NUCLEAR REGULATORY COMMISSION
[Docket No. 50-302]
In the Matter of Florida Power Corporation, et al.; Crystal
River, Unit 3; Revocation of Exemption
I
The Florida Power Corporation, et. al. (FPC or the licensee) is the
holder of Facility Operating License No. DPR-72, which authorizes
operation of Crystal River Unit 3. The license provides that the
licensee is subject to all rules, regulations, and orders of the
Nuclear Regulatory Commission (the Commission) now or hereafter in
effect.
The facility consists of a pressurized-water reactor at the
licensee's site located in Citrus County, Florida.
II
With respect to certain generic issues for facilities operating
prior to January 1, 1979, except to the extent set forth in 10 CFR
50.48(b), 10 CFR Part 50, Appendix R, sets forth fire protection
features required to satisfy general design Criterion 3 of the
Commission's regulations. Pursuant to 10 CFR Part 50, Appendix R,
Section III. O, ``Oil collection system for reactor coolant pump,'' the
reactor coolant pump (RCP) shall be equipped with an oil collection
system which ``* * * shall be capable of collecting lube oil from all
potential pressurized and unpressurized leakage sites in the RCP lube
oil system.''
When replacing the RCP motors with new motors and re-designed RCP
lube oil system, physical interference and other design difficulties
prevented four specific sites in the RCP motor lube oil system from
accommodating an oil collection system for collecting potential oil
leakage. By letter dated June 7, 1993, as supplemented March 28, 1994,
the licensee submitted an exemption request to exclude these four
specific sites from leakage protection. On October 7, 1994, as appended
on September 17, 1996, the NRC granted the requested exemption because
it was determined that a collection system at the four specific sites
was not necessary to achieve the underlying purpose of the regulation.
By letter dated November 13, 1997, the licensee informed the NRC
that modifications had been made to the RCP Oil Collection System such
that collection coverage for these four potential leakage sites was
assured, and that the Crystal River Unit 3 RCP Oil Collection System
now conforms to the requirements of 10 CFR Part 50, Appendix R, Section
III. O. In the FPC
[[Page 48254]]
letter, it was stated that the exemption issued on October 7, 1994, was
no longer needed.
III
The NRC has reviewed the information submitted by the licensee and
concludes that the exemption granted for the four oil collection sites
in the RCP motor lube oil system is no longer necessary. Specifically,
the licensee has stated that modifications have been completed on the
RCP Oil Collection System such that the system now conforms to the
requirements of 10 CFR Part 50, Appendix R, Section III. O.
IV
Accordingly, the Commission hereby revokes the specific exemption
from 10 CFR Part 50, Appendix R, Section III. O, granted on October 7,
1994, as appended September 17, 1996, relating to oil collection in the
RCPs.
This Revocation of Exemption is effective upon issuance.
Dated at Rockville, Maryland, this 1st day of September 1998.
For the Nuclear Regulatory Commission.
Robert A. Capra,
Acting Director, Division of Reator Projects I/II, Office of Nuclear
Reactor Regulation.
[FR Doc. 98-24128 Filed 9-8-98; 8:45 am]