Blue Heron Hydro LLC; Notice of Application Ready for 
Environmental Analysis and Soliciting Comments, Recommendations, Terms 
and Conditions, and Prescriptions

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Original Minor License.
    b. Project No.: 13368-002.
    c. Date filed: November 1, 2010.
    d. Applicant: Blue Heron Hydro LLC.
    e. Name of Project: Townshend Dam Hydroelectric Project.
    f. Location: At the U.S. Army Corps of Engineers Townshend Dam on 
the West River near the Town of Townshend, Windham County, Vermont.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
    h. Applicant Contact: Lori Barg, Blue Heron Hydro LLC, 113 Bartlett 
Road, Plainfield, Vermont 05667. (802) 454-1874.
    i. FERC Contact: Dr. Nicholas Palso, (202) 502-8854 or 
[email protected].
    j. Deadline for filing comments, recommendations, terms and 
conditions, and prescriptions: 60 days from the issuance date of this 
notice; reply comments are due 105 days from the issuance date of this 
notice.
    All documents may be filed electronically via the Internet. See 18 
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web 
site http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at [email protected] or toll free at 1-866-208-3676, 
or for TTY, (202) 502-8659. Although the Commission strongly encourages 
electronic filing, documents may also be paper-filed. To paper-file, 
mail an original and seven copies to: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street, NE., 
Washington, DC 20426.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. This application has been accepted and is now ready for 
environmental analysis.
    l. Project Description: The Townshend Dam Hydroelectric Project 
would utilize the U.S. Army Corps of Engineers' existing Townshend Dam 
and reservoir and would consist of: (1) Two turbine generator modules 
located within the existing intake tower, each containing 6 horizontal 
mixed flow turbines directly connected to 6 submersible generator units 
for a total installed capacity of 925 kilowatts; (2) a new 12.47-
kilovolt, 430-foot-long transmission line; and (3) appurtenant 
facilities. The project would have an estimated average annual 
generation of approximately 2,000 megawatt-hours.
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at http://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    All filings must (1) bear in all capital letters the title 
``COMMENTS'', ``REPLY COMMENTS'', ``RECOMMENDATIONS,'' ``TERMS AND 
CONDITIONS,'' or ``PRESCRIPTIONS;'' (2) set forth in the heading the 
name of the applicant and the project number of the application to 
which the filing responds; (3) furnish

[[Page 35876]]

the name, address, and telephone number of the person submitting the 
filing; and (4) otherwise comply with the requirements of 18 CFR 
385.2001 through 385.2005. All comments, recommendations, terms and 
conditions or prescriptions must set forth their evidentiary basis and 
otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may 
obtain copies of the application directly from the applicant. Each 
filing must be accompanied by proof of service on all persons listed on 
the service list prepared by the Commission in this proceeding, in 
accordance with 18 CFR 4.34(b), and 385.2010.
    You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via e-mail of new filings and 
issuances related to this or other pending projects. For assistance, 
contact FERC Online Support.
    n. Public notice of the filing of the initial development 
application, which has already been given, established the due date for 
filing competing applications or notices of intent. Under the 
Commission's regulations, any competing development application must be 
filed in response to and in compliance with public notice of the 
initial development application. No competing applications or notices 
of intent may be filed in response to this notice.

    Dated: June 13, 2011.
Kimberly D. Bose,
Secretary.