    <TITLE>CAIR SO2 allowance allocations to CAIR SO2 opt-in units.</TITLE>
    <GRANULENUM>97.288</GRANULENUM>
    <HEADING>Section 97.288</HEADING>
    <ANCESTORS>
      <PARENT HEADING="Title 40" SEQ="4">Protection of Environment</PARENT>
      <PARENT HEADING="CHAPTER I" SEQ="3">ENVIRONMENTAL PROTECTION AGENCY (CONTINUED)</PARENT>
      <PARENT HEADING="SUBCHAPTER C" SEQ="2">AIR PROGRAMS (CONTINUED)</PARENT>
      <PARENT HEADING="PART 97" SEQ="1">FEDERAL NOX BUDGET TRADING PROGRAM AND CAIR NOX AND SO2 TRADING PROGRAMS</PARENT>
      <PARENT HEADING="Subpart III" SEQ="0">CAIR SO2 Opt-in Units</PARENT>
    </ANCESTORS>
  </FDSYS>
  <SECTION>
    <SECTNO>§ 97.288</SECTNO>
    <SUBJECT>CAIR SO2 allowance allocations to CAIR SO2 opt-in units.</SUBJECT>
    <P>(a) <E T="03">Timing requirements</E>. (1) When the CAIR opt-in permit is issued under § 97.284(e), the permitting authority will allocate CAIR SO<E T="52">2</E> allowances to the CAIR SO<E T="52">2</E> opt-in unit, and submit to the Administrator the allocation for the control period in which a CAIR SO<E T="52">2</E> opt-in unit enters the CAIR SO<E T="52">2</E> Trading Program under § 97.284(g), in accordance with paragraph (b) or (c) of this section.</P>

    <P>(2) By no later than October 31 of the control period after the control period in which a CAIR SO<E T="52">2</E> opt-in unit enters the CAIR SO<E T="52">2</E> Trading Program under § 97.284(g) and October 31 of each year thereafter, the permitting authority will allocate CAIR SO<E T="52">2</E> allowances to the CAIR SO<E T="52">2</E> opt-in unit, and submit to the Administrator the allocation for the control period that includes such submission deadline and in which the unit is a CAIR SO<E T="52">2</E> opt-in unit, in accordance with paragraph (b) or (c) of this section.</P>
    <P>(b) <E T="03">Calculation of allocation</E>. For each control period for which a CAIR SO<E T="52">2</E> opt-in unit is to be allocated CAIR SO<E T="52">2</E> allowances, the permitting authority will allocate in accordance with the following procedures, if provided in a State implementation plan revision submitted in accordance with § 51.124(r)(1), (2), or (3) of this chapter and approved by the Administrator:</P>
    <P>(1) The heat input (in mmBtu) used for calculating the CAIR SO<E T="52">2</E> allowance allocation will be the lesser of:</P>
    <P>(i) The CAIR SO<E T="52">2</E> opt-in unit's baseline heat input determined under § 97.284(c); or</P>
    <P>(ii) The CAIR SO<E T="52">2</E> opt-in unit's heat input, as determined in accordance with subpart HHH of this part, for the <PRTPAGE P="967"/>immediately prior control period, except when the allocation is being calculated for the control period in which the CAIR SO<E T="52">2</E> opt-in unit enters the CAIR SO<E T="52">2</E> Trading Program under § 97.284(g).</P>
    <P>(2) The SO<E T="52">2</E> emission rate (in lb/mmBtu) used for calculating CAIR SO<E T="52">2</E> allowance allocations will be the lesser of:</P>
    <P>(i) The CAIR SO<E T="52">2</E> opt-in unit's baseline SO<E T="52">2</E> emissions rate (in lb/mmBtu) determined under § 97.284(d) and multiplied by 70 percent; or</P>
    <P>(ii) The most stringent State or Federal SO<E T="52">2</E> emissions limitation applicable to the CAIR SO<E T="52">2</E> opt-in unit at any time during the control period for which CAIR SO<E T="52">2</E> allowances are to be allocated.</P>
    <P>(3) The permitting authority will allocate CAIR SO<E T="52">2</E> allowances to the CAIR SO<E T="52">2</E> opt-in unit with a tonnage equivalent equal to, or less than by the smallest possible amount, the heat input under paragraph (b)(1) of this section, multiplied by the SO<E T="52">2</E> emission rate under paragraph (b)(2) of this section, and divided by 2,000 lb/ton.</P>

    <P>(c) Notwithstanding paragraph (b) of this section and if the CAIR designated representative requests, and the permitting authority issues a CAIR opt-in permit (based on a demonstration of the intent to repower stated under § 97.283(a)(5)) providing for, allocation to a CAIR SO<E T="52">2</E> opt-in unit of CAIR SO<E T="52">2</E> allowances under this paragraph (subject to the conditions in §§ 97.284(h) and 97.286(g)), the permitting authority will allocate to the CAIR SO<E T="52">2</E> opt-in unit as follows, if provided in a State implementation plan revision submitted in accordance with § 51.124(r)(1), (2), or (3) of this chapter and approved by the Administrator:</P>

    <P>(1) For each control period in 2010 through 2014 for which the CAIR SO<E T="52">2</E> opt-in unit is to be allocated CAIR SO<E T="52">2</E> allowances,</P>
    <P>(i) The heat input (in mmBtu) used for calculating CAIR SO<E T="52">2</E> allowance allocations will be determined as described in paragraph (b)(1) of this section.</P>
    <P>(ii) The SO<E T="52">2</E> emission rate (in lb/mmBtu) used for calculating CAIR SO<E T="52">2</E> allowance allocations will be the lesser of:</P>
    <P>(A) The CAIR SO<E T="52">2</E> opt-in unit's baseline SO<E T="52">2</E> emissions rate (in lb/mmBtu) determined under § 97.284(d); or</P>
    <P>(B) The most stringent State or Federal SO<E T="52">2</E> emissions limitation applicable to the CAIR SO<E T="52">2</E> opt-in unit at any time during the control period in which the CAIR SO<E T="52">2</E> opt-in unit enters the CAIR SO<E T="52">2</E> Trading Program under § 97.284(g).</P>
    <P>(iii) The permitting authority will allocate CAIR SO<E T="52">2</E> allowances to the CAIR SO<E T="52">2</E> opt-in unit with a tonnage equivalent equal to, or less than by the smallest possible amount, the heat input under paragraph (c)(1)(i) of this section, multiplied by the SO<E T="52">2</E> emission rate under paragraph (c)(1)(ii) of this section, and divided by 2,000 lb/ton.</P>

    <P>(2) For each control period in 2015 and thereafter for which the CAIR SO<E T="52">2</E> opt-in unit is to be allocated CAIR SO<E T="52">2</E> allowances,</P>
    <P>(i) The heat input (in mmBtu) used for calculating the CAIR SO<E T="52">2</E> allowance allocations will be determined as described in paragraph (b)(1) of this section.</P>
    <P>(ii) The SO<E T="52">2</E> emission rate (in lb/mmBtu) used for calculating the CAIR SO<E T="52">2</E> allowance allocation will be the lesser of:</P>
    <P>(A) The CAIR SO<E T="52">2</E> opt-in unit's baseline SO<E T="52">2</E> emissions rate (in lb/mmBtu) determined under § 97.284(d) multiplied by 10 percent; or</P>
    <P>(B) The most stringent State or Federal SO<E T="52">2</E> emissions limitation applicable to the CAIR SO<E T="52">2</E> opt-in unit at any time during the control period for which CAIR SO<E T="52">2</E> allowances are to be allocated.</P>
    <P>(iii) The permitting authority will allocate CAIR SO<E T="52">2</E> allowances to the CAIR SO<E T="52">2</E> opt-in unit with a tonnage equivalent equal to, or less than by the smallest possible amount, the heat input under paragraph (c)(2)(i) of this section, multiplied by the SO<E T="52">2</E> emission rate under paragraph (c)(2)(ii) of this section, and divided by 2,000 lb/ton.</P>
    <P>(d) <E T="03">Recordation.</E> If provided in a State implementation plan revision submitted in accordance with § 51.124(r)(1), (2), or (3) of this chapter and approved by the Administrator:</P>

    <P>(1) The Administrator will record, in the compliance account of the source that includes the CAIR SO<E T="52">2</E> opt-in unit, <PRTPAGE P="968"/>the CAIR SO<E T="52">2</E> allowances allocated by the permitting authority to the CAIR SO<E T="52">2</E> opt-in unit under paragraph (a)(1) of this section.</P>
    <P>(2) By December 1 of the control period in which a CAIR SO<E T="52">2</E> opt-in unit enters the CAIR SO<E T="52">2</E> Trading Program under § 97.284(g) and December 1 of each year thereafter, the Administrator will record, in the compliance account of the source that includes the CAIR SO<E T="52">2</E> opt-in unit, the CAIR SO<E T="52">2</E> allowances allocated by the permitting authority to the CAIR SO<E T="52">2</E> opt-in unit under paragraph (a)(2) of this section.</P>