</ENT>
                </ROW>
                <TNOTE>
                  <SU>a</SU> Corrected to 7 percent oxygen, dry basis.</TNOTE>
              </GPOTABLE>

              <P>(1) A State plan may allow nitrogen oxides emissions averaging as specified <PRTPAGE P="90"/>in paragraphs (d)(1)(i) through (d)(1)(v) of this section.</P>
              <P>(i) The owner or operator of a municipal waste combustor plant may elect to implement a nitrogen oxides emissions averaging plan for the designated facilities that are located at that plant and that are subject to subpart Cb, except as specified in paragraphs (d)(1)(i)(A) and (d)(1)(i)(B) of this section.</P>
              <P>(A) Municipal waste combustor units subject to subpart Ea or Eb cannot be included in the emissions averaging plan.</P>
              <P>(B) Mass burn refractory municipal waste combustor units and other municipal waste combustor technologies not listed in paragraph (d)(1)(iii) of this section may not be included in the emissions averaging plan.</P>
              <P>(ii) The designated facilities included in the nitrogen oxides emissions averaging plan must be identified in the initial compliance report specified in § 60.59b(f) or in the annual report specified in § 60.59b(g), as applicable, prior to implementing the averaging plan. The designated facilities being included in the averaging plan may be redesignated each calendar year. Partial year redesignation is allowable with State approval.</P>
              <P>(iii) To implement the emissions averaging plan, the average daily (24-hour) nitrogen oxides emission concentration level for gases discharged from the designated facilities being included in the emissions averaging plan must be no greater than the levels specified in table 2 of this subpart. Table 2 provides emission limits for the nitrogen oxides concentration level for each type of designated facility.</P>
              <GPOTABLE CDEF="s25,10C" COLS="2" OPTS="L2">

                <TTITLE>Table 2—Nitrogen Oxides Limits For Existing Designated Facilities Included in an Emissions Averaging Plan at a Municpial Waste Combustor Plant<E T="51">a</E>
                </TTITLE>
                <BOXHD>
                  <CHED H="1">Municipal waste combustor technology</CHED>
                  <CHED H="1">Nitrogen oxides emission limit (parts per million by volume)<E T="51">b</E>
                  </CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">Mass burn waterwall</ENT>
                  <ENT>185</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Mass burn rotary waterwall</ENT>
                  <ENT>220</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Refuse-derived fuel combustor</ENT>
                  <ENT>230</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Fluidized bed combustor</ENT>
                  <ENT>220</ENT>
                </ROW>
                <TNOTE>
                  <E T="51">a</E> Mass burn refractory municipal waste combustors and other MWC technologies not listed above may not be included in an emissions averaging plan.</TNOTE>
                <TNOTE>
                  <E T="51">b</E> Corrected to 7 percent oxygen, dry basis.</TNOTE>
              </GPOTABLE>
              <P>(iv) Under the emissions averaging plan, the average daily nitrogen oxides emissions specified in paragraph (d)(1)(iii) of this section shall be calculated using equation (1). Designated facilities that are offline shall not be included in calculating the average daily nitrogen oxides emission level.</P>
              <MATH DEEP="61" SPAN="1">
                <MID>ER19de95.000</MID>
              </MATH>
              <FP>where:</FP>
              
              <FP SOURCE="FP-1">NO<E T="52">X 24-hr</E>=24-hr daily average nitrogen oxides emission concentration level for the emissions averaging plan (parts per million by volume corrected to 7 percent oxygen).</FP>
              <FP SOURCE="FP-1">NO<E T="52">X i-hr</E>=24-hr daily average nitrogen oxides emission concentration level for designated facility i (parts per million by volume, corrected to 7 percent oxygen), calculated according to the procedures in § 60.58b(h) of this subpart.</FP>
              <FP SOURCE="FP-1">S<E T="52">i</E>=maximum demonstrated municipal waste combustor unit load for designated facility i (pounds per hour steam or feedwater flow as determined in the most recent dioxin/furan performance test).</FP>
              <FP SOURCE="FP-1">h=total number of designated facilities being included in the daily emissions average.</FP>
              

              <P>(v) For any day in which any designated facility included in the emissions averaging plan is offline, the owner or operator of the municipal <PRTPAGE P="91"/>waste combustor plant must demonstrate compliance according to either paragraph (d)(1)(v)(A) of this section or both paragraphs (d)(1)(v)(B) and (d)(1)(v)(C) of this section.</P>
              <P>(A) Compliance with the applicable limits specified in table 2 of this subpart shall be demonstrated using the averaging procedure specified in paragraph (d)(1)(iv) of this section for the designated facilities that are online.</P>
              <P>(B) For each of the designated facilities included in the emissions averaging plan, the nitrogen oxides emissions on a daily average basis shall be calculated and shall be equal to or less than the maximum daily nitrogen oxides emission level achieved by that designated facility on any of the days during which the emissions averaging plan was achieved with all designated facilities online during the most recent calendar quarter. The requirements of this paragraph do not apply during the first quarter of operation under the emissions averaging plan.</P>

              <P>(C) The average nitrogen oxides emissions (kilograms per day) calculated according to paragraph (d)(1)(v)(C)(<E T="03">2</E>) of this section shall not exceed the average nitrogen oxides emissions (kilograms per day) calculated according to paragraph (d)(1)(v)(C)(<E T="03">1</E>) of this section.</P>
              <P>(<E T="03">1</E>) For all days during which the emissions averaging plan was implemented and achieved and during which all designated facilities were online, the average nitrogen oxides emissions shall be calculated. The average nitrogen oxides emissions (kilograms per day) shall be calculated on a calendar year basis according to paragraphs (d)(1)(v)(C)(<E T="03">1</E>)(<E T="03">i</E>) through (d)(1)(v)(C)(<E T="03">1</E>)(<E T="03">iii</E>) of this section.</P>
              <P>(<E T="03">i</E>) For each designated facility included in the emissions averaging plan, the daily amount of nitrogen oxides emitted (kilograms per day) shall be calculated based on the hourly nitrogen oxides data required under § 60.38b(a) and specified under § 60.58b(h)(5) of subpart Eb of this part, the flue gas flow rate determined using table 19-1 of EPA Reference Method 19 or a State-approved method, and the hourly average steam or feedwater flow rate.</P>
              <P>(<E T="03">ii</E>) The daily total nitrogen oxides emissions shall be calculated as the sum of the daily nitrogen oxides emissions from each designated facility calculated under paragraph (d)(1)(v)(C)(<E T="03">1</E>)(<E T="03">i</E>) of this section.</P>
              <P>(<E T="03">iii</E>) The average nitrogen oxides emissions (kilograms per day) on a calendar year basis shall be calculated as the sum of all daily total nitrogen oxides emissions calculated under paragraph (d)(1)(v)(C)(<E T="03">1</E>)(<E T="03">ii</E>) of this section divided by the number of calendar days for which a daily total was calculated.</P>
              <P>(<E T="03">2</E>) For all days during which one or more of the designated facilities under the emissions averaging plan was offline, the average nitrogen oxides emissions shall be calculated. The average nitrogen oxides emissions (kilograms per day) shall be calculated on a calendar year basis according to paragraphs (d)(1)(v)(C)(<E T="03">2</E>)(<E T="03">i</E>) through (d)(1)(v)(C)(<E T="03">2</E>)(<E T="03">iii</E>) of this section.</P>
              <P>(<E T="03">i</E>) For each designated facility included in the emissions averaging plan, the daily amount of nitrogen oxides emitted (kilograms per day) shall be calculated based on the hourly nitrogen oxides data required under § 60.38b(a) and specified under § 60.58b(h)(5) of subpart Eb of this part, the flue gas flow rate determined using table 19-1 of EPA Reference Method 19 or a State-approved method, and the hourly average steam or feedwater flow rate.</P>
              <P>(<E T="03">ii</E>) The daily total nitrogen oxides emissions shall be calculated as the sum of the daily nitrogen oxides emissions from each designated facility calculated under paragraph (d)(1)(v)(C)(<E T="03">2</E>)(<E T="03">i</E>) of this section.</P>
              <P>(<E T="03">iii</E>) The average nitrogen oxides emissions (kilograms per day) on a calendar year basis shall be calculated as the sum of all daily total nitrogen oxides emissions calculated under paragraph (d)(1)(v)(C)(<E T="03">2</E>)(<E T="03">ii</E>) of this section divided by the number of calendar days for which a daily total was calculated.</P>
              <P>(2) A State plan may establish a program to allow owners or operators of municipal waste combustor plants to engage in trading of nitrogen oxides emission credits. A trading program must be approved by the Administrator before implementation.</P>

              <P>(3) For approval, a State plan shall be submitted by August 25, 1998 and shall include emission limits for nitrogen <PRTPAGE P="92"/>oxides from fluidized bed combustors at least as protective as the emission limits listed in paragraphs (d)(3)(i) and (d)(3)(ii) of this section.</P>
              <P>(i) The emission limit for nitrogen oxides contained in the gases discharged to the atmosphere from a designated facility that is a fluidized bed combustor is 180 parts per million by volume, corrected to 7 percent oxygen.</P>
              <P>(ii) If a State plan allows nitrogen oxides emissions averaging as specified in paragraphs (d)(1)(i) through (d)(1)(v) of this section, the emission limit for nitrogen oxides contained in the gases discharged to the atmosphere from a designated facility that is a fluidized bed combustor is 165 parts per million by volume, corrected to 7 percent oxygen.</P>
              <CITA>[60 FR 65415, Dec. 19, 1995, as amended at 62 FR 45119, 45125, Aug. 25, 1997]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.34b</SECTNO>
              <SUBJECT>Emission guidelines for municipal waste combustor operating practices.</SUBJECT>
              <P>(a) For approval, a State plan shall include emission limits for carbon monoxide at least as protective as the emission limits for carbon monoxide listed in table 3 of this subpart. Table 3 provides emission limits for the carbon monoxide concentration level for each type of designated facility.</P>
              <GPOTABLE CDEF="s100,10,10" COLS="3" OPTS="L2">
                <TTITLE>Table 3—Municipal Waste Combustor Operating Guidelines</TTITLE>
                <BOXHD>
                  <CHED H="1">Municipal waste combustor technology</CHED>
                  <CHED H="1">Carbon monoxide emissions level (parts per million by volume)<E T="51">a</E>
                  </CHED>
                  <CHED H="1">Averaging time (hrs)<E T="51">b</E>
                  </CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">Mass burn waterwall</ENT>
                  <ENT>100</ENT>
                  <ENT>4</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Mass burn refractory</ENT>
                  <ENT>100</ENT>
                  <ENT>4</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Mass burn rotary refractory</ENT>
                  <ENT>100</ENT>
                  <ENT>24</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Mass burn rotary waterwall</ENT>
                  <ENT>250</ENT>
                  <ENT>24</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Modular starved air</ENT>
                  <ENT>50</ENT>
                  <ENT>4</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Modular excess air</ENT>
                  <ENT>50</ENT>
                  <ENT>4</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Refuse-derived fuel stoker</ENT>
                  <ENT>200</ENT>
                  <ENT>24</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Buddling fluidized bed combustor</ENT>
                  <ENT>100</ENT>
                  <ENT>4</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Circulating fluidized bed combustor</ENT>
                  <ENT>100</ENT>
                  <ENT>4</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Pulverized coal/refuse-derived fuel mixed fuel-fired combustor</ENT>
                  <ENT>150</ENT>
                  <ENT>4</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Spreader stoker coal/refuse-derived fuel mixed fuel-fired combustor</ENT>
                  <ENT>200</ENT>
                  <ENT>24</ENT>
                </ROW>
                <TNOTE>
                  <E T="51">a</E> Measured at the combustor outlet in conjunction with a measurement of oxygen concentration, corrected to 7 percent oxygen, dry basis. Calculated as an arithmetic average.</TNOTE>
                <TNOTE>
                  <E T="51">b</E> Averaging times are 4-hour or 24-hour block averages.</TNOTE>
              </GPOTABLE>
              <P>(b) For approval, a State plan shall include requirements for municipal waste combustor operating practices at least as protective as those requirements listed in § 60.53b(b) and (c) of subpart Eb of this part.</P>
              <CITA>[60 FR 65415, Dec. 19, 1995, as amended at 62 FR 45120, 45125, Aug. 25, 1997]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.35b</SECTNO>
              <SUBJECT>Emission guidelines for municipal waste combustor operator training and certification.</SUBJECT>
              <P>For approval, a State plan shall include requirements for designated facilities for municipal waste combustor operator training and certification at least as protective as those requirements listed in § 60.54b of subpart Eb of this part. The State plan shall require compliance with these requirements according to the schedule specified in § 60.39b(c)(4).</P>
              <CITA>[60 FR 65415, Dec. 19, 1995, as amended at 62 FR 45120, Aug. 25, 1997]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.36b</SECTNO>
              <SUBJECT>Emission guidelines for municipal waste combustor fugitive ash emissions.</SUBJECT>
              <P>For approval, a State plan shall include requirements for municipal waste combustor fugitive ash emissions at least as protective as those requirements listed in § 60.55b of subpart Eb of this part.</P>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.37b</SECTNO>
              <SUBJECT>Emission guidelines for air curtain incinerators.</SUBJECT>

              <P>For approval, a State plan shall include emission limits for opacity for <PRTPAGE P="93"/>air curtain incinerators at least as protective as those listed in § 60.56b of subpart Eb of this part.</P>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.38b</SECTNO>
              <SUBJECT>Compliance and performance testing.</SUBJECT>
              <P>(a) For approval, a State plan shall include the performance testing methods listed in § 60.58b of subpart Eb of this part, as applicable, except as provided for under § 60.24(b)(2) of subpart B of this part and paragraphs (b) and (c) of this section.</P>
              <P>(b) For approval, a State plan shall include for designated facilities the alternative performance testing schedule for dioxins/furans specified in § 60.58b(g)(5)(iii) of subpart Eb of this part, as applicable, for those designated facilities that achieve a dioxin/furan emission level less than or equal to 15 nanograms per dry standard cubic meter total mass, corrected to 7 percent oxygen.</P>
              <P>(c) [Reserved]</P>
              <CITA>[60 FR 65415, Dec. 19, 1995, as amended at 62 FR 45120, Aug. 25, 1997]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.39b</SECTNO>
              <SUBJECT>Reporting and recordkeeping guidelines and compliance schedules.</SUBJECT>
              <P>(a) For approval, a State plan shall include the reporting and recordkeeping provisions listed in § 60.59b of subpart Eb of this part, as applicable, except for the siting requirements under § 60.59b(a), (b)(5), and (d)(11) of subpart Eb of this part.</P>
              <P>(b) Not later than December 19, 1996, each State in which a designated facility is located shall submit to the EPA Administrator a plan to implement and enforce all provisions of this subpart except those specified under § 60.33b (a)(4), (b)(3), and (d)(3). The compliance schedule specified in this paragraph is in accordance with section 129(b)(2) of the Act and supersedes the compliance schedule provided in § 60.23(a)(1) of subpart B of this part.</P>
              <P>(c) For approval, a State plan shall include the compliance schedules specified in paragraphs (c)(1) through (c)(5) of this section.</P>
              <P>(1) A State plan shall allow designated facilities to comply with all requirements of a State plan (or close) within 1 year after approval of the State plan, except as provided by paragraph (c)(1)(i) and (c)(1)(ii) of this section.</P>
              <P>(i) A State plan that allows designated facilities more than 1 year but less than 3 years following the date of issuance of a revised construction or operation permit, if a permit modification is required, or more than 1 year but less than 3 years following approval of the State plan, if a permit modification is not required, shall include measurable and enforceable incremental steps of progress toward compliance. Suggested measurable and enforceable activities are specified in paragraphs (c)(1)(i)(A) through (c)(1)(i)(J) of this section.</P>
              <P>(A) Date for obtaining services of an architectural and engineering firm regarding the air pollution control device(s);</P>
              <P>(B) Date for obtaining design drawings of the air pollution control device(s);</P>
              <P>(C) Date for submittal of permit modifications, if necessary;</P>
              <P>(D) Date for submittal of the final control plan to the Administrator. [§ 60.21 (h)(1) of subpart B of this part.];</P>
              <P>(E) Date for ordering the air pollution control device(s);</P>
              <P>(F) Date for obtaining the major components of the air pollution control device(s);</P>
              <P>(G) Date for initiation of site preparation for installation of the air pollution control device(s);</P>
              <P>(H) Date for initiation of installation of the air pollution control device(s);</P>
              <P>(I) Date for initial startup of the air pollution control device(s); and</P>
              <P>(J) Date for initial performance test(s) of the air pollution control device(s).</P>
              <P>(ii) A State plan that allows designated facilities more than 1 year but up to 3 years after State plan approval to close shall require a closure agreement. The closure agreement must include the date of plant closure.</P>

              <P>(2) If the State plan requirements for a designated facility include a compliance schedule longer than 1 year after approval of the State plan in accordance with paragraph (c)(1)(i) or (c)(1)(ii) of this section, the State plan submittal (for approval) shall include performance test results for dioxin/furan emissions for each designated facility <PRTPAGE P="94"/>that has a compliance schedule longer than 1 year following the approval of the State plan, and the performance test results shall have been conducted during or after 1990. The performance test shall be conducted according to the procedures in § 60.38b.</P>
              <P>(3) [Reserved]</P>
              <P>(4) A State plan shall require compliance with the municipal waste combustor operator training and certification requirements under § 60.35b according to the schedule specified in paragraphs (c)(4)(i) through (c)(4)(iii) of this section.</P>
              <P>(i) [Reserved]</P>
              <P>(ii) For designated facilities, the State plan shall require compliance with the municipal waste combustor operator training and certification requirements specified under § 60.54b (a) through (c) of subpart Eb of this part by the date 6 months after the date of startup or 12 months after State plan approval, whichever is later.</P>
              <P>(iii) For designated facilities, the State plan shall require compliance with the requirements specified in § 60.54b (d), (f), and (g) of subpart Eb of this part no later than 6 months after startup or 12 months after State plan approval, whichever is later.</P>
              <P>(A) The requirement specified in § 60.54b(d) of subpart Eb of this part does not apply to chief facility operators, shift supervisors, and control room operators who have obtained full certification from the American Society of Mechanical Engineers on or before the date of State plan approval.</P>
              <P>(B) The owner or operator of a designated facility may request that the EPA Administrator waive the requirement specified in § 60.54b(d) of subpart Eb of this part for chief facility operators, shift supervisors, and control room operators who have obtained provisional certification from the American Society of Mechanical Engineers on or before the date of State plan approval.</P>

              <P>(C) The initial training requirements specified in § 60.54b(f)(1) of subpart Eb of this part shall be completed no later than the date specified in paragraph (c)(4)(iii)(C)(<E T="03">1</E>), (c)(4)(iii)(C)(<E T="03">2</E>), or (c)(4)(iii)(C)(<E T="03">3</E>), of this section whichever is later.</P>
              <P>(<E T="03">1</E>) The date 6 months after the date of startup of the affected facility;</P>
              <P>(<E T="03">2</E>) Twelve months after State plan approval; or</P>
              <P>(<E T="03">3</E>) The date prior to the day when the person assumes responsibilities affecting municipal waste combustor unit operation.</P>
              <P>(5) A State plan shall require all designated facilities for which construction, modification, or reconstruction is commenced after June 26, 1987 to comply with the emission limit for mercury specified in § 60.33b(a)(3) and the emission limit for dioxins/furans specified in § 60.33b(c)(1) within 1 year following issuance of a revised construction or operation permit, if a permit modification is required, or within 1 year following approval of the State plan, whichever is later.</P>
              <P>(d) In the event no plan for implementing the emission guidelines is approved by EPA, all designated facilities meeting the applicability requirements under § 60.32b shall be in compliance with all of the guidelines, except those specified under § 60.33b (a)(4), (b)(3), and (d)(3), no later than December 19, 2000.</P>
              <P>(e) Not later than August 25, 1998, each State in which a designated facility is operating shall submit to the EPA Administrator a plan to implement and enforce all provisions of this subpart specified in § 60.33b (a)(4), (b)(3), and (d)(3).</P>
              <P>(f) In the event no plan for implementing the emission guidelines is approved by EPA, all designated facilities meeting the applicability requirements under § 60.32b shall be in compliance with all of the guidelines, including those specified under § 60.33b (a)(4), (b)(3), and (d)(3), no later than August 26, 2002.</P>
              <CITA>[60 FR 65415, Dec. 19, 1995, as amended at 62 FR 45120, 45125, Aug. 25, 1997]</CITA>
            </SECTION>
          </SUBPART>
          <SUBPART>
            <HD SOURCE="HED">Subpart Cc—Emission Guidelines and Compliance Times for Municipal Solid Waste Landfills</HD>
            <SOURCE>
              <HD SOURCE="HED">Source:</HD>
              <P>61 FR 9919, Mar. 12, 1996, unless otherwise noted.</P>
            </SOURCE>
            <SECTION>
              <PRTPAGE P="95"/>
              <SECTNO>§ 60.30c</SECTNO>
              <SUBJECT>Scope.</SUBJECT>
              <P>This subpart contains emission guidelines and compliance times for the control of certain designated pollutants from certain designated municipal solid waste landfills in accordance with section 111(d) of the Act and subpart B.</P>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.31c</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <P>Terms used but not defined in this subpart have the meaning given them in the Act and in subparts A, B, and WWW of this part.</P>
              <P>
                <E T="03">Municipal solid waste landfill</E> or <E T="03">MSW landfill</E> means an entire disposal facility in a contiguous geographical space where household waste is placed in or on land. An MSW landfill may also receive other types of RCRA Subtitle D wastes such as commercial solid waste, nonhazardous sludge, conditionally exempt small quantity generator waste, and industrial solid waste. Portions of an MSW landfill may be separated by access roads. An MSW landfill may be publicly or privately owned. An MSW landfill may be a new MSW landfill, an existing MSW landfill or a lateral expansion.</P>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.32c</SECTNO>
              <SUBJECT>Designated facilities.</SUBJECT>
              <P>(a) The designated facility to which the guidelines apply is each existing MSW landfill for which construction, reconstruction or modification was commenced before May 30, 1991.</P>
              <P>(b) Physical or operational changes made to an existing MSW landfill solely to comply with an emission guideline are not considered a modification or reconstruction and would not subject an existing MSW landfill to the requirements of subpart WWW [see § 60.750 of Subpart WWW].</P>
              <P>(c) For purposes of obtaining an operating permit under title V of the Act, the owner or operator of a MSW landfill subject to this subpart with a design capacity less than 2.5 million megagrams or 2.5 million cubic meters is not subject to the requirement to obtain an operating permit for the landfill under part 70 or 71 of this chapter, unless the landfill is otherwise subject to either part 70 or 71. For purposes of submitting a timely application for an operating permit under part 70 or 71, the owner or operator of a MSW landfill subject to this subpart with a design capacity greater than or equal to 2.5 million megagrams and 2.5 million cubic meters on the effective date of EPA approval of the State's program under section 111(d) of the Act, and not otherwise subject to either part 70 or 71, becomes subject to the requirements of §§ 70.5(a)(1)(i) or 71.5(a)(1)(i) of this chapter 90 days after the effective date of such 111(d) program approval, even if the design capacity report is submitted earlier.</P>
              <P>(d) When a MSW landfill subject to this subpart is closed, the owner or operator is no longer subject to the requirement to maintain an operating permit under part 70 or 71 of this chapter for the landfill if the landfill is not otherwise subject to the requirements of either part 70 or 71 and if either of the following conditions are met.</P>
              <P>(1) The landfill was never subject to the requirement for a control system under § 60.33c(c) of this subpart; or</P>
              <P>(2) The owner or operator meets the conditions for control system removal specified in § 60.752(b)(2)(v) of subpart WWW.</P>
              <CITA>[61 FR 9919, Mar. 12, 1996, as amended at 63 FR 32750, June 16, 1998]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.33c</SECTNO>
              <SUBJECT>Emission guidelines for municipal solid waste landfill emissions.</SUBJECT>
              <P>(a) For approval, a State plan shall include control of MSW landfill emissions at each MSW landfill meeting the following three conditions:</P>
              <P>(1) The landfill has accepted waste at any time since November 8, 1987, or has additional design capacity available for future waste deposition;</P>
              <P>(2) The landfill has a design capacity greater than or equal to 2.5 million megagrams and 2.5 million cubic meters. The landfill may calculate design capacity in either megagrams or cubic meters for comparison with the exemption values. Any density conversions shall be documented and submitted with the design capacity report; and</P>
              <P>(3) The landfill has a nonmethane organic compound emission rate of 50 megagrams per year or more.</P>

              <P>(b) For approval, a State plan shall include the installation of a collection and control system meeting the conditions provided in § 60.752(b)(2)(ii) of this <PRTPAGE P="96"/>part at each MSW landfill meeting the conditions in paragraph (a) of this section. The State plan shall include a process for State review and approval of the site-specific design plans for the gas collection and control system(s).</P>
              <P>(c) For approval, a State plan shall include provisions for the control of collected MSW landfill emissions through the use of control devices meeting the requirements of paragraph (c)(1), (2), or (3) of this section, except as provided in § 60.24.</P>
              <P>(1) An open flare designed and operated in accordance with the parameters established in § 60.18; or</P>
              <P>(2) A control system designed and operated to reduce NMOC by 98 weight percent; or</P>
              <P>(3) An enclosed combustor designed and operated to reduce the outlet NMOC concentration to 20 parts per million as hexane by volume, dry basis at 3 percent oxygen, or less.</P>
              <P>(d) For approval, a State plan shall require each owner or operator of an MSW landfill having a design capacity less than 2.5 million megagrams by mass or 2.5 million cubic meters by volume to submit an initial design capacity report to the Administrator as provided in § 60.757(a)(2) of subpart WWW by the date specified in § 60.35c of this subpart. The landfill may calculate design capacity in either megagrams or cubic meters for comparison with the exemption values. Any density conversions shall be documented and submitted with the report. Submittal of the initial design capacity report shall fulfill the requirements of this subpart except as provided in paragraph (d)(1) and (d)(2) of this section.</P>
              <P>(1) The owner or operator shall submit an amended design capacity report as provided in § 60.757(a)(3) of subpart WWW. [Guidance: Note that if the design capacity increase is the result of a modification, as defined in § 60.751 of subpart WWW, that was commenced on or after May 30, 1991, the landfill will become subject to subpart WWW instead of this subpart. If the design capacity increase is the result of a change in operating practices, density, or some other change that is not a modification, the landfill remains subject to this subpart.]</P>
              <P>(2) When an increase in the maximum design capacity of a landfill with an initial design capacity less than 2.5 million megagrams or 2.5 million cubic meters results in a revised maximum design capacity equal to or greater than 2.5 million megagrams and 2.5 million cubic meters, the owner or operator shall comply with paragraph (e) of this section.</P>
              <P>(e) For approval, a State plan shall require each owner or operator of an MSW landfill having a design capacity equal to or greater than 2.5 million megagrams and 2.5 million cubic meters to either install a collection and control system as provided in paragraph (b) of this section and § 60.752(b)(2) of subpart WWW or calculate an initial NMOC emission rate for the landfill using the procedures specified in § 60.34c of this subpart and § 60.754 of subpart WWW. The NMOC emission rate shall be recalculated annually, except as provided in § 60.757(b)(1)(ii) of subpart WWW.</P>
              <P>(1) If the calculated NMOC emission rate is less than 50 megagrams per year, the owner or operator shall:</P>
              <P>(i) Submit an annual emission report, except as provided for in § 60.757(b)(1)(ii); and</P>
              <P>(ii) Recalculate the NMOC emission rate annually using the procedures specified in § 60.754(a)(1) of subpart WWW until such time as the calculated NMOC emission rate is equal to or greater than 50 megagrams per year, or the landfill is closed.</P>
              <P>(2)(i) If the NMOC emission rate, upon initial calculation or annual recalculation required in paragraph (e)(1)(ii) of this section, is equal to or greater than 50 megagrams per year, the owner or operator shall install a collection and control system as provided in paragraph (b) of this section and § 60.752(b)(2) of subpart WWW.</P>
              <P>(ii) If the landfill is permanently closed, a closure notification shall be submitted to the Administrator as provided in § 60.35c of this subpart and § 60.757(d) of subpart WWW.</P>
              <CITA>[61 FR 9919, Mar. 12, 1996, as amended at 63 FR 32750, June 16, 1998; 64 FR 9261, Feb. 24, 1999]</CITA>
            </SECTION>
            <SECTION>
              <PRTPAGE P="97"/>
              <SECTNO>§ 60.34c</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <P>For approval, a State plan shall include provisions for: the calculation of the landfill NMOC emission rate listed in § 60.754, as applicable, to determine whether the landfill meets the condition in § 60.33c(a)(3); the operational standards in § 60.753; the compliance provisions in § 60.755; and the monitoring provisions in § 60.756.</P>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.35c</SECTNO>
              <SUBJECT>Reporting and recordkeeping guidelines.</SUBJECT>
              <P>For approval, a State plan shall include the recordkeeping and reporting provisions listed in §§ 60.757 and 60.758, as applicable, except as provided under § 60.24.</P>
              <P>(a) For existing MSW landfills subject to this subpart the initial design capacity report shall be submitted no later than 90 days after the effective date of EPA approval of the State's plan under section 111(d) of the Act.</P>
              <P>(b) For existing MSW landfills covered by this subpart with a design capacity equal to or greater than 2.5 million megagrams and 2.5 million cubic meters, the initial NMOC emission rate report shall be submitted no later than 90 days after the effective date of EPA approval of the State's plan under section 111(d) of the Act.</P>
              <CITA>[61 FR 9919, Mar. 12, 1996, as amended at 64 FR 9262, Feb. 24, 1999]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.36c</SECTNO>
              <SUBJECT>Compliance times.</SUBJECT>
              <P>(a) Except as provided for under paragraph (b) of this section, planning, awarding of contracts, and installation of MSW landfill air emission collection and control equipment capable of meeting the emission guidelines established under § 60.33c shall be accomplished within 30 months after the date the initial NMOC emission rate report shows NMOC emissions equal or exceed 50 megagrams per year.</P>
              <P>(b) For each existing MSW landfill meeting the conditions in § 60.33c(a)(1) and § 60.33c(a)(2) whose NMOC emission rate is less than 50 megagrams per year on the effective date of the State emission standard, installation of collection and control systems capable of meeting emission guidelines in § 60.33c shall be accomplished within 30 months of the date when the condition in § 60.33c(a)(3) is met (i.e., the date of the first annual nonmethane organic compounds emission rate which equals or exceeds 50 megagrams per year).</P>
              <CITA>[61 FR 9919, Mar. 12, 1996, as amended at 63 FR 32750, June 16, 1998]</CITA>
            </SECTION>
          </SUBPART>
          <SUBPART>
            <HD SOURCE="HED">Subpart Cd—Emissions Guidelines and Compliance Times for Sulfuric Acid Production Units</HD>
            <SOURCE>
              <HD SOURCE="HED">Source:</HD>
              <P>60 FR 65414, Dec. 19, 1995, unless otherwise noted.</P>
            </SOURCE>
            <SECTION>
              <SECTNO>§ 60.30d</SECTNO>
              <SUBJECT>Designated facilities.</SUBJECT>
              <P>Sulfuric acid production units. The designated facility to which §§ 60.31d and 60.32d apply is each existing “sulfuric acid production unit” as defined in § 60.81(a) of subpart H of this part.</P>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.31d</SECTNO>
              <SUBJECT>Emissions guidelines.</SUBJECT>
              <P>Sulfuric acid production units. The emission guideline for designated facilities is 0.25 grams sulfuric acid mist (as measured by EPA Reference Method 8 of appendix A of this part) per kilogram (0.5 pounds per ton) of sulfuric acid produced, the production being expressed as 100 percent sulfuric acid.</P>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.32d</SECTNO>
              <SUBJECT>Compliance times.</SUBJECT>
              <P>Sulfuric acid production units. Planning, awarding of contracts, and installation of equipment capable of attaining the level of the emission guideline established under § 60.31d can be accomplished within 17 months after the effective date of a State emission standard for sulfuric acid mist.</P>
            </SECTION>
          </SUBPART>
          <SUBPART>
            <HD SOURCE="HED">Subpart Ce—Emission Guidelines and Compliance Times for Hospital/Medical/Infectious Waste Incinerators</HD>
            <SOURCE>
              <HD SOURCE="HED">Source:</HD>
              <P>62 FR 48379, Sept. 15, 1997, unless otherwise noted.</P>
            </SOURCE>
            <SECTION>
              <SECTNO>§ 60.30e</SECTNO>
              <SUBJECT>Scope.</SUBJECT>

              <P>This subpart contains emission guidelines and compliance times for the control of certain designated pollutants from hospital/medical/infectious waste incinerator(s) (HMIWI) in accordance with sections 111 and 129 of <PRTPAGE P="98"/>the Clean Air Act and subpart B of this part. The provisions in these emission guidelines supersede the provisions of § 60.24(f) of subpart B of this part.</P>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.31e</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <P>Terms used but not defined in this subpart have the meaning given them in the Clean Air Act and in subparts A, B, and Ec of this part.</P>
              <P>
                <E T="03">Standard Metropolitan Statistical Area</E> or <E T="03">SMSA</E> means any areas listed in OMB Bulletin No. 93-17 entitled “Revised Statistical Definitions for Metropolitan Areas” dated June 30, 1993 (incorporated by reference, see § 60.17).</P>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.32e</SECTNO>
              <SUBJECT>Designated facilities.</SUBJECT>
              <P>(a) Except as provided in paragraphs (b) through (h) of this section, the designated facility to which the guidelines apply is each individual HMIWI for which construction was commenced on or before June 20, 1996.</P>
              <P>(b) A combustor is not subject to this subpart during periods when only pathological waste, low-level radioactive waste, and/or chemotherapeutic waste (all defined in § 60.51c) is burned, provided the owner or operator of the combustor:</P>
              <P>(1) Notifies the Administrator of an exemption claim; and</P>
              <P>(2) Keeps records on a calendar quarter basis of the periods of time when only pathological waste, low-level radioactive waste, and/or chemotherapeutic waste is burned.</P>
              <P>(c) Any co-fired combustor (defined in § 60.51c) is not subject to this subpart if the owner or operator of the co-fired combustor:</P>
              <P>(1) Notifies the Administrator of an exemption claim;</P>
              <P>(2) Provides an estimate of the relative weight of hospital waste, medical/infectious waste, and other fuels and/or wastes to be combusted; and</P>
              <P>(3) Keeps records on a calendar quarter basis of the weight of hospital waste and medical/infectious waste combusted, and the weight of all other fuels and wastes combusted at the co-fired combustor.</P>
              <P>(d) Any combustor required to have a permit under Section 3005 of the Solid Waste Disposal Act is not subject to this subpart.</P>
              <P>(e) Any combustor which meets the applicability requirements under subpart Cb, Ea, or Eb of this part (standards or guidelines for certain municipal waste combustors) is not subject to this subpart.</P>
              <P>(f) Any pyrolysis unit (defined in § 60.51c) is not subject to this subpart.</P>
              <P>(g) Cement kilns firing hospital waste and/or medical/infectious waste are not subject to this subpart.</P>
              <P>(h) Physical or operational changes made to an existing HMIWI unit solely for the purpose of complying with emission guidelines under this subpart are not considered a modification and do not result in an existing HMIWI unit becoming subject to the provisions of subpart Ec (see § 60.50c).</P>
              <P>(i) Beginning September 15, 2000, or on the effective date of an EPA approved operating permit program under Clean Air Act title V and the implementing regulations under 40 CFR part 70 in the State in which the unit is located, whichever date is later, designated facilities subject to this subpart shall operate pursuant to a permit issued under the EPA-approved operating permit program.</P>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.33e</SECTNO>
              <SUBJECT>Emission guidelines.</SUBJECT>
              <P>(a) For approval, a State plan shall include the requirements for emission limits at least as protective as those requirements listed in Table 1 of this subpart, except as provided for in paragraph (b) of this section.</P>
              <P>(b) For approval, a State plan shall include the requirements for emission limits at least as protective as those requirements listed in Table 2 of this subpart for any small HMIWI which is located more than 50 miles from the boundary of the nearest Standard Metropolitan Statistical Area (defined in § 60.31e) and which burns less than 2,000 pounds per week of hospital waste and medical/infectious waste. The 2,000 lb/week limitation does not apply during performance tests.</P>
              <P>(c) For approval, a State plan shall include the requirements for stack opacity at least as protective as § 60.52c(b) of subpart Ec of this part.</P>
            </SECTION>
            <SECTION>
              <PRTPAGE P="99"/>
              <SECTNO>§ 60.34e</SECTNO>
              <SUBJECT>Operator training and qualification guidelines.</SUBJECT>
              <P>For approval, a State plan shall include the requirements for operator training and qualification at least as protective as those requirements listed in § 60.53c of subpart Ec of this part. The State plan shall require compliance with these requirements according to the schedule specified in § 60.39e(e).</P>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.35e</SECTNO>
              <SUBJECT>Waste management guidelines.</SUBJECT>
              <P>For approval, a State plan shall include the requirements for a waste management plan at least as protective as those requirements listed in § 60.55c of subpart Ec of this part.</P>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.36e</SECTNO>
              <SUBJECT>Inspection guidelines.</SUBJECT>
              <P>(a) For approval, a State plan shall require that each small HMIWI subject to the emission limits under § 60.33e(b) undergo an initial equipment inspection that is at least as protective as the following within 1 year following approval of the State plan:</P>
              <P>(1) At a minimum, an inspection shall include the following:</P>
              <P>(i) Inspect all burners, pilot assemblies, and pilot sensing devices for proper operation; clean pilot flame sensor, as necessary;</P>
              <P>(ii) Ensure proper adjustment of primary and secondary chamber combustion air, and adjust as necessary;</P>
              <P>(iii) Inspect hinges and door latches, and lubricate as necessary;</P>
              <P>(iv) Inspect dampers, fans, and blowers for proper operation;</P>
              <P>(v) Inspect HMIWI door and door gaskets for proper sealing;</P>
              <P>(vi) Inspect motors for proper operation;</P>
              <P>(vii) Inspect primary chamber refractory lining; clean and repair/replace lining as necessary;</P>
              <P>(viii) Inspect incinerator shell for corrosion and/or hot spots;</P>
              <P>(ix) Inspect secondary/tertiary chamber and stack, clean as necessary;</P>
              <P>(x) Inspect mechanical loader, including limit switches, for proper operation, if applicable;</P>
              <P>(xi) Visually inspect waste bed (grates), and repair/seal, as appropriate;</P>
              <P>(xii) For the burn cycle that follows the inspection, document that the incinerator is operating properly and make any necessary adjustments;</P>
              <P>(xiii) Inspect air pollution control device(s) for proper operation, if applicable;</P>
              <P>(xiv) Inspect waste heat boiler systems to ensure proper operation, if applicable;</P>
              <P>(xv) Inspect bypass stack components;</P>
              <P>(xvi) Ensure proper calibration of thermocouples, sorbent feed systems and any other monitoring equipment; and</P>
              <P>(xvii) Generally observe that the equipment is maintained in good operating condition.</P>
              <P>(2) Within 10 operating days following an equipment inspection all necessary repairs shall be completed unless the owner or operator obtains written approval from the State agency establishing a date whereby all necessary repairs of the designated facility shall be completed.</P>
              <P>(b) For approval, a State plan shall require that each small HMIWI subject to the emission limits under § 60.33e(b) undergo an equipment inspection annually (no more than 12 months following the previous annual equipment inspection), as outlined in paragraphs (a)(1) and (a)(2) of this section.</P>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.37e</SECTNO>
              <SUBJECT>Compliance, performance testing, and monitoring guidelines.</SUBJECT>
              <P>(a) Except as provided in paragraph (b) of this section, for approval, a State plan shall include the requirements for compliance and performance testing listed in § 60.56c of subpart Ec of this part, excluding the fugitive emissions testing requirements under § 60.56c(b)(12) and (c)(3).</P>
              <P>(b) For approval, a State plan shall require any small HMIWI subject to the emission limits under § 60.33e(b) to meet the following compliance and performance testing requirements:</P>

              <P>(1) Conduct the performance testing requirements in § 60.56c(a), (b)(1) through (b)(9), (b)(11) (Hg only), and (c)(1) of subpart Ec of this part. The 2,000 lb/week limitation under § 60.33e(b) does not apply during performance tests.<PRTPAGE P="100"/>
              </P>
              <P>(2) Establish maximum charge rate and minimum secondary chamber temperature as site-specific operating parameters during the initial performance test to determine compliance with applicable emission limits.</P>
              <P>(3) Following the date on which the initial performance test is completed or is required to be completed under § 60.8, whichever date comes first, ensure that the designated facility does not operate above the maximum charge rate or below the minimum secondary chamber temperature measured as 3-hour rolling averages (calculated each hour as the average of the previous 3 operating hours) at all times except during periods of startup, shutdown and malfunction. Operating parameter limits do not apply during performance tests. Operation above the maximum charge rate or below the minimum secondary chamber temperature shall constitute a violation of the established operating parameter(s).</P>
              <P>(4) Except as provided in paragraph (b)(5) of this section, operation of the designated facility above the maximum charge rate and below the minimum secondary chamber temperature (each measured on a 3-hour rolling average) simultaneously shall constitute a violation of the PM, CO, and dioxin/furan emission limits.</P>
              <P>(5) The owner or operator of a designated facility may conduct a repeat performance test within 30 days of violation of applicable operating parameter(s) to demonstrate that the designated facility is not in violation of the applicable emission limit(s). Repeat performance tests conducted pursuant to this paragraph must be conducted using the identical operating parameters that indicated a violation under paragraph (b)(4) of this section.</P>
              <P>(c) For approval, a State plan shall include the requirements for monitoring listed in § 60.57c of subpart Ec of this part, except as provided for under paragraph (d) of this section.</P>
              <P>(d) For approval, a State plan shall include requirements for any small HMIWI subject to the emission limits under § 60.33e(b) to meet the following monitoring requirements:</P>
              <P>(1) Install, calibrate (to manufacturers' specifications), maintain, and operate a device for measuring and recording the temperature of the secondary chamber on a continuous basis, the output of which shall be recorded, at a minimum, once every minute throughout operation.</P>
              <P>(2) Install, calibrate (to manufacturers' specifications), maintain, and operate a device which automatically measures and records the date, time, and weight of each charge fed into the HMIWI.</P>
              <P>(3) The owner or operator of a designated facility shall obtain monitoring data at all times during HMIWI operation except during periods of monitoring equipment malfunction, calibration, or repair. At a minimum, valid monitoring data shall be obtained for 75 percent of the operating hours per day and for 90 percent of the operating hours per calendar quarter that the designated facility is combusting hospital waste and/or medical/infectious waste.</P>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.38e</SECTNO>
              <SUBJECT>Reporting and recordkeeping guidelines.</SUBJECT>
              <P>(a) For approval, a State plan shall include the reporting and recordkeeping requirements listed in § 60.58c(b), (c), (d), (e), and (f) of subpart Ec of this part, excluding § 60.58c(b)(2)(ii) (fugitive emissions) and (b)(7) (siting).</P>
              <P>(b) For approval, a State plan shall require the owner or operator of each small HMIWI subject to the emission limits under § 60.33e(b) to:</P>
              <P>(1) Maintain records of the annual equipment inspections, any required maintenance, and any repairs not completed within 10 days of an inspection or the timeframe established by the State regulatory agency; and</P>
              <P>(2) Submit an annual report containing information recorded under paragraph (b)(1) of this section no later than 60 days following the year in which data were collected. Subsequent reports shall be sent no later than 12 calendar months following the previous report (once the unit is subject to permitting requirements under Title V of the Act, the owner or operator must submit these reports semiannually). The report shall be signed by the facilities manager.</P>
            </SECTION>
            <SECTION>
              <PRTPAGE P="101"/>
              <SECTNO>§ 60.39e</SECTNO>
              <SUBJECT>Compliance times.</SUBJECT>
              <P>(a) Not later than September 15, 1998, each State in which a designated facility is operating shall submit to the Administrator a plan to implement and enforce the emission guidelines.</P>
              <P>(b) Except as provided in paragraphs (c) and (d) of this section, State plans shall provide that designated facilities comply with all requirements of the State plan on or before the date 1 year after EPA approval of the State plan, regardless of whether a designated facility is identified in the State plan inventory required by § 60.25(a) of subpart B of this part.</P>
              <P>(c) State plans that specify measurable and enforceable incremental steps of progress towards compliance for designated facilities planning to install the necessary air pollution control equipment may allow compliance on or before the date 3 years after EPA approval of the State plan (but not later than the September 16, 2002. Suggested measurable and enforceable activities to be included in State plans are:</P>
              <P>(1) Date for submitting a petition for site specific operating parameters under § 60.56c(i) of subpart Ec of this part.</P>
              <P>(2) Date for obtaining services of an architectural and engineering firm regarding the air pollution control device(s);</P>
              <P>(3) Date for obtaining design drawings of the air pollution control device(s);</P>
              <P>(4) Date for ordering the air pollution control device(s);</P>
              <P>(5) Date for obtaining the major components of the air pollution control device(s);</P>
              <P>(6) Date for initiation of site preparation for installation of the air pollution control device(s);</P>
              <P>(7) Date for initiation of installation of the air pollution control device(s);</P>
              <P>(8) Date for initial startup of the air pollution control device(s); and</P>
              <P>(9) Date for initial compliance test(s) of the air pollution control device(s).</P>
              <P>(d) State plans that include provisions allowing designated facilities to petition the State for extensions beyond the compliance times required in paragraph (b) of this section shall:</P>
              <P>(1) Require that the designated facility requesting an extension submit the following information in time to allow the State adequate time to grant or deny the extension within 1 year after EPA approval of the State plan:</P>
              <P>(i) Documentation of the analyses undertaken to support the need for an extension, including an explanation of why up to 3 years after EPA approval of the State plan is sufficient time to comply with the State plan while 1 year after EPA approval of the State plan is not sufficient. The documentation shall also include an evaluation of the option to transport the waste offsite to a commercial medical waste treatment and disposal facility on a temporary or permanent basis; and</P>
              <P>(ii) Documentation of measurable and enforceable incremental steps of progress to be taken towards compliance with the emission guidelines.</P>
              <P>(2) Include procedures for granting or denying the extension; and</P>
              <P>(3) If an extension is granted, require compliance with the emission guidelines on or before the date 3 years after EPA approval of the State plan (but not later than September 16, 2002.</P>
              <P>(e) For approval, a State plan shall require compliance with § 60.34e—Operator training and qualification guidelines and § 60.36e—Inspection guidelines by the date 1 year after EPA approval of a State plan.</P>
              <P>(f) The Administrator shall develop, implement, and enforce a plan for existing HMIWI located in any State that has not submitted an approvable plan within date 2 years after September 15, 1997. Such plans shall ensure that each designated facility is in compliance with the provisions of this subpart no later than date 5 years after September 15, 1997.</P>
            </SECTION>
            <APPENDIX>
              <EAR>Pt. 60, Subpt. Ce, Table 1</EAR>

              <HD SOURCE="HED">Table 1 to Subpart Ce—Emission Limits for Small, Medium, and Large HMIWI<PRTPAGE P="102"/>
              </HD>
              <GPOTABLE CDEF="s50,r100,r50,r50,xs85" COLS="5" OPTS="L2">
                <BOXHD>
                  <CHED H="1">Pollutant</CHED>
                  <CHED H="1">Units (7 percent oxygen, dry basis)</CHED>
                  <CHED H="1">Emission limits</CHED>
                  <CHED H="2">HMIWI size</CHED>
                  <CHED H="3">Small</CHED>
                  <CHED H="3">Medium</CHED>
                  <CHED H="3">Large</CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">Particulate matter</ENT>
                  <ENT>Milligrams per dry standard cubic meter (grains per dry standard cubic foot)</ENT>
                  <ENT>115 (0.05)</ENT>
                  <ENT>69 (0.03)</ENT>
                  <ENT>34 (0.015).</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Carbon monoxide</ENT>
                  <ENT>Parts per million by volume</ENT>
                  <ENT>40</ENT>
                  <ENT>40</ENT>
                  <ENT>40.</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Dioxins/furans</ENT>
                  <ENT>Nanograms per dry standard cubic meter total dioxins/furans (grains per billion dry standard cubic feet) or nanograms per dry standard cubic meter TEQ (grains per billion dry standard cubic feet)</ENT>
                  <ENT>125 (55) or 2.3 (1.0)</ENT>
                  <ENT>125 (55) or 2.3 (1.0)</ENT>
                  <ENT>125 (55) or 2.3 (1.0).</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Hydrogen chloride</ENT>
                  <ENT>Parts per million by volume or percent reduction</ENT>
                  <ENT>100 or 93%</ENT>
                  <ENT>100 or 93%</ENT>
                  <ENT>100 or 93%.</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Sulfur dioxide</ENT>
                  <ENT>Parts per million by volume</ENT>
                  <ENT>55</ENT>
                  <ENT>55</ENT>
                  <ENT>55.</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Nitrogen oxides</ENT>
                  <ENT>Parts per million by volume</ENT>
                  <ENT>250</ENT>
                  <ENT>250</ENT>
                  <ENT>250.</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Lead</ENT>
                  <ENT>Milligrams per dry standard cubic meter (grains per thousand dry standard cubic feet) or percent reduction</ENT>
                  <ENT>1.2 (0.52) or 70%</ENT>
                  <ENT>1.2 (0.52) or 70%</ENT>
                  <ENT>1.2 (0.52) or 70%.</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Cadmium</ENT>
                  <ENT>Milligrams per dry standard cubic meter (grains per thousand dry standard cubic feet) or percent reduction</ENT>
                  <ENT>0.16 (0.07) or 65%</ENT>
                  <ENT>0.16 (0.07) or 65%.</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Mercury</ENT>
                  <ENT>Milligrams per dry standard cubic meter (grains per thousand dry standard cubic feet) or percent reduction</ENT>
                  <ENT>0.55 (0.24) or 85%</ENT>
                  <ENT>0.55 (0.24) or 85%</ENT>
                  <ENT>0.55 (0.24) or 85%.</ENT>
                </ROW>
              </GPOTABLE>
            </APPENDIX>
            <APPENDIX>
              <PRTPAGE P="103"/>
              <EAR>Pt. 60, Subpt. Ce, Table 2</EAR>
              <HD SOURCE="HED">Table 2 to Subpart Ce—Emissions Limits for Small HMIWI Which Meet the Criteria Under § 60.33e(b)</HD>
              <GPOTABLE CDEF="s50,r100,xs50" COLS="3" OPTS="L2">
                <BOXHD>
                  <CHED H="1">Pollutant</CHED>
                  <CHED H="1">Units (7 percent oxygen, dry basis)</CHED>
                  <CHED H="1">HMIWI emission limits</CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">Particulate matter</ENT>
                  <ENT>Milligrams per dry standard cubic meter (grains per dry standard cubic foot)</ENT>
                  <ENT>197 (0.086).</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Carbon monoxide</ENT>
                  <ENT>Parts per million by volume</ENT>
                  <ENT>40.</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Dioxins/furans</ENT>
                  <ENT>nanograms per dry standard cubic meter total dioxins/furans (grains per billion dry standard cubic feet) or nanograms per dry standard cubic meter TEQ (grains per billion dry standard cubic feet)</ENT>
                  <ENT>800 (350) or 15 (6.6).</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Hydrogen chloride</ENT>
                  <ENT>Parts per million by volume</ENT>
                  <ENT>3100.</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Sulfur dioxide</ENT>
                  <ENT>Parts per million by volume</ENT>
                  <ENT>55.</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Nitrogen oxides</ENT>
                  <ENT>Parts per million by volume</ENT>
                  <ENT>250.</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Lead</ENT>
                  <ENT>Milligrams per dry standard cubic meter (grains per thousand dry standard cubic feet)</ENT>
                  <ENT>10 (4.4).</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Cadmium</ENT>
                  <ENT>Milligrams per dry standard cubic meter (grains per thousand dry standard cubic feet)</ENT>
                  <ENT>4 (1.7).</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Mercury</ENT>
                  <ENT>Milligrams per dry standard cubic meter (grains per thousands dry standard cubic feet)</ENT>
                  <ENT>7.5 (3.3).</ENT>
                </ROW>
              </GPOTABLE>
            </APPENDIX>
          </SUBPART>
          <SUBPART>
            <HD SOURCE="HED">Subpart D—Standards of Performance for Fossil-Fuel-Fired Steam Generators for Which Construction is Commenced After August 17, 1971</HD>
            <SECTION>
              <SECTNO>§ 60.40</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <P>(a) The affected facilities to which the provisions of this subpart apply are:</P>
              <P>(1) Each fossil-fuel-fired steam generating unit of more than 73 megawatts heat input rate (250 million Btu per hour).</P>
              <P>(2) Each fossil-fuel and wood-residue-fired steam generating unit capable of firing fossil fuel at a heat input rate of more than 73 megawatts (250 million Btu per hour).</P>
              <P>(b) Any change to an existing fossil-fuel-fired steam generating unit to accommodate the use of combustible materials, other than fossil fuels as defined in this subpart, shall not bring that unit under the applicability of this subpart.</P>
              <P>(c) Except as provided in paragraph (d) of this section, any facility under paragraph (a) of this section that commenced construction or modification after August 17, 1971, is subject to the requirements of this subpart.</P>
              <P>(d) The requirements of §§ 60.44 (a)(4), (a)(5), (b) and (d), and 60.45(f)(4)(vi) are applicable to lignite-fired steam generating units that commenced construction or modification after December 22, 1976.</P>
              <P>(e) Any facility covered under subpart Da is not covered under this subpart.</P>
              <CITA>[42 FR 37936, July 25, 1977, as amended at 43 FR 9278, Mar. 7, 1978; 44 FR 33612, June 17, 1979]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.41</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <P>As used in this subpart, all terms not defined herein shall have the meaning given them in the Act, and in subpart A of this part.</P>
              <P>(a) <E T="03">Fossil-fuel fired steam generating unit</E> means a furnace or boiler used in the process of burning fossil fuel for the purpose of producing steam by heat transfer.</P>
              <P>(b) <E T="03">Fossil fuel</E> means natural gas, petroleum, coal, and any form of solid, liquid, or gaseous fuel derived from such materials for the purpose of creating useful heat.</P>
              <P>(c) <E T="03">Coal refuse</E> means waste-products of coal mining, cleaning, and coal preparation operations (e.g. culm, gob, etc.) containing coal, matrix material, clay, and other organic and inorganic material.</P>
              <P>(d) <E T="03">Fossil fuel and wood residue-fired steam generating unit</E> means a furnace or boiler used in the process of burning fossil fuel and wood residue for the purpose of producing steam by heat transfer.</P>
              <P>(e) <E T="03">Wood residue</E> means bark, sawdust, slabs, chips, shavings, mill trim, and other wood products derived from wood processing and forest management operations.<PRTPAGE P="104"/>
              </P>
              <P>(f) <E T="03">Coal</E> means all solid fuels classified as anthracite, bituminous, subbituminous, or lignite by ASTM D388-77, 90, 91, 95, or 98a (incorporated by reference—see §60.17).</P>
              <CITA>[39 FR 20791, June 14, 1974, as amended at 40 FR 2803, Jan. 16, 1975; 41 FR 51398, Nov. 22, 1976; 43 FR 9278, Mar. 7, 1978; 48 FR 3736, Jan. 27, 1983; 65 FR 61752, Oct. 17, 2000]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.42</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <P>(a) On and after the date on which the performance test required to be conducted by § 60.8 is completed, no owner or operator subject to the provisions of this subpart shall cause to be discharged into the atmosphere from any affected facility any gases which:</P>
              <P>(1) Contain particulate matter in excess of 43 nanograms per joule heat input (0.10 lb per million Btu) derived from fossil fuel or fossil fuel and wood residue.</P>
              <P>(2) Exhibit greater than 20 percent opacity except for one six-minute period per hour of not more than 27 percent opacity.</P>
              <P>(b)(1) On or after December 28, 1979, no owner or operator shall cause to be discharged into the atmosphere from the Southwestern Public Service Company's Harrington Station #1, in Amarillo, TX, any gases which exhibit greater than 35 percent opacity, except that a maximum or 42 percent opacity shall be permitted for not more than 6 minutes in any hour.</P>
              <P>(2) Interstate Power Company shall not cause to be discharged into the atmosphere from its Lansing Station Unit No. 4 in Lansing, IA, any gases which exhibit greater than 32 percent opacity, except that a maximum of 39 percent opacity shall be permitted for not more than six minutes in any hour.</P>
              <CITA>[39 FR 20792, June 14, 1974, as amended at 41 FR 51398, Nov. 22, 1976; 42 FR 61537, Dec. 5, 1977; 44 FR 76787, Dec. 28, 1979; 45 FR 36077, May 29, 1980; 45 FR 47146, July 14, 1980; 46 FR 57498, Nov. 24, 1981; 61 FR 49976, Sept. 24, 1996; 65 FR 61752, Oct. 17, 2000]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.43</SECTNO>
              <SUBJECT>Standard for sulfur dioxide.</SUBJECT>
              <P>(a) On and after the date on which the performance test required to be conducted by § 60.8 is completed, no owner or operator subject to the provisions of this subpart shall cause to be discharged into the atmosphere from any affected facility any gases which contain sulfur dioxide in excess of:</P>
              <P>(1) 340 nanograms per joule heat input (0.80 lb per million Btu) derived from liquid fossil fuel or liquid fossil fuel and wood residue.</P>
              <P>(2) 520 nanograms per joule heat input (1.2 lb per million Btu) derived from solid fossil fuel or solid fossil fuel and wood residue, except as provided in paragraph (e) of this section.</P>

              <P>(b) When different fossil fuels are burned simultaneously in any combination, the applicable standard (in ng/J) shall be determined by proration using the following formula:
              </P>
              <FP SOURCE="FP-1">PS<E T="52">SO2</E>=[<E T="03">y</E>(340) +<E T="03">z</E>(520)]/(<E T="03">y</E>+<E T="03">z</E>)</FP>
              
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">PS<E T="52">SO2</E> is the prorated standard for sulfur dioxide when burning different fuels simultaneously, in nanograms per joule heat input derived from all fossil fuels fired or from all fossil fuels and wood residue fired,</FP>
                <FP SOURCE="FP-1">
                  <E T="03">y</E> is the percentage of total heat input derived from liquid fossil fuel, and</FP>
                <FP SOURCE="FP-1">
                  <E T="03">z</E> is the percentage of total heat input derived from solid fossil fuel.</FP>
              </EXTRACT>
              
              <P>(c) Compliance shall be based on the total heat input from all fossil fuels burned, including gaseous fuels.</P>
              <P>(d) [Reserved]</P>
              <P>(e) Units 1 and 2 (as defined in appendix G) at the Newton Power Station owned or operated by the Central Illinois Public Service Company will be in compliance with paragraph (a)(2) of this section if Unit 1 and Unit 2 individually comply with paragraph (a)(2) of this section or if the combined emission rate from Units 1 and 2 does not exceed 470 nanograms per joule (1.1 lb per million Btu) combined heat input to Units 1 and 2.</P>
              <CITA>[39 FR 20792, June 14, 1974, as amended at 41 FR 51398, Nov. 22, 1976; 52 FR 28954, Aug. 4, 1987]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.44</SECTNO>
              <SUBJECT>Standard for nitrogen oxides.</SUBJECT>

              <P>(a) On and after the date on which the performance test required to be conducted by § 60.8 is completed, no owner or operator subject to the provisions of this subpart shall cause to be discharged into the atmosphere from any affected facility any gases which contain nitrogen oxides, expressed as NO<E T="52">2</E> in excess of:<PRTPAGE P="105"/>
              </P>
              <P>(1) 86 nanograms per joule heat input (0.20 lb per million Btu) derived from gaseous fossil fuel.</P>
              <P>(2) 129 nanograms per joule heat input (0.30 lb per million Btu) derived from liquid fossil fuel, liquid fossil fuel and wood residue, or gaseous fossil fuel and wood residue.</P>
              <P>(3) 300 nanograms per joule heat input (0.70 lb per million Btu) derived from solid fossil fuel or solid fossil fuel and wood residue (except lignite or a solid fossil fuel containing 25 percent, by weight, or more of coal refuse).</P>
              <P>(4) 260 nanograms per joule heat input (0.60 lb per million Btu) derived from lignite or lignite and wood residue (except as provided under paragraph (a)(5) of this section).</P>
              <P>(5) 340 nanograms per joule heat input (0.80 lb per million Btu) derived from lignite which is mined in North Dakota, South Dakota, or Montana and which is burned in a cyclone-fired unit.</P>
              <P>(b) Except as provided under paragraphs (c) and (d) of this section, when different fossil fuels are burned simultaneously in any combination, the applicable standard (in ng/J) is determined by proration using the following formula:</P>
              <GPH DEEP="20" SPAN="1">
                <GID>EC16NO91.000</GID>
              </GPH>
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">
                  <E T="03">PS</E>
                  <E T="52">NOx</E>=is the prorated standard for nitrogen oxides when burning different fuels simultaneously, in nanograms per joule heat input derived from all fossil fuels fired or from all fossil fuels and wood residue fired;</FP>
                <FP SOURCE="FP-1">
                  <E T="03">w=</E> is the percentage of total heat input derived from lignite;</FP>
                <FP SOURCE="FP-1">
                  <E T="03">x=</E> is the percentage of total heat input derived from gaseous fossil fuel;</FP>
                <FP SOURCE="FP-1">
                  <E T="03">y=</E> is the percentage of total heat input derived from liquid fossil fuel; and</FP>
                <FP SOURCE="FP-1">
                  <E T="03">z=</E> is the percentage of total heat input derived from solid fossil fuel (except lignite).</FP>
              </EXTRACT>
              
              <P>(c) When a fossil fuel containing at least 25 percent, by weight, of coal refuse is burned in combination with gaseous, liquid, or other solid fossil fuel or wood residue, the standard for nitrogen oxides does not apply.</P>
              <P>(d) Cyclone-fired units which burn fuels containing at least 25 percent of lignite that is mined in North Dakota, South Dakota, or Montana remain subject to paragraph (a)(5) of this section regardless of the types of fuel combusted in combination with that lignite.</P>
              <CITA>[39 FR 20792, June 14, 1974, as amended at 41 FR 51398, Nov. 22, 1976; 43 FR 9278, Mar. 7, 1978; 51 FR 42797, Nov. 25, 1986]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.45</SECTNO>
              <SUBJECT>Emission and fuel monitoring.</SUBJECT>
              <P>(a) Each owner or operator shall install, calibrate, maintain, and operate continuous monitoring systems for measuring the opacity of emissions, sulfur dioxide emissions, nitrogen oxides emissions, and either oxygen or carbon dioxide except as provided in paragraph (b) of this section.</P>
              <P>(b) Certain of the continuous monitoring system requirements under paragraph (a) of this section do not apply to owners or operators under the following conditions:</P>
              <P>(1) For a fossil fuel-fired steam generator that burns only gaseous fossil fuel, continuous monitoring systems for measuring the opacity of emissions and sulfur dioxide emissions are not required.</P>
              <P>(2) For a fossil fuel-fired steam generator that does not use a flue gas desulfurization device, a continuous monitoring system for measuring sulfur dioxide emissions is not required if the owner or operator monitors sulfur dioxide emissions by fuel sampling and analysis.</P>

              <P>(3) Notwithstanding § 60.13(b), installation of a continuous monitoring system for nitrogen oxides may be delayed until after the initial performance tests under § 60.8 have been conducted. If the owner or operator demonstrates during the performance test that emissions of nitrogen oxides are less than 70 percent of the applicable standards in § 60.44, a continuous monitoring system for measuring nitrogen oxides emissions is not required. If the initial performance test results show that nitrogen oxide emissions are greater than 70 percent of the applicable standard, the owner or operator shall install a continuous monitoring system for nitrogen oxides within one year after the date of the initial performance tests under § 60.8 and comply with all other applicable monitoring requirements under this part.<PRTPAGE P="106"/>
              </P>
              <P>(4) If an owner or operator does not install any continuous monitoring systems for sulfur oxides and nitrogen oxides, as provided under paragraphs (b)(1) and (b)(3) or paragraphs (b)(2) and (b)(3) of this section a continuous monitoring system for measuring either oxygen or carbon dioxide is not required.</P>
              <P>(c) For performance evaluations under § 60.13(c) and calibration checks under § 60.13(d), the following procedures shall be used:</P>
              <P>(1) Methods 6, 7, and 3B, as applicable, shall be used for the performance evaluations of sulfur dioxide and nitrogen oxides continuous monitoring systems. Acceptable alternative methods for Methods 6, 7, and 3B are given in § 60.46(d).</P>
              <P>(2) Sulfur dioxide or nitric oxide, as applicable, shall be used for preparing calibration gas mixtures under Performance Specification 2 of appendix B to this part.</P>
              <P>(3) For affected facilities burning fossil fuel(s), the span value for a continuous monitoring system measuring the opacity of emissions shall be 80, 90, or 100 percent and for a continuous monitoring system measuring sulfur oxides or nitrogen oxides the span value shall be determined as follows:</P>
              <GPOTABLE CDEF="s25,13,17" COLS="3" OPTS="L2">
                <TDESC>[In parts per million]</TDESC>
                <BOXHD>
                  <CHED H="1">Fossil fuel</CHED>
                  <CHED H="1">Span value for sulfur dioxide</CHED>
                  <CHED H="1">Span value for nitrogen oxides</CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">Gas</ENT>
                  <ENT>(<SU>1</SU> )</ENT>
                  <ENT>500</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Liquid</ENT>
                  <ENT>1,000</ENT>
                  <ENT>500</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Solid</ENT>
                  <ENT>1,500</ENT>
                  <ENT>1000</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Combinations</ENT>
                  <ENT>1,000<E T="03">y</E>+1,500<E T="03">z</E>
                  </ENT>
                  <ENT>500(<E T="03">x</E>+<E T="03">y</E> )+1,000<E T="03">z</E>
                  </ENT>
                </ROW>
                <TNOTE>
                  <SU>1</SU> Not applicable.</TNOTE>
              </GPOTABLE>
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">x=the fraction of total heat input derived from gaseous fossil fuel, and</FP>
                <FP SOURCE="FP-1">y=the fraction of total heat input derived from liquid fossil fuel, and</FP>
                <FP SOURCE="FP-1">z=the fraction of total heat input derived from solid fossil fuel.</FP>
              </EXTRACT>
              
              <P>(4) All span values computed under paragraph (c)(3) of this section for burning combinations of fossil fuels shall be rounded to the nearest 500 ppm.</P>
              <P>(5) For a fossil fuel-fired steam generator that simultaneously burns fossil fuel and nonfossil fuel, the span value of all continuous monitoring systems shall be subject to the Administrator's approval.</P>
              <P>(d) [Reserved]</P>
              <P>(e) For any continuous monitoring system installed under paragraph (a) of this section, the following conversion procedures shall be used to convert the continuous monitoring data into units of the applicable standards (ng/J, lb/million Btu):</P>

              <P>(1) When a continuous monitoring system for measuring oxygen is selected, the measurement of the pollutant concentration and oxygen concentration shall each be on a consistent basis (wet or dry). Alternative procedures approved by the Administrator shall be used when measurements are on a wet basis. When measurements are on a dry basis, the following conversion procedure shall be used:
              </P>
              <FP SOURCE="FP-1">
                <E T="03">E=CF</E>[20.9/(20.9—percent O<E T="52">2</E>)]</FP>
              
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">E, C, F, and %O<E T="52">2</E> are determined under paragraph (f) of this section.</FP>
              </EXTRACT>
              

              <P>(2) When a continuous monitoring system for measuring carbon dioxide is selected, the measurement of the pollutant concentration and carbon dioxide concentration shall each be on a consistent basis (wet or dry) and the following conversion procedure shall be used:
              </P>
              <FP SOURCE="FP-1">
                <E T="03">E=CF</E>
                <E T="52">c</E> [100/percent CO<E T="52">2</E>]</FP>
              
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">E, C, F<E T="52">c</E> and %CO<E T="52">2</E> are determined under paragraph (f) of this section.</FP>
              </EXTRACT>
              
              <P>(f) The values used in the equations under paragraphs (e) (1) and (2) of this section are derived as follows:</P>
              <P>(1) <E T="03">E</E>=pollutant emissions, ng/J (lb/million Btu).</P>
              <P>(2) <E T="03">C</E>=pollutant concentration, ng/dscm (lb/dscf), determined by multiplying the average concentration (ppm) for each one-hour period by 4.15×10 <E T="51">4</E> M ng/dscm per ppm (2.59×10 <E T="51">−9</E> M lb/dscf per ppm) where <E T="03">M</E>=pollutant molecular weight, g/g-mole (lb/lb-mole). <E T="03">M</E>=64.07 for sulfur dioxide and 46.01 for nitrogen oxides.</P>
              <P>(3) %O<E T="52">2</E>, %CO<E T="52">2</E>=oxygen or carbon dioxide volume (expressed as percent), determined with equipment specified under paragraph (a) of this section.</P>
              <P>(4) F, F<E T="52">c</E>=a factor representing a ratio of the volume of dry flue gases generated to the calorific value of the fuel <PRTPAGE P="107"/>combusted (F), and a factor representing a ratio of the volume of carbon dioxide generated to the calorific value of the fuel combusted (F<E T="52">c</E>), respectively. Values of F and F<E T="52">c</E> are given as follows:</P>

              <P>(i) For anthracite coal as classified according to ASTM D388-77, 90, 91, 95, or 98a (incorporated by reference—see § 60.17), F=2,723×10<E T="51">−17</E> dscm/J (10,140 dscf/million Btu and F<E T="52">c</E>=0.532×10 <E T="51">−17</E> scm CO<E T="52">2</E>/J (1,980 scf CO<E T="52">2</E>/million Btu).</P>

              <P>(ii) For subbituminous and bituminous coal as classified according to ASTM D388-77, 90, 91, 95, or 98a (incorporated by reference—see § 60.17), F=2.637×10 <E T="51">−7</E> dscm/J (9,820 dscf/million Btu) and F<E T="52">c</E>=0.486×10<E T="51">−7</E> scm CO<E T="52">2</E>/J (1,810 scf CO<E T="52">2</E>/million Btu).</P>

              <P>(iii) For liquid fossil fuels including crude, residual, and distillate oils, <E T="03">F</E>=2.476×10<E T="51">−7</E> dscm/J (9,220 dscf/million Btu) and <E T="03">F</E>
                <E T="24">c</E>=0.384×10<E T="51">−7</E> scm <E T="03">CO</E>
                <E T="52">2</E>/J (1,430 scf <E T="03">CO</E>
                <E T="52">2</E>/million Btu).</P>
              <P>(iv) For gaseous fossil fuels, <E T="03">F</E>=2.347×10 <E T="51">−7</E> dscm/J (8,740 dscf/million Btu). For natural gas, propane, and butane fuels, <E T="03">F</E>
                <E T="24">c</E>=0.279×10 <E T="51">−7</E> scm <E T="03">CO</E>
                <E T="52">2</E>/<E T="03">J</E> (1,040 scf <E T="03">CO</E>
                <E T="52">2</E>/million Btu) for natural gas, 0.322×10 <E T="51">−7</E> scm <E T="03">CO</E>
                <E T="52">2</E>/<E T="03">J</E> (1,200 scf <E T="03">CO</E>
                <E T="52">2</E>/million Btu) for propane, and 0.338×10 <E T="51">−7</E> scm <E T="03">CO</E>
                <E T="52">2</E>/<E T="03">J</E> (1,260 scf <E T="03">CO</E>
                <E T="52">2</E>/million Btu) for butane.</P>
              <P>(v) For bark F=2.589×10<E T="51">−7</E> dscm/J (9,640 dscf/million Btu) and F<E T="52">c</E>=0.500×10<E T="51">−7</E> scm CO<E T="52">2</E>/J (1,840 scf CO<E T="52"> 2</E>/ million Btu). For wood residue other than bark F=2.492×10<E T="51">−7</E> dscm/J (9,280 dscf/million Btu) and F<E T="52">c</E>=0.494×10<E T="51">−7</E> scm CO<E T="52">2</E>/J (1,860 scf CO<E T="52"> 2</E>/ million Btu).</P>

              <P>(vi) For lignite coal as classified according to ASTM D388-77, 90, 91, 95, or 98a (incorporated by reference—see § 60.17), F=2.659×10<E T="51">−7</E> dscm/J (9,900 dscf/million Btu) and F<E T="52">c</E>=0.516×10 <E T="51">−7</E> scm CO<E T="52">2</E>/J (1,920 scf CO<E T="52">2</E>/million Btu).</P>

              <P>(5) The owner or operator may use the following equation to determine an <E T="03">F</E> factor (dscm/J or dscf/million Btu) on a dry basis (if it is desired to calculate <E T="03">F</E> on a wet basis, consult the Administrator) or <E T="03">F</E>
                <E T="24">c</E> factor (scm <E T="03">CO</E>
                <E T="52">2</E>/<E T="03">J</E>, or scf <E T="03">CO</E>
                <E T="52">2</E>/million Btu) on either basis in lieu of the <E T="03">F</E> or <E T="03">F</E>
                <E T="24">c</E> factors specified in paragraph (f)(4) of this section:</P>
              <GPH DEEP="151" SPAN="2">
                <GID>EC16NO91.001</GID>
              </GPH>
              <P>(i) H, C, S, N, and O are content by weight of hydrogen, carbon, sulfur, nitrogen, and oxygen (expressed as percent), respectively, as determined on the same basis as GCV by ultimate analysis of the fuel fired, using ASTM D3178-73 (Reapproved 1979), 89, or D3176-74 or 89 (solid fuels) or computed from results using ASTM D1137-53 or 75, D1945-64, 76, 91, or 96 or D1946-77 or 90 (Reapproved 1994) (gaseous fuels) as applicable. (These five methods are incorporated by reference—see § 60.17.)</P>

              <P>(ii) GVC is the gross calorific value (kJ/kg, Btu/lb) of the fuel combusted determined by the ASTM test methods D2015-77 for solid fuels and D1826-77 for gaseous fuels as applicable. (These two methods are incorporated by reference—see § 60.17.)<PRTPAGE P="108"/>
              </P>

              <P>(iii) For affected facilities which fire both fossil fuels and nonfossil fuels, the <E T="03">F</E> or <E T="03">F</E>
                <E T="24">c</E> value shall be subject to the Administrator's approval.</P>

              <P>(6) For affected facilities firing combinations of fossil fuels or fossil fuels and wood residue, the <E T="03">F</E> or <E T="03">F</E>
                <E T="24">c</E> factors determined by paragraphs (f)(4) or (f)(5) of this section shall be prorated in accordance with the applicable formula as follows:</P>
              <GPH DEEP="29" SPAN="1">
                <GID>EC16NO91.002</GID>
              </GPH>
              <EXTRACT>
                <FP>where:</FP>
                <FP SOURCE="FP-1">
                  <E T="03">X</E>
                  <E T="24">i</E>=the fraction of total heat input derived from each type of fuel (e.g. natural gas, bituminous coal, wood residue, etc.)</FP>
                <FP SOURCE="FP-1">
                  <E T="03">F</E>
                  <E T="24">i</E> or (<E T="03">F</E>
                  <E T="24">c</E>)<E T="24">i</E>=the applicable <E T="03">F</E> or <E T="03">F</E>
                  <E T="24">c</E> factor for each fuel type determined in accordance with paragraphs (f)(4) and (f)(5) of this section.</FP>
                <FP SOURCE="FP-1">
                  <E T="03">n</E>=the number of fuels being burned in combination.</FP>
              </EXTRACT>
              
              <P>(g) Excess emission and monitoring system performance reports shall be submitted to the Administrator semiannually for each six-month period in the calendar year. All semiannual reports shall be postmarked by the 30th day following the end of each six-month period. Each excess emission and MSP report shall include the information required in § 60.7(c). Periods of excess emissions and monitoring systems (MS) downtime that shall be reported are defined as follows:</P>
              <P>(1) <E T="03">Opacity.</E> Excess emissions are defined as any six-minute period during which the average opacity of emissions exceeds 20 percent opacity, except that one six-minute average per hour of up to 27 percent opacity need not be reported.</P>
              <P>(i) For sources subject to the opacity standard of § 60.42(b)(1), excess emissions are defined as any six-minute period during which the average opacity of emissions exceeds 35 percent opacity, except that one six-minute average per hour of up to 42 percent opacity need not be reported.</P>
              <P>(ii) For sources subject to the opacity standard of § 60.42(b)(2), excess emissions are defined as any six-minute period during which the average opacity of emissions exceeds 32 percent opacity, except that one six-minute average per hour of up to 39 percent opacity need not be reported.</P>
              <P>(2) <E T="03">Sulfur dioxide.</E> Excess emissions for affected facilities are defined as:</P>
              <P>(i) Any three-hour period during which the average emissions (arithmetic average of three contiguous one-hour periods) of sulfur dioxide as measured by a continuous monitoring system exceed the applicable standard under § 60.43.</P>
              <P>(3) <E T="03">Nitrogen oxides.</E> Excess emissions for affected facilities using a continuous monitoring system for measuring nitrogen oxides are defined as any three-hour period during which the average emissions (arithmetic average of three contiguous one-hour periods) exceed the applicable standards under § 60.44.</P>
              <CITA>[40 FR 46256, Oct. 6, 1975]</CITA>
              <EDNOTE>
                <HD SOURCE="HED">Editorial Note 1:</HD>
                <P>For <E T="04">Federal Register</E> citations affecting § 60.45, see the List of CFR Sections Affected, which appears in the Finding Aids section of the printed volume and on GPO Access.</P>
              </EDNOTE>
              <EDNOTE>
                <HD SOURCE="HED">Editorial Note 2:</HD>
                <P>At 65 FR 61752, Oct. 17, 2000, § 60.45(f)(5)(ii) was amended by revising the words “ASTM D1826-77” to read “ASTM D1826-77 or 94.”and by revising the words “ASTM D2015-77” to read “ASTM D2015-77 (Reapproved 1978), 96, or D5865-98.” However, this amendment could not be incorporated because these words do not exist in paragraph (f)(5)(ii).</P>
              </EDNOTE>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.46</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <P>(a) In conducting the performance tests required in § 60.8, the owner or operator shall use as reference methods and procedures the test methods in appendix A of this part or other methods and procedures as specified in this section, except as provided in § 60.8(b). Acceptable alternative methods and procedures are given in paragraph (d) of this section.</P>

              <P>(b) The owner or operator shall determine compliance with the particulate matter, SO<E T="52">2</E>, and NO<E T="52">X</E> standards in §§ 60.42, 60.43, and 60.44 as follows:</P>
              <P>(1) The emission rate (E) of particulate matter, SO<E T="52">2</E>, or NO<E T="52">X</E> shall be computed for each run using the following equation:
              </P>
              <FP SOURCE="FP-1">E=C F<E T="52">d</E> (20.9)/(20.9-% 0<E T="52">2</E>)</FP>
              
              <EXTRACT>

                <FP SOURCE="FP-1">E = emission rate of pollutant, ng/J (1b/million Btu).<PRTPAGE P="109"/>
                </FP>
                <FP SOURCE="FP-1">C = concentration of pollutant, ng/dscm (1b/dscf).</FP>
                <FP SOURCE="FP-1">%O<E T="52">2</E> = oxygen concentration, percent dry basis.</FP>
                <FP SOURCE="FP-1">F<E T="52">d</E> = factor as determined from Method 19.</FP>
              </EXTRACT>
              
              <P>(2) Method 5 shall be used to determine the particular matter concentration (C) at affected facilities without wet flue-gas-desulfurization (FGD) systems and Method 5B shall be used to determine the particulate matter concentration (C) after FGD systems.</P>
              <P>(i) The sampling time and sample volume for each run shall be at least 60 minutes and 0.85 dscm (30 dscf). The probe and filter holder heating systems in the sampling train shall be set to provide an average gas temperature of 160±14 °C (320±25 °F).</P>

              <P>(ii) The emission rate correction factor, integrated or grab sampling and analysis procedure of Method 3B shall be used to determine the O<E T="52">2</E> concentration (%O<E T="52">2</E>). The O<E T="52">2</E> sample shall be obtained simultaneously with, and at the same traverse points as, the particulate sample. If the grab sampling procedure is used, the O<E T="52">2</E> concentration for the run shall be the arithmetic mean of the sample O<E T="52">2</E> concentrations at all traverse points.</P>

              <P>(iii) If the particulate run has more than 12 traverse points, the O<E T="52">2</E> traverse points may be reduced to 12 provided that Method 1 is used to locate the 12 O<E T="52">2</E> traverse points.</P>
              <P>(3) Method 9 and the procedures in § 60.11 shall be used to determine opacity.</P>
              <P>(4) Method 6 shall be used to determine the SO<E T="52">2</E> concentration.</P>
              <P>(i) The sampling site shall be the same as that selected for the particulate sample. The sampling location in the duct shall be at the centroid of the cross section or at a point no closer to the walls than 1 m (3.28 ft). The sampling time and sample volume for each sample run shall be at least 20 minutes and 0.020 dscm (0.71 dscf). Two samples shall be taken during a 1-hour period, with each sample taken within a 30-minute interval.</P>

              <P>(ii) The emission rate correction factor, integrated sampling and analysis procedure of Method 3B shall be used to determine the O<E T="52">2</E> concentration (%O<E T="52">2</E>). The O<E T="52">2</E> sample shall be taken simultaneously with, and at the same point as, the SO<E T="52">2</E> sample. The SO<E T="52">2</E> emission rate shall be computed for each pair of SO<E T="52">2</E> and O<E T="52">2</E> samples. The SO<E T="52">2</E> emission rate (E) for each run shall be the arithmetic mean of the results of the two pairs of samples.</P>
              <P>(5) Method 7 shall be used to determine the NO<E T="52">X</E> concentration.</P>

              <P>(i) The sampling site and location shall be the same as for the SO<E T="52">2</E> sample. Each run shall consist of four grab samples, with each sample taken at about 15-minute intervals.</P>
              <P>(ii) For each NO<E T="52">X</E> sample, the emission rate correction factor, grab sampling and analysis procedure of Method 3B shall be used to determine the O<E T="52">2</E> concentration (%O<E T="52">2</E>). The sample shall be taken simultaneously with, and at the same point as, the NO<E T="52">X</E> sample.</P>
              <P>(iii) The NO<E T="52">X</E> emission rate shall be computed for each pair of NO<E T="52">X</E> and O<E T="52">2</E> samples. The NO<E T="52">X</E> emission rate (E) for each run shall be the arithmetic mean of the results of the four pairs of samples.</P>
              <P>(c) When combinations of fossil fuels or fossil fuel and wood residue are fired, the owner or operator (in order to compute the prorated standard as shown in §§ 60.43(b) and 60.44(b)) shall determine the percentage (w, x, y, or z) of the total heat input derived from each type of fuel as follows:</P>
              <P>(1) The heat input rate of each fuel shall be determined by multiplying the gross calorific value of each fuel fired by the rate of each fuel burned.</P>
              <P>(2) ASTM Methods D2015-77 (Reapproved 1978), 96, or D5865-98 (solid fuels), D240-76 or 92 (liquid fuels), or D1826-77 or 94 (gaseous fuels) (incorporated by reference—see § 60.17) shall be used to determine the gross calorific values of the fuels. The method used to determine the calorific value of wood residue must be approved by the Administrator.</P>
              <P>(3) Suitable methods shall be used to determine the rate of each fuel burned during each test period, and a material balance over the steam generating system shall be used to confirm the rate.</P>

              <P>(d) The owner or operator may use the following as alternatives to the reference methods and procedures in this section or in other sections as specified:<PRTPAGE P="110"/>
              </P>
              <P>(1) The emission rate (E) of particulate matter, SO<E T="52">2</E> and NO<E T="52">X</E> may be determined by using the F<E T="52">c</E> factor, provided that the following procedure is used:</P>

              <P>(i) The emission rate (E) shall be computed using the following equation:
              </P>
              <FP SOURCE="FP-1">E=C F<E T="52">c</E> (100/%CO<E T="52">2</E>)</FP>
              
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">E=emission rate of pollutant, ng/J (lb/million Btu).</FP>
                <FP SOURCE="FP-1">C=concentration of pollutant, ng/dscm (lb/dscf).</FP>
                <FP SOURCE="FP-1">%CO<E T="52">2</E>=carbon dioxide concentration, percent dry basis.</FP>
                <FP SOURCE="FP-1">F<E T="52">c</E>=factor as determined in appropriate sections of Method 19.</FP>
              </EXTRACT>
              
              <P>(ii) If and only if the average F<E T="52">c</E> factor in Method 19 is used to calculate E and either E is from 0.97 to 1.00 of the emission standard or the relative accuracy of a continuous emission monitoring system is from 17 to 20 percent, then three runs of Method 3B shall be used to determine the O<E T="52">2</E> and CO<E T="52">2</E> concentration according to the procedures in paragraph (b) (2)(ii), (4)(ii), or (5)(ii) of this section. Then if F<E T="52">o</E> (average of three runs), as calculated from the equation in Method 3B, is more than ±3 percent than the average F<E T="52">o</E> value, as determined from the average values of F<E T="52">d</E> and F<E T="52">c</E> in Method 19, i.e., F<E T="52">oa</E>=0.209 (F<E T="52">da</E>/F<E T="52">ca</E>), then the following procedure shall be followed:</P>
              <P>(A) When F<E T="52">o</E> is less than 0.97 F<E T="52">oa</E>, then E shall be increased by that proportion under 0.97 F<E T="52">oa</E>, e.g., if F<E T="52">o</E> is 0.95 F<E T="52">oa</E>, E shall be increased by 2 percent. This recalculated value shall be used to determine compliance with the emission standard.</P>
              <P>(B) When F<E T="52">o</E> is less than 0.97 F<E T="52">oa</E> and when the average difference (d<AC T="8"/>) between the continuous monitor minus the reference methods is negative, then E shall be increased by that proportion under 0.97 F<E T="52">oa</E>, e.g., if F<E T="52">o</E> is 0.95 F<E T="52">oa</E>, E shall be increased by 2 percent. This recalculated value shall be used to determine compliance with the relative accuracy specification.</P>
              <P>(C) When F<E T="52">o</E> is greater than 1.03 F<E T="52">oa</E> and when the average difference d<AC T="8"/> is positive, then E shall be decreased by that proportion over 1.03 F<E T="52">oa</E>, e.g., if F<E T="52">o</E> is 1.05 F<E T="52">oa</E>, E shall be decreased by 2 percent. This recalculated value shall be used to determine compliance with the relative accuracy specification.</P>
              <P>(2) For Method 5 or 5B, Method 17 may be used at facilities with or without wet FGD systems if the stack gas temperature at the sampling location does not exceed an average temperature of 160 °C (320 °F). The procedures of sections 2.1 and 2.3 of Method 5B may be used with Method 17 only if it is used after wet FGD systems. Method 17 shall not be used after wet FGD systems if the effluent gas is saturated or laden with water droplets.</P>
              <P>(3) Particulate matter and SO<E T="52">2</E> may be determined simultaneously with the Method 5 train provided that the following changes are made:</P>
              <P>(i) The filter and impinger apparatus in sections 2.1.5 and 2.1.6 of Method 8 is used in place of the condenser (section 2.1.7) of Method 5.</P>

              <P>(ii) All applicable procedures in Method 8 for the determination of SO<E T="52">2</E> (including moisture) are used:</P>

              <P>(4) For Method 6, Method 6C may be used. Method 6A may also be used whenever Methods 6 and 3B data are specified to determine the SO<E T="52">2</E> emission rate, under the conditions in paragraph (d)(1) of this section.</P>

              <P>(5) For Method 7, Method 7A, 7C, 7D, or 7E may be used. If Method 7C, 7D, or 7E is used, the sampling time for each run shall be at least 1 hour and the integrated sampling approach shall be used to determine the O<E T="52">2</E> concentration (%O<E T="52">2</E>) for the emission rate correction factor.</P>
              <P>(6) For Method 3, Method 3A or 3B may be used.</P>
              <P>(7) For Method 3B, Method 3A may be used.</P>
              <CITA>[54 FR 6662, Feb. 14, 1989; 54 FR 21344, May 17, 1989, as amended at 55 FR 5212, Feb. 14, 1990; 65 FR 61752, Oct. 17, 2000]</CITA>
            </SECTION>
          </SUBPART>
          <SUBPART>
            <HD SOURCE="HED">Subpart Da—Standards of Performance for Electric Utility Steam Generating Units for Which Construction is Commenced After September 18, 1978</HD>
            <SOURCE>
              <HD SOURCE="HED">Source:</HD>
              <P>44 FR 33613, June 11, 1979, unless otherwise noted.</P>
            </SOURCE>
            <SECTION>
              <PRTPAGE P="111"/>
              <SECTNO>§ 60.40a</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <P>(a) The affected facility to which this subpart applies is each electric utility steam generating unit:</P>
              <P>(1) That is capable of combusting more than 73 megawatts (250 million Btu/hour) heat input of fossil fuel (either alone or in combination with any other fuel); and</P>
              <P>(2) For which construction or modification is commenced after September 18, 1978.</P>
              <P>(b) Unless and until subpart GG of this part extends the applicability of subpart GG of this part to electric utility steam generators, this subpart applies to electric utility combined cycle gas turbines that are capable of combusting more than 73 megawatts (250 million Btu/hour) heat input of fossil fuel in the steam generator. Only emissions resulting from combustion of fuels in the steam generating unit are subject to this subpart. (The gas turbine emissions are subject to subpart GG of this part.)</P>
              <P>(c) Any change to an existing fossil-fuel-fired steam generating unit to accommodate the use of combustible materials, other than fossil fuels, shall not bring that unit under the applicability of this subpart.</P>
              <P>(d) Any change to an existing steam generating unit originally designed to fire gaseous or liquid fossil fuels, to accommodate the use of any other fuel (fossil or nonfossil) shall not bring that unit under the applicability of this subpart.</P>
              <CITA>[44 FR 33613, June 11, 1979, as amended at 63 FR 49453, Sept. 16, 1998]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.41a</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <P>As used in this subpart, all terms not defined herein shall have the meaning given them in the Act and in subpart A of this part.</P>
              <P>
                <E T="03">Anthracite</E> means coal that is classified as anthracite according to the American Society of Testing and Materials' (ASTM) Standard Specification for Classification of Coals by Rank D388-77 (incorporated by reference—see §60.17).</P>
              <P>
                <E T="03">Available purchase power</E> means the lesser of the following:</P>
              <P>(a) The sum of available system capacity in all neighboring companies.</P>
              <P>(b) The sum of the rated capacities of the power interconnection devices between the principal company and all neighboring companies, minus the sum of the electric power load on these interconnections.</P>
              <P>(c) The rated capacity of the power transmission lines between the power interconnection devices and the electric generating units (the unit in the principal company that has the malfunctioning flue gas desulfurization system and the unit(s) in the neighboring company supplying replacement electrical power) less the electric power load on these transmission lines.</P>
              <P>
                <E T="03">Available system capacity</E> means the capacity determined by subtracting the system load and the system emergency reserves from the net system capacity.</P>
              <P>
                <E T="03">Boiler operating day</E> means a 24-hour period during which fossil fuel is combusted in a steam generating unit for the entire 24 hours.</P>
              <P>
                <E T="03">Coal refuse</E> means waste products of coal mining, physical coal cleaning, and coal preparation operations (e.g. culm, gob, etc.) containing coal, matrix material, clay, and other organic and inorganic material.</P>
              <P>
                <E T="03">Combined cycle gas turbine</E> means a stationary turbine combustion system where heat from the turbine exhaust gases is recovered by a steam generating unit.</P>
              <P>
                <E T="03">Duct burner</E> means a device that combusts fuel and that is placed in the exhaust duct from another source, such as a stationary gas turbine, internal combustion engine, kiln, etc., to allow the firing of additional fuel to heat the exhaust gases before the exhaust gases enter a heat recovery steam generating unit.</P>
              <P>
                <E T="03">Electric utility combined cycle gas turbine</E> means any combined cycle gas turbine used for electric generation that is constructed for the purpose of supplying more than one-third of its potential electric output capacity and more than 25 MW electrical output to any utility power distribution system for sale. Any steam distribution system that is constructed for the purpose of providing steam to a steam electric generator that would produce electrical power for sale is also considered <PRTPAGE P="112"/>in determining the electrical energy output capacity of the affected facility.</P>
              <P>
                <E T="03">Electric utility company</E> means the largest interconnected organization, business, or governmental entity that generates electric power for sale (e.g., a holding company with operating subsidiary companies).</P>
              <P>
                <E T="03">Electric utility steam generating unit</E> means any steam electric generating unit that is constructed for the purpose of supplying more than one-third of its potential electric output capacity and more than 25 MW electrical output to any utility power distribution system for sale. Any steam supplied to a steam distribution system for the purpose of providing steam to a steam-electric generator that would produce electrical energy for sale is also considered in determining the electrical energy output capacity of the affected facility.</P>
              <P>
                <E T="03">Emergency condition</E> means that period of time when:</P>
              <P>(a) The electric generation output of an affected facility with a malfunctioning flue gas desulfurization system cannot be reduced or electrical output must be increased because:</P>
              <P>(1) All available system capacity in the principal company interconnected with the affected facility is being operated, and</P>
              <P>(2) All available purchase power interconnected with the affected facility is being obtained, or</P>
              <P>(b) The electric generation demand is being shifted as quickly as possible from an affected facility with a malfunctioning flue gas desulfurization system to one or more electrical generating units held in reserve by the principal company or by a neighboring company, or</P>
              <P>(c) An affected facility with a malfunctioning flue gas desulfurization system becomes the only available unit to maintain a part or all of the principal company's system emergency reserves and the unit is operated in spinning reserve at the lowest practical electric generation load consistent with not causing significant physical damage to the unit. If the unit is operated at a higher load to meet load demand, an emergency condition would not exist unless the conditions under (a) of this definition apply.</P>
              <P>
                <E T="03">Fossil fuel</E> means natural gas, petroleum, coal, and any form of solid, liquid, or gaseous fuel derived from such material for the purpose of creating useful heat.</P>
              <P>
                <E T="03">Gross output</E> means the gross useful work performed by the steam generated. For units generating only electricity, the gross useful work performed is the gross electrical output from the turbine/generator set. For cogeneration units, the gross useful work performed is the gross electrical output plus one half the useful thermal output (i.e., steam delivered to an industrial process).</P>
              <P>
                <E T="03">24-hour period</E> means the period of time between 12:01 a.m. and 12:00 midnight.</P>
              <P>
                <E T="03">Interconnected</E> means that two or more electric generating units are electrically tied together by a network of power transmission lines, and other power transmission equipment.</P>
              <P>
                <E T="03">Lignite</E> means coal that is classified as lignite A or B according to the American Society of Testing and Materials' (ASTM) Standard Specification for Classification of Coals by Rank D388-77, 90, 91, 95, or 98a (incorporated by reference—see §60.17).</P>
              <P>
                <E T="03">Neighboring company</E> means any one of those electric utility companies with one or more electric power interconnections to the principal company and which have geographically adjoining service areas.</P>
              <P>
                <E T="03">Net system capacity</E> means the sum of the net electric generating capability (not necessarily equal to rated capacity) of all electric generating equipment owned by an electric utility company (including steam generating units, internal combustion engines, gas turbines, nuclear units, hydroelectric units, and all other electric generating equipment) plus firm contractual purchases that are interconnected to the affected facility that has the malfunctioning flue gas desulfurization system. The electric generating capability of equipment under multiple ownership is prorated based on ownership unless the proportional entitlement to electric output is otherwise established by contractual arrangement.</P>
              <P>
                <E T="03">Noncontinental area</E> means the State of Hawaii, the Virgin Islands, Guam, American Samoa, the Commonwealth <PRTPAGE P="113"/>of Puerto Rico, or the Northern Mariana Islands.</P>
              <P>
                <E T="03">Potential combustion concentration</E> means the theoretical emissions (ng/J, lb/million Btu heat input) that would result from combustion of a fuel in an uncleaned state without emission control systems) and:</P>
              <P>(a) For particulate matter is:</P>
              <P>(1) 3,000 ng/J (7.0 lb/million Btu) heat input for solid fuel; and</P>
              <P>(2) 73 ng/J (0.17 lb/million Btu) heat input for liquid fuels.</P>
              <P>(b) For sulfur dioxide is determined under § 60.48a(b).</P>
              <P>(c) For nitrogen oxides is:</P>
              <P>(1) 290 ng/J (0.67 lb/million Btu) heat input for gaseous fuels;</P>
              <P>(2) 310 ng/J (0.72 lb/million Btu) heat input for liquid fuels; and</P>
              <P>(3) 990 ng/J (2.30 lb/million Btu) heat input for solid fuels.</P>
              <P>
                <E T="03">Potential electrical output capacity</E> is defined as 33 percent of the maximum design heat input capacity of the steam generating unit (e.g., a steam generating unit with a 100-MW (340 million Btu/hr) fossil-fuel heat input capacity would have a 33-MW potential electrical output capacity). For electric utility combined cycle gas turbines the potential electrical output capacity is determined on the basis of the fossil-fuel firing capacity of the steam generator exclusive of the heat input and electrical power contribution by the gas turbine.</P>
              <P>
                <E T="03">Principal company</E> means the electric utility company or companies which own the affected facility.</P>
              <P>
                <E T="03">Resource recovery unit</E> means a facility that combusts more than 75 percent non-fossil fuel on a quarterly (calendar) heat input basis.</P>
              <P>
                <E T="03">Solid-derived fuel</E> means any solid, liquid, or gaseous fuel derived from solid fuel for the purpose of creating useful heat and includes, but is not limited to, solvent refined coal, liquified coal, and gasified coal.</P>
              <P>
                <E T="03">Spare flue gas desulfurization system module</E> means a separate system of sulfur dioxide emission control equipment capable of treating an amount of flue gas equal to the total amount of flue gas generated by an affected facility when operated at maximum capacity divided by the total number of nonspare flue gas desulfurization modules in the system.</P>
              <P>
                <E T="03">Spinning reserve</E> means the sum of the unutilized net generating capability of all units of the electric utility company that are synchronized to the power distribution system and that are capable of immediately accepting additional load. The electric generating capability of equipment under multiple ownership is prorated based on ownership unless the proportional entitlement to electric output is otherwise established by contractual arrangement.</P>
              <P>
                <E T="03">Steam generating unit</E> means any furnace, boiler, or other device used for combusting fuel for the purpose of producing steam (including fossil-fuel-fired steam generators associated with combined cycle gas turbines; nuclear steam generators are not included).</P>
              <P>
                <E T="03">Subbituminous coal</E> means coal that is classified as subbituminous A, B, or C according to the American Society of Testing and Materials (ASTM) Standard Specification for Classification of Coals by Rank D388-77, 90, 91, 95, or 98a (incorporated by reference—see §60.17).</P>
              <P>
                <E T="03">System emergency reserves</E> means an amount of electric generating capacity equivalent to the rated capacity of the single largest electric generating unit in the electric utility company (including steam generating units, internal combustion engines, gas turbines, nuclear units, hydroelectric units, and all other electric generating equipment) which is interconnected with the affected facility that has the malfunctioning flue gas desulfurization system. The electric generating capability of equipment under multiple ownership is prorated based on ownership unless the proportional entitlement to electric output is otherwise established by contractual arrangement.</P>
              <P>
                <E T="03">System load</E> means the entire electric demand of an electric utility company's service area interconnected with the affected facility that has the malfunctioning flue gas desulfurization system plus firm contractual sales to other electric utility companies. Sales to other electric utility companies (e.g., emergency power) not on a firm contractual basis may also be included in the system load when no available system capacity exists in the electric <PRTPAGE P="114"/>utility company to which the power is supplied for sale.</P>
              <CITA>[44 FR 33613, June 11, 1979, as amended at 48 FR 3737, Jan. 27, 1983; 63 FR 49453, Sept. 16, 1998; 65 FR 61752, Oct. 17, 2000; 66 FR 18551, Apr. 10, 2001]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.42a</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <P>(a) On and after the date on which the performance test required to be conducted under § 60.8 is completed, no owner or operator subject to the provisions of this subpart shall cause to be discharged into the atmosphere from any affected facility any gases which contain particulate matter in excess of:</P>
              <P>(1) 13 ng/J (0.03 lb/million Btu) heat input derived from the combustion of solid, liquid, or gaseous fuel;</P>
              <P>(2) 1 percent of the potential combustion concentration (99 percent reduction) when combusting solid fuel; and</P>
              <P>(3) 30 percent of potential combustion concentration (70 percent reduction) when combusting liquid fuel.</P>
              <P>(b) On and after the date the particulate matter performance test required to be conducted under § 60.8 is completed, no owner or operator subject to the provisions of this subpart shall cause to be discharged into the atmosphere from any affected facility any gases which exhibit greater than 20 percent opacity (6-minute average), except for one 6-minute period per hour of not more than 27 percent opacity.</P>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.43a</SECTNO>
              <SUBJECT>Standard for sulfur dioxide.</SUBJECT>
              <P>(a) On and after the date on which the initial performance test required to be conducted under § 60.8 is completed, no owner or operator subject to the provisions of this subpart shall cause to be discharged into the atmosphere from any affected facility which combusts solid fuel or solid-derived fuel, except as provided under paragraphs (c), (d), (f) or (h) of this section, any gases which contain sulfur dioxide in excess of:</P>
              <P>(1) 520 ng/J (1.20 lb/million Btu) heat input and 10 percent of the potential combustion concentration (90 percent reduction), or</P>
              <P>(2) 30 percent of the potential combustion concentration (70 percent reduction), when emissions are less than 260 ng/J (0.60 lb/million Btu) heat input.</P>
              <P>(b) On and after the date on which the initial performance test required to be conducted under § 60.8 is completed, no owner or operator subject to the provisions of this subpart shall cause to be discharged into the atmosphere from any affected facility which combusts liquid or gaseous fuels (except for liquid or gaseous fuels derived from solid fuels and as provided under paragraphs (e) or (h) of this section), any gases which contain sulfur dioxide in excess of:</P>
              <P>(1) 340 ng/J (0.80 lb/million Btu) heat input and 10 percent of the potential combustion concentration (90 percent reduction), or</P>
              <P>(2) 100 percent of the potential combustion concentration (zero percent reduction) when emissions are less than 86 ng/J (0.20 lb/million Btu) heat input.</P>
              <P>(c) On and after the date on which the initial performance test required to be conducted under § 60.8 is complete, no owner or operator subject to the provisions of this subpart shall cause to be discharged into the atmosphere from any affected facility which combusts solid solvent refined coal (SRC-I) any gases which contain sulfur dioxide in excess of 520 ng/J (1.20 lb/million Btu) heat input and 15 percent of the potential combustion concentration (85 percent reduction) except as provided under paragraph (f) of this section; compliance with the emission limitation is determined on a 30-day rolling average basis and compliance with the percent reduction requirement is determined on a 24-hour basis.</P>
              <P>(d) Sulfur dioxide emissions are limited to 520 ng/J (1.20 lb/million Btu) heat input from any affected facility which:</P>
              <P>(1) Combusts 100 percent anthracite,</P>
              <P>(2) Is classified as a resource recovery unit, or</P>
              <P>(3) Is located in a noncontinental area and combusts solid fuel or solid-derived fuel.</P>
              <P>(e) Sulfur dioxide emissions are limited to 340 ng/J (0.80 lb/million Btu) heat input from any affected facility which is located in a noncontinental area and combusts liquid or gaseous fuels (excluding solid-derived fuels).</P>

              <P>(f) The emission reduction requirements under this section do not apply to any affected facility that is operated <PRTPAGE P="115"/>under an SO<E T="52">2</E> commercial demonstration permit issued by the Administrator in accordance with the provisions of § 60.45a.</P>
              <P>(g) Compliance with the emission limitation and percent reduction requirements under this section are both determined on a 30-day rolling average basis except as provided under paragraph (c) of this section.</P>
              <P>(h) When different fuels are combusted simultaneously, the applicable standard is determined by proration using the following formula:</P>

              <P>(1) If emissions of sulfur dioxide to the atmosphere are greater than 260 ng/J (0.60 lb/million Btu) heat input
              </P>
              <FP SOURCE="FP-1">E<E T="52">s</E>=(340x+520 y)/100 and</FP>
              <FP SOURCE="FP-1">%P<E T="52">s</E>=10</FP>
              

              <P>(2) If emissions of sulfur dioxide to the atmosphere are equal to or less than 260 ng/J (0.60 lb/million Btu) heat input:
              </P>
              <FP SOURCE="FP-1">E<E T="52">s</E>=(340x+520 y)/100 and</FP>
              <FP SOURCE="FP-1">%P<E T="52">s</E>=(10x+30 y)/100</FP>
              
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">E<E T="52">s</E> is the prorated sulfur dioxide emission limit (ng/J heat input),</FP>
                <FP SOURCE="FP-1">%P<E T="52">s</E> is the percentage of potential sulfur dioxide emission allowed.</FP>
                <FP SOURCE="FP-1">x is the percentage of total heat input derived from the combustion of liquid or gaseous fuels (excluding solid-derived fuels)</FP>
                <FP SOURCE="FP-1">y is the percentage of total heat input derived from the combustion of solid fuel (including solid-derived fuels)</FP>
              </EXTRACT>
              <CITA>[44 FR 33613, June 11, 1979, as amended at 54 FR 6663, Feb. 14, 1989; 54 FR 21344, May 17, 1989; 65 FR 61752, Oct. 17, 2000]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.44a</SECTNO>
              <SUBJECT>Standard for nitrogen oxides.</SUBJECT>

              <P>(a) On and after the date on which the initial performance test required to be conducted under § 60.8 is completed, no owner or operator subject to the provisions of this subpart shall cause to be discharged into the atmosphere from any affected facility, except as provided under paragraphs (b) and (d) of this section, any gases which contain nitrogen oxides (expressed as NO<E T="52">2</E>) in excess of the following emission limits, based on a 30-day rolling average, except as provided under § 60.46a(j)(1):</P>
              <P>(1) <E T="03">NO</E>
                <E T="54">x</E>
                <E T="03">emission limits.</E>
              </P>
              <GPOTABLE CDEF="s25,9,9" COLS="3" OPTS="L2">
                <BOXHD>
                  <CHED H="1">Fuel type</CHED>
                  <CHED H="1">Emission limit for heat input</CHED>
                  <CHED H="2">ng/J</CHED>
                  <CHED H="2">(lb/million Btu)</CHED>
                </BOXHD>
                <ROW>
                  <ENT I="11">Gaseous fuels:</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">Coal-derived fuels</ENT>
                  <ENT>210</ENT>
                  <ENT>0.50</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">All other fuels</ENT>
                  <ENT>86</ENT>
                  <ENT>0.20</ENT>
                </ROW>
                <ROW>
                  <ENT I="11">Liquid fuels:</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">Coal-derived fuels</ENT>
                  <ENT>210</ENT>
                  <ENT>0.50</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">Shale oil</ENT>
                  <ENT>210</ENT>
                  <ENT>0.50</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">All other fuels</ENT>
                  <ENT>130</ENT>
                  <ENT>0.30</ENT>
                </ROW>
                <ROW>
                  <ENT I="11">Solid fuels:</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">Coal-derived fuels</ENT>
                  <ENT>210</ENT>
                  <ENT>0.50</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">Any fuel containing more than 25%, by weight, coal refuse</ENT>
                  <ENT>(<SU>1</SU> )</ENT>
                  <ENT>(<SU>1</SU> )</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">Any fuel containing more than 25%, by weight, lignite if the lignite is mined in North Dakota, South Dakota, or Montana, and is combusted in a slag tap furnace<SU>2</SU>
                  </ENT>
                  <ENT>340</ENT>
                  <ENT>0.80</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">Any fuel containing more than 25%, by weight, lignite not subject to the 340 ng/J heat input emission limit<SU>2</SU>.</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">Subbituminous coal</ENT>
                  <ENT>210</ENT>
                  <ENT>0.50</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">Bituminous coal</ENT>
                  <ENT>260</ENT>
                  <ENT>0.60</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">Anthracite coal</ENT>
                  <ENT>260</ENT>
                  <ENT>0.60</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">All other fuels</ENT>
                  <ENT>260</ENT>
                  <ENT>0.60</ENT>
                </ROW>
                <TNOTE>
                  <SU>1</SU> Exempt from NO<E T="52">X</E> standards and NO<E T="52">X</E> monitoring requirements.</TNOTE>
                <TNOTE>
                  <SU>2</SU> Any fuel containing less than 25%, by weight, lignite is not prorated but its percentage is added to the percentage of the predominant fuel.</TNOTE>
              </GPOTABLE>
              <P>(2) <E T="03">NO</E>
                <E T="54">x</E>
                <E T="03">reduction requirement.</E>
              </P>
              <GPOTABLE CDEF="s25,12" COLS="2" OPTS="L2">
                <BOXHD>
                  <CHED H="1">Fuel type</CHED>
                  <CHED H="1">Percent reduction of potential combustion concentration</CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">Gaseous fuels</ENT>
                  <ENT O="oi0">25</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Liquid fuels</ENT>
                  <ENT O="oi0">30</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Solid fuels</ENT>
                  <ENT O="oi0">65</ENT>
                </ROW>
              </GPOTABLE>
              <P>(b) The emission limitations under paragraph (a) of this section do not apply to any affected facility which is combusting coal-derived liquid fuel and is operating under a commercial demonstration permit issued by the Administrator in accordance with the provisions of § 60.45a.</P>

              <P>(c) Except as provided under paragraph (d) of this section, when two or more fuels are combusted simultaneously, the applicable standard is determined by proration using the following formula:
              </P>
              <FP SOURCE="FP-1">E<E T="52">n</E>=[86 w+130×+210 y+260 z+340 v]/100</FP>
              
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">E<E T="52">n</E>  is the applicable standard for nitrogen oxides when multiple fuels are combusted simultaneously (ng/J heat input);</FP>

                <FP SOURCE="FP-1">w is the percentage of total heat input derived from the combustion of fuels subject to the 86 ng/J heat input standard;<PRTPAGE P="116"/>
                </FP>
                <FP SOURCE="FP-1">x is the percentage of total heat input derived from the combustion of fuels subject to the 130 ng/J heat input standard;</FP>
                <FP SOURCE="FP-1">y is the percentage of total heat input derived from the combustion of fuels subject to the 210 ng/J heat input standard;</FP>
                <FP SOURCE="FP-1">z is the percentage of total heat input derived from the combustion of fuels subject to the 260 ng/J heat input standard; and</FP>
                <FP SOURCE="FP-1">v is the percentage of total heat input delivered from the combustion of fuels subject to the 340 ng/J heat input standard.</FP>
              </EXTRACT>
              

              <P>(d)(1) On and after the date on which the initial performance test required to be conducted under § 60.8 is completed, no new source owner or operator subject to the provisions of this subpart shall cause to be discharged into the atmosphere from any affected facility for which construction commenced after July 9, 1997 any gases which contain nitrogen oxides (expressed as NO<E T="52">2</E>) in excess of 200 nanograms per joule (1.6 pounds per megawatt-hour) gross energy output, based on a 30-day rolling average, except as provided under § 60.46a(k)(1).</P>

              <P>(2) On and after the date on which the initial performance test required to be conducted under § 60.8 is completed, no existing source owner or operator subject to the provisions of this subpart shall cause to be discharged into the atmosphere from any affected facility for which reconstruction commenced after July 9, 1997 any gases which contain nitrogen oxides (expressed as NO<E T="52">2</E>) in excess of 65 ng/Jl (0.15 pounds per million Btu) heat input, based on a 30-day rolling average.</P>
              <CITA>[44 FR 33613, June 11, 1979, as amended at 54 FR 6664, Feb. 14, 1989; 63 FR 49453, Sept. 16, 1998; 66 FR 18551, Apr. 10, 2001; 66 FR 42610, Aug. 14, 2001]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.45a</SECTNO>
              <SUBJECT>Commercial demonstration permit.</SUBJECT>
              <P>(a) An owner or operator of an affected facility proposing to demonstrate an emerging technology may apply to the Administrator for a commercial demonstration permit. The Administrator will issue a commercial demonstration permit in accordance with paragraph (e) of this section. Commercial demonstration permits may be issued only by the Administrator, and this authority will not be delegated.</P>

              <P>(b) An owner or operator of an affected facility that combusts solid solvent refined coal (SRC-I) and who is issued a commercial demonstration permit by the Administrator is not subject to the SO<E T="52">2</E> emission reduction requirements under § 60.43a(c) but must, as a minimum, reduce SO<E T="52">2</E> emissions to 20 percent of the potential combustion concentration (80 percent reduction) for each 24-hour period of steam generator operation and to less than 520 ng/J (1.20 lb/million Btu) heat input on a 30-day rolling average basis.</P>

              <P>(c) An owner or operator of a fluidized bed combustion electric utility steam generator (atmospheric or pressurized) who is issued a commercial demonstration permit by the Administrator is not subject to the SO<E T="52">2</E> emission reduction requirements under § 60.43a(a) but must, as a minimum, reduce SO<E T="52">2</E> emissions to 15 percent of the potential combustion concentration (85 percent reduction) on a 30-day rolling average basis and to less than 520 ng/J (1.20 lb/million Btu) heat input on a 30-day rolling average basis.</P>

              <P>(d) The owner or operator of an affected facility that combusts coal-derived liquid fuel and who is issued a commercial demonstration permit by the Administrator is not subject to the applicable NO<E T="52">X</E> emission limitation and percent reduction under § 60.44a(a) but must, as a minimum, reduce emissions to less than 300 ng/J (0.70 lb/million Btu) heat input on a 30-day rolling average basis.</P>
              <P>(e) Commercial demonstration permits may not exceed the following equivalent MW electrical generation capacity for any one technology category, and the total equivalent MW electrical generation capacity for all commercial demonstration plants may not exceed 15,000 MW.</P>
              <GPOTABLE CDEF="s25,8,12" COLS="3" OPTS="L2">
                <BOXHD>
                  <CHED H="1">Technology</CHED>
                  <CHED H="1">Pollutant</CHED>
                  <CHED H="1">Equivalent electrical capacity (MW electrical output)</CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">Solid solvent refined coal (SRC I)</ENT>
                  <ENT>SO<E T="52">2</E>
                  </ENT>
                  <ENT>6,000-10,000</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Fluidized bed combustion (atmospheric)</ENT>
                  <ENT>SO<E T="52">2</E>
                  </ENT>
                  <ENT>400-3,000</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Fluidized bed combustion (pressurized)</ENT>
                  <ENT>SO<E T="52">2</E>
                  </ENT>
                  <ENT>400-1,200</ENT>
                </ROW>
                <ROW RUL="n,n,s">
                  <ENT I="01">Coal liquification</ENT>
                  <ENT>NO<E T="52">X</E>
                  </ENT>
                  <ENT>750-10,000</ENT>
                </ROW>
                <ROW>
                  <PRTPAGE P="117"/>
                  <ENT I="03">Total allowable for all technologies</ENT>
                  <ENT/>
                  <ENT>15,000</ENT>
                </ROW>
              </GPOTABLE>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.46a</SECTNO>
              <SUBJECT>Compliance provisions.</SUBJECT>
              <P>(a) Compliance with the particulate matter emission limitation under § 60.42a(a)(1) constitutes compliance with the percent reduction requirements for particulate matter under § 60.42a(a)(2) and (3).</P>
              <P>(b) Compliance with the nitrogen oxides emission limitation under § 60.44a(a) constitutes compliance with the percent reduction requirements under § 60.44a(a)(2).</P>
              <P>(c) The particulate matter emission standards under § 60.42a and the nitrogen oxides emission standards under § 60.44a apply at all times except during periods of startup, shutdown, or malfunction. The sulfur dioxide emission standards under § 60.43a apply at all times except during periods of startup, shutdown, or when both emergency conditions exist and the procedures under paragraph (d) of this section are implemented.</P>
              <P>(d) During emergency conditions in the principal company, an affected facility with a malfunctioning flue gas desulfurization system may be operated if sulfur dioxide emissions are minimized by:</P>
              <P>(1) Operating all operable flue gas desulfurization system modules, and bringing back into operation any malfunctioned module as soon as repairs are completed,</P>
              <P>(2) Bypassing flue gases around only those flue gas desulfurization system modules that have been taken out of operation because they were incapable of any sulfur dioxide emission reduction or which would have suffered significant physical damage if they had remained in operation, and</P>
              <P>(3) Designing, constructing, and operating a spare flue gas desulfurization system module for an affected facility larger than 365 MW (1,250 million Btu/hr) heat input (approximately 125 MW electrical output capacity). The Administrator may at his discretion require the owner or operator within 60 days of notification to demonstrate spare module capability. To demonstrate this capability, the owner or operator must demonstrate compliance with the appropriate requirements under paragraph (a), (b), (d), (e), and (h) under § 60.43a for any period of operation lasting from 24 hours to 30 days when:</P>
              <P>(i) Any one flue gas desulfurization module is not operated,</P>
              <P>(ii) The affected facility is operating at the maximum heat input rate,</P>
              <P>(iii) The fuel fired during the 24-hour to 30-day period is representative of the type and average sulfur content of fuel used over a typical 30-day period, and</P>
              <P>(iv) The owner or operator has given the Administrator at least 30 days notice of the date and period of time over which the demonstration will be performed.</P>
              <P>(e) After the initial performance test required under § 60.8, compliance with the sulfur dioxide emission limitations and percentage reduction requirements under § 60.43a and the nitrogen oxides emission limitations under § 60.44a is based on the average emission rate for 30 successive boiler operating days. A separate performance test is completed at the end of each boiler operating day after the initial performance test, and a new 30 day average emission rate for both sulfur dioxide and nitrogen oxides and a new percent reduction for sulfur dioxide are calculated to show compliance with the standards.</P>

              <P>(f) For the initial performance test required under § 60.8, compliance with the sulfur dioxide emission limitations and percent reduction requirements under § 60.43a and the nitrogen oxides emission limitation under § 60.44a is based on the average emission rates for sulfur dioxide, nitrogen oxides, and percent reduction for sulfur dioxide for the first 30 successive boiler operating days. The initial performance test is the only test in which at least 30 days prior notice is required unless otherwise specified by the Administrator. The initial performance test is to be scheduled so that the first boiler operating day of the 30 successive boiler operating days is completed within 60 days after achieving the maximum production rate at which the affected facility will be operated, but not later <PRTPAGE P="118"/>than 180 days after initial startup of the facility.</P>

              <P>(g) Compliance is determined by calculating the arithmetic average of all hourly emission rates for SO<E T="52">2</E> and NO<E T="52">X</E> for the 30 successive boiler operating days, except for data obtained during startup, shutdown, malfunction (NO<E T="52">X</E> only), or emergency conditions (SO<E T="52">2</E> only). Compliance with the percentage reduction requirement for SO<E T="52">2</E> is determined based on the average inlet and average outlet SO<E T="52">2</E> emission rates for the 30 successive boiler operating days.</P>
              <P>(h) If an owner or operator has not obtained the minimum quantity of emission data as required under § 60.47a of this subpart, compliance of the affected facility with the emission requirements under §§ 60.43a and 60.44a of this subpart for the day on which the 30-day period ends may be determined by the Administrator by following the applicable procedures in section 7 of Method 19.</P>
              <P>(i) <E T="03">Compliance provisions for sources subject to § 60.44a(d)(1).</E> The owner or operator of an affected facility subject to § 60.44a(d)(1) (new source constructed after July 7, 1997) shall calculate NO<E T="52">X</E> emissions by multiplying the average hourly NO<E T="52">X</E> output concentration, measured according to the provisions of § 60.47a(c), by the average hourly flow rate, measured according to the provisions of § 60.47a(l), and divided by the average hourly gross energy output, measured according to the provisions of § 60.47a(k).</P>
              <P>(j) <E T="03">Compliance provisions for duct burners subject to § 60.44a(a)(1).</E> To determine compliance with the emissions limits for NO<E T="52">X</E> required by § 60.44a(a) for duct burners used in combined cycle systems, either of the procedures described in paragraph (j)(1) or (2) of this section may be used:</P>
              <P>(1) The owner or operator of an affected duct burner shall conduct the performance test required under § 60.8 using the appropriate methods in appendix A of this part. Compliance with the emissions limits under § 60.44a(a)(1) is determined on the average of three (nominal 1-hour) runs for the initial and subsequent performance tests. During the performance test, one sampling site shall be located in the exhaust of the turbine prior to the duct burner. A second sampling site shall be located at the outlet from the heat recovery steam generating unit. Measurements shall be taken at both sampling sites during the performance test; or</P>

              <P>(2) The owner or operator of an affected duct burner may elect to determine compliance by using the continuous emission monitoring system specified under § 60.47a for measuring NO<E T="52">X</E> and oxygen and meet the requirements of § 60.47a. Data from a CEMS certified (or recertified) according to the provisions of 40 CFR 75.20, meeting the QA and QC requirements of 40 CFR 75.21, and validated according to 40 CFR 75.23 may be used. The sampling site shall be located at the outlet from the steam generating unit. The NO<E T="52">X</E> emission rate at the outlet from the steam generating unit shall constitute the NO<E T="52">X</E> emission rate from the duct burner of the combined cycle system.</P>
              <P>(k) <E T="03">Compliance provisions for duct burners subject to § 60.44a(d)(1).</E> To determine compliance with the emissions limits for NO<E T="52">X</E> required by § 60.44a(d)(1) for duct burners used in combined cycle systems, either of the procedures described in paragraphs (k)(1) and (2) of this section may be used:</P>

              <P>(1) The owner or operator of an affected duct burner used in combined cycle systems shall determine compliance with the NO<E T="52">X</E> standard in § 60.44a(d)(1) as follows:</P>
              <P>(i) The emission rate (E) of NO<E T="52">X</E> shall be computed using Equation 1 of this section:
              </P>
              <FP SOURCE="FP-1">E = [(Csg × Qsg)−(Cte × Qte)]/(Osg × h) (Eq. 1)</FP>
              
              <EXTRACT>
                <FP>Where:</FP>
                
                <FP SOURCE="FP-1">E = emission rate of NO<E T="52">X</E> from the duct burner, ng/J (lb/Mwh) gross output</FP>
                <FP SOURCE="FP-1">Csg = average hourly concentration of NO<E T="52">X</E> exiting the steam generating unit, ng/dscm (lb/dscf)</FP>
                <FP SOURCE="FP-1">Cte = average hourly concentration of NO<E T="52">X</E> in the turbine exhaust upstream from duct burner, ng/dscm (lb/dscf)</FP>
                <FP SOURCE="FP-1">Qsg = average hourly volumetric flow rate of exhaust gas from steam generating unit, dscm/hr (dscf/hr)</FP>
                <FP SOURCE="FP-1">Qte = average hourly volumetric flow rate of exhaust gas from combustion turbine, dscm/hr (dscf/hr)</FP>
                <FP SOURCE="FP-1">Osg = average hourly gross energy output from steam generating unit, J (Mwh)</FP>

                <FP SOURCE="FP-1">h = average hourly fraction of the total heat input to the steam generating unit derived <PRTPAGE P="119"/>from the combustion of fuel in the affected duct burner</FP>
              </EXTRACT>
              

              <P>(ii) Method 7E of appendix A of this part shall be used to determine the NO<E T="52">X</E> concentrations (Csg and Cte). Method 2, 2F or 2G of appendix A of this part, as appropriate, shall be used to determine the volumetric flow rates (Qsg and Qte) of the exhaust gases. The volumetric flow rate measurements shall be taken at the same time as the concentration measurements.</P>
              <P>(iii) The owner or operator shall develop, demonstrate, and provide information satisfactory to the Administrator to determine the average hourly gross energy output from the steam generating unit, and the average hourly percentage of the total heat input to the steam generating unit derived from the combustion of fuel in the affected duct burner.</P>
              <P>(iv) Compliance with the emissions limits under § 60.44a (d)(1) is determined by the three-run average (nominal 1-hour runs) for the initial and subsequent performance tests.</P>

              <P>(2) The owner or operator of an affected duct burner used in a combined cycle system may elect to determine compliance with the NO<E T="52">X</E> standard in § 60.44a(d)(1) on a 30-day rolling average basis as indicated in paragraphs (k)(2)(i) through (iv) of this section.</P>
              <P>(i) The emission rate (E) of NO<E T="52">X</E> shall be computed using Equation 2 of this section:
              </P>
              <FP SOURCE="FP-1">E = (Csg × Qsd) /Occ (Eq. 2)</FP>
              
              <EXTRACT>
                <FP>Where:</FP>
                
                <FP SOURCE="FP-1">E = emission rate of NO<E T="52">X</E> from the duct burner, ng/J (lb/Mwh) gross output</FP>
                <FP SOURCE="FP-1">Csg = average hourly concentration of NO<E T="52">X</E> exiting the steam generating unit, ng/dscm (lb/dscf)</FP>
                <FP SOURCE="FP-1">Qsg = average hourly volumetric flow rate of exhaust gas from steam generating unit, dscm/hr (dscf/hr)</FP>
                <FP SOURCE="FP-1">Occ = average hourly gross energy output from entire combined cycle unit, J (Mwh)</FP>
              </EXTRACT>
              

              <P>(ii) The continuous emissions monitoring system specified under § 60.47a for measuring NO<E T="52">X</E> and oxygen shall be used to determine the average hourly NO<E T="52">X</E> concentrations (Csg). The continuous flow monitoring system specified in § 60.47a(l) shall be used to determine the volumetric flow rate (Qsg) of the exhaust gas. The sampling site shall be located at the outlet from the steam generating unit. Data from a continuous flow monitoring system certified (or recertified) following procedures specified in 40 CFR 75.20, meeting the quality assurance and quality control requirements of 40 CFR 75.21, and validated according to 40 CFR 75.23 may be used.</P>
              <P>(iii) The continuous monitoring system specified under § 60.47a(k) for measuring and determining gross energy output shall be used to determine the average hourly gross energy output from the entire combined cycle unit (Occ), which is the combined output from the combustion turbine and the steam generating unit.</P>

              <P>(iv) The owner or operator may, in lieu of installing, operating, and recording data from the continuous flow monitoring system specified in § 60.47a(l), determine the mass rate (lb/hr) of NO<E T="52">X</E> emissions by installing, operating, and maintaining continuous fuel flowmeters following the appropriate measurements procedures specified in appendix D of 40 CFR part 75. If this compliance option is selected, the emission rate (E) of NO<E T="52">X</E> shall be computed using Equation 3 of this section:
              </P>
              <FP SOURCE="FP-1">E = (ERsg × Hcc) /Occ (Eq. 3)</FP>
              
              <EXTRACT>
                <FP>Where:</FP>
                
                <FP SOURCE="FP-1">E = emission rate of NO<E T="52">X</E> from the duct burner, ng/J (lb/Mwh) gross output</FP>
                <FP SOURCE="FP-1">ERsg = average hourly emission rate of NO<E T="52">X</E> exiting the steam generating unit heat input calculated using appropriate F-factor as described in Method 19, ng/J (lb/million Btu)</FP>
                <FP SOURCE="FP-1">Hcc = average hourly heat input rate of entire combined cycle unit, J/hr (million Btu/hr)</FP>
                <FP SOURCE="FP-1">Occ = average hourly gross energy output from entire combined cycle unit, J (Mwh)</FP>
              </EXTRACT>
              
              <P>(3) When an affected duct burner steam generating unit utilizes a common steam turbine with one or more affected duct burner steam generating units, the owner or operator shall either:</P>
              <P>(i) Determine compliance with the applicable NO<E T="52">X</E> emissions limits by measuring the emissions combined with the emissions from the other unit(s) utilizing the common steam turbine; or</P>

              <P>(ii) Develop, demonstrate, and provide information satisfactory to the <PRTPAGE P="120"/>Administrator on methods for apportioning the combined gross energy output from the steam turbine for each of the affected duct burners. The Administrator may approve such demonstrated substitute methods for apportioning the combined gross energy output measured at the steam turbine whenever the demonstration ensures accurate estimation of emissions regulated under this part.</P>
              <CITA>[44 FR 33613, June 11, 1979, as amended at 54 FR 6664, Feb. 14, 1989; 63 FR 49454, Sept. 16, 1998; 66 FR 18552, Apr. 10, 2001; 66 FR 31178, June 11, 2001]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.47a</SECTNO>
              <SUBJECT>Emission monitoring.</SUBJECT>
              <P>(a) The owner or operator of an affected facility shall install, calibrate, maintain, and operate a continuous monitoring system, and record the output of the system, for measuring the opacity of emissions discharged to the atmosphere, except where gaseous fuel is the only fuel combusted. If opacity interference due to water droplets exists in the stack (for example, from the use of an FGD system), the opacity is monitored upstream of the interference (at the inlet to the FGD system). If opacity interference is experienced at all locations (both at the inlet and outlet of the sulfur dioxide control system), alternate parameters indicative of the particulate matter control system's performance are monitored (subject to the approval of the Administrator).</P>
              <P>(b) The owner or operator of an affected facility shall install, calibrate, maintain, and operate a continuous monitoring system, and record the output of the system, for measuring sulfur dioxide emissions, except where natural gas is the only fuel combusted, as follows:</P>
              <P>(1) Sulfur dioxide emissions are monitored at both the inlet and outlet of the sulfur dioxide control device.</P>
              <P>(2) For a facility which qualifies under the provisions of § 60.43a(d), sulfur dioxide emissions are only monitored as discharged to the atmosphere.</P>
              <P>(3) An “as fired” fuel monitoring system (upstream of coal pulverizers) meeting the requirements of Method 19may be used to determine potential sulfur dioxide emissions in place of a continuous sulfur dioxide emission monitor at the inlet to the sulfur dioxide control device as required under paragraph (b)(1) of this section.</P>
              <P>(c)(1) The owner or operator of an affected facility shall install, calibrate, maintain, and operate a continuous monitoring system, and record the output of the system, for measuring nitrogen oxides emissions discharged to the atmosphere; or</P>
              <P>(2) If the owner or operator has installed a nitrogen oxides emission rate continuous emission monitoring system (CEMS) to meet the requirements of part 75 of this chapter and is continuing to meet the ongoing requirements of part 75 of this chapter, that CEMS may be used to meet the requirements of this section, except that the owner or operator shall also meet the requirements of § 60.49a. Data reported to meet the requirements of § 60.49a shall not include data substituted using the missing data procedures in subpart D of part 75 of this chapter, nor shall the data have been bias adjusted according to the procedures of part 75 of this chapter.</P>
              <P>(d) The owner or operator of an affected facility shall install, calibrate, maintain, and operate a continuous monitoring system, and record the output of the system, for measuring the oxygen or carbon dioxide content of the flue gases at each location where sulfur dioxide or nitrogen oxides emissions are monitored.</P>
              <P>(e) The continuous monitoring systems under paragraphs (b), (c), and (d) of this section are operated and data recorded during all periods of operation of the affected facility including periods of startup, shutdown, malfunction or emergency conditions, except for continuous monitoring system breakdowns, repairs, calibration checks, and zero and span adjustments.</P>

              <P>(f) The owner or operator shall obtain emission data for at least 18 hours in at least 22 out of 30 successive boiler operating days. If this minimum data requirement cannot be met with a continuous monitoring system, the owner or operator shall supplement emission data with other monitoring systems approved by the Administrator or the reference methods and procedures as described in paragraph (h) of this section.<PRTPAGE P="121"/>
              </P>
              <P>(g) The 1-hour averages required under paragraph § 60.13(h) are expressed in ng/J (lb/million Btu) heat input and used to calculate the average emission rates under § 60.46a. The 1-hour averages are calculated using the data points required under § 60.13(b). At least two data points must be used to calculate the 1-hour averages.</P>
              <P>(h) When it becomes necessary to supplement continuous monitoring system data to meet the minimum data requirements in paragraph (f) of this section, the owner or operator shall use the reference methods and procedures as specified in this paragraph. Acceptable alternative methods and procedures are given in paragraph (j) of this section.</P>
              <P>(1) Method 6 shall be used to determine the SO<E T="52">2</E> concentration at the same location as the SO<E T="52">2</E> monitor. Samples shall be taken at 60-minute intervals. The sampling time and sample volume for each sample shall be at least 20 minutes and 0.020 dscm (0.71 dscf). Each sample represents a 1-hour average.</P>
              <P>(2) Method 7 shall be used to determine the NO<E T="52">X</E> concentration at the same location as the NO<E T="52">X</E> monitor. Samples shall be taken at 30-minute intervals. The arithmetic average of two consecutive samples represents a 1-hour average.</P>

              <P>(3) The emission rate correction factor, integrated bag sampling and analysis procedure of Method 3B shall be used to determine the O<E T="52">2</E> or CO<E T="52">2</E> concentration at the same location as the O<E T="52">2</E> or CO<E T="52">2</E> monitor. Samples shall be taken for at least 30 minutes in each hour. Each sample represents a 1-hour average.</P>
              <P>(4) The procedures in Method 19 shall be used to compute each 1-hour average concentration in ng/J (1b/million Btu) heat input.</P>
              <P>(i) The owner or operator shall use methods and procedures in this paragraph to conduct monitoring system performance evaluations under § 60.13(c) and calibration checks under § 60.13(d). Acceptable alternative methods and procedures are given in paragraph (j) of this section.</P>
              <P>(1) Methods 3B, 6, and 7 shall be used to determine O<E T="52">2</E>, SO<E T="52">2</E>, and NO<E T="52">X</E> concentrations, respectively.</P>
              <P>(2) SO<E T="52">2</E> or NO<E T="52">X</E> (NO), as applicable, shall be used for preparing the calibration gas mixtures (in N<E T="52">2</E>, as applicable) under Performance Specification 2 of appendix B of this part.</P>
              <P>(3) For affected facilities burning only fossil fuel, the span value for a continuous monitoring system for measuring opacity is between 60 and 80 percent and for a continuous monitoring system measuring nitrogen oxides is determined as follows:</P>
              <GPOTABLE CDEF="s25,18" COLS="2" OPTS="L2">
                <BOXHD>
                  <CHED H="1">Fossil fuel</CHED>
                  <CHED H="1">Span value for nitrogen oxides (ppm)</CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">Gas</ENT>
                  <ENT>500</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Liquid</ENT>
                  <ENT>500</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Solid</ENT>
                  <ENT>1,000</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Combination</ENT>
                  <ENT>500 (x+y)+1,000z</ENT>
                </ROW>
              </GPOTABLE>
              <EXTRACT>
                <FP>where:</FP>
                <FP SOURCE="FP-1">x is the fraction of total heat input derived from gaseous fossil fuel,</FP>
                <FP SOURCE="FP-1">y is the fraction of total heat input derived from liquid fossil fuel, and</FP>
                <FP SOURCE="FP-1">z is the fraction of total heat input derived from solid fossil fuel.</FP>
              </EXTRACT>
              
              <P>(4) All span values computed under paragraph (b)(3) of this section for burning combinations of fossil fuels are rounded to the nearest 500 ppm.</P>
              <P>(5) For affected facilities burning fossil fuel, alone or in combination with non-fossil fuel, the span value of the sulfur dioxide continuous monitoring system at the inlet to the sulfur dioxide control device is 125 percent of the maximum estimated hourly potential emissions of the fuel fired, and the outlet of the sulfur dioxide control device is 50 percent of maximum estimated hourly potential emissions of the fuel fired.</P>
              <P>(j) The owner or operator may use the following as alternatives to the reference methods and procedures specified in this section:</P>
              <P>(1) For Method 6, Method 6A or 6B (whenever Methods 6 and 3 or 3B data are used) or 6C may be used. Each Method 6B sample obtained over 24 hours represents 24 1-hour averages. If Method 6A or 6B is used under paragraph (i) of this section, the conditions under § 60.46(d)(1) apply; these conditions do not apply under paragraph (h) of this section.</P>

              <P>(2) For Method 7, Method 7A, 7C, 7D, or 7E may be used. If Method 7C, 7D, or 7E is used, the sampling time for each run shall be 1 hour.<PRTPAGE P="122"/>
              </P>
              <P>(3) For Method 3, Method 3A or 3B may be used if the sampling time is 1 hour.</P>
              <P>(4) For Method 3B, Method 3A may be used.</P>
              <P>(k) The procedures specified in paragraphs (k)(1) through (3) of this section shall be used to determine gross output for sources demonstrating compliance with the output-based standard under § 60.44a(d)(1).</P>
              <P>(1) The owner or operator of an affected facility with electricity generation shall install, calibrate, maintain, and operate a wattmeter; measure gross electrical output in megawatt-hour on a continuous basis; and record the output of the monitor.</P>
              <P>(2) The owner or operator of an affected facility with process steam generation shall install, calibrate, maintain, and operate meters for steam flow, temperature, and pressure; measure gross process steam output in joules per hour (or Btu per hour) on a continuous basis; and record the output of the monitor.</P>
              <P>(3) For affected facilities generating process steam in combination with electrical generation, the gross energy output is determined from the gross electrical output measured in accordance with paragraph (k)(1) of this section plus 50 percent of the gross thermal output of the process steam measured in accordance with paragraph (k)(2) of this section.</P>
              <P>(l) The owner or operator of an affected facility demonstrating compliance with the output-based standard under § 60.44a(d)(1) shall install, certify, operate, and maintain a continuous flow monitoring system meeting the requirements of Performance Specification 6 of appendix B and procedure 1 of appendix F of this subpart, and record the output of the system, for measuring the flow of exhaust gases discharged to the atmosphere; or</P>
              <P>(m) Alternatively, data from a continuous flow monitoring system certified according to the requirements of 40 CFR 75.20, meeting the applicable quality control and quality assurance requirements of 40 CFR 75.21, and validated according to 40 CFR 75.23, may be used.</P>
              <P>(n) Gas-fired and oil-fired units. The owner or operator of an affected unit that qualifies as a gas-fired or oil-fired unit, as defined in 40 CFR 72.2, may use, as an alternative to the requirements specified in either paragraph (l) or (m) of this section, a fuel flow monitoring system certified and operated according to the requirements of appendix D of 40 CFR part 75.</P>

              <P>(o) The owner or operator of a duct burner, as described in § 60.41a, which is subject to the NO<E T="52">X</E> standards of § 60.44a(a)(1) or (d)(1) is not required to install or operate a continuous emissions monitoring system to measure NO<E T="52">X</E> emissions; a wattmeter to measure gross electrical output; meters to measure steam flow, temperature, and pressure; and a continuous flow monitoring system to measure the flow of exhaust gases discharged to the atmosphere.</P>
              <CITA>[44 FR 33613, June 11, 1979, as amended at 54 FR 6664, Feb. 14, 1989; 55 FR 5212, Feb. 14, 1990; 55 FR 18876, May 7, 1990; 63 FR 49454, Sept. 16, 1998; 65 FR 61752, Oct. 17, 2000; 66 FR 18553, Apr. 10, 2001]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.48a</SECTNO>
              <SUBJECT>Compliance determination pro-cedures and methods.</SUBJECT>

              <P>(a) In conducting the performance tests required in § 60.8, the owner or operator shall use as reference methods and procedures the methods in appendix A of this part or the methods and procedures as specified in this section, except as provided in § 60.8(b). Section 60.8(f) does not apply to this section for SO<E T="52">2</E> and NO<E T="52">X</E>. Acceptable alternative methods are given in paragraph (e) of this section.</P>
              <P>(b) The owner or operator shall determine compliance with the particulate matter standards in § 60.42a as follows:</P>
              <P>(1) The dry basis F factor (O<E T="52">2</E>) procedures in Method 19 shall be used to compute the emission rate of particulate matter.</P>
              <P>(2) For the particular matter concentration, Method 5 shall be used at affected facilities without wet FGD systems and Method 5B shall be used after wet FGD systems.</P>

              <P>(i) The sampling time and sample volume for each run shall be at least 120 minutes and 1.70 dscm (60 dscf). The probe and filter holder heating system in the sampling train may be set to provide an average gas temperature of no greater than 160±14 °C (320±25 °F).<PRTPAGE P="123"/>
              </P>

              <P>(ii) For each particulate run, the emission rate correction factor, integrated or grab sampling and analysis procedures of Method 3B shall be used to determine the O<E T="52">2</E> concentration. The O<E T="52">2</E> sample shall be obtained simultaneously with, and at the same traverse points as, the particulate run. If the particulate run has more than 12 traverse points, the O<E T="52">2</E> traverse points may be reduced to 12 provided that Method 1 is used to locate the 12 O<E T="52">2</E> traverse points. If the grab sampling procedure is used, the O<E T="52">2</E> concentration for the run shall be the arithmetic mean of the sample O<E T="52">2</E> concentrations at all traverse points.</P>
              <P>(3) Method 9 and the procedures in § 60.11 shall be used to determine opacity.</P>

              <P>(c) The owner or operator shall determine compliance with the SO<E T="52">2</E> standards in § 60.43a as follows:</P>
              <P>(1) The percent of potential SO<E T="52">2</E> emissions (%P<E T="52">s</E>) to the atmosphere shall be computed using the following equation:
              </P>
              <FP SOURCE="FP-1">%P<E T="52">s</E>=[(100—%R<E T="52">f</E>) (100—%R<E T="52">g</E>)]/100</FP>
              
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">%P<E T="52">s</E>=percent of potential SO<E T="52">2</E> emissions, percent.</FP>
                <FP SOURCE="FP-1">%R<E T="52">f</E>=percent reduction from fuel pretreatment, percent.</FP>
                <FP SOURCE="FP-1">%R<E T="52">g</E>=percent reduction by SO<E T="52">2</E> control system, percent.</FP>
              </EXTRACT>
              

              <P>(2) The procedures in Method 19 may be used to determine percent reduction (%R<E T="52">f</E>) of sulfur by such processes as fuel pretreatment (physical coal cleaning, hydrodesulfurization of fuel oil, etc.), coal pulverizers, and bottom and flyash interactions. This determination is optional.</P>

              <P>(3) The procedures in Method 19 shall be used to determine the percent SO<E T="52">2</E> reduction (%R<E T="52">g</E>) of any SO<E T="52">2</E> control system. Alternatively, a combination of an “as fired” fuel monitor and emission rates measured after the control system, following the procedures in Method 19, may be used if the percent reduction is calculated using the average emission rate from the SO<E T="52">2</E> control device and the average SO<E T="52">2</E> input rate from the “as fired” fuel analysis for 30 successive boiler operating days.</P>
              <P>(4) The appropriate procedures in Method 19 shall be used to determine the emission rate.</P>

              <P>(5) The continuous monitoring system in § 60.47a (b) and (d) shall be used to determine the concentrations of SO<E T="52">2</E> and CO<E T="52">2</E> or O<E T="52">2</E>.</P>

              <P>(d) The owner or operator shall determine compliance with the NO<E T="52">X</E> standard in § 60.44a as follows:</P>

              <P>(1) The appropriate procedures in Method 19 shall be used to determine the emission rate of NO<E T="52">X</E>.</P>

              <P>(2) The continous monitoring system in § 60.47a (c) and (d) shall be used to determine the concentrations of NO<E T="52">X</E> and CO<E T="52">2</E> or O<E T="52">2</E>.</P>
              <P>(e) The owner or operator may use the following as alternatives to the reference methods and procedures specified in this section:</P>
              <P>(1) For Method 5 or 5B, Method 17 may be used at facilities with or without wet FGD systems if the stack temperature at the sampling location does not exceed an average temperature of 160 °C (320 °F). The procedures of §§ 2.1 and 2.3 of Method 5B may be used in Method 17 only if it is used after wet FGD systems. Method 17 shall not be used after wet FGD systems if the effluent is saturated or laden with water droplets.</P>
              <P>(2) The F<E T="52">c</E> factor (CO<E T="52">2</E>) procedures in Method 19 may be used to compute the emission rate of particulate matter under the stipulations of § 60.46(d)(1). The CO<E T="52">2</E> shall be determined in the same manner as the O<E T="52">2</E> concentration.</P>
              <P>(f) Electric utility combined cycle gas turbines are performance tested for particulate matter, sulfur dioxide, and nitrogen oxides using the procedures of Method 19. The sulfur dioxide and nitrogen oxides emission rates from the gas turbine used in Method 19 calculations are determined when the gas turbine is performance tested under subpart GG. The potential uncontrolled particulate matter emission rate from a gas turbine is defined as 17 ng/J (0.04 lb/million Btu) heat input.</P>
              <CITA>[44 FR 33613, June 11, 1979, as amended at 54 FR 6664, Feb. 14, 1989; 55 FR 5212, Feb. 14, 1990; 65 FR 61752, Oct. 17, 2000]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.49a</SECTNO>
              <SUBJECT>Reporting requirements.</SUBJECT>

              <P>(a) For sulfur dioxide, nitrogen oxides, and particulate matter emissions, the performance test data from the initial performance test and from the performance evaluation of the continuous <PRTPAGE P="124"/>monitors (including the transmissometer) are submitted to the Administrator.</P>
              <P>(b) For sulfur dioxide and nitrogen oxides the following information is reported to the Administrator for each 24-hour period.</P>
              <P>(1) Calendar date.</P>
              <P>(2) The average sulfur dioxide and nitrogen oxide emission rates (ng/J or lb/million Btu) for each 30 successive boiler operating days, ending with the last 30-day period in the quarter; reasons for non-compliance with the emission standards; and, description of corrective actions taken.</P>
              <P>(3) Percent reduction of the potential combustion concentration of sulfur dioxide for each 30 successive boiler operating days, ending with the last 30-day period in the quarter; reasons for non-compliance with the standard; and, description of corrective actions taken.</P>
              <P>(4) Identification of the boiler operating days for which pollutant or dilutent data have not been obtained by an approved method for at least 18 hours of operation of the facility; justification for not obtaining sufficient data; and description of corrective actions taken.</P>

              <P>(5) Identification of the times when emissions data have been excluded from the calculation of average emission rates because of startup, shutdown, malfunction (NO<E T="52">X</E> only), emergency conditions (SO<E T="52">2</E> only), or other reasons, and justification for excluding data for reasons other than startup, shutdown, malfunction, or emergency conditions.</P>
              <P>(6) Identification of “F” factor used for calculations, method of determination, and type of fuel combusted.</P>
              <P>(7) Identification of times when hourly averages have been obtained based on manual sampling methods.</P>
              <P>(8) Identification of the times when the pollutant concentration exceeded full span of the continuous monitoring system.</P>
              <P>(9) Description of any modifications to the continuous monitoring system which could affect the ability of the continuous monitoring system to comply with Performance Specifications 2 or 3.</P>
              <P>(c) If the minimum quantity of emission data as required by § 60.47a is not obtained for any 30 successive boiler operating days, the following information obtained under the requirements of § 60.46a(h) is reported to the Administrator for that 30-day period:</P>

              <P>(1) The number of hourly averages available for outlet emission rates (n<E T="52">o</E>) and inlet emission rates (n<E T="52">i</E>) as applicable.</P>

              <P>(2) The standard deviation of hourly averages for outlet emission rates (s<E T="52">o</E>) and inlet emission rates (s<E T="52">i</E>) as applicable.</P>

              <P>(3) The lower confidence limit for the mean outlet emission rate (E<E T="52">o</E>*) and the upper confidence limit for the mean inlet emission rate (E<E T="52">i</E>*) as applicable.</P>
              <P>(4) The applicable potential combustion concentration.</P>

              <P>(5) The ratio of the upper confidence limit for the mean outlet emission rate (E<E T="52">o</E>*) and the allowable emission rate (E<E T="52">std</E>) as applicable.</P>
              <P>(d) If any standards under § 60.43a are exceeded during emergency conditions because of control system malfunction, the owner or operator of the affected facility shall submit a signed statement:</P>
              <P>(1) Indicating if emergency conditions existed and requirements under § 60.46a(d) were met during each period, and</P>
              <P>(2) Listing the following information:</P>
              <P>(i) Time periods the emergency condition existed;</P>
              <P>(ii) Electrical output and demand on the owner or operator's electric utility system and the affected facility;</P>
              <P>(iii) Amount of power purchased from interconnected neighboring utility companies during the emergency period;</P>
              <P>(iv) Percent reduction in emissions achieved;</P>
              <P>(v) Atmospheric emission rate (ng/J) of the pollutant discharged; and</P>
              <P>(vi) Actions taken to correct control system malfunction.</P>
              <P>(e) If fuel pretreatment credit toward the sulfur dioxide emission standard under § 60.43a is claimed, the owner or operator of the affected facility shall submit a signed statement:</P>

              <P>(1) Indicating what percentage cleaning credit was taken for the calendar <PRTPAGE P="125"/>quarter, and whether the credit was determined in accordance with the provisions of § 60.48a and Method 19 (appendix A); and</P>
              <P>(2) Listing the quantity, heat content, and date each pretreated fuel shipment was received during the previous quarter; the name and location of the fuel pretreatment facility; and the total quantity and total heat content of all fuels received at the affected facility during the previous quarter.</P>
              <P>(f) For any periods for which opacity, sulfur dioxide or nitrogen oxides emissions data are not available, the owner or operator of the affected facility shall submit a signed statement indicating if any changes were made in operation of the emission control system during the period of data unavailability. Operations of the control system and affected facility during periods of data unavailability are to be compared with operation of the control system and affected facility before and following the period of data unavailability.</P>
              <P>(g) The owner or operator of the affected facility shall submit a signed statement indicating whether:</P>
              <P>(1) The required continuous monitoring system calibration, span, and drift checks or other periodic audits have or have not been performed as specified.</P>
              <P>(2) The data used to show compliance was or was not obtained in accordance with approved methods and procedures of this part and is representative of plant performance.</P>
              <P>(3) The minimum data requirements have or have not been met; or, the minimum data requirements have not been met for errors that were unavoidable.</P>
              <P>(4) Compliance with the standards has or has not been achieved during the reporting period.</P>
              <P>(h) For the purposes of the reports required under § 60.7, periods of excess emissions are defined as all 6-minute periods during which the average opacity exceeds the applicable opacity standards under § 60.42a(b). Opacity levels in excess of the applicable opacity standard and the date of such excesses are to be submitted to the Administrator each calendar quarter.</P>
              <P>(i) The owner or operator of an affected facility shall submit the written reports required under this section and subpart A to the Administrator semiannually for each six-month period. All semiannual reports shall be postmarked by the 30th day following the end of each six-month period.</P>

              <P>(j) The owner or operator of an affected facility may submit electronic quarterly reports for SO<E T="52">2</E> and/or NO<E T="52">X</E> and/or opacity in lieu of submitting the written reports required under paragraphs (b) and (h) of this section. The format of each quarterly electronic report shall be coordinated with the permitting authority. The electronic report(s) shall be submitted no later than 30 days after the end of the calendar quarter and shall be accompanied by a certification statement from the owner or operator, indicating whether compliance with the applicable emission standards and minimum data requirements of this subpart was achieved during the reporting period. Before submitting reports in the electronic format, the owner or operator shall coordinate with the permitting authority to obtain their agreement to submit reports in this alternative format.</P>
              <CITA>[44 FR 33613, June 11, 1979, as amended at 63 FR 49454, Sept. 16, 1998; 64 FR 7464, Feb. 12, 1999]</CITA>
            </SECTION>
          </SUBPART>
          <SUBPART>
            <HD SOURCE="HED">Subpart Db—Standards of Performance for Industrial-Commercial-Institutional Steam Generating Units</HD>
            <SECTION>
              <SECTNO>§ 60.40b</SECTNO>
              <SUBJECT>Applicability and delegation of authority.</SUBJECT>
              <P>(a) The affected facility to which this subpart applies is each steam generating unit that commences construction, modification, or reconstruction after June 19, 1984, and that has a heat input capacity from fuels combusted in the steam generating unit of greater than 29 MW (100 million Btu/hour).</P>
              <P>(b) Any affected facility meeting the applicability requirements under paragraph (a) of this section and commencing construction, modification, or reconstruction after June 19, 1984, but on or before June 19, 1986, is subject to the following standards:</P>

              <P>(1) Coal-fired affected facilities having a heat input capacity between 29 and 73 MW (100 and 250 million Btu/<PRTPAGE P="126"/>hour), inclusive, are subject to the particulate matter and nitrogen oxides standards under this subpart.</P>
              <P>(2) Coal-fired affected facilities having a heat input capacity greater than 73 MW (250 million Btu/hour) and meeting the applicability requirements under subpart D (Standards of performance for fossil-fuel-fired steam generators; § 60.40) are subject to the particulate matter and nitrogen oxides standards under this subpart and to the sulfur dioxide standards under subpart D (§ 60.43).</P>
              <P>(3) Oil-fired affected facilities having a heat input capacity between 29 and 73 MW (100 and 250 million Btu/hour), inclusive, are subject to the nitrogen oxides standards under this subpart.</P>
              <P>(4) Oil-fired affected facilities having a heat input capacity greater than 73 MW (250 million Btu/hour) and meeting the applicability requirements under subpart D (Standards of performance for fossil-fuel-fired steam generators; § 60.40) are also subject to the nitrogen oxides standards under this subpart and the particulate matter and sulfur dioxide standards under subpart D (§ 60.42 and § 60.43).</P>
              <P>(c) Affected facilities which also meet the applicability requirements under subpart J (Standards of performance for petroleum refineries; § 60.104) are subject to the particulate matter and nitrogen oxides standards under this subpart and the sulfur dioxide standards under subpart J (§ 60.104).</P>
              <P>(d) Affected facilities which also meet the applicability requirements under subpart E (Standards of performance for incinerators; § 60.50) are subject to the nitrogen oxides and particulate matter standards under this subpart.</P>
              <P>(e) Steam generating units meeting the applicability requirements under subpart Da (Standards of performance for electric utility steam generating units; § 60.40a) are not subject to this subpart.</P>
              <P>(f) Any change to an existing steam generating unit for the sole purpose of combusting gases containing TRS as defined under § 60.281 is not considered a modification under § 60.14 and the steam generating unit is not subject to this subpart.</P>
              <P>(g) In delegating implementation and enforcement authority to a State under section 111(c) of the Act, the following authorities shall be retained by the Administrator and not transferred to a State.</P>
              <P>(1) Section 60.44b(f).</P>
              <P>(2) Section 60.44b(g).</P>
              <P>(3) Section 60.49b(a)(4).</P>
              <P>(h) Affected facilities which meet the applicability requirements under subpart Eb (Standards of performance for municipal waste combustors; § 60.50b) are not subject to this subpart.</P>
              <P>(i) Unless and until subpart GG of this part is revised to extend the applicability of subpart GG of this part to steam generator units subject to this subpart, this subpart will continue to apply to combined cycle gas turbines that are capable of combusting more than 29 MW (100 million Btu/hour) heat input of fossil fuel in the steam generator. Only emissions resulting from combustion of fuels in the steam generating unit are subject to this subpart. (The gas turbine emissions are subject to subpart GG of this part.)</P>
              <P>(j) Any affected facility meeting the applicability requirements under paragraph (a) of this section and commencing construction, modification, or reconstruction after June 19, 1986 is not subject to Subpart D (Standards of Performance for Fossil-Fuel-Fired Steam Generators, § 60.40).</P>
              <CITA>[52 FR 47842, Dec. 16, 1987, as amended at 63 FR 49454, Sept. 16, 1998; 65 FR 61752, Oct. 17, 2000]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.41b</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <P>As used in this subpart, all terms not defined herein shall have the meaning given them in the Act and in subpart A of this part.</P>
              <P>
                <E T="03">Annual capacity factor</E> means the ratio between the actual heat input to a steam generating unit from the fuels listed in § 60.42b(a), § 60.43b(a), or § 60.44b(a), as applicable, during a calendar year and the potential heat input to the steam generating unit had it been operated for 8,760 hours during a calendar year at the maximum steady state design heat input capacity. In the case of steam generating units that are rented or leased, the actual heat input <PRTPAGE P="127"/>shall be determined based on the combined heat input from all operations of the affected facility in a calendar year.</P>
              <P>
                <E T="03">Byproduct/waste</E> means any liquid or gaseous substance produced at chemical manufacturing plants, petroleum refineries, or pulp and paper mills (except natural gas, distillate oil, or residual oil) and combusted in a steam generating unit for heat recovery or for disposal. Gaseous substances with carbon dioxide levels greater than 50 percent or carbon monoxide levels greater than 10 percent are not byproduct/waste for the purpose of this subpart.</P>
              <P>
                <E T="03">Chemical manufacturing plants</E> means industrial plants which are classified by the Department of Commerce under Standard Industrial Classification (SIC) Code 28.</P>
              <P>
                <E T="03">Coal</E> means all solid fuels classified as anthracite, bituminous, sub-bi-tum-i-nous, or lignite by the American Society of Testing and Materials in ASTM D388-77, 90, 91, 95, or 98a, Standard Specification for Classification of Coals by Rank (IBR—see § 60.17), coal refuse, and petroleum coke. Coal-derived synthetic fuels, including but not limited to solvent refined coal, gasified coal, coal-oil mixtures, and coal-water mixtures, are also included in this definition for the purposes of this subpart.</P>
              <P>
                <E T="03">Coal refuse</E> means any byproduct of coal mining or coal cleaning operations with an ash content greater than 50 percent, by weight, and a heating value less than 13,900 kJ/kg (6,000 Btu/lb) on a dry basis.</P>
              <P>
                <E T="03">Combined cycle system</E> means a system in which a separate source, such as a gas turbine, internal combustion engine, kiln, etc., provides exhaust gas to a heat recovery steam generating unit.</P>
              <P>
                <E T="03">Conventional technology</E> means wet flue gas desulfurization (FGD) technology, dry FGD technology, atmospheric fluidized bed combustion technology, and oil hydrodesulfurization technology.</P>
              <P>
                <E T="03">Distillate oil</E> means fuel oils that contain 0.05 weight percent nitrogen or less and comply with the specifications for fuel oil numbers 1 and 2, as defined by the American Society of Testing and Materials in ASTM D396-78, 89, 90, 92, 96, or 98, Standard Specifications for Fuel Oils (incorporated by reference—see § 60.17).</P>
              <P>
                <E T="03">Dry flue gas desulfurization technology</E> means a sulfur dioxide control system that is located downstream of the steam generating unit and removes sulfur oxides from the combustion gases of the steam generating unit by contacting the combustion gases with an alkaline slurry or solution and forming a dry powder material. This definition includes devices where the dry powder material is subsequently converted to another form. Alkaline slurries or solutions used in dry flue gas de-sul-fur-i-za-tion technology include but are not limited to lime and sodium.</P>
              <P>
                <E T="03">Duct burner</E> means a device that combusts fuel and that is placed in the exhaust duct from another source, such as a stationary gas turbine, internal combustion engine, kiln, etc., to allow the firing of additional fuel to heat the exhaust gases before the exhaust gases enter a heat recovery steam generating unit.</P>
              <P>
                <E T="03">Emerging technology</E> means any sulfur dioxide control system that is not defined as a conventional technology under this section, and for which the owner or operator of the facility has applied to the Administrator and received approval to operate as an emerging technology under § 60.49b(a)(4).</P>
              <P>
                <E T="03">Federally enforceable</E> means all limitations and conditions that are enforceable by the Administrator, including the requirements of 40 CFR parts 60 and 61, requirements within any applicable State Implementation Plan, and any permit requirements established under 40 CFR 52.21 or under 40 CFR 51.18 and 40 CFR 51.24.</P>
              <P>
                <E T="03">Fluidized bed combustion technology</E> means combustion of fuel in a bed or series of beds (including but not limited to bubbling bed units and circulating bed units) of limestone aggregate (or other sorbent materials) in which these materials are forced upward by the flow of combustion air and the gaseous products of combustion.</P>
              <P>
                <E T="03">Fuel pretreatment</E> means a process that removes a portion of the sulfur in a fuel before combustion of the fuel in a steam generating unit.</P>
              <P>
                <E T="03">Full capacity</E> means operation of the steam generating unit at 90 percent or more of the maximum steady-state design heat input capacity.<PRTPAGE P="128"/>
              </P>
              <P>
                <E T="03">Heat input</E> means heat derived from combustion of fuel in a steam generating unit and does not include the heat input from preheated combustion air, recirculated flue gases, or exhaust gases from other sources, such as gas turbines, internal combustion engines, kilns, etc.</P>
              <P>
                <E T="03">Heat release rate</E> means the steam generating unit design heat input capacity (in MW or Btu/hour) divided by the furnace volume (in cubic meters or cubic feet); the furnace volume is that volume bounded by the front furnace wall where the burner is located, the furnace side waterwall, and extending to the level just below or in front of the first row of convection pass tubes.</P>
              <P>
                <E T="03">Heat transfer medium</E> means any material that is used to transfer heat from one point to another point.</P>
              <P>
                <E T="03">High heat release rate</E> means a heat release rate greater than 730,000 J/sec-m<SU>3</SU> (70,000 Btu/hour-ft<SU>3</SU>).</P>
              <P>
                <E T="03">Lignite</E> means a type of coal classified as lignite A or lignite B by the American Society of Testing and Materials in ASTM D388-77, 90, 91, 95, or 98a, Standard Specification for Classification of Coals by Rank (IBR—see § 60.17).</P>
              <P>
                <E T="03">Low heat release rate</E> means a heat release rate of 730,000 J/sec-m<SU>3</SU> (70,000 Btu/hour-ft<SU>3</SU>) or less.</P>
              <P>
                <E T="03">Mass-feed stoker steam generating unit</E> means a steam generating unit where solid fuel is introduced directly into a retort or is fed directly onto a grate where it is combusted.</P>
              <P>
                <E T="03">Maximum heat input capacity</E> means the ability of a steam generating unit to combust a stated maximum amount of fuel on a steady state basis, as determined by the physical design and characteristics of the steam generating unit.</P>
              <P>
                <E T="03">Municipal-type solid waste</E> means refuse, more than 50 percent of which is waste consisting of a mixture of paper, wood, yard wastes, food wastes, plastics, leather, rubber, and other combustible materials, and noncombustible materials such as glass and rock.</P>
              <P>
                <E T="03">Natural gas</E> means (1) a naturally occurring mixture of hydrocarbon and nonhydrocarbon gases found in geologic formations beneath the earth's surface, of which the principal constituent is methane; or (2) liquid petroleum gas, as defined by the American Society for Testing and Materials in ASTM D1835-82, 86, 87, 91, or 97, “Standard Specification for Liquid Petroleum Gases” (IBR—see § 60.17).</P>
              <P>
                <E T="03">Noncontinental area</E> means the State of Hawaii, the Virgin Islands, Guam, American Samoa, the Commonwealth of Puerto Rico, or the Northern Mariana Islands.</P>
              <P>
                <E T="03">Oil</E> means crude oil or petroleum or a liquid fuel derived from crude oil or petroleum, including distillate and residual oil.</P>
              <P>
                <E T="03">Petroleum refinery</E> means industrial plants as classified by the Department of Commerce under Standard Industrial Classification (SIC) Code 29.</P>
              <P>
                <E T="03">Potential sulfur dioxide emission rate</E> means the theoretical sulfur dioxide emissions (ng/J, lb/million Btu heat input) that would result from combusting fuel in an uncleaned state and without using emission control systems.</P>
              <P>
                <E T="03">Process heater</E> means a device that is primarily used to heat a material to initiate or promote a chemical reaction in which the material participates as a reactant or catalyst.</P>
              <P>
                <E T="03">Pulp and paper mills</E> means industrial plants which are classified by the Department of Commerce under North American Industry Classification System (NAICS) Code 322 or Standard Industrial Classification (SIC) Code 26.</P>
              <P>
                <E T="03">Pulverized coal-fired steam generating unit</E> means a steam generating unit in which pulverized coal is introduced into an air stream that carries the coal to the combustion chamber of the steam generating unit where it is fired in suspension. This includes both conventional pulverized coal-fired and micropulverized coal-fired steam generating units.</P>
              <P>
                <E T="03">Residual oil</E> means crude oil, fuel oil numbers 1 and 2 that have a nitrogen content greater than 0.05 weight percent, and all fuel oil numbers 4, 5 and 6, as defined by the American Society of Testing and Materials in ASTM D396-78, Standard Specifications for Fuel Oils (IBR—see § 60.17).</P>
              <P>
                <E T="03">Spreader stoker steam generating unit</E> means a steam generating unit in which solid fuel is introduced to the combustion zone by a mechanism that throws the fuel onto a grate from <PRTPAGE P="129"/>above. Combustion takes place both in suspension and on the grate.</P>
              <P>
                <E T="03">Steam generating unit</E> means a device that combusts any fuel or byproduct/waste to produce steam or to heat water or any other heat transfer medium. This term includes any municipal-type solid waste incinerator with a heat recovery steam generating unit or any steam generating unit that combusts fuel and is part of a cogeneration system or a combined cycle system. This term does not include process heaters as they are defined in this subpart.</P>
              <P>
                <E T="03">Steam generating unit operating day</E> means a 24-hour period between 12:00 midnight and the following midnight during which any fuel is combusted at any time in the steam generating unit. It is not necessary for fuel to be combusted continuously for the entire 24-hour period.</P>
              <P>
                <E T="03">Very low sulfur oil</E> means an oil that contains no more than 0.5 weight percent sulfur or that, when combusted without sulfur dioxide emission control, has a sulfur dioxide emission rate equal to or less than 215 ng/J (0.5 lb/million Btu) heat input.</P>
              <P>
                <E T="03">Wet flue gas desulfurization technology</E> means a sulfur dioxide control system that is located downstream of the steam generating unit and removes sulfur oxides from the combustion gases of the steam generating unit by contacting the combustion gas with an alkaline slurry or solution and forming a liquid material. This definition applies to devices where the aqueous liquid material product of this contact is subsequently converted to other forms. Alkaline reagents used in wet flue gas desulfurization technology include, but are not limited to, lime, limestone, and sodium.</P>
              <P>
                <E T="03">Wet scrubber system</E> means any emission control device that mixes an aqueous stream or slurry with the exhaust gases from a steam generating unit to control emissions of particulate matter or sulfur dioxide.</P>
              <P>
                <E T="03">Wood</E> means wood, wood residue, bark, or any derivative fuel or residue thereof, in any form, including, but not limited to, sawdust, sanderdust, wood chips, scraps, slabs, millings, shavings, and processed pellets made from wood or other forest residues.</P>
              <CITA>[52 FR 47842, Dec. 16, 1987, as amended at 54 FR 51819, Dec. 18, 1989; 65 FR 61752, Oct. 17, 2000; 66 FR 49834, Oct. 1, 2001]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.42b</SECTNO>
              <SUBJECT>Standard for sulfur dioxide.</SUBJECT>

              <P>(a) Except as provided in paragraphs (b), (c), (d), or (j) of this section, on and after the date on which the performance test is completed or required to be completed under § 60.8 of this part, whichever date comes first, no owner or operator of an affected facility that combusts coal or oil shall cause to be discharged into the atmosphere any gases that contain sulfur dioxide in excess of 10 percent (0.10) of the potential sulfur dioxide emission rate (90 percent reduction) and that contain sulfur dioxide in excess of the emission limit determined according to the following formula:
              </P>
              <FP SOURCE="FP-1">E<E T="52">s</E>=(K<E T="52">a</E> H<E T="52">a</E>+K<E T="52">b</E> H<E T="52">b</E>)/(H<E T="52">a</E>+H<E T="52">b</E>)</FP>
              
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">E<E T="52">s</E> is the sulfur dioxide emission limit, in ng/J or lb/million Btu heat input,</FP>
                <FP SOURCE="FP-1">K<E T="52">a</E> is 520 ng/J (or 1.2 lb/million Btu),</FP>
                <FP SOURCE="FP-1">K<E T="52">b</E> is 340 ng/J (or 0.80 lb/million Btu),</FP>
                <FP SOURCE="FP-1">H<E T="52">a</E> is the heat input from the combustion of coal, in J (million Btu),</FP>
                <FP SOURCE="FP-1">H<E T="52">b</E> is the heat input from the combustion of oil, in J (million Btu).</FP>
              </EXTRACT>
              
              <FP>Only the heat input supplied to the affected facility from the combustion of coal and oil is counted under this section. No credit is provided for the heat input to the affected facility from the combustion of natural gas, wood, municipal-type solid waste, or other fuels or heat input to the affected facility from exhaust gases from another source, such as gas turbines, internal combustion engines, kilns, etc.</FP>

              <P>(b) On and after the date on which the performance test is completed or required to be completed under § 60.8 of this part, whichever comes first, no owner or operator of an affected facility that combusts coal refuse alone in a fluidized bed combustion steam generating unit shall cause to be discharged into the atmosphere any gases that contain sulfur dioxide in excess of 20 percent of the potential sulfur dioxide emission rate (80 percent reduction) and that contain sulfur dioxide in excess of 520 ng/J (1.2 lb/million Btu) heat <PRTPAGE P="130"/>input. If coal or oil is fired with coal refuse, the affected facility is subject to paragraph (a) or (d) of this section, as applicable.</P>

              <P>(c) On and after the date on which the performance test is completed or is required to be completed under § 60.8 of this part, whichever comes first, no owner or operator of an affected facility that combusts coal or oil, either alone or in combination with any other fuel, and that uses an emerging technology for the control of sulfur dioxide emissions, shall cause to be discharged into the atmosphere any gases that contain sulfur dioxide in excess of 50 percent of the potential sulfur dioxide emission rate (50 percent reduction) and that contain sulfur dioxide in excess of the emission limit determined according to the following formula:
              </P>
              <FP SOURCE="FP-1">E<E T="52">s</E>=(K<E T="52">c</E> H<E T="52">c</E>+K<E T="52">d</E> H<E T="52">d</E>)/H<E T="52">c</E>+H<E T="52">d</E>)</FP>
              
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">E<E T="52">s</E> is the sulfur dioxide emission limit, expressed in ng/J (lb/million Btu) heat input,</FP>
                <FP SOURCE="FP-1">K<E T="52">c</E> is 260 ng/J (0.60 lb/million Btu),</FP>
                <FP SOURCE="FP-1">K<E T="52">d</E> is 170 ng/J (0.40 lb/million Btu),</FP>
                <FP SOURCE="FP-1">H<E T="52">c</E> is the heat input from the combustion of coal, J (million Btu),</FP>
                <FP SOURCE="FP-1">H<E T="52">d</E> is the heat input from the combustion of oil, J (million Btu).</FP>
              </EXTRACT>
              
              <FP>Only the heat input supplied to the affected facility from the combustion of coal and oil is counted under this section. No credit is provided for the heat input to the affected facility from the combustion of natural gas, wood, municipal-type solid waste, or other fuels, or from the heat input to the affected facility from exhaust gases from another source, such as gas turbines, internal combustion engines, kilns, etc.</FP>
              <P>(d) On and after the date on which the performance test is completed or required to be completed under § 60.8 of this part, whichever comes first, no owner or operator of an affected facility listed in paragraphs (d) (1), (2), or (3) of this section shall cause to be discharged into the atmosphere any gases that contain sulfur dioxide in excess of 520 ng/J (1.2 lb/million Btu) heat input if the affected facility combusts coal, or 215 ng/J (0.5 lb/million Btu) heat input if the affected facility combusts oil other than very low sulfur oil. Percent reduction requirements are not applicable to affected facilities under paragraphs (d)(1), (2), or (3).</P>
              <P>(1) Affected facilities that have an annual capacity factor for coal and oil of 30 percent (0.30) or less and are subject to a Federally enforceable permit limiting the operation of the affected facility to an annual capacity factor for coal and oil of 30 percent (0.30) or less;</P>
              <P>(2) Affected facilities located in a noncontinental area; or</P>
              <P>(3) Affected facilities combusting coal or oil, alone or in combination with any other fuel, in a duct burner as part of a combined cycle system where 30 percent (0.30) or less of the heat input to the steam generating unit is from combustion of coal and oil in the duct burner and 70 percent (0.70) or more of the heat input to the steam generating unit is from the exhaust gases entering the duct burner.</P>
              <P>(e) Except as provided in paragraph (f) of this section, compliance with the emission limits, fuel oil sulfur limits, and/or percent reduction requirements under this section are determined on a 30-day rolling average basis.</P>
              <P>(f) Except as provided in paragraph (j)(2) of this section, compliance with the emission limits or fuel oil sulfur limits under this section is determined on a 24-hour average basis for affected facilities that (1) have a Federally enforceable permit limiting the annual capacity factor for oil to 10 percent or less, (2) combust only very low sulfur oil, and (3) do not combust any other fuel.</P>
              <P>(g) Except as provided in paragraph (i) of this section, the sulfur dioxide emission limits and percent reduction requirements under this section apply at all times, including periods of startup, shutdown, and malfunction.</P>
              <P>(h) Reductions in the potential sulfur dioxide emission rate through fuel pretreatment are not credited toward the percent reduction requirement under paragraph (c) of this section unless:</P>
              <P>(1) Fuel pretreatment results in a 50 percent or greater reduction in potential sulfur dioxide emissions and</P>

              <P>(2) Emissions from the pretreated fuel (without combustion or post combustion sulfur dioxide control) are <PRTPAGE P="131"/>equal to or less than the emission limits specified in paragraph (c) of this section.</P>
              <P>(i) An affected facility subject to paragraph (a), (b), or (c) of this section may combust very low sulfur oil or natural gas when the sulfur dioxide control system is not being operated because of malfunction or maintenance of the sulfur dioxide control system.</P>
              <P>(j) Percent reduction requirements are not applicable to affected facilities combusting only very low sulfur oil. The owner or operator of an affected facility combusting very low sulfur oil shall demonstrate that the oil meets the definition of very low sulfur oil by: (1) Following the performance testing procedures as described in § 60.45b(c) or § 60.45b(d), and following the monitoring procedures as described in § 60.47b(a) or § 60.47b(b) to determine sulfur dioxide emission rate or fuel oil sulfur content; or (2) maintaining fuel receipts as described in § 60.49b(r).</P>
              <CITA>[52 FR 47842, Dec. 16, 1987, as amended at 54 FR 51819, Dec. 18, 1989; 65 FR 61752, Oct. 17, 2000]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.43b</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <P>(a) On and after the date on which the initial performance test is completed or is required to be completed under § 60.8 of this part, whichever comes first, no owner or operator of an affected facility which combusts coal or combusts mixtures of coal with other fuels, shall cause to be discharged into the atmosphere from that affected facility any gases that contain particulate matter in excess of the following emission limits:</P>
              <P>(1) 22 ng/J (0.051 lb/million Btu) heat input,</P>
              <P>(i) If the affected facility combusts only coal, or</P>
              <P>(ii) If the affected facility combusts coal and other fuels and has an annual capacity factor for the other fuels of 10 percent (0.10) or less.</P>
              <P>(2) 43 ng/J (0.10 lb/million Btu) heat input if the affected facility combusts coal and other fuels and has an annual capacity factor for the other fuels greater than 10 percent (0.10) and is subject to a federally enforceable requirement limiting operation of the affected facility to an annual capacity factor greater than 10 percent (0.10) for fuels other than coal.</P>
              <P>(3) 86 ng/J (0.20 lb/million Btu) heat input if the affected facility combusts coal or coal and other fuels and</P>
              <P>(i) Has an annual capacity factor for coal or coal and other fuels of 30 percent (0.30) or less,</P>
              <P>(ii) Has a maximum heat input capacity of 73 MW (250 million Btu/hour) or less,</P>
              <P>(iii) Has a federally enforceable requirement limiting operation of the affected facility to an annual capacity factor of 30 percent (0.30) or less for coal or coal and other solid fuels, and</P>
              <P>(iv) Construction of the affected facility commenced after June 19, 1984, and before November 25, 1986.</P>
              <P>(b) On and after the date on which the performance test is completed or required to be completed under 60.8 of this part, whichever date comes first, no owner or operator of an affected facility that combusts oil (or mixtures of oil with other fuels) and uses a conventional or emerging technology to reduce sulfur dioxide emissions shall cause to be discharged into the atmosphere from that affected facility any gases that contain particulate matter in excess of 43 ng/J (0.10 lb/million Btu) heat input.</P>
              <P>(c) On and after the date on which the initial performance test is completed or is required to be completed under § 60.8 of this part, whichever date comes first, no owner or operator of an affected facility that combusts wood, or wood with other fuels, except coal, shall cause to be discharged from that affected facility any gases that contain particulate matter in excess of the following emission limits:</P>
              <P>(1) 43 ng/J (0.10 lb/million Btu) heat input if the affected facility has an annual capacity factor greater than 30 percent (0.30) for wood.</P>
              <P>(2) 86 ng/J (0.20 lb/million Btu) heat input if</P>
              <P>(i) The affected facility has an annual capacity factor of 30 percent (0.30) or less for wood,</P>

              <P>(ii) Is subject to a federally enforceable requirement limiting operation of the affected facility to an annual capacity factor of 30 percent (0.30) or less for wood, and<PRTPAGE P="132"/>
              </P>
              <P>(iii) Has a maximum heat input capacity of 73 MW (250 million Btu/hour) or less.</P>
              <P>(d) On and after the date on which the initial performance test is completed or is required to be completed under § 60.8 of this part, whichever date comes first, no owner or operator of an affected facility that combusts municipal-type solid waste or mixtures of municipal-type solid waste with other fuels, shall cause to be discharged into the atmosphere from that affected facility any gases that contain particulate matter in excess of the following emission limits:</P>
              <P>(1) 43 ng/J (0.10 lb/million Btu) heat input,</P>
              <P>(i) If the affected facility combusts only municipal-type solid waste, or</P>
              <P>(ii) If the affected facility combusts municipal-type solid waste and other fuels and has an annual capacity factor for the other fuels of 10 percent (0.10) or less.</P>
              <P>(2) 86 ng/J (0.20 lb/million Btu) heat input if the affected facility combusts municipal-type solid waste or municipal-type solid waste and other fuels; and</P>
              <P>(i) Has an annual capacity factor for municipal-type solid waste and other fuels of 30 percent (0.30) or less,</P>
              <P>(ii) Has a maximum heat input capacity of 73 MW (250 million Btu/hour) or less,</P>
              <P>(iii) Has a federally enforceable requirement limiting operation of the affected facility to an annual capacity factor of 30 percent (0.30) for municipal-type solid waste, or municipal-type solid waste and other fuels, and</P>
              <P>(iv) Construction of the affected facility commenced after June 19, 1984, but before November 25, 1986.</P>
              <P>(e) For the purposes of this section, the annual capacity factor is determined by dividing the actual heat input to the steam generating unit during the calendar year from the combustion of coal, wood, or municipal-type solid waste, and other fuels, as applicable, by the potential heat input to the steam generating unit if the steam generating unit had been operated for 8,760 hours at the maximum design heat input capacity.</P>
              <P>(f) On and after the date on which the initial performance test is completed or is required to be completed under 60.8 of this part, whichever date comes first, no owner or operator of an affected facility that combusts coal, oil, wood, or mixtures of these fuels with any other fuels shall cause to be discharged into the atmosphere any gases that exhibit greater than 20 percent opacity (6-minute average), except for one 6-minute period per hour of not more than 27 percent opacity.</P>
              <P>(g) The particulate matter and opacity standards apply at all times, except during periods of startup, shutdown or malfunction.</P>
              <CITA>[52 FR 47842, Dec. 16, 1987, as amended at 54 FR 51819, Dec. 18, 1989; 65 FR 61752, Oct. 17, 2000]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.44b</SECTNO>
              <SUBJECT>Standard for nitrogen oxides.</SUBJECT>

              <P>(a) Except as provided under paragraphs (k) and (l) of this section, on and after the date on which the initial performance test is completed or is required to be completed under § 60.8 of this part, whichever date comes first, no owner or operator of an affected facility that is subject to the provisions of this section and that combusts only coal, oil, or natural gas shall cause to be discharged into the atmosphere from that affected facility any gases that contain nitrogen oxides (expressed as NO<E T="52">2</E>) in excess of the following emission limits:</P>
              <GPOTABLE CDEF="s25,12" COLS="2" OPTS="L2">
                <BOXHD>
                  <CHED H="1">Fuel/Steam generating unit type</CHED>
                  <CHED H="1">Nitrogen oxide emission limits ng/J (lb/million Btu) (expressed as NO<E T="52">2</E>) heat input</CHED>
                </BOXHD>
                <ROW>
                  <ENT I="11">(1) Natural gas and distillate oil, except (4):</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">(i) Low heat release rate</ENT>
                  <ENT>43 (0.10)</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">(ii) High heat release rate</ENT>
                  <ENT>86 (0.20)</ENT>
                </ROW>
                <ROW>
                  <ENT I="11">(2) Residual oil:</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">(i) Low heat release rate</ENT>
                  <ENT>130 (0.30)</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">(ii) High heat release rate</ENT>
                  <ENT>170 (0.40)</ENT>
                </ROW>
                <ROW>
                  <ENT I="11">(3) Coal:</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">(i) Mass-feed stoker</ENT>
                  <ENT>210 (0.50)</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">(ii) Spreader stoker and fluidized bed combustion</ENT>
                  <ENT>260 (0.60)</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">(iii) Pulverized coal</ENT>
                  <ENT>300 (0.70)</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">(iv) Lignite, except (v)</ENT>
                  <ENT>260 (0.60)</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">(v) Lignite mined in North Dakota, South Dakota, or Montana and combusted in a slag tap furnace</ENT>
                  <ENT>340 (0.80)</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">(vi) Coal-derived synthetic fuels</ENT>
                  <ENT>210 (0.50)</ENT>
                </ROW>
                <ROW>
                  <ENT I="11">(4) Duct burner used in a combined cycle system:</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">(i) Natural gas and distillate oil</ENT>
                  <ENT>86 (0.20)</ENT>
                </ROW>
                <ROW>
                  <ENT I="02">(ii) Residual oil</ENT>
                  <ENT>170 (0.40)</ENT>
                </ROW>
              </GPOTABLE>
              <PRTPAGE P="133"/>

              <P>(b) Except as provided under paragraphs (k) and (l) of this section, on and after the date on which the initial performance test is completed or is required to be completed under § 60.8 of this part, whichever date comes first, no owner or operator of an affected facility that simultaneously combusts mixtures of coal, oil, or natural gas shall cause to be discharged into the atmosphere from that affected facility any gases that contain nitrogen oxides in excess of a limit determined by the use of the following formula:
              </P>
              <FP SOURCE="FP-1">E<E T="52">n</E>=[(EL<E T="52">go</E> H<E T="52">go</E>)+(EL<E T="52">ro</E> H<E T="52">ro</E>)+(EL<E T="52">c</E> H<E T="52">c</E>)]/(H<E T="52">go</E>+H<E T="52">ro</E>+H<E T="52">c</E>)</FP>
              
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">E<E T="52">n</E> is the nitrogen oxides emission limit (expressed as NO<E T="52">2</E>), ng/J (lb/million Btu)</FP>
                <FP SOURCE="FP-1">EL<E T="52">go</E> is the appropriate emission limit from paragraph (a)(1) for combustion of natural gas or distillate oil, ng/J (lb/million Btu)</FP>
                <FP SOURCE="FP-1">H<E T="52">go</E> is the heat input from combustion of natural gas or distillate oil,</FP>
                <FP SOURCE="FP-1">EL<E T="52">ro</E> is the appropriate emission limit from paragraph (a)(2) for combustion of residual oil,</FP>
                <FP SOURCE="FP-1">H<E T="52">ro</E> is the heat input from combustion of residual oil,</FP>
                <FP SOURCE="FP-1">EL<E T="52">c</E> is the appropriate emission limit from paragraph (a)(3) for combustion of coal, and</FP>
                <FP SOURCE="FP-1">H<E T="52">c</E> is the heat input from combustion of coal.</FP>
              </EXTRACT>
              
              <P>(c) Except as provided under paragraph (l) of this section, on and after the date on which the initial performance test is completed or is required to be completed under § 60.8 of this part, whichever date comes first, no owner or operator of an affected facility that simultaneously combusts coal or oil, or a mixture of these fuels with natural gas, and wood, municipal-type solid waste, or any other fuel shall cause to be discharged into the atmosphere any gases that contain nitrogen oxides in excess of the emission limit for the coal or oil, or mixtures of these fuels with natural gas combusted in the affected facility, as determined pursuant to paragraph (a) or (b) of this section, unless the affected facility has an annual capacity factor for coal or oil, or mixture of these fuels with natural gas of 10 percent (0.10) or less and is subject to a federally enforceable requirement that limits operation of the affected facility to an annual capacity factor of 10 percent (0.10) or less for coal, oil, or a mixture of these fuels with natural gas.</P>
              <P>(d) On and after the date on which the initial performance test is completed or is required to be completed under § 60.8 of this part, whichever date comes first, no owner or operator of an affected facility that simultaneously combusts natural gas with wood, municipal-type solid waste, or other solid fuel, except coal, shall cause to be discharged into the atmosphere from that affected facility any gases that contain nitrogen oxides in excess of 130 ng/J (0.30 lb/million Btu) heat input unless the affected facility has an annual capacity factor for natural gas of 10 percent (0.10) or less and is subject to a federally enforceable requirement that limits operation of the affected facility to an annual capacity factor of 10 percent (0.10) or less for natural gas.</P>

              <P>(e) Except as provided under paragraph (l) of this section, on and after the date on which the initial performance test is completed or is required to be completed under § 60.8 of this part, whichever date comes first, no owner or operator of an affected facility that simultaneously combusts coal, oil, or natural gas with byproduct/waste shall cause to be discharged into the atmosphere any gases that contain nitrogen oxides in excess of the emission limit determined by the following formula unless the affected facility has an annual capacity factor for coal, oil, and natural gas of 10 percent (0.10) or less and is subject to a federally enforceable requirement that limits operation of the affected facility to an annual capacity factor of 10 percent (0.10) or less:
              </P>
              <FP SOURCE="FP-1">E<E T="52">n</E>=[(EL<E T="52">go</E> H<E T="52">go</E>)+(EL<E T="52">ro</E> H<E T="52">ro</E>)+ (EL<E T="52">c</E> H<E T="52">c</E>)]/(H<E T="52">go</E>+H<E T="52">ro</E>+H<E T="52">c</E>)</FP>
              
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">E<E T="52">n</E> is the nitrogen oxides emission limit (expressed as NO<E T="52">2</E>), ng/J (lb/million Btu)</FP>
                <FP SOURCE="FP-1">EL<E T="52">go</E> is the appropriate emission limit from paragraph (a)(1) for combustion of natural gas or distillate oil, ng/J (lb/million Btu).</FP>
                <FP SOURCE="FP-1">H<E T="52">go</E> is the heat input from combustion of natural gas, distillate oil and gaseous byproduct/waste, ng/J (lb/million Btu).</FP>
                <FP SOURCE="FP-1">EL<E T="52">ro</E> is the appropriate emission limit from paragraph (a)(2) for combustion of residual oil, ng/J (lb/million Btu)</FP>
                <FP SOURCE="FP-1">H<E T="52">ro</E> is the heat input from combustion of residual oil and/or liquid byproduct/waste.<PRTPAGE P="134"/>
                </FP>
                <FP SOURCE="FP-1">EL<E T="52">c</E> is the appropriate emission limit from paragraph (a)(3) for combustion of coal, and</FP>
                <FP SOURCE="FP-1">H<E T="52">c</E> is the heat input from combustion of coal.</FP>
              </EXTRACT>
              
              <P>(f) Any owner or operator of an affected facility that combusts byproduct/waste with either natural gas or oil may petition the Administrator within 180 days of the initial startup of the affected facility to establish a nitrogen oxides emission limit which shall apply specifically to that affected facility when the byproduct/waste is combusted. The petition shall include sufficient and appropriate data, as determined by the Administrator, such as nitrogen oxides emissions from the affected facility, waste composition (including nitrogen content), and combustion conditions to allow the Administrator to confirm that the affected facility is unable to comply with the emission limits in paragraph (e) of this section and to determine the appropriate emission limit for the affected facility.</P>
              <P>(1) Any owner or operator of an affected facility petitioning for a facility-specific nitrogen oxides emission limit under this section shall:</P>
              <P>(i) Demonstrate compliance with the emission limits for natural gas and distillate oil in paragraph (a)(1) of this section or for residual oil in paragraph (a)(2) of this section, as appropriate, by conducting a 30-day performance test as provided in § 60.46b(e). During the performance test only natural gas, distillate oil, or residual oil shall be combusted in the affected facility; and</P>
              <P>(ii) Demonstrate that the affected facility is unable to comply with the emission limits for natural gas and distillate oil in paragraph (a)(1) of this section or for residual oil in paragraph (a)(2) of this section, as appropriate, when gaseous or liquid byproduct/waste is combusted in the affected facility under the same conditions and using the same technological system of emission reduction applied when demonstrating compliance under paragraph (f)(1)(i) of this section.</P>
              <P>(2) The nitrogen oxides emission limits for natural gas or distillate oil in paragraph (a)(1) of this section or for residual oil in paragraph (a)(2) of this section, as appropriate, shall be applicable to the affected facility until and unless the petition is approved by the Administrator. If the petition is approved by the Administrator, a facility-specific nitrogen oxides emission limit will be established at the nitrogen oxides emission level achievable when the affected facility is combusting oil or natural gas and byproduct/waste in a manner that the Administrator determines to be consistent with minimizing nitrogen oxides emissions.</P>
              <P>(g) Any owner or operator of an affected facility that combusts hazardous waste (as defined by 40 CFR part 261 or 40 CFR part 761) with natural gas or oil may petition the Administrator within 180 days of the initial startup of the affected facility for a waiver from compliance with the nitrogen oxides emission limit which applies specifically to that affected facility. The petition must include sufficient and appropriate data, as determined by the Administrator, on nitrogen oxides emissions from the affected facility, waste destruction efficiencies, waste composition (including nitrogen content), the quantity of specific wastes to be combusted and combustion conditions to allow the Administrator to determine if the affected facility is able to comply with the nitrogen oxides emission limits required by this section. The owner or operator of the affected facility shall demonstrate that when hazardous waste is combusted in the affected facility, thermal destruction efficiency requirements for hazardous waste specified in an applicable federally enforceable requirement preclude compliance with the nitrogen oxides emission limits of this section. The nitrogen oxides emission limits for natural gas or distillate oil in paragraph (a)(1) of this section or for residual oil in paragraph (a)(2) of this section, as appropriate, are applicable to the affected facility until and unless the petition is approved by the Administrator. (See 40 CFR 761.70 for regulations applicable to the incineration of materials containing polychlorinated biphenyls (PCB's).)</P>

              <P>(h) For purposes of paragraph (i) of this section, the nitrogen oxide standards under this section apply at all times including periods of startup, shutdown, or malfunction.<PRTPAGE P="135"/>
              </P>
              <P>(i) Except as provided under paragraph (j) of this section, compliance with the emission limits under this section is determined on a 30-day rolling average basis.</P>
              <P>(j) Compliance with the emission limits under this section is determined on a 24-hour average basis for the initial performance test and on a 3-hour average basis for subsequent performance tests for any affected facilities that:</P>
              <P>(1) Combust, alone or in combination, only natural gas, distillate oil, or residual oil with a nitrogen content of 0.30 weight percent or less;</P>
              <P>(2) Have a combined annual capacity factor of 10 percent or less for natural gas, distillate oil, and residual oil with a nitrogen content of 0.30 weight percent or less; and</P>
              <P>(3) Are subject to a Federally enforceable requirement limiting operation of the affected facility to the firing of natural gas, distillate oil, and/or residual oil with a nitrogen content of 0.30 weight percent or less and limiting operation of the affected facility to a combined annual capacity factor of 10 percent or less for natural gas, distillate oil, and residual oil and a nitrogen content of 0.30 weight percent or less.</P>
              <P>(k) Affected facilities that meet the criteria described in paragraphs (j) (1), (2), and (3) of this section, and that have a heat input capacity of 73 MW (250 million Btu/hour) or less, are not subject to the nitrogen oxides emission limits under this section.</P>

              <P>(l) On and after the date on which the initial performance test is completed or is required to be completed under § 60.8, whichever date comes first, no owner or operator of an affected facility which commenced construction or reconstruction after July 9, 1997 shall cause to be discharged into the atmosphere from that affected facility any gases that contain nitrogen oxides (expressed as NO<E T="52">2</E>) in excess of the following limits:</P>

              <P>(1) If the affected facility combusts coal, oil, or natural gas, or a mixture of these fuels, or with any other fuels: A limit of 86 ng/J<E T="52">I</E> (0.20 lb/million Btu) heat input unless the affected facility has an annual capacity factor for coal, oil, and natural gas of 10 percent (0.10) or less and is subject to a federally enforceable requirement that limits operation of the facility to an annual capacity factor of 10 percent (0.10) or less for coal, oil, and natural gas; or</P>

              <P>(2) If the affected facility has a low heat release rate and combusts natural gas or distillate oil in excess of 30 percent of the heat input from the combustion of all fuels, a limit determined by use of the following formula:
              </P>
              <FP SOURCE="FP-1">E<E T="52">n</E> = [(0.10 * H<E T="52">go</E>) + (0.20 * H<E T="52">r</E>)]/(H<E T="52">go</E> + H<E T="52">r</E>)</FP>
              
              <EXTRACT>
                <FP>Where:</FP>
                
                <FP SOURCE="FP-1">E<E T="52">n</E> is the NO<E T="52">X</E> emission limit, (lb/million Btu),</FP>
                <FP SOURCE="FP-1">H<E T="52">go</E> is the heat input from combustion of natural gas or distillate oil, and</FP>
                <FP SOURCE="FP-1">H<E T="52">r</E> is the heat input from combustion of any other fuel.</FP>
              </EXTRACT>
              <CITA>[52 FR 47842, Dec. 16, 1987, as amended at 54 FR 51825, Dec. 18, 1989; 63 FR 49454, Sept. 16, 1998; 66 FR 42610, Aug. 14, 2001]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.45b</SECTNO>
              <SUBJECT>Compliance and performance test methods and procedures for sulfur dioxide.</SUBJECT>
              <P>(a) The sulfur dioxide emission standards under § 60.42b apply at all times.</P>
              <P>(b) In conducting the performance tests required under § 60.8, the owner or operator shall use the methods and procedures in appendix A of this part or the methods and procedures as specified in this section, except as provided in § 60.8(b). Section 60.8(f) does not apply to this section. The 30-day notice required in § 60.8(d) applies only to the initial performance test unless otherwise specified by the Administrator.</P>

              <P>(c) The owner or operator of an affected facility shall conduct performance tests to determine compliance with the percent of potential sulfur dioxide emission rate (% P<E T="52">s</E>) and the sulfur dioxide emission rate (E<E T="52">s</E>) pursuant to § 60.42b following the procedures listed below, except as provided under paragraph (d) of this section.</P>

              <P>(1) The initial performance test shall be conducted over the first 30 consecutive operating days of the steam generating unit. Compliance with the sulfur dioxide standards shall be determined using a 30-day average. The first operating day included in the initial performance test shall be scheduled within 30 days after achieving the maximum production rate at which the affected facility will be operated, but not later <PRTPAGE P="136"/>than 180 days after initial startup of the facility.</P>
              <P>(2) If only coal or only oil is combusted, the following procedures are used:</P>

              <P>(i) The procedures in Method 19 are used to determine the hourly sulfur dioxide emission rate (E<E T="52">ho</E>) and the 30-day average emission rate (E<E T="52">ao</E>). The hourly averages used to compute the 30-day averages are obtained from the continuous emission monitoring system of § 60.47b (a) or (b).</P>

              <P>(ii) The percent of potential sulfur dioxide emission rate (% P<E T="52">s</E>) emitted to the atmosphere is computed using the following formula:
              </P>
              <FP SOURCE="FP-1">% P<E T="52">s</E>=100 (1−% R<E T="52">g</E>/100)(1−% R<E T="52">f</E>/100)</FP>
              
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">% R<E T="52">g</E> is the sulfur dioxide removal efficiency of the control device as determined by Method 19, in percent.</FP>
                <FP SOURCE="FP-1">% R<E T="52">f</E> is the sulfur dioxide removal efficiency of fuel pretreatment as determined by Method 19, in percent.</FP>
              </EXTRACT>
              
              <P>(3) If coal or oil is combusted with other fuels, the same procedures required in paragraph (c)(2) of this section are used, except as provided in the following:</P>

              <P>(i) An adjusted hourly sulfur dioxide emission rate (E<E T="52">ho</E>
                <E T="51">o</E>) is used in Equation 19-19 of Method 19 to compute an adjusted 30-day average emission rate (E<E T="52">ao</E>
                <E T="51">o</E>). The E<E T="52">ho</E> is computed using the following formula:
              </P>
              <FP SOURCE="FP-1">E<E T="52">ho</E>
                <E T="51">o</E>=[E<E T="52">ho</E>−E<E T="52">w</E>(1−X<E T="52">k</E>)]/X<E T="52">k</E>
              </FP>
              
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">E<E T="52">ho</E>
                  <E T="51">o</E> is the adjusted hourly sulfur dioxide emission rate, ng/J (lb/million Btu).</FP>
                <FP SOURCE="FP-1">E<E T="52">ho</E> is the hourly sulfur dioxide emission rate, ng/J (lb/million Btu).</FP>
                <FP SOURCE="FP-1">E<E T="52">w</E> is the sulfur dioxide concentration in fuels other than coal and oil combusted in the affected facility, as determined by the fuel sampling and analysis procedures in Method 19, ng/J (lb/million Btu). The value E<E T="52">w</E> for each fuel lot is used for each hourly average during the time that the lot is being combusted.</FP>
                <FP SOURCE="FP-1">X<E T="52">k</E> is the fraction of total heat input from fuel combustion derived from coal, oil, or coal and oil, as determined by applicable procedures in Method 19.</FP>
              </EXTRACT>
              

              <P>(ii) To compute the percent of potential sulfur dioxide emission rate (% P<E T="52">s</E>), an adjusted % R<E T="52">g</E> (% R<E T="52">g</E>
                <E T="51">o</E>) is computed from the adjusted E<E T="52">ao</E>
                <E T="51">o</E> from paragraph (b)(3)(i) of this section and an adjusted average sulfur dioxide inlet rate (E<E T="52">ai</E>
                <E T="51">o</E>) using the following formula:
              </P>
              <FP SOURCE="FP-1">% R<E T="52">g</E>
                <E T="51">o</E>=100 (1.0−E<E T="52">ao</E>
                <E T="51">o</E>/E<E T="52">ai</E>
                <E T="51">o</E>)</FP>
              
              <FP>To compute E<E T="52">ai</E>
                <E T="51">o</E>, an adjusted hourly sulfur dioxide inlet rate (E<E T="52">hi</E>
                <E T="51">o</E>) is used. The E<E T="52">hi</E>
                <E T="51">o</E> is computed using the following formula:</FP>
              
              <FP SOURCE="FP-1">E<E T="52">hi</E>
                <E T="51">o</E>=[E<E T="52">hi</E>−E<E T="52">w</E>(1−X<E T="52">k</E>)]/X<E T="52">k</E>
              </FP>
              
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">E<E T="52">hi</E>
                  <E T="51">o</E> is the adjusted hourly sulfur dioxide inlet rate, ng/J (lb/million Btu).</FP>
                <FP SOURCE="FP-1">E<E T="52">hi</E> is the hourly sulfur dioxide inlet rate, ng/J (lb/million Btu).</FP>
              </EXTRACT>
              

              <P>(4) The owner or operator of an affected facility subject to paragraph (b)(3) of this section does not have to measure parameters E<E T="52">w</E> or X<E T="52">k</E> if the owner or operator elects to assume that X<E T="52">k</E>=1.0. Owners or operators of affected facilities who assume X<E T="52">k</E>=1.0 shall</P>
              <P>(i) Determine % P<E T="52">s</E> following the procedures in paragraph (c)(2) of this section, and</P>
              <P>(ii) Sulfur dioxide emissions (E<E T="52">s</E>) are considered to be in compliance with sulfur dioxide emission limits under § 60.42b.</P>

              <P>(5) The owner or operator of an affected facility that qualifies under the provisions of § 60.42b(d) does not have to measure parameters E<E T="52">w</E> or X<E T="52">k</E> under paragraph (b)(3) of this section if the owner or operator of the affected facility elects to measure sulfur dioxide emission rates of the coal or oil following the fuel sampling and analysis procedures under Method 19.</P>
              <P>(d) Except as provided in paragraph (j), the owner or operator of an affected facility that combusts only very low sulfur oil, has an annual capacity factor for oil of 10 percent (0.10) or less, and is subject to a Federally enforceable requirement limiting operation of the affected facility to an annual capacity factor for oil of 10 percent (0.10) or less shall:</P>
              <P>(1) Conduct the initial performance test over 24 consecutive steam generating unit operating hours at full load;</P>

              <P>(2) Determine compliance with the standards after the initial performance test based on the arithmetic average of the hourly emissions data during each steam generating unit operating day if a continuous emission measurement <PRTPAGE P="137"/>system (CEMS) is used, or based on a daily average if Method 6B or fuel sampling and analysis procedures under Method 19 are used.</P>
              <P>(e) The owner or operator of an affected facility subject to § 60.42b(d)(1) shall demonstrate the maximum design capacity of the steam generating unit by operating the facility at maximum capacity for 24 hours. This demonstration will be made during the initial performance test and a subsequent demonstration may be requested at any other time. If the 24-hour average firing rate for the affected facility is less than the maximum design capacity provided by the manufacturer of the affected facility, the 24-hour average firing rate shall be used to determine the capacity utilization rate for the affected facility, otherwise the maximum design capacity provided by the manufacturer is used.</P>
              <P>(f) For the initial performance test required under § 60.8, compliance with the sulfur dioxide emission limits and percent reduction requirements under § 60.42b is based on the average emission rates and the average percent reduction for sulfur dioxide for the first 30 consecutive steam generating unit operating days, except as provided under paragraph (d) of this section. The initial performance test is the only test for which at least 30 days prior notice is required unless otherwise specified by the Administrator. The initial performance test is to be scheduled so that the first steam generating unit operating day of the 30 successive steam generating unit operating days is completed within 30 days after achieving the maximum production rate at which the affected facility will be operated, but not later than 180 days after initial startup of the facility. The boiler load during the 30-day period does not have to be the maximum design load, but must be representative of future operating conditions and include at least one 24-hour period at full load.</P>
              <P>(g) After the initial performance test required under § 60.8, compliance with the sulfur dioxide emission limits and percent reduction requirements under § 60.42b is based on the average emission rates and the average percent reduction for sulfur dioxide for 30 successive steam generating unit operating days, except as provided under paragraph (d). A separate performance test is completed at the end of each steam generating unit operating day after the initial performance test, and a new 30-day average emission rate and percent reduction for sulfur dioxide are calculated to show compliance with the standard.</P>

              <P>(h) Except as provided under paragraph (i) of this section, the owner or operator of an affected facility shall use all valid sulfur dioxide emissions data in calculating % P<E T="52">s</E> and E<E T="52">ho</E> under paragraph (c), of this section whether or not the minimum emissions data requirements under § 60.46b are achieved. All valid emissions data, including valid sulfur dioxides emission data collected during periods of startup, shutdown and malfunction, shall be used in calculating % P<E T="52">s</E> and E<E T="52">ho</E> pursuant to paragraph (c) of this section.</P>

              <P>(i) During periods of malfunction or maintenance of the sulfur dioxide control systems when oil is combusted as provided under § 60.42b(i), emission data are not used to calculate % P<E T="52">s</E> or E<E T="52">s</E> under § 60.42b (a), (b) or (c), however, the emissions data are used to determine compliance with the emission limit under § 60.42b(i).</P>
              <P>(j) The owner or operator of an affected facility that combusts very low sulfur oil is not subject to the compliance and performance testing requirements of this section if the owner or operator obtains fuel receipts as described in § 60.49b(r).</P>
              <CITA>[52 FR 47842, Dec. 16, 1987, as amended at 54 FR 51820, 51825, Dec. 18, 1989]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.46b</SECTNO>
              <SUBJECT>Compliance and performance test methods and procedures for particulate matter and nitrogen oxides.</SUBJECT>
              <P>(a) The particulate matter emission standards and opacity limits under § 60.43b apply at all times except during periods of startup, shutdown, or malfunction. The nitrogen oxides emission standards under § 60.44b apply at all times.</P>

              <P>(b) Compliance with the particulate matter emission standards under § 60.43b shall be determined through performance testing as described in paragraph (d) of this section.<PRTPAGE P="138"/>
              </P>
              <P>(c) Compliance with the nitrogen oxides emission standards under § 60.44b shall be determined through performance testing under paragraph (e) or (f), or under paragraphs (g) and (h) of this section, as applicable.</P>
              <P>(d) To determine compliance with the particulate matter emission limits and opacity limits under § 60.43b, the owner or operator of an affected facility shall conduct an initial performance test as required under § 60.8 using the following procedures and reference methods:</P>
              <P>(1) Method 3B is used for gas analysis when applying Method 5 or Method 17.</P>
              <P>(2) Method 5, Method 5B, or Method 17 shall be used to measure the concentration of particulate matter as follows:</P>
              <P>(i) Method 5 shall be used at affected facilities without wet flue gas desulfurization (FGD) systems; and</P>
              <P>(ii) Method 17 may be used at facilities with or without wet scrubber systems provided the stack gas temperature does not exceed a temperature of 160 °C (320 °F). The procedures of sections 2.1 and 2.3 of Method 5B may be used in Method 17 only if it is used after a wet FGD system. Do not use Method 17 after wet FGD systems if the effluent is saturated or laden with water droplets.</P>
              <P>(iii) Method 5B is to be used only after wet FGD systems.</P>
              <P>(3) Method 1 is used to select the sampling site and the number of traverse sampling points. The sampling time for each run is at least 120 minutes and the minimum sampling volume is 1.7 dscm (60 dscf) except that smaller sampling times or volumes may be approved by the Administrator when necessitated by process variables or other factors.</P>
              <P>(4) For Method 5, the temperature of the sample gas in the probe and filter holder is monitored and is maintained at 160±14 °C (320±25 °F).</P>
              <P>(5) For determination of particulate matter emissions, the oxygen or carbon dioxide sample is obtained simultaneously with each run of Method 5, Method 5B or Method 17 by traversing the duct at the same sampling location.</P>
              <P>(6) For each run using Method 5, Method 5B or Method 17, the emission rate expressed in nanograms per joule heat input is determined using:</P>
              <P>(i) The oxygen or carbon dioxide measurements and particulate matter measurements obtained under this section,</P>
              <P>(ii) The dry basis F factor, and</P>
              <P>(iii) The dry basis emission rate calculation procedure contained in Method 19.</P>
              <P>(7) Method 9 is used for determining the opacity of stack emissions.</P>
              <P>(e) To determine compliance with the emission limits for nitrogen oxides required under § 60.44b, the owner or operator of an affected facility shall conduct the performance test as required under § 60.8 using the continuous system for monitoring nitrogen oxides under § 60.48(b).</P>
              <P>(1) For the initial compliance test, nitrogen oxides from the steam generating unit are monitored for 30 successive steam generating unit operating days and the 30-day average emission rate is used to determine compliance with the nitrogen oxides emission standards under § 60.44b. The 30-day average emission rate is calculated as the average of all hourly emissions data recorded by the monitoring system during the 30-day test period.</P>
              <P>(2) Following the date on which the initial performance test is completed or is required to be completed under § 60.8 of this part, whichever date comes first, the owner or operator of an affected facility which combusts coal or which combusts residual oil having a nitrogen content greater than 0.30 weight percent shall determine compliance with the nitrogen oxides emission standards under § 60.44b on a continuous basis through the use of a 30-day rolling average emission rate. A new 30-day rolling average emission rate is calculated each steam generating unit operating day as the average of all of the hourly nitrogen oxides emission data for the preceding 30 steam generating unit operating days.</P>

              <P>(3) Following the date on which the initial performance test is completed or is required to be completed under § 60.8 of this part, whichever date comes first, the owner or operator of an affected facility which has a heat input <PRTPAGE P="139"/>capacity greater than 73 MW (250 million Btu/hour) and which combusts natural gas, distillate oil, or residual oil having a nitrogen content of 0.30 weight percent or less shall determine compliance with the nitrogen oxides standards under § 60.44b on a continuous basis through the use of a 30-day rolling average emission rate. A new 30-day rolling average emission rate is calculated each steam generating unit operating day as the average of all of the hourly nitrogen oxides emission data for the preceding 30 steam generating unit operating days.</P>
              <P>(4) Following the date on which the initial performance test is completed or required to be completed under § 60.8 of this part, whichever date comes first, the owner or operator of an affected facility which has a heat input capacity of 73 MW (250 million Btu/hour) or less and which combusts natural gas, distillate oil, or residual oil having a nitrogen content of 0.30 weight percent or less shall upon request determine compliance with the nitrogen oxides standards under § 60.44b through the use of a 30-day performance test. During periods when performance tests are not requested, nitrogen oxides emissions data collected pursuant to § 60.48b(g)(1) or § 60.48b(g)(2) are used to calculate a 30-day rolling average emission rate on a daily basis and used to prepare excess emission reports, but will not be used to determine compliance with the nitrogen oxides emission standards. A new 30-day rolling average emission rate is calculated each steam generating unit operating day as the average of all of the hourly nitrogen oxides emission data for the preceding 30 steam generating unit operating days.</P>
              <P>(5) If the owner or operator of an affected facility which combusts residual oil does not sample and analyze the residual oil for nitrogen content, as specified in § 60.49b(e), the requirements of paragraph (iii) of this section apply and the provisions of paragraph (iv) of this section are inapplicable.</P>

              <P>(f) To determine compliance with the emissions limits for NO<E T="52">X</E> required by § 60.44b(a)(4) or § 60.44b(l) for duct burners used in combined cycle systems, either of the procedures described in paragraph (f)(1) or (2) of this section may be used:</P>
              <P>(1) The owner or operator of an affected facility shall conduct the performance test required under § 60.8 as follows:</P>
              <P>(i) The emissions rate (E) of NO<E T="52">X</E> shall be computed using Equation of 1 this section:
              </P>
              <FP SOURCE="FP-1">E = Esg + (Hg /Hb)(Esg − Eg) (Eq. 1)</FP>
              
              <EXTRACT>
                <FP>Where:</FP>
                
                <FP SOURCE="FP-1">E = emissions rate of NO<E T="52">X</E> from the duct burner, ng/J (lb/million Btu) heat input</FP>
                <FP SOURCE="FP-1">Esg = combined effluent emissions rate, in ng/J (lb/million Btu) heat input using appropriate F-Factor as described in Method 19</FP>
                <FP SOURCE="FP-1">Hg = heat input rate to the combustion turbine, in Joules/hour (million Btu/hour)</FP>
                <FP SOURCE="FP-1">Hb = heat input rate to the duct burner, in Joules/hour (million Btu/hour)</FP>
                <FP SOURCE="FP-1">Eg = emissions rate from the combustion turbine, in ng/J (lb/million Btu) heat input calculated using appropriate F-Factor as described in Method 19</FP>
              </EXTRACT>
              

              <P>(ii) Method 7E of appendix A of this part shall be used to determine the NO<E T="52">X</E> concentrations. Method 3A or 3B of appendix A of this part shall be used to determine oxygen concentration.</P>
              <P>(iii) The owner or operator shall identify and demonstrate to the Administrator's satisfaction suitable methods to determine the average hourly heat input rate to the combustion turbine and the average hourly heat input rate to the affected duct burner.</P>
              <P>(iv) Compliance with the emissions limits under § 60.44b (a)(4) or § 60.44b(l) is determined by the three-run average (nominal 1-hour runs) for the initial and subsequent performance tests; or</P>

              <P>(2) The owner or operator of an affected facility may elect to determine compliance on a 30-day rolling average basis by using the continuous emission monitoring system specified under § 60.48b for measuring NO<E T="52">X</E> and oxygen and meet the requirements of § 60.48b. The sampling site shall be located at the outlet from the steam generating unit. The NO<E T="52">X</E> emissions rate at the outlet from the steam generating unit shall constitute the NO<E T="52">X</E> emissions rate from the duct burner of the combined cycle system.</P>

              <P>(g) The owner or operator of an affected facility described in § 60.44b(j) or <PRTPAGE P="140"/>§ 60.44b(k) shall demonstrate the maximum heat input capacity of the steam generating unit by operating the facility at maximum capacity for 24 hours. The owner or operator of an affected facility shall determine the maximum heat input capacity using the heat loss method described in sections 5 and 7.3 of the ASME <E T="03">Power Test Codes</E> 4.1 (see IBR § 60.17(h)). This demonstration of maximum heat input capacity shall be made during the initial performance test for affected facilities that meet the criteria of § 60.44b(j). It shall be made within 60 days after achieving the maximum production rate at which the affected facility will be operated, but not later than 180 days after initial start-up of each facility, for affected facilities meeting the criteria of § 60.44b(k). Subsequent demonstrations may be required by the Administrator at any other time. If this demonstration indicates that the maximum heat input capacity of the affected facility is less than that stated by the manufacturer of the affected facility, the maximum heat input capacity determined during this demonstration shall be used to determine the capacity utilization rate for the affected facility. Otherwise, the maximum heat input capacity provided by the manufacturer is used.</P>
              <P>(h) The owner or operator of an affected facility described in § 60.44b(j) that has a heat input capacity greater than 73 MW (250 million Btu/hour) shall:</P>
              <P>(1) Conduct an initial performance test as required under § 60.8 over a minimum of 24 consecutive steam generating unit operating hours at maximum heat input capacity to demonstrate compliance with the nitrogen oxides emission standards under § 60.44b using Method 7, 7A, 7E, or other approved reference methods; and</P>
              <P>(2) Conduct subsequent performance tests once per calendar year or every 400 hours of operation (whichever comes first) to demonstrate compliance with the nitrogen oxides emission standards under § 60.44b over a minimum of 3 consecutive steam generating unit operating hours at maximum heat input capacity using Method 7, 7A, 7E, or other approved reference methods.</P>
              <CITA>[52 FR 47842, Dec. 16, 1987, as amended at 54 FR 51820, 51825, Dec. 18, 1989; 55 FR 18876, May 7, 1990; 65 FR 61752, Oct. 17, 2000; 66 FR 18553, Apr. 10, 2001]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.47b</SECTNO>
              <SUBJECT>Emission monitoring for sulfur dioxide.</SUBJECT>

              <P>(a) Except as provided in paragraphs (b) and (f) of this section, the owner or operator of an affected facility subject to the sulfur dioxide standards under § 60.42b shall install, calibrate, maintain, and operate continuous emission monitoring systems (CEMS) for measuring sulfur dioxide concentrations and either oxygen (O<E T="52">2</E>) or carbon dioxide (CO<E T="52">2</E>) concentrations and shall record the output of the systems. The sulfur dioxide and either oxygen or carbon dioxide concentrations shall both be monitored at the inlet and outlet of the sulfur dioxide control device.</P>
              <P>(b) As an alternative to operating CEMS as required under paragraph (a) of this section, an owner or operator may elect to determine the average sulfur dioxide emissions and percent reduction by:</P>
              <P>(1) Collecting coal or oil samples in an as-fired condition at the inlet to the steam generating unit and analyzing them for sulfur and heat content according to Method 19. Method 19 provides procedures for converting these measurements into the format to be used in calculating the average sulfur dioxide input rate, or</P>

              <P>(2) Measuring sulfur dioxide according to Method 6B at the inlet or outlet to the sulfur dioxide control system. An initial stratification test is required to verify the adequacy of the Method 6B sampling location. The stratification test shall consist of three paired runs of a suitable sulfur dioxide and carbon dioxide measurement train operated at the candidate location and a second similar train operated according to the procedures in section 3.2 and the applicable procedures in section 7 of Performance Specification 2. Method 6B, Method 6A, or a combination of Methods 6 and 3 or 3B or Methods 6C <PRTPAGE P="141"/>and 3A are suitable measurement techniques. If Method 6B is used for the second train, sampling time and timer operation may be adjusted for the stratification test as long as an adequate sample volume is collected; however, both sampling trains are to be operated similarly. For the location to be adequate for Method 6B 24-hour tests, the mean of the absolute difference between the three paired runs must be less than 10 percent.</P>
              <P>(3) A daily sulfur dioxide emission rate, E<E T="52">D</E>, shall be determined using the procedure described in Method 6A, section 7.6.2 (Equation 6A-8) and stated in ng/J (lb/million Btu) heat input.</P>
              <P>(4) The mean 30-day emission rate is calculated using the daily measured values in ng/J (lb/million Btu) for 30 successive steam generating unit operating days using equation 19-20 of Method 19.</P>
              <P>(c) The owner or operator of an affected facility shall obtain emission data for at least 75 percent of the operating hours in at least 22 out of 30 successive boiler operating days. If this minimum data requirement is not met with a single monitoring system, the owner or operator of the affected facility shall supplement the emission data with data collected with other monitoring systems as approved by the Administrator or the reference methods and procedures as described in paragraph (b) of this section.</P>
              <P>(d) The 1-hour average sulfur dioxide emission rates measured by the CEMS required by paragraph (a) of this section and required under § 60.13(h) is expressed in ng/J or lb/million Btu heat input and is used to calculate the average emission rates under § 60.42b. Each 1-hour average sulfur dioxide emission rate must be based on more than 30 minutes of steam generating unit operation and include at least 2 data points with each representing a 15-minute period. Hourly sulfur dioxide emission rates are not calculated if the affected facility is operated less than 30 minutes in a 1-hour period and are not counted toward determination of a steam generating unit operating day.</P>
              <P>(e) The procedures under § 60.13 shall be followed for installation, evaluation, and operation of the CEMS.</P>
              <P>(1) All CEMS shall be operated in accordance with the applicable procedures under Performance Specifications 1, 2, and 3 (appendix B).</P>
              <P>(2) Quarterly accuracy determinations and daily calibration drift tests shall be performed in accordance with Procedure 1 (appendix F).</P>
              <P>(3) For affected facilities combusting coal or oil, alone or in combination with other fuels, the span value of the sulfur dioxide CEMS at the inlet to the sulfur dioxide control device is 125 percent of the maximum estimated hourly potential sulfur dioxide emissions of the fuel combusted, and the span value of the CEMS at the outlet to the sulfur dioxide control device is 50 percent of the maximum estimated hourly potential sulfur dioxide emissions of the fuel combusted.</P>
              <P>(f) The owner or operator of an affected facility that combusts very low sulfur oil is not subject to the emission monitoring requirements of this section if the owner or operator obtains fuel receipts as described in § 60.49b(r).</P>
              <CITA>[52 FR 47842, Dec. 16, 1987, as amended at 54 FR 51820, Dec. 18, 1989; 55 FR 5212, Feb. 14, 1990; 55 FR 18876, May 7, 1990]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.48b</SECTNO>
              <SUBJECT>Emission monitoring for particulate matter and nitrogen oxides.</SUBJECT>
              <P>(a) The owner or operator of an affected facility subject to the opacity standard under § 60.43b shall install, calibrate, maintain, and operate a continuous monitoring system for measuring the opacity of emissions discharged to the atmosphere and record the output of the system.</P>
              <P>(b) Except as provided under paragraphs (g), (h), and (i) of this section, the owner or operator of an affected facility shall comply with either paragraphs (b)(1) or (b)(2) of this section.</P>
              <P>(1) Install, calibrate, maintain, and operate a continuous monitoring system, and record the output of the system, for measuring nitrogen oxides emissions discharged to the atmosphere; or</P>

              <P>(2) If the owner or operator has installed a nitrogen oxides emission rate continuous emission monitoring system (CEMS) to meet the requirements of part 75 of this chapter and is continuing to meet the ongoing requirements of part 75 of this chapter, that <PRTPAGE P="142"/>CEMS may be used to meet the requirements of this section, except that the owner or operator shall also meet the requirements of § 60.49b. Data reported to meet the requirements of § 60.49b shall not include data substituted using the missing data procedures in subpart D of part 75 of this chapter, nor shall the data have been bias adjusted according to the procedures of part 75 of this chapter.</P>
              <P>(c) The continuous monitoring systems required under paragraph (b) of this section shall be operated and data recorded during all periods of operation of the affected facility except for continuous monitoring system breakdowns and repairs. Data is recorded during calibration checks, and zero and span adjustments.</P>
              <P>(d) The 1-hour average nitrogen oxides emission rates measured by the continuous nitrogen oxides monitor required by paragraph (b) of this section and required under § 60.13(h) shall be expressed in ng/J or lb/million Btu heat input and shall be used to calculate the average emission rates under § 60.44b. The 1-hour averages shall be calculated using the data points required under § 60.13(b). At least 2 data points must be used to calculate each 1-hour average.</P>
              <P>(e) The procedures under § 60.13 shall be followed for installation, evaluation, and operation of the continuous monitoring systems.</P>
              <P>(1) For affected facilities combusting coal, wood or municipal-type solid waste, the span value for a continuous monitoring system for measuring opacity shall be between 60 and 80 percent.</P>
              <P>(2) For affected facilities combusting coal, oil, or natural gas, the span value for nitrogen oxides is determined as follows:</P>
              <GPOTABLE CDEF="s25,15" COLS="2" OPTS="L2">
                <BOXHD>
                  <CHED H="1">Fuel</CHED>
                  <CHED H="1">Span values for nitrogen oxides (PPM)</CHED>
                </BOXHD>
                <ROW>
                  <ENT I="01">Natural gas</ENT>
                  <ENT>500</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Oil</ENT>
                  <ENT>500</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Coal</ENT>
                  <ENT>1,000</ENT>
                </ROW>
                <ROW>
                  <ENT I="01">Mixtures</ENT>
                  <ENT>500(x+y)+1,000z</ENT>
                </ROW>
              </GPOTABLE>
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">x is the fraction of total heat input derived from natural gas,</FP>
                <FP SOURCE="FP-1">y is the fraction of total heat input derived from oil, and</FP>
                <FP SOURCE="FP-1">z is the fraction of total heat input derived from coal.</FP>
              </EXTRACT>
              
              <P>(3) All span values computed under paragraph (e)(2) of this section for combusting mixtures of regulated fuels are rounded to the nearest 500 ppm.</P>
              <P>(f) When nitrogen oxides emission data are not obtained because of continuous monitoring system breakdowns, repairs, calibration checks and zero and span adjustments, emission data will be obtained by using standby monitoring systems, Method 7, Method 7A, or other approved reference methods to provide emission data for a minimum of 75 percent of the operating hours in each steam generating unit operating day, in at least 22 out of 30 successive steam generating unit operating days.</P>
              <P>(g) The owner or operator of an affected facility that has a heat input capacity of 73 MW (250 million Btu/hour) or less, and which has an annual capacity factor for residual oil having a nitrogen content of 0.30 weight percent or less, natural gas, distillate oil, or any mixture of these fuels, greater than 10 percent (0.10) shall:</P>
              <P>(1) Comply with the provisions of paragraphs (b), (c), (d), (e)(2), (e)(3), and (f) of this section, or</P>
              <P>(2) Monitor steam generating unit operating conditions and predict nitrogen oxides emission rates as specified in a plan submitted pursuant to § 60.49b(c).</P>

              <P>(h) The owner or operator of a duct burner, as described in § 60.41b, which is subject to the NO<E T="52">X</E> standards of § 60.44b(a)(4) or § 60.44b(l) is not required to install or operate a continuous emissions monitoring system to measure NO<E T="52">X</E> emissions.</P>
              <P>(i) The owner or operator of an affected facility described in § 60.44b(j) or § 60.44b(k) is not required to install or operate a continuous monitoring system for measuring nitrogen oxides emissions.</P>
              <CITA>[52 FR 47842, Dec. 16, 1987, as amended at 54 FR 51825, Dec. 18, 1989; 63 FR 49455, Sept. 16, 1998; 66 FR 18553, Apr. 10, 2001]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.49b</SECTNO>
              <SUBJECT>Reporting and recordkeeping requirements.</SUBJECT>

              <P>(a) The owner or operator of each affected facility shall submit notification of the date of initial startup, as provided by § 60.7. This notification shall include:<PRTPAGE P="143"/>
              </P>
              <P>(1) The design heat input capacity of the affected facility and identification of the fuels to be combusted in the affected facility,</P>
              <P>(2) If applicable, a copy of any Federally enforceable requirement that limits the annual capacity factor for any fuel or mixture of fuels under §§ 60.42b(d)(1), 60.43b(a)(2), (a)(3)(iii), (c)(2)(ii), (d)(2)(iii), 60.44b(c), (d), (e), (i), (j), (k), 60.45b(d), (g), 60.46b(h), or 60.48b(i),</P>
              <P>(3) The annual capacity factor at which the owner or operator anticipates operating the facility based on all fuels fired and based on each individual fuel fired, and,</P>
              <P>(4) Notification that an emerging technology will be used for controlling emissions of sulfur dioxide. The Administrator will examine the description of the emerging technology and will determine whether the technology qualifies as an emerging technology. In making this determination, the Administrator may require the owner or operator of the affected facility to submit additional information concerning the control device. The affected facility is subject to the provisions of § 60.42b(a) unless and until this determination is made by the Administrator.</P>
              <P>(b) The owner or operator of each affected facility subject to the sulfur dioxide, particulate matter, and/or nitrogen oxides emission limits under §§ 60.42b, 60.43b, and 60.44b shall submit to the Administrator the performance test data from the initial performance test and the performance evaluation of the CEMS using the applicable performance specifications in appendix B. The owner or operator of each affected facility described in § 60.44b(j) or § 60.44b(k) shall submit to the Administrator the maximum heat input capacity data from the demonstration of the maximum heat input capacity of the affected facility.</P>
              <P>(c) The owner or operator of each affected facility subject to the nitrogen oxides standard of § 60.44b who seeks to demonstrate compliance with those standards through the monitoring of steam generating unit operating conditions under the provisions of § 60.48b(g)(2) shall submit to the Administrator for approval a plan that identifies the operating conditions to be monitored under § 60.48b(g)(2) and the records to be maintained under § 60.49b(j). This plan shall be submitted to the Administrator for approval within 360 days of the initial startup of the affected facility. The plan shall:</P>
              <P>(1) Identify the specific operating conditions to be monitored and the relationship between these operating conditions and nitrogen oxides emission rates (i.e., ng/J or lbs/million Btu heat input). Steam generating unit operating conditions include, but are not limited to, the degree of staged combustion (i.e., the ratio of primary air to secondary and/or tertiary air) and the level of excess air (i.e., flue gas oxygen level);</P>
              <P>(2) Include the data and information that the owner or operator used to identify the relationship between nitrogen oxides emission rates and these operating conditions;</P>
              <P>(3) Identify how these operating conditions, including steam generating unit load, will be monitored under § 60.48b(g) on an hourly basis by the owner or operator during the period of operation of the affected facility; the quality assurance procedures or practices that will be employed to ensure that the data generated by monitoring these operating conditions will be representative and accurate; and the type and format of the records of these operating conditions, including steam generating unit load, that will be maintained by the owner or operator under § 60.49b(j).</P>
              <FP>If the plan is approved, the owner or operator shall maintain records of predicted nitrogen oxide emission rates and the monitored operating conditions, including steam generating unit load, identified in the plan.</FP>

              <P>(d) The owner or operator of an affected facility shall record and maintain records of the amounts of each fuel combusted during each day and calculate the annual capacity factor individually for coal, distillate oil, residual oil, natural gas, wood, and municipal-type solid waste for the reporting period. The annual capacity factor is determined on a 12-month rolling average basis with a new annual capacity factor calculated at the end of each calendar month.<PRTPAGE P="144"/>
              </P>
              <P>(e) For an affected facility that combusts residual oil and meets the criteria under §§ 60.46b(e)(4), 60.44b (j), or (k), the owner or operator shall maintain records of the nitrogen content of the residual oil combusted in the affected facility and calculate the average fuel nitrogen content for the reporting period. The nitrogen content shall be determined using ASTM Method D3431-80, Test Method for Trace Nitrogen in Liquid Petroleum Hydrocarbons (IBR-see § 60.17), or fuel suppliers. If residual oil blends are being combusted, fuel nitrogen specifications may be prorated based on the ratio of residual oils of different nitrogen content in the fuel blend.</P>
              <P>(f) For facilities subject to the opacity standard under § 60.43b, the owner or operator shall maintain records of opacity.</P>
              <P>(g) Except as provided under paragraph (p) of this section, the owner or operator of an affected facility subject to the nitrogen oxides standards under § 60.44b shall maintain records of the following information for each steam generating unit operating day:</P>
              <P>(1) Calendar date.</P>

              <P>(2) The average hourly nitrogen oxides emission rates (expressed as NO<E T="52">2</E>) (ng/J or lb/million Btu heat input) measured or predicted.</P>
              <P>(3) The 30-day average nitrogen oxides emission rates (ng/J or lb/million Btu heat input) calculated at the end of each steam generating unit operating day from the measured or predicted hourly nitrogen oxide emission rates for the preceding 30 steam generating unit operating days.</P>
              <P>(4) Identification of the steam generating unit operating days when the calculated 30-day average nitrogen oxides emission rates are in excess of the nitrogen oxides emissions standards under § 60.44b, with the reasons for such excess emissions as well as a description of corrective actions taken.</P>
              <P>(5) Identification of the steam generating unit operating days for which pollutant data have not been obtained, including reasons for not obtaining sufficient data and a description of corrective actions taken.</P>
              <P>(6) Identification of the times when emission data have been excluded from the calculation of average emission rates and the reasons for excluding data.</P>
              <P>(7) Identification of “F” factor used for calculations, method of determination, and type of fuel combusted.</P>
              <P>(8) Identification of the times when the pollutant concentration exceeded full span of the continuous monitoring system.</P>
              <P>(9) Description of any modifications to the continuous monitoring system that could affect the ability of the continuous monitoring system to comply with Performance Specification 2 or 3.</P>
              <P>(10) Results of daily CEMS drift tests and quarterly accuracy assessments as required under appendix F, Procedure 1.</P>
              <P>(h) The owner or operator of any affected facility in any category listed in paragraphs (h) (1) or (2) of this section is required to submit excess emission reports for any excess emissions which occurred during the reporting period.</P>
              <P>(1) Any affected facility subject to the opacity standards under § 60.43b(e) or to the operating parameter monitoring requirements under § 60.13(i)(1).</P>
              <P>(2) Any affected facility that is subject to the nitrogen oxides standard of § 60.44b, and that</P>
              <P>(i) Combusts natural gas, distillate oil, or residual oil with a nitrogen content of 0.3 weight percent or less, or</P>
              <P>(ii) Has a heat input capacity of 73 MW (250 million Btu/hour) or less and is required to monitor nitrogen oxides emissions on a continuous basis under § 60.48b(g)(1) or steam generating unit operating conditions under § 60.48b(g)(2).</P>
              <P>(3) For the purpose of § 60.43b, excess emissions are defined as all 6-minute periods during which the average opacity exceeds the opacity standards under § 60.43b(f).</P>
              <P>(4) For purposes of § 60.48b(g)(1), excess emissions are defined as any calculated 30-day rolling average nitrogen oxides emission rate, as determined under § 60.46b(e), which exceeds the applicable emission limits in § 60.44b.</P>

              <P>(i) The owner or operator of any affected facility subject to the continuous monitoring requirements for nitrogen oxides under § 60.48(b) shall submit reports containing the information recorded under paragraph (g) of this section.<PRTPAGE P="145"/>
              </P>
              <P>(j) The owner or operator of any affected facility subject to the sulfur dioxide standards under § 60.42b shall submit reports.</P>
              <P>(k) For each affected facility subject to the compliance and performance testing requirements of § 60.45b and the reporting requirement in paragraph (j) of this section, the following information shall be reported to the Administrator:</P>
              <P>(1) Calendar dates covered in the reporting period.</P>
              <P>(2) Each 30-day average sulfur dioxide emission rate (ng/J or 1b/million Btu heat input) measured during the reporting period, ending with the last 30-day period; reasons for noncompliance with the emission standards; and a description of corrective actions taken.</P>
              <P>(3) Each 30-day average percent reduction in sulfur dioxide emissions calculated during the reporting period, ending with the last 30-day period; reasons for noncompliance with the emission standards; and a description of corrective actions taken.</P>
              <P>(4) Identification of the steam generating unit operating days that coal or oil was combusted and for which sulfur dioxide or diluent (oxygen or carbon dioxide) data have not been obtained by an approved method for at least 75 percent of the operating hours in the steam generating unit operating day; justification for not obtaining sufficient data; and description of corrective action taken.</P>
              <P>(5) Identification of the times when emissions data have been excluded from the calculation of average emission rates; justification for excluding data; and description of corrective action taken if data have been excluded for periods other than those during which coal or oil were not combusted in the steam generating unit.</P>
              <P>(6) Identification of “F” factor used for calculations, method of determination, and type of fuel combusted.</P>
              <P>(7) Identification of times when hourly averages have been obtained based on manual sampling methods.</P>
              <P>(8) Identification of the times when the pollutant concentration exceeded full span of the CEMS.</P>
              <P>(9) Description of any modifications to the CEMS that could affect the ability of the CEMS to comply with Performance Specification 2 or 3.</P>
              <P>(10) Results of daily CEMS drift tests and quarterly accuracy assessments as required under appendix F, Procedure 1.</P>
              <P>(11) The annual capacity factor of each fired as provided under paragraph (d) of this section.</P>
              <P>(l) For each affected facility subject to the compliance and performance testing requirements of § 60.45b(d) and the reporting requirements of paragraph (j) of this section, the following information shall be reported to the Administrator:</P>
              <P>(1) Calendar dates when the facility was in operation during the reporting period;</P>
              <P>(2) The 24-hour average sulfur dioxide emission rate measured for each steam generating unit operating day during the reporting period that coal or oil was combusted, ending in the last 24-hour period in the quarter; reasons for noncompliance with the emission standards; and a description of corrective actions taken;</P>
              <P>(3) Identification of the steam generating unit operating days that coal or oil was combusted for which sulfur dioxide or diluent (oxygen or carbon dioxide) data have not been obtained by an approved method for at least 75 percent of the operating hours; justification for not obtaining sufficient data; and description of corrective action taken.</P>
              <P>(4) Identification of the times when emissions data have been excluded from the calculation of average emission rates; justification for excluding data; and description of corrective action taken if data have been excluded for periods other than those during which coal or oil were not combusted in the steam generating unit.</P>
              <P>(5) Identification of “F” factor used for calculations, method of determination, and type of fuel combusted.</P>
              <P>(6) Identification of times when hourly averages have been obtained based on manual sampling methods.</P>
              <P>(7) Identification of the times when the pollutant concentration exceeded full span of the CEMS.</P>

              <P>(8) Description of any modifications to the CEMS which could affect the <PRTPAGE P="146"/>ability of the CEMS to comply with Performance Specification 2 or 3.</P>
              <P>(9) Results of daily CEMS drift tests and quarterly accuracy assessments as required under appendix F, Procedure 1.</P>
              <P>(m) For each affected facility subject to the sulfur dioxide standards under § 60.42(b) for which the minimum amount of data required under § 60.47b(f) were not obtained during the reporting period, the following information is reported to the Administrator in addition to that required under paragraph (k) of this section:</P>
              <P>(1) The number of hourly averages available for outlet emission rates and inlet emission rates.</P>
              <P>(2) The standard deviation of hourly averages for outlet emission rates and inlet emission rates, as determined in Method 19, section 7.</P>
              <P>(3) The lower confidence limit for the mean outlet emission rate and the upper confidence limit for the mean inlet emission rate, as calculated in Method 19, section 7.</P>
              <P>(4) The ratio of the lower confidence limit for the mean outlet emission rate and the allowable emission rate, as determined in Method 19, section 7.</P>

              <P>(n) If a percent removal efficiency by fuel pretreatment (i.e., % R<E T="52">f</E>) is used to determine the overall percent reduction (i.e., % R<E T="52">o</E>) under § 60.45b, the owner or operator of the affected facility shall submit a signed statement with the report.</P>

              <P>(1) Indicating what removal efficiency by fuel pretreatment (i.e., % R<E T="52">f</E>) was credited during the reporting period;</P>
              <P>(2) Listing the quantity, heat content, and date each pre-treated fuel shipment was received during the reporting period, the name and location of the fuel pretreatment facility; and the total quantity and total heat content of all fuels received at the affected facility during the reporting period.</P>
              <P>(3) Documenting the transport of the fuel from the fuel pretreatment facility to the steam generating unit.</P>
              <P>(4) Including a signed statement from the owner or operator of the fuel pretreatment facility certifying that the percent removal efficiency achieved by fuel pretreatment was determined in accordance with the provisions of Method 19 (appendix A) and listing the heat content and sulfur content of each fuel before and after fuel pretreatment.</P>
              <P>(o) All records required under this section shall be maintained by the owner or operator of the affected facility for a period of 2 years following the date of such record.</P>
              <P>(p) The owner or operator of an affected facility described in § 60.44b(j) or (k) shall maintain records of the following information for each steam generating unit operating day:</P>
              <P>(1) Calendar date,</P>
              <P>(2) The number of hours of operation, and</P>
              <P>(3) A record of the hourly steam load.</P>
              <P>(q) The owner or operator of an affected facility described in § 60.44b(j) or § 60.44b(k) shall submit to the Administrator a report containing:</P>
              <P>(1) The annual capacity factor over the previous 12 months;</P>
              <P>(2) The average fuel nitrogen content during the reporting period, if residual oil was fired; and</P>
              <P>(3) If the affected facility meets the criteria described in § 60.44b(j), the results of any nitrogen oxides emission tests required during the reporting period, the hours of operation during the reporting period, and the hours of operation since the last nitrogen oxides emission test.</P>
              <P>(r) The owner or operator of an affected facility who elects to demonstrate that the affected facility combusts only very low sulfur oil under § 60.42b(j)(2) shall obtain and maintain at the affected facility fuel receipts from the fuel supplier which certify that the oil meets the definition of distillate oil as defined in § 60.41b. For the purposes of this section, the oil need not meet the fuel nitrogen content specification in the definition of distillate oil. Reports shall be submitted to the Administrator certifying that only very low sulfur oil meeting this definition was combusted in the affected facility during the reporting period.</P>
              <P>(s) Facility specific nitrogen oxides standard for Cytec Industries Fortier Plant's C.AOG incinerator located in Westwego, Louisiana:</P>
              <P>(1) <E T="03">Definitions.</E>
                <PRTPAGE P="147"/>
              </P>
              <P>
                <E T="03">Oxidation zone</E> is defined as the portion of the C.AOG incinerator that extends from the inlet of the oxidizing zone combustion air to the outlet gas stack.</P>
              <P>
                <E T="03">Reducing zone</E> is defined as the portion of the C.AOG incinerator that extends from the burner section to the inlet of the oxidizing zone combustion air.</P>
              <P>
                <E T="03">Total inlet air</E> is defined as the total amount of air introduced into the C.AOG incinerator for combustion of natural gas and chemical by-product waste and is equal to the sum of the air flow into the reducing zone and the air flow into the oxidation zone.</P>
              <P>(2) <E T="03">Standard for nitrogen oxides.</E> (i) When fossil fuel alone is combusted, the nitrogen oxides emission limit for fossil fuel in § 60.44b(a) applies.</P>
              <P>(ii) When natural gas and chemical by-product waste are simultaneously combusted, the nitrogen oxides emission limit is 289 ng/J (0.67 lb/million Btu) and a maximum of 81 percent of the total inlet air provided for combustion shall be provided to the reducing zone of the C.AOG incinerator.</P>
              <P>(3) <E T="03">Emission monitoring.</E> (i) The percent of total inlet air provided to the reducing zone shall be determined at least every 15 minutes by measuring the air flow of all the air entering the reducing zone and the air flow of all the air entering the oxidation zone, and compliance with the percentage of total inlet air that is provided to the reducing zone shall be determined on a 3-hour average basis.</P>
              <P>(ii) The nitrogen oxides emission limit shall be determined by the compliance and performance test methods and procedures for nitrogen oxides in § 60.46b(i).</P>
              <P>(iii) The monitoring of the nitrogen oxides emission limit shall be performed in accordance with § 60.48b.</P>
              <P>(4) <E T="03">Reporting and recordkeeping requirements.</E> (i) The owner or operator of the C.AOG incinerator shall submit a report on any excursions from the limits required by paragraph (a)(2) of this section to the Administrator with the quarterly report required by paragraph (i) of this section.</P>
              <P>(ii) The owner or operator of the C.AOG incinerator shall keep records of the monitoring required by paragraph (a)(3) of this section for a period of 2 years following the date of such record.</P>
              <P>(iii) The owner of operator of the C.AOG incinerator shall perform all the applicable reporting and recordkeeping requirements of this section.</P>
              <P>(t) Facility-specific nitrogen oxides standard for Rohm and Haas Kentucky Incorporated's Boiler No. 100 located in Louisville, Kentucky:</P>
              <P>(1) <E T="03">Definitions.</E>
              </P>
              <P>
                <E T="03">Air ratio control damper</E> is defined as the part of the low nitrogen oxides burner that is adjusted to control the split of total combustion air delivered to the reducing and oxidation portions of the combustion flame.</P>
              <P>
                <E T="03">Flue gas recirculation line</E> is defined as the part of Boiler No. 100 that recirculates a portion of the boiler flue gas back into the combustion air.</P>
              <P>(2) <E T="03">Standard for nitrogen oxides.</E> (i) When fossil fuel alone is combusted, the nitrogen oxides emission limit for fossil fuel in § 60.44b(a) applies.</P>
              <P>(ii) When fossil fuel and chemical by-product waste are simultaneously combusted, the nitrogen oxides emission limit is 473 ng/J (1.1 lb/million Btu), and the air ratio control damper tee handle shall be at a minimum of 5 inches (12.7 centimeters) out of the boiler, and the flue gas recirculation line shall be operated at a minimum of 10 percent open as indicated by its valve opening position indicator.</P>
              <P>(3) <E T="03">Emission monitoring for nitrogen oxides.</E> (i) The air ratio control damper tee handle setting and the flue gas recirculation line valve opening position indicator setting shall be recorded during each 8-hour operating shift.</P>
              <P>(ii) The nitrogen oxides emission limit shall be determined by the compliance and performance test methods and procedures for nitrogen oxides in § 60.46b.</P>
              <P>(iii) The monitoring of the nitrogen oxides emission limit shall be performed in accordance with § 60.48b.</P>
              <P>(4) <E T="03">Reporting and recordkeeping requirements.</E> (i) The owner or operator of Boiler No. 100 shall submit a report on any excursions from the limits required by paragraph (b)(2) of this section to the Administrator with the quarterly report required by § 60.49b(i).<PRTPAGE P="148"/>
              </P>
              <P>(ii) The owner or operator of Boiler No. 100 shall keep records of the monitoring required by paragraph (b)(3) of this section for a period of 2 years following the date of such record.</P>
              <P>(iii) The owner of operator of Boiler No. 100 shall perform all the applicable reporting and recordkeeping requirements of § 60.49b.</P>
              <P>(u) <E T="03">Site-specific standard for Merck &amp; Co., Inc.'s Stonewall Plant in Elkton, Virginia.</E> (1) This paragraph applies only to the pharmaceutical manufacturing facility, commonly referred to as the Stonewall Plant, located at Route 340 South, in Elkton, Virginia (“site”) and only to the natural gas-fired boilers installed as part of the powerhouse conversion required pursuant to 40 CFR 52.2454(g). The requirements of this paragraph shall apply, and the requirements of §§ 60.40b through 60.49b(t) shall not apply, to the natural gas-fired boilers installed pursuant to 40 CFR 52.2454(g).</P>

              <P>(i) The site shall equip the natural gas-fired boilers with low nitrogen oxide (NO<E T="52">X</E>) technology.</P>

              <P>(ii) The site shall install, calibrate, maintain, and operate a continuous monitoring and recording system for measuring NO<E T="52">X</E> emissions discharged to the atmosphere and opacity using a continuous emissions monitoring system or a predictive emissions monitoring system.</P>
              <P>(iii) Within 180 days of the completion of the powerhouse conversion, as required by 40 CFR 52.2454, the site shall perform a stack test to quantify criteria pollutant emissions.</P>
              <P>(2) [Reserved]</P>

              <P>(v) The owner or operator of an affected facility may submit electronic quarterly reports for SO<E T="52">2</E> and/or NO<E T="52">X</E> and/or opacity in lieu of submitting the written reports required under paragraphs (h), (i), (j), (k) or (l) of this section. The format of each quarterly electronic report shall be coordinated with the permitting authority. The electronic report(s) shall be submitted no later than 30 days after the end of the calendar quarter and shall be accompanied by a certification statement from the owner or operator, indicating whether compliance with the applicable emission standards and minimum data requirements of this subpart was achieved during the reporting period. Before submitting reports in the electronic format, the owner or operator shall coordinate with the permitting authority to obtain their agreement to submit reports in this alternative format.</P>
              <P>(w) The reporting period for the reports required under this subpart is each 6 month period. All reports shall be submitted to the Administrator and shall be postmarked by the 30th day following the end of the reporting period.</P>
              <CITA>[52 FR 47842, Dec. 16, 1987, as amended at 54 FR 51820, 51825, Dec. 18, 1989; 60 FR 28062, May 30, 1995; 61 FR 14031, Mar. 29, 1996; 62 FR 52641, Oct. 8, 1997; 63 FR 49455, Sept. 16, 1998; 64 FR 7464, Feb. 12, 1999; 65 FR 13243, Mar. 13, 2000]</CITA>
            </SECTION>
          </SUBPART>
          <SUBPART>
            <HD SOURCE="HED">Subpart Dc—Standards of Performance for Small Industrial-Commercial-Institutional Steam Generating Units</HD>
            <SOURCE>
              <HD SOURCE="HED">Source:</HD>
              <P>55 FR 37683, Sept. 12, 1990, unless otherwise noted.</P>
            </SOURCE>
            <SECTION>
              <SECTNO>§ 60.40c</SECTNO>
              <SUBJECT>Applicability and delegation of authority.</SUBJECT>
              <P>(a) Except as provided in paragraph (d) of this section, the affected facility to which this subpart applies is each steam generating unit for which construction, modification, or reconstruction is commenced after June 9, 1989 and that has a maximum design heat input capacity of 29 megawatts (MW) (100 million Btu per hour (Btu/hr)) or less, but greater than or equal to 2.9 MW (10 million Btu/hr).</P>
              <P>(b) In delegating implementation and enforcement authority to a State under section 111(c) of the Clean Air Act, § 60.48c(a)(4) shall be retained by the Administrator and not transferred to a State.</P>

              <P>(c) Steam generating units which meet the applicability requirements in paragraph (a) of this section are not subject to the sulfur dioxide (SO<E T="52">2</E>) or particulate matter (PM) emission limits, performance testing requirements, or monitoring requirements under this subpart (§§ 60.42c, 60.43c, 60.44c, 60.45c, 60.46c, or 60.47c) during periods of combustion research, as defined in § 60.41c.</P>

              <P>(d) Any temporary change to an existing steam generating unit for the <PRTPAGE P="149"/>purpose of conducting combustion research is not considered a modification under § 60.14.</P>
              <CITA>[55 FR 37683, Sept. 12, 1990, as amended at 61 FR 20736, May 8, 1996]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.41c</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <P>As used in this subpart, all terms not defined herein shall have the meaning given them in the Clean Air Act and in subpart A of this part.</P>
              <P>
                <E T="03">Annual capacity factor</E> means the ratio between the actual heat input to a steam generating unit from an individual fuel or combination of fuels during a period of 12 consecutive calendar months and the potential heat input to the steam generating unit from all fuels had the steam ch a separate source (such as a stationary gas turbine, internal combustion engine, or kiln) provides exhaust gas to a steam generating unit.</P>
              <P>
                <E T="03">Coal</E> means all solid fuels classified as anthracite, bituminous, subbituminous, or lignite by the American Society for Testing and Materials in ASTM D388-77, “Standard Specification for Classification of Coals by Rank” (incorporated by reference—see § 60.17); coal refuse; and petroleum coke. Synthetic fuels derived from coal for the purpose of creating useful heat, including but not limited to solvent-refined coal, gasified coal, coal-oil mixtures, and coal-water mixtures, are included in this definition for the purposes of this subpart.</P>
              <P>
                <E T="03">Coal refuse</E> means any by-product of coal mining or coal cleaning operations with an ash content greater than 50 percent (by weight) and a heating value less than 13,900 kilojoules per kilogram (kJ/kg) (6,000 Btu per pound (Btu/lb) on a dry basis.</P>
              <P>
                <E T="03">Cogeneration steam generating unit</E> means a steam generating unit that simultaneously produces both electrical (or mechanical) and thermal energy from the same primary energy source.</P>
              <P>
                <E T="03">Combined cycle system</E> means a system in which a separate source (such as a stationary gas turbine, internal combustion engine, or kiln) provides exhaust gas to a steam generating unit.</P>
              <P>
                <E T="03">Combustion research</E> means the experimental firing of any fuel or combination of fuels in a steam generating unit for the purpose of conducting research and development of more efficient combustion or more effective prevention or control of air pollutant emissions from combustion, provided that, during these periods of research and development, the heat generated is not used for any purpose other than preheating combustion air for use by that steam generating unit (i.e., the heat generated is released to the atmosphere without being used for space heating, process heating, driving pumps, preheating combustion air for other units, generating electricity, or any other purpose).</P>
              <P>
                <E T="03">Conventional technology</E> means wet flue gas desulfurization technology, dry flue gas desulfurization technology, atmospheric fluidized bed combustion technology, and oil hydrodesulfurization technology.</P>
              <P>
                <E T="03">Distillate oil</E> means fuel oil that complies with the specifications for fuel oil numbers 1 or 2, as defined by the American Society for Testing and Materials in ASTM D396-78, 89, 90, 92, 96, or 98, “Standard Specification for Fuel Oils” (incorporated by reference—see § 60.17).</P>
              <P>
                <E T="03">Dry flue gas desulfurization technology</E> means a sulfur dioxide (SO<E T="52">2</E>) control system that is located between the steam generating unit and the exhaust vent or stack, and that removes sulfur oxides from the combustion gases of the steam generating unit by contacting the combustion gases with an alkaline slurry or solution and forming a dry powder material. This definition includes devices where the dry powder material is subsequently converted to another form. Alkaline reagents used in dry flue gas desulfurization systems include, but are not limited to, lime and sodium compounds.</P>
              <P>
                <E T="03">Duct burner</E> means a device that combusts fuel and that is placed in the exhaust duct from another source (such as a stationary gas turbine, internal combustion engine, kiln, etc.) to allow the firing of additional fuel to heat the exhaust gases before the exhaust gases enter a steam generating unit.</P>
              <P>
                <E T="03">Emerging technology</E> means any SO<E T="52">2</E> control system that is not defined as a conventional technology under this <PRTPAGE P="150"/>section, and for which the owner or operator of the affected facility has received approval from the Administrator to operate as an emerging technology under § 60.48c(a)(4).</P>
              <P>
                <E T="03">Federally enforceable</E> means all limitations and conditions that are enforceable by the Administrator, including the requirements of 40 CFR Parts 60 and 61, requirements within any applicable State implementation plan, and any permit requirements established under 40 CFR 52.21 or under 40 CFR 51.18 and 40 CFR 51.24.</P>
              <P>
                <E T="03">Fluidized bed combustion technology</E> means a device wherein fuel is distributed onto a bed (or series of beds) of limestone aggregate (or other sorbent materials) for combustion; and these materials are forced upward in the device by the flow of combustion air and the gaseous products of combustion. Fluidized bed combustion technology includes, but is not limited to, bubbling bed units and circulating bed units.</P>
              <P>
                <E T="03">Fuel pretreatment</E> means a process that removes a portion of the sulfur in a fuel before combustion of the fuel in a steam generating unit.</P>
              <P>
                <E T="03">Heat input</E> means heat derived from combustion of fuel in a steam generating unit and does not include the heat derived from preheated combustion air, recirculated flue gases, or exhaust gases from other sources (such as stationary gas turbines, internal combustion engines, and kilns).</P>
              <P>
                <E T="03">Heat transfer medium</E> means any material that is used to transfer heat from one point to another point.</P>
              <P>
                <E T="03">Maximum design heat input capacity</E> means the ability of a steam generating unit to combust a stated maximum amount of fuel (or combination of fuels) on a steady state basis as determined by the physical design and characteristics of the steam generating unit.</P>
              <P>
                <E T="03">Natural gas</E> means (1) a naturally occurring mixture of hydrocarbon and nonhydrocarbon gases found in geologic formations beneath the earth's surface, of which the principal constituent is methane, or (2) liquefied petroleum (LP) gas, as defined by the American Society for Testing and Materials in ASTM D1835-86, 87, 91, or 97, “Standard Specification for Liquefied Petroleum Gases” (incorporated by reference—see § 60.17).</P>
              <P>
                <E T="03">Noncontinental area</E> means the State of Hawaii, the Virgin Islands, Guam, American Samoa, the Commonwealth of Puerto Rico, or the Northern Mariana Islands.</P>
              <P>
                <E T="03">Oil</E> means crude oil or petroleum, or a liquid fuel derived from crude oil or petroleum, including distillate oil and residual oil.</P>
              <P>
                <E T="03">Potential sulfur dioxide emission rate</E> means the theoretical SO<E T="52">2</E> emissions (nanograms per joule [ng/J], or pounds per million Btu [lb/million Btu] heat input) that would result from combusting fuel in an uncleaned state and without using emission control systems.</P>
              <P>
                <E T="03">Process heater</E> means a device that is primarily used to heat a material to initiate or promote a chemical reaction in which the material participates as a reactant or catalyst.</P>
              <P>
                <E T="03">Residual oil</E> means crude oil, fuel oil that does not comply with the specifications under the definition of distillate oil, and all fuel oil numbers 4, 5, and 6, as defined by the American Society for Testing and Materials in ASTM D396-78, 89, 90, 92, 96, or 98, “Standard Specification for Fuel Oils” (incorporated by reference—see § 60.17).</P>
              <P>
                <E T="03">Steam generating unit</E> means a device that combusts any fuel and produces steam or heats water or any other heat transfer medium. This term includes any duct burner that combusts fuel and is part of a combined cycle system. This term does not include process heaters as defined in this subpart.</P>
              <P>
                <E T="03">Steam generating unit operating day</E> means a 24-hour period between 12:00 midnight and the following midnight during which any fuel is combusted at any time in the steam generating unit. It is not necessary for fuel to be combusted continuously for the entire 24-hour period.</P>
              <P>
                <E T="03">Wet flue gas desulfurization technology</E> means an SO<E T="52">2</E> control system that is located between the steam generating unit and the exhaust vent or stack, and that removes sulfur oxides from the combustion gases of the steam generating unit by contacting the combustion gases with an alkaline slurry or solution and forming a liquid material. This definition includes devices where <PRTPAGE P="151"/>the liquid material is subsequently converted to another form. Alkaline reagents used in wet flue gas desulfurization systems include, but are not limited to, lime, limestone, and sodium compounds.</P>
              <P>
                <E T="03">Wet scrubber system</E> means any emission control device that mixes an aqueous stream or slurry with the exhaust gases from a steam generating unit to control emissions of particulate matter (PM) or SO<E T="52">2</E>.</P>
              <P>
                <E T="03">Wood</E> means wood, wood residue, bark, or any derivative fuel or residue thereof, in any form, including but not limited to sawdust, sanderdust, wood chips, scraps, slabs, millings, shavings, and processed pellets made from wood or other forest residues.</P>
              <CITA>[55 FR 37683, Sept. 12, 1990, as amended at 61 FR 20736, May 8, 1996; 65 FR 61752, Oct. 17, 2000]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.42c</SECTNO>
              <SUBJECT>Standard for sulfur dioxide.</SUBJECT>

              <P>(a) Except as provided in paragraphs (b), (c), and (e) of this section, on and after the date on which the initial performance test is completed or required to be completed under § 60.8 of this part, whichever date comes first, the owner or operator of an affected facility that combusts only coal shall neither: (1) cause to be discharged into the atmosphere from that affected facility any gases that contain SO<E T="52">2</E> in excess of 10 percent (0.10) of the potential SO<E T="52">2</E> emission rate (90 percent reduction); nor (2) cause to be discharged into the atmosphere from that affected facility any gases that contain SO<E T="52">2</E> in excess of 520 ng/J (1.2 lb/million Btu) heat input. If coal is combusted with other fuels, the affected facility is subject to the 90 percent SO<E T="52">2</E> reduction requirement specified in this paragraph and the emission limit is determined pursuant to paragraph (e)(2) of this section.</P>
              <P>(b) Except as provided in paragraphs (c) and (e) of this section, on and after the date on which the initial performance test is completed or required to be completed under § 60.8 of this part, whichever date comes first, the owner or operator of an affected facility that:</P>
              <P>(1) Combusts coal refuse alone in a fluidized bed combustion steam generating unit shall neither:</P>

              <P>(i) Cause to be discharged into the atmosphere from that affected facility any gases that contain SO<E T="52">2</E> in excess of 20 percent (0.20) of the potential SO<E T="52">2</E> emission rate (80 percent reduction); nor</P>

              <P>(ii) Cause to be discharged into the atmosphere from that affected facility any gases that contain SO<E T="52">2</E> in excess of 520 ng/J (1.2 lb/million Btu) heat input. If coal is fired with coal refuse, the affected facility is subject to paragraph (a) of this section. If oil or any other fuel (except coal) is fired with coal refuse, the affected facility is subject to the 90 percent SO<E T="52">2</E> reduction requirement specified in paragraph (a) of this section and the emission limit determined pursuant to paragraph (e)(2) of this section.</P>

              <P>(2) Combusts only coal and that uses an emerging technology for the control of SO<E T="52">2</E> emissions shall neither:</P>

              <P>(i) Cause to be discharged into the atmosphere from that affected facility any gases that contain SO<E T="52">2</E> in excess of 50 percent (0.50) of the potential SO<E T="52">2</E> emission rate (50 percent reduction); nor</P>

              <P>(ii) Cause to be discharged into the atmosphere from that affected facility any gases that contain SO<E T="52">2</E> in excess of 260 ng/J (0.60 lb/million Btu) heat input. If coal is combusted with other fuels, the affected facility is subject to the 50 percent SO<E T="52">2</E> reduction requirement specified in this paragraph and the emission limit determined pursuant to paragraph (e)(2) of this section.</P>

              <P>(c) On and after the date on which the initial performance test is completed or required to be completed under § 60.8 of this part, whichever date comes first, no owner or operator of an affected facility that combusts coal, alone or in combination with any other fuel, and is listed in paragraphs (c)(1), (2), (3), or (4) of this section shall cause to be discharged into the atmosphere from that affected facility any gases that contain SO<E T="52">2</E> in excess of the emission limit determined pursuant to paragraph (e)(2) of this section. Percent reduction requirements are not applicable to affected facilities under paragraphs (c)(1), (2), (3), or (4).</P>
              <P>(1) Affected facilities that have a heat input capacity of 22 MW (75 million Btu/hr) or less.</P>

              <P>(2) Affected facilities that have an annual capacity for coal of 55 percent <PRTPAGE P="152"/>(0.55) or less and are subject to a Federally enforceable requirement limiting operation of the affected facility to an annual capacity factor for coal of 55 percent (0.55) or less.</P>
              <P>(3) Affected facilities located in a noncontinental area.</P>
              <P>(4) Affected facilities that combust coal in a duct burner as part of a combined cycle system where 30 percent (0.30) or less of the heat entering the steam generating unit is from combustion of coal in the duct burner and 70 percent (0.70) or more of the heat entering the steam generating unit is from exhaust gases entering the duct burner.</P>

              <P>(d) On and after the date on which the initial performance test is completed or required to be completed under § 60.8 of this part, whichever date comes first, no owner or operator of an affected facility that combusts oil shall cause to be discharged into the atmosphere from that affected facility any gases that contain SO<E T="52">2</E> in excess of 215 ng/J (0.50 lb/million Btu) heat input; or, as an alternative, no owner or operator of an affected facility that combusts oil shall combust oil in the affected facility that contains greater than 0.5 weight percent sulfur. The percent reduction requirements are not applicable to affected facilities under this paragraph.</P>

              <P>(e) On and after the date on which the initial performance test is completed or required to be completed under § 60.8 of this part, whichever date comes first, no owner or operator of an affected facility that combusts coal, oil, or coal and oil with any other fuel shall cause to be discharged into the atmosphere from that affected facility any gases that contain SO<E T="52">2</E> in excess of the following:</P>
              <P>(1) The percent of potential SO<E T="52">2</E> emission rate required under paragraph (a) or (b)(2) of this section, as applicable, for any affected facility that</P>
              <P>(i) Combusts coal in combination with any other fuel,</P>
              <P>(ii) Has a heat input capacity greater than 22 MW (75 million Btu/hr), and</P>
              <P>(iii) Has an annual capacity factor for coal greater than 55 percent (0.55); and</P>

              <P>(2) The emission limit determined according to the following formula for any affected facility that combusts coal, oil, or coal and oil with any other fuel:
              </P>
              <FP SOURCE="FP-1">E<E T="52">s</E>=(K<E T="52">a</E> H<E T="52">a</E>+K<E T="52">b</E> H<E T="52">b</E>+K<E T="52">c</E> H<E T="52">c</E>)/H<E T="52">a</E>+H<E T="52">b</E>+H<E T="52">c</E>)</FP>
              
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">E<E T="52">s</E>is the SO<E T="52">2</E> emission limit, expressed in ng/J or lb/million Btu heat input,</FP>
                <FP SOURCE="FP-1">K<E T="52">a</E>is 520 ng/J (1.2 lb/million Btu),</FP>
                <FP SOURCE="FP-1">K<E T="52">b</E>is 260 ng/J (0.60 lb/million Btu),</FP>
                <FP SOURCE="FP-1">K<E T="52">c</E>is 215 ng/J (0.50 lb/million Btu),</FP>
                <FP SOURCE="FP-1">H<E T="52">a</E>is the heat input from the combustion of coal, except coal combusted in an affected facility subject to paragraph (b)(2) of this section, in Joules (J) [million Btu]</FP>
                <FP SOURCE="FP-1">H<E T="52">b</E>is the heat input from the combustion of coal in an affected facility subject to paragraph (b)(2) of this section, in J (million Btu)</FP>
                <FP SOURCE="FP-1">H<E T="52">c</E>is the heat input from the combustion of oil, in J (million Btu).</FP>
              </EXTRACT>
              
              <P>(f) Reduction in the potential SO<E T="52">2</E> emission rate through fuel pretreatment is not credited toward the percent reduction requirement under paragraph (b)(2) of this section unless:</P>

              <P>(1) Fuel pretreatment results in a 50 percent (0.50) or greater reduction in the potential SO<E T="52">2</E> emission rate; and</P>

              <P>(2) Emissions from the pretreated fuel (without either combustion or post-combustion SO<E T="52">2</E> control) are equal to or less than the emission limits specified under paragraph (b)(2) of this section.</P>
              <P>(g) Except as provided in paragraph (h) of this section, compliance with the percent reduction requirements, fuel oil sulfur limits, and emission limits of this section shall be determined on a 30-day rolling average basis.</P>
              <P>(h) For affected facilities listed under paragraphs (h)(1), (2), or (3) of this section, compliance with the emission limits or fuel oil sulfur limits under this section may be determined based on a certification from the fuel supplier, as described under § 60.48c(f)(1), (2), or (3), as applicable.</P>
              <P>(1) Distillate oil-fired affected facilities with heat input capacities between 2.9 and 29 MW (10 and 100 million Btu/hr).</P>
              <P>(2) Residual oil-fired affected facilities with heat input capacities between 2.9 and 8.7 MW (10 and 30 million Btu/hr).</P>

              <P>(3) Coal-fired facilities with heat input capacities between 2.9 and 8.7 MW (10 and 30 million Btu/hr).<PRTPAGE P="153"/>
              </P>
              <P>(i) The SO<E T="52">2</E> emission limits, fuel oil sulfur limits, and percent reduction requirements under this section apply at all times, including periods of startup, shutdown, and malfunction.</P>
              <P>(j) Only the heat input supplied to the affected facility from the combustion of coal and oil is counted under this section. No credit is provided for the heat input to the affected facility from wood or other fuels or for heat derived from exhaust gases from other sources, such as stationary gas turbines, internal combustion engines, and kilns.</P>
              <CITA>[55 FR 37683, Sept. 12, 1990, as amended at 65 FR 61753, Oct. 17, 2000]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.43c</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>
              <P>(a) On and after the date on which the initial performance test is completed or required to be completed under § 60.8 of this part, whichever date comes first, no owner or operator of an affected facility that combusts coal or combusts mixtures of coal with other fuels and has a heat input capacity of 8.7 MW (30 million Btu/hr) or greater, shall cause to be discharged into the atmosphere from that affected facility any gases that contain PM in excess of the following emission limits:</P>
              <P>(1) 22 ng/J (0.051 lb/million Btu) heat input if the affected facility combusts only coal, or combusts coal with other fuels and has an annual capacity factor for the other fuels of 10 percent (0.10) or less.</P>
              <P>(2) 43 ng/J (0.10 lb/million Btu) heat imput if the affected facility combusts coal with other fuels, has an annual capacity factor for the other fuels greater than 10 percent (0.10), and is subject to a federally enforceable requirement limiting operation of the affected facility to an annual capacity factor greater than 10 percent (0.10) for fuels other than coal.</P>
              <P>(b) On and after the date on which the initial performance test is completed or required to be completed under § 60.8 of this part, whichever date comes first, no owner or operator of an affected facility that combusts wood or combusts mixtures of wood with other fuels (except coal) and has a heat input capacity of 8.7 MW (30 million Btu/hr) or greater, shall cause to be discharged into the atmosphere from that affected facility any gases that contain PM in excess of the following emissions limits:</P>
              <P>(1) 43 ng/J (0.10 lb/million Btu) heat input if the affected facility has an annual capacity factor for wood greater than 30 percent (0.30); or</P>
              <P>(2) 130 ng/J (0.30 lb/million Btu) heat input if the affected facility has an annual capacity factor for wood of 30 percent (0.30) or less and is subject to a federally enforceable requirement limiting operation of the affected facility to an annual capacity factor for wood of 30 percent (0.30) or less.</P>
              <P>(c) On and after the date on which the initial performance test is completed or required to be completed under § 60.8 of this part, whichever date comes first, no owner or operator of an affected facility that combusts coal, wood, or oil and has a heat input capacity of 8.7 MW (30 million Btu/hr) or greater shall cause to be discharged into the atmosphere from that affected facility any gases that exhibit greater than 20 percent opacity (6-minute average), except for one 6-minute period per hour of not more than 27 percent opacity.</P>
              <P>(d) The PM and opacity standards under this section apply at all times, except during periods of startup, shutdown, or malfunction.</P>
              <CITA>[55 FR 37683, Sept. 12, 1990, as amended at 65 FR 61753, Oct. 17, 2000]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.44c</SECTNO>
              <SUBJECT>Compliance and performance test methods and procedures for sulfur dioxide.</SUBJECT>
              <P>(a) Except as provided in paragraphs (g) and (h) of this section and in § 60.8(b), performance tests required under § 60.8 shall be conducted following the procedures specified in paragraphs (b), (c), (d), (e), and (f) of this section, as applicable. Section 60.8(f) does not apply to this section. The 30-day notice required in § 60.8(d) applies only to the initial performance test unless otherwise specified by the Administrator.</P>

              <P>(b) The initial performance test required under § 60.8 shall be conducted over 30 consecutive operating days of the steam generating unit. Compliance with the percent reduction requirements and SO<E T="52">2</E> emission limits under <PRTPAGE P="154"/>§ 60.42c shall be determined using a 30-day average. The first operating day included in the initial performance test shall be scheduled within 30 days after achieving the maximum production rate at which the affect facility will be operated, but not later than 180 days after the initial startup of the facility. The steam generating unit load during the 30-day period does not have to be the maximum design heat input capacity, but must be representative of future operating conditions.</P>

              <P>(c) After the initial performance test required under paragraph (b) and § 60.8, compliance with the percent reduction requirements and SO<E T="52">2</E> emission limits under § 60.42c is based on the average percent reduction and the average S0<E T="52">2</E> emission rates for 30 consecutive steam generating unit operating days. A separate performance test is completed at the end of each steam generating unit operating day, and a new 30-day average percent reduction and SO<E T="52">2</E> emission rate are calculated to show compliance with the standard.</P>

              <P>(d) If only coal, only oil, or a mixture of coal and oil is combusted in an affected facility, the procedures in Method 19 are used to determine the hourly SO<E T="52">2</E> emission rate (E<E T="52">ho</E>) and the 30-day average SO<E T="52">2</E> emission rate (E<E T="52">ao</E>). The hourly averages used to compute the 30-day averages are obtained from the continuous emission monitoring system (CEMS). Method 19 shall be used to calculate E<E T="52">ao</E> when using daily fuel sampling or Method 6B.</P>
              <P>(e) If coal, oil, or coal and oil are combusted with other fuels:</P>
              <P>(1) An adjusted E<E T="52">ho</E> (E<E T="52">ho</E>o) is used in Equation 19-19 of Method 19 to compute the adjusted E<E T="52">ao</E> (E<E T="52">ao</E>o). The E<E T="52">ho</E>o is computed using the following formula:
              </P>
              <FP SOURCE="FP-1">E<E T="52">ho</E>o=[E<E T="52">ho</E>−E<E T="52">w</E>(1−X<E T="52">k</E>)]/X<E T="52">k</E>
              </FP>
              
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">E<E T="52">ho</E>ois the adjusted E<E T="52">ho</E>, ng/J (lb/million Btu)</FP>
                <FP SOURCE="FP-1">E<E T="52">ho</E>is the hourly SO<E T="52">2</E> emission rate, ng/J (lb/million Btu)</FP>
                <FP SOURCE="FP-1">E<E T="52">w</E>is the SO<E T="52">2</E> concentration in fuels other than coal and oil combusted in the affected facility, as determined by fuel sampling and analysis procedures in Method 9, ng/J (lb/million Btu). The value E<E T="52">w</E> for each fuel lot is used for each hourly average during the time that the lot is being combusted. The owner or operator does not have to measure E<E T="52">w</E> if the owner or operator elects to assume E<E T="52">w</E>=0.</FP>
                <FP SOURCE="FP-1">X<E T="52">k</E>is the fraction of the total heat input from fuel combustion derived from coal and oil, as determined by applicable procedures in Method 19.</FP>
              </EXTRACT>
              

              <P>(2) The owner or operator of an affected facility that qualifies under the provisions of § 60.42c(c) or (d) [where percent reduction is not required] does not have to measure the parameters E<E T="52">w</E> or X<E T="52">k</E> if the owner or operator of the affected facility elects to measure emission rates of the coal or oil using the fuel sampling and analysis procedures under Method 19.</P>

              <P>(f) Affected facilities subject to the percent reduction requirements under § 60.42c(a) or (b) shall determine compliance with the SO<E T="52">2</E> emission limits under § 60.42c pursuant to paragraphs (d) or (e) of this section, and shall determine compliance with the percent reduction requirements using the following procedures:</P>

              <P>(1) If only coal is combusted, the percent of potential SO<E T="52">2</E> emission rate is computed using the following formula:
              </P>
              <FP SOURCE="FP-1">%P<E T="52">s</E>=100(1−%R<E T="52">g</E>/100)(1−%R<E T="52">f</E>/100)</FP>
              
              <EXTRACT>
                <FP>where</FP>
                
                <FP SOURCE="FP-1">%P<E T="52">s</E>is the percent of potential SO<E T="52">2</E> emission rate, in percent</FP>
                <FP SOURCE="FP-1">%R<E T="52">g</E>is the SO<E T="52">2</E> removal efficiency of the control device as determined by Method 19, in percent</FP>
                <FP SOURCE="FP-1">%R<E T="52">f</E>is the SO<E T="52">2</E> removal efficiency of fuel pretreatment as determined by Method 19, in percent</FP>
              </EXTRACT>
              
              <P>(2) If coal, oil, or coal and oil are combusted with other fuels, the same procedures required in paragraph (f)(1) of this section are used, except as provided for in the following:</P>
              <P>(i) To compute the %P<E T="52">s</E>, an adjusted %R<E T="52">g</E> (%R<E T="52">g</E>o) is computed from E<E T="52">ao</E>o from paragraph (e)(1) of this section and an adjusted average SO<E T="52">2</E> inlet rate (E<E T="52">ai</E>o) using the following formula:
              </P>
              <FP SOURCE="FP-1">%R<E T="52">g</E>o=100 [1.0− E<E T="52">ao</E>o/E<E T="52">ai</E>o)]</FP>
              
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">%R<E T="52">g</E>ois the adjusted %R<E T="52">g</E>, in percent</FP>
                <FP SOURCE="FP-1">E<E T="52">ao</E>ois the adjusted E<E T="52">ao</E>, ng/J (lb/million Btu)</FP>
                <FP SOURCE="FP-1">E<E T="52">ai</E>ois the adjusted average SO<E T="52">2</E> inlet rate, ng/J (lb/million Btu)</FP>
              </EXTRACT>
              
              <P>(ii) To compute E<E T="52">ai</E>o, an adjusted hourly SO<E T="52">2</E> inlet rate (E<E T="52">hi</E>o) is used. The <PRTPAGE P="155"/>E<E T="52">hi</E>o is computed using the following formula:
              </P>
              <FP SOURCE="FP-1">E<E T="52">hi</E>o=[E<E T="52">hi</E>− E<E T="52">w</E> (1−X<E T="52">k</E>)]/X<E T="52">k</E>
              </FP>
              
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">E<E T="52">hi</E>ois the adjusted E<E T="52">hi</E>, ng/J (lb/million Btu)</FP>
                <FP SOURCE="FP-1">E<E T="52">hi</E>is the hourly SO<E T="52">2</E> inlet rate, ng/J (lb/million Btu)</FP>
                <FP SOURCE="FP-1">E<E T="52">w</E>is the SO<E T="52">2</E> concentration in fuels other than coal and oil combusted in the affected facility, as determined by fuel sampling and analysis procedures in Method 19, ng/J (lb/million Btu). The value E<E T="52">w</E> for each fuel lot is used for each hourly average during the time that the lot is being combusted. The owner or operator does not have to measure E<E T="52">w</E> if the owner or operator elects to assume E<E T="52">w</E> = O.</FP>
                <FP SOURCE="FP-1">X<E T="52">k</E>is the fraction of the total heat input from fuel combustion derived from coal and oil, as determined by applicable procedures in Method 19.</FP>
              </EXTRACT>
              
              <P>(g) For oil-fired affected facilities where the owner or operator seeks to demonstrate compliance with the fuel oil sulfur limits under § 60.42c based on shipment fuel sampling, the initial performance test shall consist of sampling and analyzing the oil in the initial tank of oil to be fired in the steam generating unit to demonstrate that the oil contains 0.5 weight percent sulfur or less. Thereafter, the owner or operator of the affected facility shall sample the oil in the fuel tank after each new shipment of oil is received, as described under § 60.46c(d)(2).</P>

              <P>(h) For affected facilities subject to § 60.42c(h)(1), (2), or (3) where the owner or operator seeks to demonstrate compliance with the SO<E T="52">2</E> standards based on fuel supplier certification, the performance test shall consist of the certification, the certification from the fuel supplier, as described under § 60.48c(f)(1), (2), or (3), as applicable.</P>

              <P>(i) The owner or operator of an affected facility seeking to demonstrate compliance with the SO<E T="52">2</E> standards under § 60.42c(c)(2) shall demonstrate the maximum design heat input capacity of the steam generating unit by operating the steam generating unit at this capacity for 24 hours. This demonstration shall be made during the initial performance test, and a subsequent demonstration may be requested at any other time. If the demonstrated 24-hour average firing rate for the affected facility is less than the maximum design heat input capacity stated by the manufacturer of the affected facility, the demonstrated 24-hour average firing rate shall be used to determine the annual capacity factor for the affected facility; otherwise, the maximum design heat input capacity provided by the manufacturer shall be used.</P>

              <P>(j) The owner or operator of an affected facility shall use all valid SO<E T="52">2</E> emissions data in calculating %P<E T="52">s</E> and E<E T="52">ho</E> under paragraphs (d), (e), or (f) of this section, as applicable, whether or not the minimum emissions data requirements under § 60.46c(f) are achieved. All valid emissions data, including valid data collected during periods of startup, shutdown, and malfunction, shall be used in calculating %P<E T="52">s</E> or E<E T="52">ho</E> pursuant to paragraphs (d), (e), or (f) of this section, as applicable.</P>
              <CITA>[55 FR 37683, Sept. 12, 1990, as amended at 65 FR 61753, Oct. 17, 2000]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.45c</SECTNO>
              <SUBJECT>Compliance and performance test methods and procedures for particulate matter.</SUBJECT>
              <P>(a) The owner or operator of an affected facility subject to the PM and/or opacity standards under § 60.43c shall conduct an initial performance test as required under § 60.8, and shall conduct subsequent performance tests as requested by the Administrator, to determine compliance with the standards using the following procedures and reference methods.</P>
              <P>(1) Method 1 shall be used to select the sampling site and the number of traverse sampling points.</P>
              <P>(2) Method 3 shall be used for gas analysis when applying Method 5, Method 5B, or Method 17.</P>
              <P>(3) Method 5, Method 5B, or Method 17 shall be used to measure the concentration of PM as follows:</P>
              <P>(i) Method 5 may be used only at affected facilities without wet scrubber systems.</P>

              <P>(ii) Method 17 may be used at affected facilities with or without wet scrubber systems provided the stack gas temperature does not exceed a temperature of 160 °C (320 °F). The procedures of Sections 8.1 and 11.1 of Method 5B may be used in Method 17 only if Method 17 is used in conjunction with a wet scrubber system. Method 17 shall not be used in conjunction with a wet <PRTPAGE P="156"/>scrubber system if the effluent is saturated or laden with water droplets.</P>
              <P>(iii) Method 5B may be used in conjunction with a wet scrubber system.</P>
              <P>(4) The sampling time for each run shall be at least 120 minutes and the minimum sampling volume shall be 1.7 dry standard cubic meters (dscm) [60 dry standard cubic feet (dscf)] except that smaller sampling times or volumes may be approved by the Administrator when necessitated by process variables or other factors.</P>
              <P>(5) For Method 5 or Method 5B, the temperature of the sample gas in the probe and filter holder shall be monitored and maintained at 160±14 °C (320±25 °F).</P>
              <P>(6) For determination of PM emissions, an oxygen or carbon dioxide measurement shall be obtained simultaneously with each run of Method 5, Method 5B, or Method 17 by traversing the duct at the same sampling location.</P>
              <P>(7) For each run using Method 5, Method 5B, or Method 17, the emission rates expressed in ng/J (lb/million Btu) heat input shall be determined using:</P>
              <P>(i) The oxygen or carbon dioxide measurements and PM measurements obtained under this section,</P>
              <P>(ii) The dry basis F-factor, and</P>
              <P>(iii) The dry basis emission rate calculation procedure contained in Method 19 (appendix A).</P>
              <P>(8) Method 9 (6-minute average of 24 observations) shall be used for determining the opacity of stack emissions.</P>
              <P>(b) The owner or operator of an affected facility seeking to demonstrate compliance with the PM standards under § 60.43c(b)(2) shall demonstrate the maximum design heat input capacity of the steam generating unit by operating the steam generating unit at this capacity for 24 hours. This demonstration shall be made during the initial performance test, and a subsequent demonstration may be requested at any other time. If the demonstrated 24-hour average firing rate for the affected facility is less than the maximum design heat input capacity stated by the manufacturer of the affected facility, the demonstrated 24-hour average firing rate shall be used to determine the annual capacity factor for the affected facility; otherwise, the maximum design heat input capacity provided by the manufacturer shall be used.</P>
              <CITA>[55 FR 37683, Sept. 12, 1990, as amended at 65 FR 61753, Oct. 17, 2000]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.46c</SECTNO>
              <SUBJECT>Emission monitoring for sulfur dioxide</SUBJECT>

              <P>(a) Except as provided in paragraphs (d) and (e) of this section, the owner or operator of an affected facility subject to the SO<E T="52">2</E> emission limits under § 60.42c shall install, calibrate, maintain, and operate a CEMS for measuring SO<E T="52">2</E> concentrations and either oxygen or carbon dioxide concentrations at the outlet of the SO<E T="52">2</E> control device (or the outlet of the steam generating unit if no SO<E T="52">2</E> control device is used), and shall record the output of the system. The owner or operator of an affected facility subject to the percent reduction requirements under § 60.42c shall measure SO<E T="52">2</E> concentrations and either oxygen or carbon dioxide concentrations at both the inlet and outlet of the SO<E T="52">2</E> control device.</P>
              <P>(b) The 1-hour average SO<E T="52">2</E> emission rates measured by a CEMS shall be expressed in ng/J or lb/million Btu heat input and shall be used to calculate the average emission rates under § 60.42c. Each 1-hour average SO<E T="52">2</E> emission rate must be based on at least 30 minutes of operation and include at least 2 data points representing two 15-minute periods. Hourly SO<E T="52">2</E> emission rates are not calculated if the affected facility is operated less than 30 minutes in a 1-hour period and are not counted toward determination of a steam generating unit operating day.</P>
              <P>(c) The procedures under § 60.13 shall be followed for installation, evaluation, and operation of the CEMS.</P>
              <P>(1) All CEMS shall be operated in accordance with the applicable procedures under Performance Specifications 1, 2, and 3 (appendix B).</P>
              <P>(2) Quarterly accuracy determinations and daily calibration drift tests shall be performed in accordance with Procedure 1 (appendix F).</P>

              <P>(3) For affected facilities subject to the percent reduction requirements under § 60.42c, the span value of the SO<E T="52">2</E> CEMS at the inlet to the SO<E T="52">2</E> control device shall be 125 percent of the maximum estimated hourly potential SO<E T="52">2</E>
                <PRTPAGE P="157"/>emission rate of the fuel combusted, and the span value of the SO<E T="52">2</E> CEMS at the outlet from the SO<E T="52">2</E> control device shall be 50 percent of the maximum estimated hourly potential SO<E T="52">2</E> emission rate of the fuel combusted.</P>

              <P>(4) For affected facilities that are not subject to the percent reduction requirements of § 60.42c, the span value of the SO<E T="52">2</E> CEMS at the outlet from the SO<E T="52">2</E> control device (or outlet of the steam generating unit if no SO<E T="52">2</E> control device is used) shall be 125 percent of the maximum estimated hourly potential SO<E T="52">2</E> emission rate of the fuel combusted.</P>

              <P>(d) As an alternative to operating a CEMS at the inlet to the SO<E T="52">2</E> control device (or outlet of the steam generating unit if no SO<E T="52">2</E> control device is used) as required under paragraph (a) of this section, an owner or operator may elect to determine the average SO<E T="52">2</E> emission rate by sampling the fuel prior to combustion. As an alternative to operating a CEMS at the outlet from the SO<E T="52">2</E> control device (or outlet of the steam generating unit if no SO<E T="52">2</E> control device is used) as required under paragraph (a) of this section, an owner or operator may elect to determine the average SO<E T="52">2</E> emission rate by using Method 6B. Fuel sampling shall be conducted pursuant to either paragraph (d)(1) or (d)(2) of this section. Method 6B shall be conducted pursuant to paragraph (d)(3) of this section.</P>

              <P>(1) For affected facilities combusting coal or oil, coal or oil samples shall be collected daily in an as-fired condition at the inlet to the steam generating unit and analyzed for sulfur content and heat content according the Method 19. Method 19 provides procedures for converting these measurements into the format to be used in calculating the average SO<E T="52">2</E> input rate.</P>
              <P>(2) As an alternative fuel sampling procedure for affected facilities combusting oil, oil samples may be collected from the fuel tank for each steam generating unit immediately after the fule tank is filled and before any oil is combusted. The owner or operator of the affected facility shall analyze the oil sample to determine the sulfur content of the oil. If a partially empty fuel tank is refilled, a new sample and analysis of the fuel in the tank would be required upon filling. Results of the fuel analysis taken after each new shipment of oil is received shall be used as the daily value when calculating the 30-day rolling average until the next shipment is received. If the fuel analysis shows that the sulfur content in the fuel tank is greater than 0.5 weight percent sulfur, the owner or operator shall ensure that the sulfur content of subsequent oil shipments is low enough to cause the 30-day rolling average sulfur content to be 0.5 weight percent sulfur or less.</P>

              <P>(3) Method 6B may be used in lieu of CEMS to measure SO<E T="52">2</E> at the inlet or outlet of the SO<E T="52">2</E> control system. An initial stratification test is required to verify the adequacy of the Method 6B sampling location. The stratification test shall consist of three paired runs of a suitable SO<E T="52">2</E> and carbon dioxide measurement train operated at the candidate location and a second similar train operated according to the procedures in § 3.2 and the applicable procedures in section 7 of Performance Specification 2 (appendix B). Method 6B, Method 6A, or a combination of Methods 6 and 3 or Methods 6C and 3A are suitable measurement techniques. If Method 6B is used for the second train, sampling time and timer operation may be adjusted for the stratification test as long as an adequate sample volume is collected; however, both sampling trains are to be operated similarly. For the location to be adequate for Method 6B 24-hour tests, the mean of the absolute difference between the three paired runs must be less than 10 percent (0.10).</P>

              <P>(e) The monitoring requirements of paragraphs (a) and (d) of this section shall not apply to affected facilities subject to § 60.42c(h) (1), (2), or (3) where the owner or operator of the affected facility seeks to demonstrate compliance with the SO<E T="52">2</E> standards based on fuel supplier certification, as described under § 60.48c(f) (1), (2), or (3), as applicable.</P>

              <P>(f) The owner or operator of an affected facility operating a CEMS pursuant to paragraph (a) of this section, or conducting as-fired fuel sampling pursuant to paragraph (d)(1) of this section, shall obtain emission data for at least 75 percent of the operating hours <PRTPAGE P="158"/>in at least 22 out of 30 successive steam generating unit operating days. If this minimum data requirement is not met with a single monitoring system, the owner or operator of the affected facility shall supplement the emission data with data collected with other monitoring systems as approved by the Administrator.</P>
              <CITA>[55 FR 37683, Sept. 12, 1990, as amended at 65 FR 61753, Oct. 17, 2000]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.47c</SECTNO>
              <SUBJECT>Emission monitoring for particulate matter.</SUBJECT>
              <P>(a) The owner or operator of an affected facility combusting coal, residual oil, or wood that is subject to the opacity standards under § 60.43c shall install, calibrate, maintain, and operate a COMS for measuring the opacity of the emissions discharged to the atmosphere and record the output of the system.</P>
              <P>(b) All COMS for measuring opacity shall be operated in accordance with the applicable procedures under Performance Specification 1 (appendix B). The span value of the opacity COMS shall be between 60 and 80 percent.</P>
              <CITA>[55 FR 37683, Sept. 12, 1990, as amended at 65 FR 61753, Oct. 17, 2000]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.48c</SECTNO>
              <SUBJECT>Reporting and recordkeeping requirements.</SUBJECT>
              <P>(a) The owner or operator of each affected facility shall submit notification of the date of construction or reconstruction, anticipated startup, and actual startup, as provided by § 60.7 of this part. This notification shall include:</P>
              <P>(1) The design heat input capacity of the affected facility and identification of fuels to be combusted in the affected facility.</P>
              <P>(2) If applicable, a copy of any Federally enforceable requirement that limits the annual capacity factor for any fuel or mixture of fuels under § 60.42c, or § 60.43c.</P>
              <P>(3) The annual capacity factor at which the owner or operator anticipates operating the affected facility based on all fuels fired and based on each individual fuel fired.</P>

              <P>(4) Notification if an emerging technology will be used for controlling SO<E T="52">2</E> emissions. The Administrator will examine the description of the control device and will determine whether the technology qualifies as an emerging technology. In making this determination, the Administrator may require the owner or operator of the affected facility to submit additional information concerning the control device. The affected facility is subject to the provisions of § 60.42c(a) or (b)(1), unless and until this determination is made by the Administrator.</P>

              <P>(b) The owner or operator of each affected facility subject to the SO<E T="52">2</E> emission limits of § 60.42c, or the PM or opacity limits of § 60.43c, shall submit to the Administrator the performance test data from the initial and any subsequent performance tests and, if applicable, the performance evaluation of the CEMS and/or COMS using the applicable performance specifications in appendix B.</P>
              <P>(c) The owner or operator of each coal-fired, residual oil-fired, or wood-fired affected facility subject to the opacity limits under § 60.43c(c) shall submit excess emission reports for any excess emissions from the affected facility which occur during the reporting period.</P>

              <P>(d) The owner or operator of each affected facility subject to the SO<E T="52">2</E> emission limits, fuel oil sulfur limits, or percent reduction requirements under § 60.42c shall submit reports to the Administrator.</P>

              <P>(e) The owner or operator of each affected facility subject to the SO<E T="52">2</E> emission limits, fuel oil sulfur limits, or percent reduction requirements under § 60.43c shall keep records and submit reports as required under paragraph (d) of this section, including the following information, as applicable.</P>
              <P>(1) Calendar dates covered in the reporting period.</P>
              <P>(2) Each 30-day average SO<E T="52">2</E> emission rate (nj/J or lb/million Btu), or 30-day average sulfur content (weight percent), calculated during the reporting period, ending with the last 30-day period; reasons for any noncompliance with the emission standards; and a description of corrective actions taken.</P>
              <P>(3) Each 30-day average percent of potential SO<E T="52">2</E> emission rate calculated during the reporting period, ending with the last 30-day period; reasons for any noncompliance with the emission <PRTPAGE P="159"/>standards; and a description of the corrective actions taken.</P>

              <P>(4) Identification of any steam generating unit operating days for which SO<E T="52">2</E> or diluent (oxygen or carbon dioxide) data have not been obtained by an approved method for at least 75 percent of the operating hours; justification for not obtaining sufficient data; and a description of corrective actions taken.</P>
              <P>(5) Identification of any times when emissions data have been excluded from the calculation of average emission rates; justification for excluding data; and a description of corrective actions taken if data have been excluded for periods other than those during which coal or oil were not combusted in the steam generating unit.</P>
              <P>(6) Identification of the F factor used in calculations, method of determination, and type of fuel combusted.</P>
              <P>(7) Identification of whether averages have been obtained based on CEMS rather than manual sampling methods.</P>
              <P>(8) If a CEMS is used, identification of any times when the pollutant concentration exceeded the full span of the CEMS.</P>
              <P>(9) If a CEMS is used, description of any modifications to the CEMS that could affect the ability of the CEMS to comply with Performance Specifications 2 or 3 (appendix B).</P>
              <P>(10) If a CEMS is used, results of daily CEMS drift tests and quarterly accuracy assessments as required under appendix F, Procedure 1.</P>
              <P>(11) If fuel supplier certification is used to demonstrate compliance, records of fuel supplier certification is used to demonstrate compliance, records of fuel supplier certification as described under paragraph (f)(1), (2), or (3) of this section, as applicable. In addition to records of fuel supplier certifications, the report shall include a certified statement signed by the owner or operator of the affected facility that the records of fuel supplier certifications submitted represent all of the fuel combusted during the reporting period.</P>
              <P>(f) Fuel supplier certification shall include the following information:</P>
              <P>(1) For distillate oil:</P>
              <P>(i) The name of the oil supplier; and</P>
              <P>(ii) A statement from the oil supplier that the oil complies with the specifications under the definition of distillate oil in § 60.41c.</P>
              <P>(2) For residual oil:</P>
              <P>(i) The name of the oil supplier;</P>
              <P>(ii) The location of the oil when the sample was drawn for analysis to determine the sulfur content of the oil, specifically including whether the oil was sampled as delivered to the affected facility, or whether the sample was drawn from oil in storage at the oil supplier's or oil refiner's facility, or other location;</P>
              <P>(iii) The sulfur content of the oil from which the shipment came (or of the shipment itself); and</P>
              <P>(iv) The method used to determine the sulfur content of the oil.</P>
              <P>(3) For coal:</P>
              <P>(i) The name of the coal supplier;</P>
              <P>(ii) The location of the coal when the sample was collected for analysis to determine the properties of the coal, specifically including whether the coal was sampled as delivered to the affected facility or whether the sample was collected from coal in storage at the mine, at a coal preparation plant, at a coal supplier's facility, or at another location. The certification shall include the name of the coal mine (and coal seam), coal storage facility, or coal preparation plant (where the sample was collected);</P>
              <P>(iii) The results of the analysis of the coal from which the shipment came (or of the shipment itself) including the sulfur content, moisture content, ash content, and heat content; and</P>
              <P>(iv) The methods used to determine the properties of the coal.</P>
              <P>(g) The owner or operator of each affected facility shall record and maintain records of the amounts of each fuel combusted during each day.</P>
              <P>(h) The owner or operator of each affected facility subject to a Federally enforceable requirement limiting the annual capacity factor for any fuel or mixture of fuels under § 60.42c or § 60.43c shall calculate the annual capacity factor individually for each fuel combusted. The annual capacity factor is determined on a 12-month rolling average basis with a new annual capacity factor calculated at the end of the calendar month.</P>

              <P>(i) All records required under this section shall be maintained by the <PRTPAGE P="160"/>owner or operator of the affected facility for a period of two years following the date of such record.</P>
              <P>(j) The reporting period for the reports required under this subpart is each six-month period. All reports shall be submitted to the Administrator and shall be postmarked by the 30th day following the end of the reporting period.</P>
              <CITA>[55 FR 37683, Sept. 12, 1990, as amended at 64 FR 7465, Feb. 12, 1999; 65 FR 61753, Oct. 17, 2000]</CITA>
            </SECTION>
          </SUBPART>
          <SUBPART>
            <HD SOURCE="HED">Subpart E—Standards of Performance for Incinerators</HD>
            <SECTION>
              <SECTNO>§ 60.50</SECTNO>
              <SUBJECT>Applicability and designation of affected facility.</SUBJECT>
              <P>(a) The provisions of this subpart are applicable to each incinerator of more than 45 metric tons per day charging rate (50 tons/day), which is the affected facility.</P>
              <P>(b) Any facility under paragraph (a) of this section that commences construction or modification after August 17, 1971, is subject to the requirements of this subpart.</P>
              <CITA>[42 FR 37936, July 25, 1977]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.51</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <P>As used in this subpart, all terms not defined herein shall have the meaning given them in the Act and in subpart A of this part.</P>
              <P>(a) <E T="03">Incinerator</E> means any furnace used in the process of burning solid waste for the purpose of reducing the volume of the waste by removing combustible matter.</P>
              <P>(b) <E T="03">Solid waste</E> means refuse, more than 50 percent of which is municipal type waste consisting of a mixture of paper, wood, yard wastes, food wastes, plastics, leather, rubber, and other combustibles, and noncombustible materials such as glass and rock.</P>
              <P>(c) <E T="03">Day</E> means 24 hours.</P>
              <CITA>[36 FR 24877, Dec. 23, 1971, as amended at 39 FR 20792, June 14, 1974]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.52</SECTNO>
              <SUBJECT>Standard for particulate matter.</SUBJECT>

              <P>(a) On and after the date on which the initial performance test is completed or required to be completed under § 60.8 of this part, whichever date comes first, no owner or operator subject to the provisions of this part shall cause to be discharged into the atmosphere from any affected facility any gases which contain particulate matter in excess of 0.18 g/dscm (0.08 gr/dscf) corrected to 12 percent CO<E T="52">2</E>.</P>
              <CITA>[39 FR 20792, June 14, 1974, as amended at 65 FR 61753, Oct. 17, 2000]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.53</SECTNO>
              <SUBJECT>Monitoring of operations.</SUBJECT>
              <P>(a) The owner or operator of any incinerator subject to the provisions of this part shall record the daily charging rates and hours of operation.</P>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.54</SECTNO>
              <SUBJECT>Test methods and procedures.</SUBJECT>
              <P>(a) In conducting the performance tests required in § 60.8, the owner or operator shall use as reference methods and procedures the test methods in appendix A of this part or other methods and procedures as specified in this section, except as provided in § 60.8(b).</P>
              <P>(b) The owner or operator shall determine compliance with the particulate matter standard in § 60.52 as follows:</P>
              <P>(1) The concentration (c<E T="52">12</E>) of particulate matter, corrected to 12 percent CO<E T="52">2</E>, shall be computed for each run using the following equation:
              </P>
              <FP SOURCE="FP-1">c<E T="52">12</E> = c<E T="52">s</E> (12/%CO<E T="52">2</E>)</FP>
              
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">c<E T="52">12</E>=concentration of particulate matter, corrected to 12 percent CO<E T="52">2</E>, g/dscm (gr/dscf).</FP>
                <FP SOURCE="FP-1">c<E T="52">s</E>=concentration of particulate matter, g/dscm (gr/dscf).</FP>
                <FP SOURCE="FP-1">%CO<E T="52">2</E>=CO<E T="52">2</E> concentration, percent dry basis.</FP>
              </EXTRACT>
              

              <P>(2) Method 5 shall be used to determine the particulate matter concentration (c<E T="52">s</E>). The sampling time and sample volume for each run shall be at least 60 minutes and 0.85 dscm (30 dscf).</P>

              <P>(3) The emission rate correction factor, integrated or grab sampling and analysis procedure of Method 3B shall be used to determine CO<E T="52">2</E> concentration (%CO<E T="52">2</E>).</P>
              <P>(i) The CO<E T="52">2</E> sample shall be obtained simultaneously with, and at the same traverse points as, the particulate run. If the particulate run has more than 12 traverse points, the CO<E T="52">2</E> traverse points may be reduced to 12 if Method 1 is used to locate the 12 CO<E T="52">2</E> traverse points. If individual CO<E T="52">2</E> samples are taken at each traverse point, the CO<E T="52">2</E>
                <PRTPAGE P="161"/>concentration (%CO<E T="52">2</E>) used in the correction equation shall be the arithmetic mean of the sample CO<E T="52">2</E> concentrations at all traverse points.</P>

              <P>(ii) If sampling is conducted after a wet scrubber, an “adjusted” CO<E T="52">2</E> concentration [(%CO<E T="52">2</E>)<E T="52">adj</E>], which accounts for the effects of CO<E T="52">2</E> absorption and dilution air, may be used instead of the CO<E T="52">2</E> concentration determined in this paragraph. The adjusted CO<E T="52">2</E> concentration shall be determined by either of the procedures in paragraph (c) of this section.</P>

              <P>(c) The owner or operator may use either of the following procedures to determine the adjusted CO<E T="52">2</E> concentration.</P>

              <P>(1) The volumetric flow rates at the inlet and outlet of the wet scrubber and the inlet CO<E T="52">2</E> concentration may be used to determine the adjusted CO<E T="52">2</E> concentration [(%CO<E T="52">2</E>)<E T="52">adj</E>] using the following equation:
              </P>
              <FP SOURCE="FP-1">(%CO<E T="52">2</E>)<E T="52">adj</E>=(%CO<E T="52">2</E>)<E T="52">di</E> (Q<E T="52">di</E>/Q<E T="52">do</E>)</FP>
              
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">(%CO<E T="52">2</E>)<E T="52">adj</E>=adjusted outlet CO<E T="52">2</E> concentration, percent dry basis.</FP>
                <FP SOURCE="FP-1">(%CO<E T="52">2</E>)<E T="52">di</E>=CO<E T="52">2</E> concentration measured before the scrubber, percent dry basis.</FP>
                <FP SOURCE="FP-1">Q<E T="52">di</E>=volumetric flow rate of effluent gas before the wet scrubber, dscm/min (dscf/min).</FP>
                <FP SOURCE="FP-1">Q<E T="52">do</E>=volumetric flow rate of effluent gas after the wet scrubber, dscm/min (dscf/min).</FP>
              </EXTRACT>
              

              <P>(i) At the outlet, Method 5 is used to determine the volumetric flow rate (Q<E T="52">do</E>) of the effluent gas.</P>

              <P>(ii) At the inlet, Method 2 is used to determine the volumetric flow rate (Q<E T="52">di</E>) of the effluent gas as follows: Two full velocity traverses are conducted, one immediately before and one immediately after each particulate run conducted at the outlet, and the results are averaged.</P>

              <P>(iii) At the inlet, the emission rate correction factor, integrated sampling and analysis procedure of Method 3B is used to determine the CO<E T="52">2</E> concentration [(%CO<E T="52">2</E>)<E T="52">di</E>] as follows: At least nine sampling points are selected randomly from the velocity traverse points and are divided randomly into three sets, equal in number of points; the first set of three or more points is used for the first run, the second set for the second run, and the third set for the third run. The CO<E T="52">2</E> sample is taken simultaneously with each particulate run being conducted at the outlet, by traversing the three sampling points (or more) and sampling at each point for equal increments of time.</P>

              <P>(2) Excess air measurements may be used to determine the adjusted CO<E T="52">2</E> concentration [(%CO<E T="52">2</E>)<E T="52">adj</E>] using the following equation:
              </P>
              <FP SOURCE="FP-1">(%CO<E T="52">2</E>)<E T="52">adj</E>=(%CO<E T="52">2</E>)<E T="52">di</E> [(100+%EA<E T="52">i</E>)/(100+%EA<E T="52">o</E>)]</FP>
              
              <EXTRACT>
                <FP>where:</FP>
                
                <FP SOURCE="FP-1">(%CO<E T="52">2</E>)<E T="52">adj</E>=adjusted outlet CO<E T="52">2</E> concentration, percent dry basis.</FP>
                <FP SOURCE="FP-1">(%CO<E T="52">2</E>)<E T="52">di</E>=CO<E T="52">2</E> concentration at the inlet of the wet scrubber, percent dry basis.</FP>
                <FP SOURCE="FP-1">%EA<E T="52">i</E>=excess air at the inlet of the scrubber, percent.</FP>
                <FP SOURCE="FP-1">%EA<E T="52">o</E>=excess air at the outlet of the scrubber, percent.</FP>
              </EXTRACT>
              

              <P>(i) A gas sample is collected as in paragraph (c)(1)(iii) of this section and the gas samples at both the inlet and outlet locations are analyzed for CO<E T="52">2</E>, O<E T="52">2</E>, and N<E T="52">2</E>.</P>
              <P>(ii) Equation 3B-3 of Method 3B is used to compute the percentages of excess air at the inlet and outlet of the wet scrubber.</P>
              <CITA>[54 FR 6665, Feb. 14, 1989, as amended at 55 FR 5212, Feb. 14, 1990; 65 FR 61753, Oct. 17, 2000]</CITA>
            </SECTION>
          </SUBPART>
          <SUBPART>
            <HD SOURCE="HED">Subpart Ea—Standards of Performance for Municipal Waste Combustors for Which Construction is Commenced After December 20, 1989 and on or Before September 20, 1994</HD>
            <SOURCE>
              <HD SOURCE="HED">Source:</HD>
              <P>56 FR 5507, Feb. 11, 1991, unless otherwise noted.</P>
            </SOURCE>
            <SECTION>
              <SECTNO>§ 60.50a</SECTNO>
              <SUBJECT>Applicability and delegation of authority.</SUBJECT>
              <P>(a) The affected facility to which this subpart applies is each municipal waste combustor unit with a municipal waste combustor unit capacity greater than 225 megagrams per day (250 tons per day) of municipal solid waste for which construction, modification, or reconstruction is commenced as specified in paragraphs (a)(1) and (a)(2) of this section.</P>

              <P>(1) Construction is commenced after December 20, 1989 and on or before September 20, 1994.<PRTPAGE P="162"/>
              </P>
              <P>(2) Modification or reconstruction is commenced after December 20, 1989 and on or before June 19, 1996.</P>
              <P>(b) [Reserved]</P>
              <P>(c) Any unit combusting a single-item waste stream of tires is not subject to this subpart if the owner or operator of the unit:</P>
              <P>(1) Notifies the Administrator of an exemption claim; and</P>
              <P>(2) Provides data documenting that the unit qualifies for this exemption.</P>
              <P>(d) Any cofired combustor, as defined under § 60.51a, located at a plant that meets the capacity specifications in paragraph (a) of this section is not subject to this subpart if the owner or operator of the cofired combustor:</P>
              <P>(1) Notifies the Administrator of an exemption claim;</P>
              <P>(2) Provides a copy of the federally enforceable permit (specified in the definition of cofired combustor in this section); and</P>
              <P>(3) Keeps a record on a calendar quarter basis of the weight of municipal solid waste combusted at the cofired combustor and the weight of all other fuels combusted at the cofired combustor.</P>
              <P>(e) Any cofired combustor that is subject to a federally enforceable permit limiting the operation of the combustor to no more than 225 megagrams per day (250 tons per day) of municipal solid waste is not subject to this subpart.</P>
              <P>(f) Physical or operational changes made to an existing municipal waste combustor unit primarily for the purpose of complying with emission guidelines under subpart Cb are not considered a modification or reconstruction and do not result in an existing municipal waste combustor unit becoming subject to this subpart.</P>
              <P>(g) A qualifying small power production facility, as defined in section 3(17)(C) of the Federal Power Act (16 U.S.C. 796(17)(C)), that burns homogeneous waste (such as automotive tires or used oil, but not including refuse-derived fuel) for the production of electric energy is not subject to this subpart if the owner or operator of the facility notifies the Administrator of an exemption claim and provides data documenting that the facility qualifies for this exemption.</P>
              <P>(h) A qualifying cogeneration facility, as defined in section 3(18)(B) of the Federal Power Act (16 U.S.C. 796(18)(B)), that burns homogeneous waste (such as automotive tires or used oil, but not including refuse-derived fuel) for the production of electric energy and steam or forms of useful energy (such as heat) that are used for industrial, commercial, heating, or cooling purposes, is not subject to this subpart if the owner or operator of the facility notifies the Administrator of an exemption claim and provides data documenting that the facility qualifies for this exemption.</P>
              <P>(i) Any unit required to have a permit under section 3005 of the Solid Waste Disposal Act is not subject to this subpart.</P>
              <P>(j) Any materials recovery facility (including primary or secondary smelters) that combusts waste for the primary purpose of recovering metals is not subject to this subpart.</P>
              <P>(k) Pyrolysis/combustion units that are an integrated part of a plastics/rubber recycling unit (as defined in § 60.51a) are not subject to this subpart if the owner or operator of the plastics/rubber recycling unit keeps records of: the weight of plastics, rubber, and/or rubber tires processed on a calendar quarter basis; the weight of chemical plant feedstocks and petroleum refinery feedstocks produced and marketed on a calendar quarter basis; and the name and address of the purchaser of the feedstocks. The combustion of gasoline, diesel fuel, jet fuel, fuel oils, residual oil, refinery gas, petroleum coke, liquified petroleum gas, propane, or butane produced by chemical plants or petroleum refineries that use feedstocks produced by plastics/rubber recycling units are not subject to this subpart.</P>
              <P>(l) The following authorities shall be retained by the Administrator and not transferred to a State:</P>
              <P>None.</P>
              <P>(m) This subpart shall become effective on August 12, 1991.</P>
              <CITA>[56 FR 5507, Feb. 11, 1991, as amended at 60 FR 65384, Dec. 19, 1995]</CITA>
            </SECTION>
            <SECTION>
              <SECTNO>§ 60.51a</SECTNO>
              <SUBJECT>Definitions.</SUBJECT>
              <P>
                <E T="03">ASME</E> means the American Society of Mechanical Engineers.<PRTPAGE P="163"/>
              </P>
              <P>
                <E T="03">Batch MWC</E> means an MWC unit designed such that it cannot combust MSW continuously 24 hours per day because the design does not allow waste to be fed to the unit or ash to be removed while combustion is occurring.</P>
              <P>
                <E T="03">Bubbling fluidized bed combustor</E> means a fluidized bed combustor in which the majority of the bed material remains in a fluidized state in the primary combustion zone.</P>
              <P>
                <E T="03">Calendar quarter</E> means a consecutive 3-month period (nonoverlapping) beginning on January 1, April 1, July 1, and October 1.</P>
              <P>
                <E T="03">Chief facility operator</E> means the person in direct charge and control of the operation of an MWC and who is responsible for daily on-site supervision, technical direction, management, and overall performance of the facility.</P>
              <P>
                <E T="03">Circulating fluidized bed combustor</E> means a fluidized bed combustor in which the majority of the fluidized bed material is carried out of the primary combustion zone and is transported back to the primary zone through a recirculation loop.</P>
              <P>
                <E T="03">Clean wood</E> means untreated wood or untreated wood products including clean untreated lumber, tree stumps (whole or chipped), and tree limbs (whole or chipped). Clean wood does not include yard waste, which is defined elsewhere in this section, or construction, renovation, and demolition wastes (which includes but is not limited to railroad ties and telephone poles), which are exempt from the definition of municipal solid waste in this section.</P>
              <P>
                <E T="03">Cofired combustor</E> means a unit combusting municipal solid waste with nonmunicipal solid waste fuel (e.g., coal, industrial process waste) and subject to a federally enforceable permit limiting the unit to combusting a fuel feed stream, 30 percent or less of the weight of which is comprised, in aggregate, of municipal solid waste as measured on a calendar quarter basis.</P>
              <P>
                <E T="03">Continuous emission monitoring system</E> or <E T="03">CEMS</E> means a monitoring system for continuously measuring the emissions of a pollutant from an affected facility.</P>
              <P>
                <E T="03">Continuous monitoring system</E> means the total equipment used to sample and condition (if applicable), to analyze, and to provide a permanent record of emissions or process parameters.</P>
              <P>
                <E T="03">Dioxin/furan</E> means total tetra- through octachlorinated dibenzo-p-dioxins and dibenzofurans.</P>
              <P>
                <E T="03">Federally-enforceable</E> means all limitations a