[Federal Register Volume 72, Number 220 (Thursday, November 15, 2007)]
[Notices]
[Page 64252]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-22349]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 72-26]
Notice of Issuance of Addendum to the Supplement to the
Environmental Assessment for the Diablo Canyon Independent Spent Fuel
Storage Installation
AGENCY: Nuclear Regulatory Commission.
ACTION: Notice of Issuance.
-----------------------------------------------------------------------
SUMMARY: Notice is hereby given that the U.S. Nuclear Regulatory
Commission (NRC) is issuing an Addendum to the supplement to the
Environmental Assessment (EA) for the Diablo Canyon Independent Spent
Fuel Storage Installation (ISFSI). NRC issued the EA and initial
Finding of No Significant Impact (FONSI) for this action on October 24,
2003, and subsequently issued a license for the Diablo Canyon ISFSI to
the Pacific Gas and Electric Company (PG&E), on March 22, 2004. The
license authorizes PG&E to receive, possess, store, and transfer spent
nuclear fuel and associated radioactive materials resulting from the
operation of the Diablo Canyon Power Plant in an ISFSI at the site for
a term of 20 years. On August 30, 2007, NRC issued a supplement to the
EA and final FONSI, in response to the June 2, 2006, decision by the
United States Court of Appeals for the Ninth Circuit, San Luis Obispo
Mothers for Peace v. NRC, 449 F.3d 1016 (9th Cir. 2006). The supplement
to the EA addressed the environmental impacts from potential terrorist
acts against the Diablo Canyon ISFSI. The Addendum lists six documents
to be added to the list of references provided in the supplement to the
EA.
FOR FURTHER INFORMATION CONTACT: James R. Hall, Senior Project Manager,
Licensing Branch, Division of Spent Fuel Storage and Transportation,
Mail Stop EBB-3D-02M, U.S. Nuclear Regulatory Commission, Washington,
DC 20555-0001. Telephone: (301) 492-3319; e-mail: jrh@nrc.gov.
SUPPLEMENTARY INFORMATION: On December 21, 2001, PG&E submitted an
application to NRC, requesting a site-specific license to build and
operate an ISFSI, to be located on the site of the Diablo Canyon Power
Plant, in San Luis Obispo County, California. The NRC staff issued an
EA and FONSI for this action on October 24, 2003, in accordance with
the National Environmental Policy Act, and in conformance with the
applicable requirements of 10 CFR part 51.
On March 22, 2004, the NRC staff issued Materials License No. SNM-
2511 to PG&E, pursuant to 10 CFR part 72, authorizing PG&E to receive,
possess, store, and transfer spent nuclear fuel and associated
radioactive materials resulting from the operation of the Diablo Canyon
Power Plant in an ISFSI at the site for a term of 20 years.
Subsequently, the San Luis Obispo Mothers for Peace and other parties
filed suit in the United States Court of Appeals for the Ninth Circuit,
asking that NRC be required to consider terrorist acts in its
environmental review associated with this licensing action. In its
decision of June 2, 2006, San Luis Obispo Mothers for Peace v. NRC, 449
F.3d 1016 (9th Cir. 2006), the Ninth Circuit held that NRC could not
categorically refuse to consider the consequences of a terrorist attack
under NEPA and remanded the case to NRC.
In response to the Ninth Circuit decision, the Commission directed
the NRC staff to prepare a revised EA, addressing the likelihood of a
terrorist attack at the Diablo Canyon ISFSI site and the potential
consequences of such an attack. On May 29, 2007, the NRC staff issued a
preliminary supplement to the EA and draft FONSI to address the
environmental impacts from potential terrorist acts against the Diablo
Canyon ISFSI. On August 30, 2007, NRC issued the final supplement to
the EA and final FONSI for this action. NRC summarized the comments
received and responded to those comments in the final supplement to the
EA, which also included a list of 14 references. Subsequent to the
issuance of the final supplement, the staff determined that certain
other documents concerning NRC's generic security assessments should
also be included in the list of references. These 6 documents are
listed in the Addendum.
Documents related to this action, including the May 29, 2007,
preliminary supplement to the EA and draft FONSI; the August 30, 2007,
EA supplement and final FONSI; the October 24, 2003, EA; and the Diablo
Canyon ISFSI license and supporting documentation, are available
electronically, at NRC's Electronic Reading Room, at: http://
www.nrc.gov/reading-rm/adams.html. From this site, you can access NRC's
Agencywide Document Access and Management System (ADAMS), which
provides text and image files of NRC's public documents. The ADAMS
accession number for the final EA supplement and final FONSI is
ML072400511, and the accession number for the Addendum is ML073040434.
For the preliminary supplement to the EA and draft FONSI, the accession
number is ML071280256. The ADAMS accession number for the October 24,
2003, EA is ML032970337; and for the ISFSI license and related
documents, the accession number is ML040780107. If you do not have
access to ADAMS, or if there are problems in accessing the documents
located in ADAMS, contact NRC's Public Document Room (PDR) Reference
staff at 1-800-397-4209, 301-415-4737, or by e-mail to pdr@nrc.gov.
These documents may also be viewed electronically on the public
computers located at NRC's PDR, O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, MD 20852. The PDR reproduction contractor
will copy documents, for a fee.
Dated at Rockville, Maryland, this 7th day of November, 2007.
For the Nuclear Regulatory Commission.
Robert A. Nelson,
Chief, Licensing Branch, Division of Spent Fuel Storage and
Transportation, Office of Nuclear Material Safety and Safeguards.
[FR Doc. E7-22349 Filed 11-14-07; 8:45 am]
BILLING CODE 7590-01-P