[Federal Register Volume 76, Number 121 (Thursday, June 23, 2011)]
[Notices]
[Page 36914]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2011-15715]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. EL11-42-000]


Astoria Generating Company, L.P., NRG Power Marketing LLC, Arthur 
Kill Power LLC, Astoria Gas Turbine Power LLC, Dunkirk Power LLC, 
Huntley Power LLC, Oswego Harbor Power LLC, TC Ravenswood, LLC, v. New 
York Independent System Operator, Inc.

Notice of Revised Comment Dates

    On June 3, 2011, Astoria Generating Company, NRG Power Marketing 
LLC, Arthur Kill Power LLC, Astoria Gas Turbine Power LLC, Dunkirk 
Power LLC, Huntley Power LLC, Oswego Harbor Power LLC and TC 
Ravenswood, LLC (Complainants) filed a complaint against the New York 
Independent System Operator (NYISO) in the captioned docket 
(Complaint). Notice of the Complaint was issued June 7, 2011, providing 
for a Comment Date of June 23, 2011, for that filing. On June 15, 2011, 
Complainants filed an amendment to the Complaint and a request for a 
shortened comment period to and including June 23, 2011, in the 
captioned docket (Amended Complaint). On June 16, 2011, NYISO filed a 
preliminary answer to the Complaint proposing June 30, 2011, as the 
Comment Date applicable to both the Complaint and the Amended 
Complaint, stating that Counsel for the Complainants supports the June 
30, 2011 date. NYISO also states that Counsel for Consolidated Edison 
Company of New York, Inc. has no objection to the Comment Date of June 
30, 2011 for both filings. Notice of the Amended Complaint was issued 
June 17, 2011, providing for a Comment Date of July 5, 2011, for that 
filing.
    Upon consideration of NYISO's request for a revised Comment Date in 
its June 16, 2011 preliminary answer, notice is hereby given that the 
Comment Dates applicable to the Complaint and the Amended Complaint are 
revised to June 30, 2011.
    Any person desiring to intervene or to protest the Complaint and 
Amended Complaint filing must file in accordance with Rules 211 and 214 
of the Commission's Rules of Practice and Procedure (18 CFR 385.211, 
385.214). Protests will be considered by the Commission in determining 
the appropriate action to be taken, but will not serve to make 
protestants parties to the proceeding. Any person wishing to become a 
party must file a notice of intervention or motion to intervene, as 
appropriate. The Respondent's answer and all interventions, or protests 
must be filed on or before the Comment Date. The Respondent's answer, 
motions to intervene, and protests must be served on the Complainants.
    The Commission encourages electronic submission of protests and 
interventions in lieu of paper using the ``eFiling'' link at http://www.ferc.gov. Persons unable to file electronically should submit an 
original and 14 copies of the protest or intervention to the Federal 
Energy Regulatory Commission, 888 First Street, NE., Washington, DC 
20426.
    These filings are accessible on-line at http://www.ferc.gov, using 
the ``eLibrary'' link and is available for review in the Commission's 
Public Reference Room in Washington, DC. There is an ``eSubscription'' 
link on the Web site that enables subscribers to receive e-mail 
notification when a document is added to a subscribed docket(s). For 
assistance with any FERC Online service, please e-mail 
[email protected], or call (866) 208-3676 (toll free). For 
TTY, call (202) 502-8659.
    Comment Date: 5 p.m. Eastern Time on June 30, 2011.

    Dated: June 17, 2011.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2011-15715 Filed 6-22-11; 8:45 am]
BILLING CODE 6717-01-P