[Federal Register Volume 75, Number 47 (Thursday, March 11, 2010)]
[Notices]
[Page 11528]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-5204]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2244-000]
Energy Northwest; Notice of Authorization for Continued Project
Operation
March 4, 2010.
On March 7, 2008, Energy Northwest, licensee for the Packwood Lake
Hydroelectric Project, filed an Application for a New License pursuant
to the Federal Power Act (FPA) and the Commission's regulations
thereunder. The Packwood Lake Hydroelectric Project is located on Lake
Creek, a tributary to the Cowlitz River, in Lewis County in
southwestern Washington.
The license for Project No. 2244 was issued for a period ending
February 28, 2010. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1),
requires the Commission, at the expiration of a license term, to issue
from year-to-year an annual license to the then licensee under the
terms and conditions of the prior license until a new license is
issued, or the project is otherwise disposed of as provided in section
15 or any other applicable section of the FPA. If the project's prior
license waived the applicability of section 15 of the FPA, then, based
on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c),
and as set forth at 18 CFR 16.21(a), if the licensee of such project
has filed an application for a subsequent license, the licensee may
continue to operate the project in accordance with the terms and
conditions of the license after the minor or minor part license
expires, until the Commission acts on its application. If the licensee
of such a project has not filed an application for a subsequent
license, then it may be required, pursuant to 18 CFR 16.21(b), to
continue project operations until the Commission issues someone else a
license for the project or otherwise orders disposition of the project.
If the project is subject to section 15 of the FPA, notice is
hereby given that an annual license for Project No. 2244 is issued to
Energy Northwest for a period effective March 1, 2010 through February
28, 2011, or until the issuance of a new license for the project or
other disposition under the FPA, whichever comes first. If issuance of
a new license (or other disposition) does not take place on or before
February 28, 2011, notice is hereby given that, pursuant to 18 CFR
16.18(c), an annual license under section 15(a)(1) of the FPA is
renewed automatically without further order or notice by the
Commission, unless the Commission orders otherwise. If the project is
not subject to section 15 of the FPA, notice is hereby given that
Energy Northwest is authorized to continue operation of the Packwood
Lake Hydroelectric Project, until such time as the Commission acts on
its application for a subsequent license.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010-5204 Filed 3-10-10; 8:45 am]
BILLING CODE 6717-01-P