<?xml version="1.0"?>
<?xml-stylesheet type="text/xsl" href="cfr.xsl"?>
<CFRGRANULE xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="CFRMergedXML.xsd">
  <FDSYS>
    <CFRTITLE>24</CFRTITLE>
    <CFRTITLETEXT>Housing and Urban Development</CFRTITLETEXT>
    <VOL>1</VOL>
    <DATE>2009-04-01</DATE>
    <ORIGINALDATE>2009-04-01</ORIGINALDATE>
    <COVERONLY>false</COVERONLY>
    <TITLE>Public hearings and meetings.</TITLE>
    <GRANULENUM>58.59</GRANULENUM>
    <HEADING>Section 58.59</HEADING>
    <ANCESTORS>
      <PARENT HEADING="Title 24" SEQ="3">Housing and Urban Development</PARENT>
      <PARENT HEADING="Subtitle A" SEQ="2">Office of the Secretary, Department of Housing and Urban Development</PARENT>
      <PARENT HEADING="PART 58" SEQ="1">ENVIRONMENTAL REVIEW PROCEDURES FOR ENTITIES ASSUMING HUD ENVIRONMENTAL RESPONSIBILITIES</PARENT>
      <PARENT HEADING="Subpart G" SEQ="0">Environmental Review Process: Procedures for Draft, Final and Supplemental Environmental Impact Statements</PARENT>
    </ANCESTORS>
  </FDSYS>
  <SECTION>
    <SECTNO>§ 58.59</SECTNO>
    <SUBJECT>Public hearings and meetings.</SUBJECT>
    <P>(a) <E T="03">Factors to consider.</E> In determining whether or not to hold public hearings in accordance with 40 CFR 1506.6, the responsible entity must consider the following factors:</P>
    <P>(1) The magnitude of the project in terms of economic costs, the geographic area involved, and the uniqueness or size of commitment of resources involved.</P>
    <P>(2) The degree of interest in or controversy concerning the project.</P>
    <P>(3) The complexity of the issues and the likelihood that information will be presented at the hearing which will be of assistance to the responsible entity.</P>
    <P>(4) The extent to which public involvement has been achieved through other means.</P>
    <P>(b) <E T="03">Procedure.</E> All public hearings must be preceded by a notice of public hearing, which must be published in the local news media 15 days before the hearing date. The Notice must:</P>
    <P>(1) State the date, time, place, and purpose of the hearing or meeting.</P>
    <P>(2) Describe the project, its estimated costs, and the project area.</P>
    <P>(3) State that persons desiring to be heard on environmental issues will be afforded the opportunity to be heard.</P>
    <P>(4) State the responsible entity's name and address and the name and address of its Certifying Officer.</P>
    <P>(5) State what documents are available, where they can be obtained, and any charges that may apply.</P>
  </SECTION>