[Federal Register Volume 77, Number 55 (Wednesday, March 21, 2012)]
[Rules and Regulations]
[Pages 16435-16447]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-6758]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
18 CFR Parts 39 and 40
[Docket No. RM11-16-000; Order No. 759]
Transmission Relay Loadability Reliability Standard
AGENCY: Federal Energy Regulatory Commission, Energy.
ACTION: Final rule.
-----------------------------------------------------------------------
SUMMARY: Pursuant to section 215 of the Federal Power Act, the
Commission approves Reliability Standard PRC-023-2 (Transmission Relay
Loadability) submitted by the North American Electric Reliability
Corporation (NERC), the Electric Reliability Organization certified by
the Commission. The Reliability Standard requires transmission owners,
generation owners, and distribution providers to set load-responsive
phase protective relays according to specific criteria to ensure that
the relays reliably detect--and protect the electric network from--
fault conditions, but do not limit transmission loadability or
interfere with system operators' ability to protect system reliability.
The Commission also approves NERC Rules of Procedure Section 1700--
Challenges to Determinations, which provides registered entities a
means to challenge determinations made by planning coordinators under
Reliability Standard PRC-023.
DATES: Effective Date: This rule will become effective May 7, 2012.
FOR FURTHER INFORMATION CONTACT:
Kevin Ryan (Legal Information), Office of the General Counsel, Federal
Energy Regulatory Commission, 888 First Street NE., Washington, DC
20426, (202) 502-6840.
Kenneth U. Hubona (Technical Information), Office of Electric
Reliability, Division of Reliability Standards, Federal Energy
Regulatory Commission, 13511 Label Lane, Suite 203, Hagerstown, MD
21740, (301) 665-1608.
SUPPLEMENTARY INFORMATION:
[[Page 16436]]
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
Before Commissioners: Jon Wellinghoff, Chairman; Philip D. Moeller,
John R. Norris, and Cheryl A. LaFleur.
Transmission Relay Loadability Reliability Standard
Docket No. RM11-16-000
Order No. 759
Final Rule
(Issued March 15, 2012)
1. Pursuant to section 215 of the Federal Power Act (FPA),\1\ the
Commission approves Reliability Standard PRC-023-2 (Transmission Relay
Loadability) submitted by the North American Electric Reliability
Corporation (NERC), the Electric Reliability Organization (ERO)
certified by the Commission. The Reliability Standard requires
transmission owners, generation owners, and distribution providers to
set load-responsive phase protective relays according to specific
criteria to ensure that the relays reliably detect--and protect the
electric network from--fault conditions, but do not limit transmission
loadability or interfere with system operators' ability to protect
system reliability.\2\ The Commission also approves NERC Rules of
Procedure Section 1700--Challenges to Determinations, which provides
registered entities a means to challenge determinations made by
planning coordinators under Reliability Standard PRC-023.
---------------------------------------------------------------------------
\1\ 16 U.S.C. 824o (2006).
\2\ In the context of the proposed Reliability Standard,
``loadability'' refers to the ability of protective relays to
refrain from operating under all permissible loading conditions on
all applicable transmission lines and transformers.
---------------------------------------------------------------------------
I. Background
A. Relay Protection Systems
2. Protective relays are devices that detect and initiate the
removal of faults on an electric system.\3\ They are designed to read
electrical measurements, such as current, voltage, and frequency, and
can be set to recognize certain measurements as indicating a fault.
When a protective relay detects a fault on an element of the system
under its protection, it sends a signal to an interrupting device(s)
(such as a circuit breaker) to disconnect the element from the rest of
the system. Impedance relays, which are the most common type of relays
used to protect transmission lines, continuously measure voltage and
current on the protected transmission line and operate when the
measured magnitude and phase angle of the impedance (voltage/current)
falls within the settings of the relay.
---------------------------------------------------------------------------
\3\ A ``fault'' is defined in the NERC Glossary of Terms used in
Reliability Standards as ``[a]n event occurring on an electric
system such as a short circuit, broken wire, or an intermittent
connection.''
---------------------------------------------------------------------------
B. Reliability Standard PRC-023-1 and Order No. 733
3. Currently effective Reliability Standard PRC-023-1 applies to
relay settings on (1) all transmission lines and transformers with low-
voltage terminals operated or connected at or above 200 kV; and (2)
those transmission lines and transformers with low voltage terminals
operated or connected between 100 kV and 200 kV that are designated by
planning coordinators as critical to the reliability of the bulk
electric system.\4\ The Reliability Standard consists of three
Requirements and an Attachment A. Requirement R1 requires entities with
certain transmission facilities to set their relays according to one of
thirteen specific settings (sub-parts R1.1 through R1.13) designed to
maximize loadability while maintaining Reliable Operation of the bulk
electric system for all fault conditions. Requirement R2 provides
additional obligations for entities that elect certain settings.
Requirement R3 requires planning coordinators to designate facilities,
operated between 100 kV and 200 kV, that are critical to the
reliability of the bulk electric system and are therefore subject to
Requirement R1. Attachment A specifies the protection systems that are
subject to and excluded from the Standard's Requirements.
---------------------------------------------------------------------------
\4\ Pursuant to section 40.3 of the Commission's regulations,
all Commission-approved Reliability Standards are available on
NERC's Web site at www.nerc.com. See 18 CFR 40.3.
---------------------------------------------------------------------------
4. On March 18, 2010, the Commission issued a Final Rule approving
Reliability Standard PRC-023-1 (Transmission Relay Loadability), that
requires transmission owners, generator owners, and distribution
providers set load-responsive phase protection relays according to
specific criteria to ensure that the relays reliably detect and protect
the electric network from all fault conditions, but do not operate
during non-fault load conditions.\5\ In addition, under section
215(d)(5) of the FPA, the Commission directed the ERO to develop
modifications to the Standard to address certain issues identified by
the Commission.
---------------------------------------------------------------------------
\5\ Transmission Relay Loadability Reliability Standard, Order
No. 733, 130 FERC ] 61,221 (2010), order on reh'g and clarification,
Order No. 733-A, 134 FERC ] 61,127 (2011); clarified, Order No. 733-
B, 136 FERC ] 61,185 (2011).
---------------------------------------------------------------------------
1. Currently Effective Requirement R1
5. Requirement R1 states that each transmission owner, generator
owner, and distribution provider subject to Reliability Standard PRC-
023-1 shall use one of the criteria prescribed in sub-parts R1.1
through R1.13 for any specific circuit terminal to prevent its phase
protective relay setting from limiting transmission system loadability
while maintaining reliable protection of the bulk electric system for
all fault conditions.
6. In Order No. 733, the Commission directed the ERO, under section
215(d)(5) of the FPA, to develop modifications to Requirement R1 to:
(1) Require that transmission owners, generator owners, and
distribution providers give their transmission operators a list of
transmission facilities that implement sub-part R1.2; \6\ (2) require
entities that have protective relays set pursuant to sub-part R1.10 to
verify that the limiting piece of equipment is capable of sustaining
the anticipated overload for the longest clearing time associated with
a fault; \7\ and (3) require the ERO to document, subject to audit by
the Commission, and to make available for review to users, owners, and
operators of the Bulk-Power System, by request, a list of those
facilities that have protective relays set pursuant to sub-part
R1.12.\8\
---------------------------------------------------------------------------
\6\ Order No. 733, 130 FERC ] 61,221, at P 186.
\7\ Id. P 203.
\8\ Id. P 224.
---------------------------------------------------------------------------
2. Currently Effective Requirement R2
7. Requirement R2 states that transmission owners, generator
owners, and distribution providers that use a circuit with the
protective relay settings determined by the practical limitations
described in specified R1 sub-parts must use the calculated circuit
capability as the circuit's facility rating and must obtain the
agreement of the planning coordinator, transmission operator, and
reliability coordinator with the calculated circuit capability.
3. Currently Effective Requirement R3
8. Requirement R3 requires planning coordinators to designate which
transmission lines and transformers with low-voltage terminals operated
or connected between 100 kV and 200 kV are critical to the reliability
of the bulk electric system and therefore subject to Requirement R1.
Sub-part R3.1 requires planning coordinators to have a process to
identify critical facilities. Sub-part R3.1.1 specifies that the
process must
[[Page 16437]]
consider input from adjoining planning coordinators and affected
reliability coordinators. Sub-parts R3.2 and R3.3 require planning
coordinators to maintain a list of critical facilities and provide it
to reliability coordinators, transmission owners, generator owners, and
distribution providers within 30 days of initially establishing it, and
within 30 days of any subsequent change.
9. In Order No. 733, the Commission directed the ERO to modify
Requirement R3 to: (1) Apply an ``add in'' approach to sub-100 kV
facilities that are owned or operated by currently registered entities
or entities that become registered entities in the future, and are
associated with a facility that is included on a critical facilities
list defined by the Regional Entity; \9\ (2) specify the test that
planning coordinators must use to determine whether a sub-200 kV
facility is critical to the reliability of the Bulk-Power System; \10\
and (3) add the Regional Entity to the list of entities that receive a
list of sub-200 kV facilities determined by the planning coordinator to
be critical to the reliability of the bulk electric system.\11\ In
addition, the Commission directed the ERO to develop an appeals process
for entities to challenge a criticality determination.\12\
---------------------------------------------------------------------------
\9\ Id. P 60.
\10\ Id. P 69.
\11\ Id. P 237.
\12\ Id. P 97.
---------------------------------------------------------------------------
4. Currently Effective Attachment A
10. Attachment A to Reliability Standard PRC-023-1 specifies which
protection systems are subject to and excluded from the Standard's
Requirements. Section 1 of Attachment A provides that the Reliability
Standard applies to any protective functions that can operate with or
without time delay, on load current, including but not limited to: (1)
Phase distance; (2) out-of-step tripping; (3) switch-on-to-fault; (4)
overcurrent relays; and (5) communication-aided protection
applications. Section 2 states that the Reliability Standard requires
evaluation of out-of-step blocking schemes \13\ to ensure that they do
not operate for faults during the loading conditions defined in the
Standard's Requirements. Finally, section 3 expressly excludes certain
relay elements and protection systems from the Reliability Standard's
Requirements.
---------------------------------------------------------------------------
\13\ ``Out-of-step blocking'' refers to a protection system that
is capable of distinguishing between a fault and a power swing. If a
power swing is detected, the protection system, ``blocks,'' or
prevents the tripping of its associated transmission facilities.
---------------------------------------------------------------------------
11. The Commission, in Order No. 733, directed the ERO to modify
Attachment A to: (1) include section 2 as an additional Requirement
with the appropriate violation risk factor and violation severity level
in the Reliability Standard; \14\ and (2) include supervising relay
elements on the list of relays and protection systems that are
specifically subject to the reliability Standard.\15\
---------------------------------------------------------------------------
\14\ Order No. 733 at 244.
\15\ Id. P 264.
---------------------------------------------------------------------------
5. Currently Effective Implementation Plan
12. Reliability Standard PRC-023-1 established staggered effective
dates for various Requirements and facilities. The Standard also
included a footnote (exceptions footnote) to the ``Effective Dates''
section honoring temporary exceptions from enforcement actions approved
by the NERC Planning Committee before NERC proposed the Reliability
Standard.
13. In Order No. 733, the Commission directed the ERO, under
section 215(d)(5), to modify the Reliability Standard to include an
implementation plan for sub-100 kV facilities \16\ and to remove the
exceptions footnote from the ``Effective Dates'' section of the
Reliability Standard.\17\
---------------------------------------------------------------------------
\16\ Id. P 283.
\17\ Id. P 284.
---------------------------------------------------------------------------
II. NERC Petition: Proposed Reliability Standard PRC-023-2 and Rule of
Procedure, Section 1700--Challenges to Determinations
14. In a March 18, 2011 Filing (March 18 Petition), NERC requests
Commission approval of Reliability Standard PRC-023-2 (Transmission
Relay Loadability) and NERC Rules of Procedure Section 1700--Challenges
to Determinations.
15. In support of the March 18 Petition, NERC states that the
proposed Reliability Standard requires transmission owners, generator
owners, and distribution providers to verify relay loadability using
methods that achieve ``the reliability goal of this Standard in an
effective and efficient manner familiar to the responsible entities.''
\18\ In addition, NERC specifically identifies the benefits of proposed
Reliability Standard PRC-023-2 as including (a) consistent
identification of operationally critical circuits operated below 200 kV
that must comply with the Requirements of the Standard, and (b)
providing transmission operators, planning coordinators, reliability
coordinators, and the ERO with more information regarding the criteria
selected by entities for verifying relay loadability.\19\
---------------------------------------------------------------------------
\18\ March 18 Petition at 42.
\19\ Id. at 5.
---------------------------------------------------------------------------
A. Reliability Standard PRC-023-2
16. Reliability Standard PRC-023-2 contains six requirements with
the stated purpose of ensuring that protective relay settings do not
limit transmission loadability, do not interfere with system operators'
ability to take remedial action to protect system reliability, and are
set to reliably detect all fault conditions and protect the electrical
network from these faults.\20\ The proposed Reliability Standard also
includes two attachments. Attachment A specifies the protection systems
that are subject to and excluded from the Standard's Requirements.
Attachment B specifies the criteria for determining the circuits which
must comply with Requirements R1 through R5.
---------------------------------------------------------------------------
\20\ Reliability Standard PRC-023-2, Section A.3 (Purpose).
---------------------------------------------------------------------------
Requirement R1
17. NERC describes Reliability Standard PRC-023-2 Requirement R1 as
follows:
Requirement R1 mandates that each Transmission Owner, Generator
Owner, and Distribution Provider shall use any one of the identified
criteria (Requirement R1, criteria 1 through 13) for any specific
circuit terminal to prevent its phase protective relay settings from
limiting transmission system loadability while maintaining reliable
protection of the [bulk electric system] for all fault conditions.
Each Transmission Owner, Generator Owner, and Distribution Provider
shall evaluate relay loadability at 0.85 per unit voltage and power
factor angle of 30 degrees[.] \21\
---------------------------------------------------------------------------
\21\ March 18 Petition at 30.
18. With the exception of clarifying language and the addition of
criterion 10.1, proposed Requirement R1 retains the same criteria as
currently existing PRC-023-1. Criteria 1 through 13 prescribe specific
criteria to be used for certain transmission system configurations.
These criteria account for the presence of devices such as series
capacitors, and address circuit and transformer thermal capability.
19. Criterion 1 specifies transmission line relay settings based on
the highest seasonal facility rating using the 4-hour thermal rating of
a transmission line, plus a design margin of 150 percent. Criterion 2
allows transmission line relays to be set so that they do not operate
at or below 115 percent of the highest seasonal 15-minute facility
rating of a circuit, when a 15-minute rating has been calculated and
published for use in real-time operations. Criterion 3 allows
[[Page 16438]]
transmission line relays to be set so that they do not operate at or
below 115 percent of the maximum theoretical power capability.
Criterion 4 may be applied where series capacitors are used on long
transmission lines to increase power transfer. Criterion 5 applies in
cases where the maximum end-of-line three-phase fault current is small
relative to the thermal loadability of the conductor. Criterion 6 may
be used for system configurations where generation is remote from load
busses or main transmission busses.
20. Criterion 7 is appropriate for system configurations that have
load centers that are remote from the generation center. Criterion 8
applies to system configurations that have one or more transmission
lines connecting a remote, net importing load center to the rest of the
system. Criterion 9 applies to the same system configuration, but
applies to the load end. Criterion 10 is specific to transmission
transformer fault protective relays and transmission lines terminated
only with a transformer. Criterion 11 may be used for transformer
overload protection relays when criterion 10 cannot be met. Criterion
12 may be used when the circuits have three or more terminals. The
limited circuit loading capability established by this criterion will
become the facility rating of the circuit. Finally, criterion 13 is
intended to apply when otherwise supportable situations and practical
limitations are not identified under criteria 1 through 12.
21. NERC explains that Reliability Standard PRC-023-2 modifies PRC-
023-1 by adding criterion 10.1 to address the Commission's directive
that entities with protective relays set pursuant to Requirement R1.10
of PRC-023-1, which is criterion 10 of Requirement 1 of PRC-023-2, must
verify that the limiting piece of equipment is capable of sustaining
the anticipated overload for the longest clearing time associated with
a fault.\22\ The criterion requires coordination so that settings on a
transformer's load responsive relay do not expose the transformer to a
fault level and duration that exceeds the transformer's mechanical
withstand capability.\23\ NERC further states in the March 18 Petition
that it believes Requirement 10.1 is equally effective and efficient as
the approach directed in Order No. 733.\24\
---------------------------------------------------------------------------
\22\ Id. at 20.
\23\ The mechanical withstand capability is determined on the
basis of the transformer's design and the periodic transformer
maintenance to preserve that capability by the owner. The withstand
capability could be compromised, for example, if the moisture level
in a transformer is allowed to increase above the design value but
remains within dielectric acceptance.
\24\ March 18 Petition at 20-21.
---------------------------------------------------------------------------
Requirement R2
22. Proposed Reliability Standard PRC-023-2 adds a new Requirement
R2 that requires each transmission owner, generation owner, and
distribution provider to set its out-of-step blocking elements to allow
tripping of phase protective relays for faults that occur during the
loading conditions modeled under Requirement R1. NERC states in the
March 18 Petition that Requirement R2 has been added to proposed
Reliability Standard PRC-023-2 to address the Commission's directive to
include section 2 of PRC-023-1 Attachment A as an additional
Requirement with the appropriate violation risk factor and violation
severity level.\25\ NERC has assigned this proposed Requirement a high
violation risk factor and a severe violation severity level reflecting
the impact to reliability of violating the Requirement.
---------------------------------------------------------------------------
\25\ Id. at 24.
---------------------------------------------------------------------------
Requirements R3, R4, and R5
23. Requirement R3 in Reliability Standard PRC-023-2 renumbers and
makes conforming edits to Requirement R2 from PRC-023-1. Requirement R4
requires an entity that chooses to use Requirement R1 criterion 2 as
the basis for verifying transmission line relay loadability to provide
its planning coordinator, transmission operator, and reliability
coordinator with an updated list of circuits associated with those
transmission line relays at least once each calendar year. Similarly,
Reliability Standard PRC-023-2 adds a new Requirement R5 that requires
entities that set transmission line relays according to Requirement R1
criterion 12 to provide an updated list of the circuits associated with
those relays to its Regional Entity at least once each calendar year,
to allow the ERO to compile a list of all circuits that have protective
relays settings that limit circuit capability. In the March 18
Petition, NERC states that new Requirements R4 and R5, respectively,
address the Commission's directives relating to providing transmission
operators a list of transmission facilities that implement criterion 2
and directing that the ERO create a list of those facilities that have
protective relays set pursuant to criterion 12.\26\
---------------------------------------------------------------------------
\26\ Id. at 20, 23.
---------------------------------------------------------------------------
Requirement R6
24. Requirement R6 of Reliability Standard PRC-023-2 requires each
planning coordinator to conduct an assessment at least once each
calendar year (but no less frequently than every 15 months) by applying
the criteria in Attachment B to determine the circuits in its planning
coordinator area for which entities must comply with Requirements R1
through R5. Sub-part 6.1 requires the planning coordinator to maintain
a list of circuits subject to PRC-023-2 per application of Attachment B
identifying the year in which any criterion in Attachment B applies.
Sub-part 6.2 requires the planning coordinator to provide the list to
all Regional Entities, reliability coordinators, transmission owners,
generators owners, and distribution providers within its planning
coordinator area within 30 calendar days of establishing the initial
list, and 30 days of any subsequent change thereto. NERC states in the
March 18 Petition that the proposed sub-part 6.2, formerly Requirement
R3.3 in PRC-023-1, modifies the Requirement in order to address the
Commission's directive to add the Regional Entity to the list of
entities that receive the list of critical facilities.\27\
---------------------------------------------------------------------------
\27\ Id. at 24.
---------------------------------------------------------------------------
Attachment A
25. Attachment A to Reliability Standard PRC-023-2 includes a new
section 1.6 that extends the Standard's applicability to include phase
overcurrent supervisory elements (i.e., phase fault detectors)
associated with current-based, communication-assisted schemes (i.e.,
pilot wire, phase comparison, and line current differential) where the
scheme is capable of inadvertent tripping for loss of communications,
even if there is no fault on the line. In addition, conforming changes
are made to proposed section 2.1, formerly section 3.1 of the PRC-023-
1, to recognize that elements described in new section 1.6 are no
longer excluded from the proposed Standard's scope. NERC states in the
March 18 Petition that these changes have been made to address the
Commission's directives to include supervising relay elements on the
list of relays and protection systems that are specifically subject to
the Reliability Standard.\28\ NERC further states that it believes
section 1.6 of Attachment A is equally effective and efficient in
addressing the Commission's concern as the approach directed in Order
No. 733.\29\
---------------------------------------------------------------------------
\28\ Id. at 25.
\29\ Id.
---------------------------------------------------------------------------
[[Page 16439]]
Attachment B
26. Attachment B of Reliability Standard PRC-023-2 specifies six
criteria that planning coordinators must apply to identify sub-200kV
facilities that are subject to compliance with the Reliability
Standard. Specifically, a facility is subject to PRC-023-2 if the
facility meets any one of the following six criteria:
Is a monitored facility of a permanent flowgate in the
Eastern Interconnection, a major transfer path within the Western
Interconnection, or a comparable monitored facility in the Quebec
Interconnection, that has been included to address reliability concerns
for loading of that circuit (Criteria B1);
Is a monitored facility of an interconnection reliability
operating limit, where the limit was determined in the planning horizon
pursuant to Reliability Standard FAC-010 (System Operating Limits
Methodology for Planning Horizon) (Criteria B2);
Forms a path to supply off-site power to a nuclear plant
as established in the nuclear plant interface requirements pursuant to
Reliability Standard NUC-001 (Nuclear Plant Interface Coordination)
(Criteria B3).\30\
---------------------------------------------------------------------------
\30\ As we stated previously, ``[w]e would expect that any
[nuclear plant interface requirements] agreed to between a nuclear
plant generator operator and transmission entity would include all
facilities needed to transmit offsite power and auxiliary power to
the nuclear facility. Mandatory Reliability Standard for Nuclear
Plant Interface Coordination, 125 FERC ] 61,065, at P 51 (2008).
---------------------------------------------------------------------------
Is identified through a sequence of power flow analyses
specified in Attachment B and performed by the planning coordinator
(Criteria B4);
Is selected by the planning coordinator based on technical
studies or assessments other than those specified above, in
consultation with the facility owner (Criteria B5); or
Is mutually agreed upon for inclusion by the planning
coordinator and the facility owner (Criteria B6).
27. NERC states in the March 18 Petition that while the six
criteria presented in Attachment B vary from some of the guidance
provided in Order No. 733, they nonetheless identify all facilities
that must be subject to proposed Reliability Standard PRC-023-2 in
order to achieve the Standard's reliability objective.\31\ NERC further
reports that it is in the process of applying the test to a
representative sample of utilities from each of the three
Interconnections and plans to file the results of these tests by
February 17, 2013. NERC states that it plans to revise Attachment B, if
necessary, pending the results of this test and clarifications made in
Order No. 733-A.\32\
---------------------------------------------------------------------------
\31\ March 18 Petition at 14.
\32\ Id. at 13.
---------------------------------------------------------------------------
28. The Commission, in Order No. 733, provided guidance that a test
to determine critical sub-200 kV facilities should include the same
simulations and assessments as the Transmission Planning (TPL)
Reliability Standards.\33\ While the TPL Standards permit manual system
adjustments between two contingencies, NERC explains in the March 18
Petition that it believes it is more informative, and in line with the
reliability objective, to require testing of double contingencies
without such manual adjustments, thereby modeling a situation in which
an operator fails to, or does not have time to, make appropriate system
adjustments. This focused testing exceeds the requirements of the TPL
Standards and, NERC asserts, is an equally efficient and effective
approach to addressing the Commission's concern that the test must be
sufficiently robust to provide assurance that all appropriate
facilities are identified and made subject to the Reliability Standard
for the Standard to achieve its purpose.
---------------------------------------------------------------------------
\33\ Order No. 733 at P 80.
---------------------------------------------------------------------------
29. In Order No. 733, the Commission also provided guidance
regarding elements of a definition of desirable system performance that
must inform any test to determine which sub-200 kV circuits are
critical to system reliability. The Commission's guidance stated, among
other things, that the power system should maintain all facilities
within their applicable thermal (i.e., current), voltage, or stability
ratings (short time ratings are applicable).\34\ In the March 18
Petition, NERC asserts that it is most appropriate to focus on avoiding
thermal loading of transmission circuits.\35\ In order to achieve its
reliability goal, NERC believes, Reliability Standard PRC-023-2 must
apply to circuits whose relays will be challenged by excessive thermal
loading to the point that a relay hampers the system operator's ability
to take remedial action. NERC believes this test is an equally
effective and efficient approach to addressing the Commission's concern
regarding the rigorousness of the test.\36\
---------------------------------------------------------------------------
\34\ Id. P 84.
\35\ March 18 Petition at 19. With respect to NERC's assertion,
the Commission agrees that avoiding thermal loading may be
appropriate criteria for some regions. However, for other regions,
such as the Western Interconnection, voltage and stability criteria
considerations would be included as appropriate.
\36\ As explained in the March 18 Petition, the system
performance measure in this test is less rigorous than that required
by TPL-003 (System Performance Following Loss of Two or More bulk
electric system Elements) because it ignores voltage and stability
ratings. NERC points out, however, that the contingency condition in
Attachment B is more stringent than that in TPL-003, and the
contingency and system performance measure were developed together
in order to align with the reliability objective of the proposed
Standard. March 18 Petition at 19.
---------------------------------------------------------------------------
Implementation Plan
30. In the March 18 Petition, NERC proposes staggered effective
dates for Reliability Standard PRC-023-2, i.e., the mandatory
compliance date after an allotted implementation period, for each of
the Standard's requirements. The implementation plan provides 18 months
for planning coordinators to apply the criteria in Attachment B and
determine which sub-200 kV circuits must be subject to the Standard.
Those entities responsible for compliance on circuits identified by a
planning coordinator pursuant to Requirement R6 are provided until the
first day of the first calendar quarter 39 months following
notification to become compliant, or until the first day of the first
calendar year in which any criterion in Attachment B applies if the
planning coordinator indentifies the circuit in an assessment of a
future year more than 39 months beyond the year in which the assessment
is conducted.
Violation Risk Factors/Violation Severity Levels
31. NERC assigns Requirements R1, R2, and R6 a ``high'' violation
risk factor, Requirement R3 a ``medium'' violation risk factor, and
Requirements R4 and R5 a ``lower'' violation risk factor. NERC also
proposes violation severity levels for each of the Requirements of
Reliability Standard PRC-023-2.
B. NERC Rules of Procedure Section 1700--Challenges to Determinations
32. In addition to the Reliability Standard, NERC included in its
petition new Rules of Procedure Section 1700--Challenges to
Determinations, which provides a process for registered entities to
challenge a planning coordinator's determination made under a
Reliability Standard that a facility operated below 200 kV is subject
to compliance with the standard. Pursuant to Rule 1702, a registered
entity is encouraged, but not required, initially to meet with the
planning coordinator to resolve any dispute. If the matter remains
unresolved, the registered entity may challenge the determination with
the appropriate Regional Entity. The registered entity may appeal the
Regional Entity's decision to NERC, and the NERC Board of Trustees
would appoint a panel to review the Regional
[[Page 16440]]
Entity decision. The Board of Trustees has the authority, but not the
duty, to review the matter upon the request of the planning coordinator
or registered entity. The registered entity may appeal the final NERC
decision to the applicable governmental authority, e.g., the Commission
for appeals within the United States.
III. Notice of Proposed Rulemaking and Comments
33. On September 15, 2011, the Commission issued a Notice of
Proposed Rulemaking (NOPR) proposing to approve Reliability Standard
PRC-023-2.\37\ In the NOPR, the Commission proposed to approve
Reliability Standard PRC-023-2. The Commission indicated that the
Version 2 standard and new Rule of Procedure 1700 adequately address
the directed modifications set forth in Order No. 733. The Commission
also proposed to accept the Attachment B criteria for identifying sub-
200 kV facilities to which the Reliability Standard applies.\38\
Finally, the Commission proposed to approve the implementation plan,
Violation Risk Factors, and Violation Severity levels.
---------------------------------------------------------------------------
\37\ Transmission Relay Loadability Reliability Standard, 136
FERC ] 61,187 (September 15, 2011) (September 15 NOPR).
\38\ Id. P 38.
---------------------------------------------------------------------------
34. In addition, the NOPR set forth certain questions regarding the
Attachment B criteria.\39\ Specifically, the Commission proposed the
following questions to be addressed in the report regarding the
application of Attachment B criteria NERC intends to file by February
17, 2013:
---------------------------------------------------------------------------
\39\ Id. PP 41-45.
---------------------------------------------------------------------------
Whether the power system assessment proposed in criterion
B4 includes the critical system conditions utilized under Reliability
Standard TPL-003-0 Requirement R1.3.2; \40\
---------------------------------------------------------------------------
\40\ Id. P. 43.
---------------------------------------------------------------------------
Whether applicable entities evaluate relay loadability
under the B4 criterion consistent with Requirement R1 which requires,
in part, that they ``evaluate relay loadability at 0.85 per unit
voltage and a power factor angle of 30 degrees'' in addition to
applicable current data; \41\
---------------------------------------------------------------------------
\41\ Id.
---------------------------------------------------------------------------
What ``technical studies or assessments'' will be used by
planning coordinators to identify critical facilities under Criterion
B5; \42\ and
---------------------------------------------------------------------------
\42\ Id. P 44.
---------------------------------------------------------------------------
Whether Attachment B is sufficiently comprehensive to
capture all circuits in a planning coordinator's area that could have
an operational impact on the reliability of the bulk electric
system.\43\
---------------------------------------------------------------------------
\43\ Id. P 45.
---------------------------------------------------------------------------
35. On September 21, 2011, notice of the September 15 NOPR was
published in the Federal Register with comments due on or before
November 21, 2011.\44\ Timely comments were filed by the American
Public Power Association (APPA), ISO New England Inc. (ISO-NE), the
Midwest Independent System Operator, Inc. (MISO), and NERC.
---------------------------------------------------------------------------
\44\ 76 FR 58,424 (2011).
---------------------------------------------------------------------------
IV. Discussion
36. Pursuant to section 215(d)(2) of the FPA, the Commission
approves Reliability Standard PRC-023-2, including the Violation Risk
Factors and Violation Severity Levels, and implementation plan. The
Reliability Standard meets the directives outlined in Order No. 733,
and further contributes to the reliability of the Bulk-Power System by
requiring load-responsive phase protection relay settings that will
provide essential facility protection for faults while not limiting
transmission loadability or interfering with system operators' ability
to protect system reliability. In addition, the Reliability Standard
provides for the consistent identification of operationally critical
circuits operated below 200 kV that must comply with the Requirements
of the Standard. Accordingly, we find that the Reliability Standard is
just, reasonable, not unduly discriminatory or preferential, and in the
public interest.
37. Also, pursuant to section 215(f) of the FPA, the Commission
approves NERC Rule of Procedure Section 1700--Challenges to
Determinations as just, reasonable, not unduly discriminatory or
preferential, in the public interest, and satisfying the requirements
of section 215(c) of the FPA.\45\ Rule of Procedure Section 1700
addresses the Order No. 733 directive for a mechanism by which a
registered entity can challenge a determination by a planning
coordinator made pursuant to Reliability Standard PRC-023-2.
---------------------------------------------------------------------------
\45\ Section 215(f) of the FPA provides, inter alia, that ``[a]
proposed rule or proposed rule change shall take effect upon a
finding by the Commission, after notice and opportunity for comment,
that the change is just, reasonable, not unduly discriminatory or
preferential, is in the public interest and satisfies the
requirements of subsection (c).''
---------------------------------------------------------------------------
38. NERC indicates in its comments that it is in the process of
applying the test set forth in Attachment B of Reliability Standard
PRC-023-2 to a representative sample of utilities from each of the
three Interconnections and will file the results of these tests in a
report on or before February 17, 2013. We adopt the NOPR proposal and
direct NERC to address in the report several specific questions
regarding the implementation of the applicability criteria set forth in
Attachment B, as discussed below.
39. Further, commenters raise a number of concerns regarding the
specific substantive Requirements of the Reliability Standard, the
Standard's Attachment B, and the violation risk factor designations.
These commenter concerns are discussed below.
A. Reliability Standard PRC-023-2
1. Requirement R1
40. Requirement 1 of PRC-023-2 provides that applicable entities
must use one of the identified criteria (Requirement R1, criteria 1
through 13) for any specific circuit terminal to prevent its phase
protective relay settings from limiting transmission system loadability
while maintaining reliable protection of the [bulk electric system] for
all fault conditions. Requirement R1.13 provides that ``[w]here other
situations present practical limitations on circuit capability, set the
phase protection relays so they do not operate at or below 115% of such
limitations.''
41. MISO contends that over-reliance on criterion R1.13 would
adversely impact operations, reliability, flexibility, and transmission
congestion costs, and lead to unnecessary transmission expansion in the
future to comply with transmission planning standards. To avoid this
result, MISO requests that the Commission clarify the applicability of
the standard by narrowing the scope of the protection systems covered
by the Standard under Attachment A. In particular, MISO requests the
Commission clarify that the following protection systems are excluded
from the standard: (a) Differential current relays and negative
sequence relays; (b) supervisory elements with unanimous consent logic;
(c) redundant voting protective relay schemes; and (d) switch-on-to-
fault protective relay schemes. We address MISO's request below.
a. Differential Current Relays & Negative Sequence Relays
42. MISO requests that we clarify that differential current relay
elements and negative sequence relay elements should not be covered by
the standard ``as they would not trip with or without time delay on
load current.'' \46\ MISO argues that the exclusion of these
[[Page 16441]]
specific relay elements from the proposed standard ``would be
consistent with the purpose and intent of the standard and would
prevent an inappropriate and unnecessary expansion of the standard's
applicability.'' \47\
---------------------------------------------------------------------------
\46\ MISO Comments at 3.
\47\ Id.
---------------------------------------------------------------------------
43. We grant MISO's request for clarification in part. As noted by
MISO, differential current relay elements and negative sequence relay
elements, by their nature, are not load responsive. As the Commission
noted previously, the exclusion of a protection system from Reliability
Standard PRC-023 appears to be unnecessary if the system is not load-
responsive.\48\ Therefore, we grant MISO's request for clarification to
the extent that non-load responsive relays are not covered by
Reliability Standard PRC-023-2, however we decline to direct NERC to
include the assets in the exclusion list of Section 3 of Attachment A
as the exclusion list should be limited to protection systems that
would otherwise be subject to the Standard.
---------------------------------------------------------------------------
\48\ Transmission Relay Loadability Reliability Standard, 127
FERC ] 61,175, at n. 98 (2009).
---------------------------------------------------------------------------
b. Supervisory Relay Elements
44. In Order No. 733, the Commission directed NERC to include
supervisory relay elements on the list of relays and protection systems
that are specifically subject to the PRC-023 Reliability Standard.\49\
In Order No. 733-B, the Commission clarified that its directive
regarding the applicability of the Reliability Standard to supervisory
relays does not foreclose the development of an approach tailored to
eliminate application of the standard to some supervisory relays but
not to others, where technically justified.\50\
---------------------------------------------------------------------------
\49\ Order No. 733 at P 264.
\50\ Order No. 733-B at P 39.
---------------------------------------------------------------------------
45. In response to the directive, NERC modified Attachment A of
Reliability Standard PRC-023-2, which identifies types of protection
systems that are subject to, and others that are excluded from, the
standard. In part, Attachment A provides that ``this standard includes
any protective functions which could trip with or without time delay,
on load current, including but not limited to * * * 1.6. Phase
overcurrent supervisory elements (i.e., phase fault detectors)
associated with current-based, communication-assisted schemes * * *
where the scheme is capable of tripping for loss of communications.''
In the March 18 Petition, NERC explained that section 1.6, while
addressing a subset of supervisory relays, is equally effective and
efficient in addressing the Commission's reliability concern. According
to NERC, including all supervisory relays would have unintended
negative impacts on system reliability by impacting the dependability
and security of certain protection systems.\51\ NERC explains that
supervisory overcurrent elements used as fault detectors ``by
themselves cannot trip on load current, with or without time delay.
Since the trip logic requires assertion of the fault detector and the
supervised protective function (which already is required to meet the
loadability requirements), the overall protective function will meet
the loadability requirement.'' \52\
---------------------------------------------------------------------------
\51\ March 18 Petition at 25-28.
\52\ Id. at 27.
---------------------------------------------------------------------------
Comments
46. In its comments, MISO raises a concern that an interpretation
of the term ``phase overcurrent supervisory elements'' in section 1.6
of Attachment A that includes elements in a unanimous consent scheme
could lead to unnecessary facility limit reductions.\53\ MISO asks the
Commission to clarify that it is acceptable to consider ``unanimous
consent'' logic when evaluating transmission relay loadability.
According to MISO, ``[i]f a relay scheme contains multiple relay
elements and requires `unanimous consent' among two or more of the
relay elements in order to initiate a tripping action [of a circuit
breaker], transmission relay loadability should be based solely on the
relay element that is least sensitive to load so long as the relay
elements could never initiate a tripping action without the operation
of the relay element least sensitive to load.'' \54\
---------------------------------------------------------------------------
\53\ MISO Comments at 4.
\54\ Id.
---------------------------------------------------------------------------
Commission Determination
47. Giving due weight to NERC's technical expertise on this issue,
we approve NERC's modification to Attachment A and find that NERC has
developed an equally efficient and effective approach to addressing the
Order No. 733 directive regarding supervisory relays. NERC's proposal
identifies a subset of supervisory relay elements, consistent with the
Commission's clarification in Order No. 733-B.
48. We deny MISO's request for clarification. There are various
types of protection schemes. MISO describes a specific protection
scheme that uses unanimous consent logic and asks whether elements of
the scheme are subject to Reliability Standard PRC-023-2. This is a
fact intensive inquiry, and we will not rule on this matter based on
the information provided in MISO's comments. If MISO seeks further
clarification of this issue, it should pursue the matter with NERC. The
Commission will not make a determination on MISO's specific scenario
without a complete record and without it going through NERC's
Reliability Standards development process or interpretation process.
c. Redundant Voting Schemes--the Most Load Sensitive Relay
49. MISO requests that we clarify how entities should handle
certain redundant voting protective relay schemes.\55\ MISO explains
that, in a redundant voting protective relay scheme for a transmission
facility, there are three protective relay schemes and only two of the
three must operate to initiate tripping. MISO argues that the most load
sensitive of these three relay schemes should be exempt from the
standard, ``so long as the most load sensitive of the three protective
relay scheme can never initiate a tripping action on its own with[out]
a tripping output from one of the other two protective relay schemes.''
\56\
---------------------------------------------------------------------------
\55\ MISO Comments at 5.
\56\ Id.
---------------------------------------------------------------------------
50. We decline to grant MISO's request on this issue. MISO's
limited comments on this issue do not provide adequate information or
technical support for its request. Without adequate support, the
Commission cannot respond to MISO's request.
d. Switch-on-to-Fault Protective Relay Schemes
51. MISO requests that the Commission clarify that a switch-on-to-
fault protective relay scheme, which is specifically included in
section 1.3 of Attachment A, may be excluded from the requirements of
the Reliability Standard if it meets each of three stated conditions
presented by MISO.\57\
---------------------------------------------------------------------------
\57\ Id. at 5-6.
---------------------------------------------------------------------------
52. Currently effective Reliability Standard PRC-023 explicitly
addresses switch-on-to-fault protective relay schemes. Switch-on-to-
fault schemes are protection systems designed to trip a transmission
line breaker when the breaker is closed into a fault. Because the
current fault detectors for these systems must be set low enough to
detect ``zero-voltage'' faults, i.e., close-in, three-phase faults,
these systems may be susceptible to operate on load.\58\ We note that
the System Protection and Control Task Force acknowledged, with
[[Page 16442]]
regard to switch-on-to-fault schemes ``* * * a concern, based on actual
events which have occurred in connection with blackouts, for the
undesired operation of [switch-on-to-fault] schemes when a breaker is
closed into a line.'' \59\ Because the relays applied in switch-on-to-
fault schemes are load-responsive, the Commission agreed with the ERO's
technical decision to make such relays subject to the requirements of
PRC-023. As noted above, MISO proposed a set of conditions that would
remove an otherwise load-responsive relay from the requirements of
Reliability Standard PRC-023. MISO has not, however, provided any
explanation or technical support for its proposed conditions.
Therefore, we decline to grant the requested clarification.
---------------------------------------------------------------------------
\58\ Order No. 733 at n. 187.
\59\ NERC Planning Committee, System Protection and Control Task
Force, ``Switch-on-to-Fault Schemes in the Context of Line Relay
Loadability,'' at 2 (June 7, 2006).
---------------------------------------------------------------------------
2. Requirement R3
53. Requirement R3 of PRC-023-2 requires a transmission owner,
generator owner and/or distribution provider to obtain the agreement of
the planning coordinator, transmission operator, and reliability
coordinator for a calculated circuit capacity with the practical
limitations described in Requirement R1, criteria 6, 7, 8, 9, 12, or
13.
a. Comments
54. MISO requests that the Commission clarify that Requirement R3
was not intended to create an obligation of the planning coordinator,
transmission operator and reliability coordinator to independently
verify or approve the calculated circuit capability provided by the
transmission owner, generation owner or distribution provider.\60\ MISO
argues that this obligation to obtain the agreement could impute an
obligation on the planning coordinator, transmission operator and/or
reliability coordinator to evaluate the calculated circuit capability
without providing corresponding criteria that should be applied in the
evaluation.\61\ MISO also requests that the Commission provide guidance
on how such entities should resolve disputes over calculated circuit
capabilities.
---------------------------------------------------------------------------
\60\ Id. at 6-7.
\61\ Id.
---------------------------------------------------------------------------
b. Commission Determination
55. We deny MISO's request for clarification. The Commission
addressed MISO's concern in Order No. 733.\62\ Specifically, in the
Order No. 733 rulemaking, commenters argued that the use of the term
``agreement'' in PRC-023-1 simply meant that ``the entity calculating
the circuit capability is required to provide the circuit capability to
the relevant functional entities'' and that ``planning coordinators,
transmission operators, and reliability coordinators must simply agree
that they will use the circuit capability provided by the transmission
owner, generator owner, or distribution owner.'' \63\ The concerns
raised at that time mirror the concerns raised by MISO; commenters
indicated that the applicable parties did not want to be ``responsible
for reviewing and approving the calculated circuit capabilities under
Requirement R[3].'' \64\
---------------------------------------------------------------------------
\62\ Order No. 733 at P 229.
\63\ Id. P 228.
\64\ Id.
---------------------------------------------------------------------------
56. The Commission rejected the commenters' arguments in Order No.
733, finding that the language ``shall obtain the agreement'' requires
that ``the entity calculating the circuit capability must reach an
understanding with the relevant functional entity that the calculated
circuit capability is capable of achieving the reliability goal of PRC-
023-1.'' \65\ In addition, the Commission clarified that since the
Standard is ``intended to ensure that protective relay settings do not
limit transmission loadability or interfere with system operators'
ability to take remedial action to protect system reliability, and to
ensure that relays reliably detect all fault conditions and protect the
electrical network from these faults,'' the agreement required under
Requirement R3 should ``center around achieving these purposes.'' \66\
Having adequately addressed this matter in Order No. 733, it is
unnecessary to elaborate further in response to MISO and, accordingly,
we deny MISO's request on this issue.
---------------------------------------------------------------------------
\65\ Id. P 229.
\66\ Id.
---------------------------------------------------------------------------
57. Further, to the extent that a dispute arises between
responsible entities over the determination of a calculated circuit
capability under Requirement R3, nothing precludes the responsible
entities from raising the dispute with the applicable Regional Entity.
3. Requirement R6
58. Requirement R6 of the Reliability Standard requires planning
coordinators to conduct an assessment applying the criteria in
Attachment B to determine a list of circuits subject to PRC-023-2
Requirements R1 through R5. Under Attachment B, the planning
coordinator is required to evaluate ``[t]ransmission lines operated
below 100 kV and transformers with low voltage terminals connected
below 100 kV that are part of the [bulk electric system].''
a. Comments
59. MISO requests clarification regarding the application of
Requirement R6 to sub-100 kV facilities.\67\ Specifically, MISO
requests clarification ``with regard to what final and FERC-approved
process is used by the Regional Entities to identify sub-100 kV
facilities `critical to the reliability of the bulk electric system.'
'' \68\ MISO further requests clarification on how planning
coordinators will be provided access to the list of such sub-100 kV
facilities, and, finally, MISO requests clarification whether the use
of such a list of sub-100 kV facilities is adequate to demonstrate
compliance with Requirement R6.
---------------------------------------------------------------------------
\67\ MISO Comments at 8.
\68\ Id.
---------------------------------------------------------------------------
b. Commission Determination
60. With regard to MISO's request concerning the identification of
sub-100 kV facilities, we note that bulk electric system facilities are
currently identified through the application of NERC's definition of
bulk electric system and NERC's registration process, as applied by the
Regional Entities.\69\ Regional Entities should inform planning
coordinators of such sub-100kV facilities that already may have been
identified so that the planning coordinator is able to fulfill its
responsibilities pursuant to Requirement R6.
---------------------------------------------------------------------------
\69\ Mandatory Reliability Standards for the Bulk-Power System,
Order No. 693 FERC Stats. & Regs. ] 31,242, at P 77 (2007).
---------------------------------------------------------------------------
61. We deny MISO's request for clarification ``that the use of such
a list as/if provided by the Regional Entities is adequate to
demonstrate compliance with a requirement to evaluate `Transmission
lines operated below 100 kV and transformers with low voltage terminals
connected below 100 kV that are part of the [bulk electric system].'
''\70\ The identification of facilities is only the first step in the
process of determining whether the Standard applies. Once a planning
coordinator has been provided with a list of sub-100 kV facilities that
are part of the bulk electric system, if any, it must apply the
criteria in Attachment B to determine whether Requirements R1 through
R5 of Reliability Standard PRC-023-2 will apply to the individual
facilities.
---------------------------------------------------------------------------
\70\ MISO Comments at 8.
---------------------------------------------------------------------------
4. Attachment B
62. Attachment B specifies which circuits must comply with
[[Page 16443]]
Requirements R1 through R5. Criterion B4 addresses circuits that are
identified through a specified sequence of power flow analyses
performed by the planning coordinator, which simulate double
contingencies without manual adjustments between the contingencies.
a. Comments
63. IS0-NE requests that the Commission direct the ERO to remove
criterion B4 of Attachment B from PRC-023-2.\71\ ISO-NE argues: (1)
That such a criterion does not accurately recognize how the bulk
electric system is operated; (2) that the system is neither planned nor
operated to withstand two overlapping outages without intervening
operator action; and (3) that such testing may result in unsolved
cases, or voltages well below criteria.\72\ As an example, ISO-NE cites
a system designed to bring on fast start generation before the second
contingency. ISO-NE argues that testing under that scenario without the
fast start generation removes transmission paths into an area, thus
increasing current flows on the remaining circuits and increasing
reactive losses, resulting in lower voltages. In addition, ISO-NE
states that unsolved cases have no flows to evaluate and therefore
cannot be analyzed as required under criterion B4, and that solved
cases with below-criteria voltage and excessive currents are
unrealistic. ISO-NE concludes that such simulations may misidentify
system conditions as severe cases when in reality they are not,
thwarting the purpose of the testing.
---------------------------------------------------------------------------
\71\ ISO-NE Comments at 4.
\72\ Id. at 2-3.
---------------------------------------------------------------------------
64. ISO-NE also asserts that criterion B4 provides no guidance on
how the planning coordinator should dispatch the system in a model that
tests overlapping contingencies, potentially resulting in different
base assumptions used by the various planning coordinators.
b. Commission Determination
65. The Commission recognizes that concerns exist regarding the
application of Attachment B. As discussed below, NERC will be providing
a summary of the base cases used in applying the Attachment B criteria
and an assessment of how the base cases used for the analysis relate to
TPL-003-0, Requirement R1.3.2 in response to our Order No. 733
directive. In the NOPR, the Commission expressed concern that criterion
B4 of Attachment B is silent as to the rigor of the simulations other
than requiring planning coordinators to use their engineering
judgment.\73\ NERC's additional information regarding the base cases
used in applying the Attachment B criteria will allow the Commission
and other interested parties to evaluate whether further modifications
to Attachment B may be warranted. Accordingly, we deny ISO-NE's request
on this issue and will not direct the ERO to develop modifications to
Attachment B at this time.
---------------------------------------------------------------------------
\73\ September 15 NOPR at P 43.
---------------------------------------------------------------------------
66. Therefore, we decline to direct NERC to remove criterion B4
from PRC-023-2 at this time.
5. Violation Risk Factors/Violation Severity Levels
67. As noted above, NERC has proposed a ``high'' violation risk
factor for Requirement R6 of Reliability Standard PRC-023-2.
a. Comments
68. MISO requests that the Commission reject the assignment of a
high violation risk factor to Requirement 6, arguing: (1) That a high
violation risk factor implies there is a direct correlation between
instability, uncontrolled separation and cascading outages and the
maintenance of a list of sub-200 kV circuits to which the planning
coordinator believes the requirements of the standard applies; (2) that
there is no such direct correlation, as evidenced by the fact that NERC
has created and the Commission is proposing to accept a process by
which entities can dispute the inclusion of circuits on the planning
coordinator's list; and (3) that appearance on or absence from the list
in itself will not cause or prevent instability, uncontrolled
separation and cascading outages; some other event or Reliability
Standards violation (i.e., operating above System Operating Limits)
would have to occur to trigger any impact to reliability.\74\
---------------------------------------------------------------------------
\74\ MISO Comments at 7-8.
---------------------------------------------------------------------------
b. Commission Determination
69. In Order No. 733, we directed NERC to assign a ``high''
violation risk factor to Requirement R3 of Reliability Standard PRC-
023-1.\75\ The Requirement at issue is renumbered Requirement R6 in
Reliability Standard PRC-023-2. NERC's assignment of a ``high''
violation risk factor to Requirement R6 is therefore consistent with
our prior directive.
---------------------------------------------------------------------------
\75\ Order No. 733 at P 297.
---------------------------------------------------------------------------
70. MISO's request is an untimely argument against an explicit
directive from Order No. 733. Therefore, we reject MISO's request for a
rejection of the assignment of a ``high'' violation risk factor to
Requirement R6.
6. NERC Report on Implementation of Attachment B
71. In Order No. 733, the Commission directed NERC to specify the
test that planning coordinators will use to determine whether a sub-200
kV facility is critical to the reliability of the Bulk-Power
System.\76\ In addition, the Commission directed NERC to file both the
test and the results of applying the test to a representative sample of
utilities from each of the three interconnections.\77\ Attachment B to
Reliability Standard PRC-023-2 represents the test filed in response to
the above described directive. The NOPR set forth questions intended to
assist the Commission's understanding regarding the implementation of
the test. Specifically, the Commission proposed that NERC address the
following questions regarding the application of Attachment B criteria
in the report:
---------------------------------------------------------------------------
\76\ Id. P 69.
\77\ Id.
---------------------------------------------------------------------------
Whether the power system assessment proposed in criterion
B4 includes the critical system conditions utilized under Reliability
Standard TPL-003-0 Requirement R1.3.2; \78\
---------------------------------------------------------------------------
\78\ Id. P 43.
---------------------------------------------------------------------------
Whether applicable entities evaluate relay loadability
under the B4 criterion consistent with Requirement R1 which requires,
in part, that they ``evaluate relay loadability at 0.85 per unit
voltage and a power factor angle of 30 degrees'' in addition to
applicable current data; \79\
---------------------------------------------------------------------------
\79\ Id.
---------------------------------------------------------------------------
What ``technical studies or assessments'' will be used by
planning coordinators to identify critical facilities under criterion
B5; \80\ and
---------------------------------------------------------------------------
\80\ Id. P 44.
---------------------------------------------------------------------------
Whether Attachment B is sufficiently comprehensive to
capture all circuits in a planning coordinator's area that could have
an operational impact on the reliability of the bulk electric
system.\81\
---------------------------------------------------------------------------
\81\ Id. P 45.
---------------------------------------------------------------------------
a. Comments
72. In its November 21, 2011 Comments, NERC, with APPA concurring,
responds to the questions proposed for inclusion in the report NERC
intends to file by February 17, 2013.
73. With regard to the question whether the power system assessment
proposed in criterion B4 includes the critical system conditions
utilized under
[[Page 16444]]
Reliability Standard TPL-003-0, Requirement R1.3.2, NERC states that
the goal of the power flow analysis is to have planning coordinators
utilize the base cases that are used for demonstrating compliance with
the TPL Reliability Standards.\82\ NERC proposes to include in its
report a summary of the base cases used in applying the Attachment B
criteria and an assessment of how the base cases used for the analysis
relate to TPL-003-0, Requirement R1.3.2.\83\
---------------------------------------------------------------------------
\82\ NERC Comments at 3.
\83\ Id.
---------------------------------------------------------------------------
74. In response to the proposed question whether applicable
entities evaluate relay loadability under the B4 criterion consistent
with Requirement R1 which requires, in part, that they ``evaluate relay
loadability at 0.85 per unit voltage and a power factor angle of 30
degrees'' in addition to applicable current data, NERC states that,
although the measures in criterion B4 of Attachment B do not explicitly
reference voltage and power factor, the measures were derived from
Requirement R1 of PRC-023-2; specifically, 0.85 per unit voltage and 30
degree power factor angle.\84\ NERC states, therefore, that it is not
necessary for it to include in the report a comparison of the results
obtained using criterion B4 to the results that would be achieved based
on assumptions consistent with Requirement R1.
---------------------------------------------------------------------------
\84\ Id.
---------------------------------------------------------------------------
75. Regarding the question proposed in the NOPR concerning what
``technical studies or assessments'' will be used by planning
coordinators to identify facilities under criterion B5, NERC states
that Attachment B does not identify a specific list to avoid
unnecessarily limiting the technical studies or assessments a planning
coordinator may use to identify circuits.\85\ NERC proposes to include
a discussion in the report on the types of studies that planning
coordinators may use.\86\
---------------------------------------------------------------------------
\85\ Id. at 4-5.
\86\ Id. at 5.
---------------------------------------------------------------------------
76. Finally, in response to the last proposed question of whether
Attachment B is sufficiently comprehensive to capture all circuits in a
planning coordinator's area that could have an operational impact on
the reliability of the bulk electric system, NERC proposes to include
in the report an assessment that demonstrates whether Attachment B is
comprehensive enough to capture all circuits that could have an
operational impact on the reliability of the bulk electric system in
the context of transmission relay loadabilty.\87\
---------------------------------------------------------------------------
\87\ Id.
---------------------------------------------------------------------------
b. Commission Determination
77. As discussed above, NERC reports that it is in the process of
applying the test set forth in Attachment B to a representative sample
of utilities from each of the three Interconnections and will file the
results of these tests in a report on or before February, 2013. In
light of the discussion in NERC's November 21 Comments,\88\ we accept
NERC's proposed plan to respond to the following three questions and
direct NERC to include in the report:
---------------------------------------------------------------------------
\88\ Id. at 12-19.
---------------------------------------------------------------------------
A summary of the base cases used in applying the
Attachment B criteria and an assessment of how the base cases used for
the analysis relate to TPL-003-0, Requirement R1.3.2;
A discussion of the types of studies that planning
coordinators may use to identify circuits under Attachment B; and
An assessment that demonstrates whether Attachment B is
comprehensive enough to capture all circuits that could have an
operational impact on the reliability of the bulk electric system in
the context of transmission relay loadabilty.
78. However, we are not persuaded by NERC's statement that it is
not necessary for NERC to include in the report a comparison of the
results obtained using criterion B4 to the results that would be
achieved based on assumptions consistent with Requirement R1. The 0.85
per unit and 30 degrees power factor criteria in Requirement R1 is
based on system conditions, voltage, current, and angle, observed prior
to the cascading stage of the blackout. Although NERC states that
criterion B4 was derived from these system criteria,\89\ the Commission
is concerned that testing, which does not, at a minimum, compare
whether criteria that do not consider voltage or angle affect the
appropriate identification of applicable facilities, is not responsive
to ensuring the reliability objective of the critical facilities test
or the reliability objective of PRC-023. For these reasons, we direct
NERC to evaluate, in the report, relay loadability under the B4
criterion consistent with Requirement R1, which requires, in part, that
NERC ``evaluate relay loadability at 0.85 per unit voltage and a power
factor angle of 30 degrees'' in addition to applicable current data.
---------------------------------------------------------------------------
\89\ Id. at 3.
---------------------------------------------------------------------------
B. NERC Rules of Procedure Section 1700--Challenges to Determinations
1. NERC Petition
79. In its petition, NERC submitted new Rules of Procedure Section
1700--Challenges to Determinations, which sets out the procedure for a
registered entity to challenge a determination by a planning
coordinator under Reliability Standard PRC-023-2.
2. NOPR
80. In the NOPR, we proposed to approve NERC Rules of Procedure
Section 1700, specifically proposed Rule 1702, finding that it
addresses the Order No. 733 directives that NERC establish a mechanism
for registered entities to challenge criticality determinations made by
a planning coordinator.
3. Comments
81. No comments were filed concerning proposed Rules of Procedure
Section 1700--Challenges to Determinations.
4. Commission Determination
82. NERC's proposal is responsive to the Commission's directive in
Order No. 733. Accordingly, we adopt our NOPR proposal and we approve,
pursuant to section 215(f) of the FPA, NERC Rule of Procedure Section
1700--Challenges to Determinations as just, reasonable, not unduly
discriminatory or preferential, in the public interest, and satisfying
the requirements of section 215(c) of the FPA.
V. Information Collection Statement
83. The Office of Management and Budget (OMB) regulations require
approval of certain information collection requirements imposed by
agency rules.\90\ Upon approval of a collection(s) of information, OMB
will assign an OMB control number and expiration date. Respondents
subject to the filing requirement of this rule will not be penalized
for failing to respond to these collections of information unless the
collections of information display a valid OMB control number. The
Paperwork Reduction Act (PRA) \91\ requires each federal agency to seek
and obtain OMB approval before undertaking a collection of information
directed to ten or more persons, or continuing a collection for which
OMB approval and validity of the control number are about to
expire.\92\
---------------------------------------------------------------------------
\90\ 5 CFR 1320.11.
\91\ 44 U.S.C. 3501-20.
\92\ 44 U.S.C. 3502(A)(3)(i), 44 U.S.C. 3507(a)(3).
---------------------------------------------------------------------------
84. The Commission is submitting these reporting and recordkeeping
[[Page 16445]]
requirements to OMB for its review and approval under section 3507(d)
of the PRA. Comments are solicited on the Commission's need for this
information, whether the information will have practical utility, the
accuracy of provided burden estimates, ways to enhance the quality,
utility, and clarity of the information to be collected, and any
suggested methods for minimizing the respondent's burden, including the
use of automated information techniques.
85. This Final Rule approves Reliability Standard PRC-023-2
(Transmission Relay Loadability) which replaces currently effective
Reliability Standard PRC-023-1 approved by the Commission in Order No.
733. Rather than creating entirely new requirements regarding the
setting of protective relays, the revised Reliability Standard instead
modifies and improves the existing Reliability Standard. Thus this
Final Rule does not impose entirely new burdens on the effected
entities. For example, the currently effective Reliability Standard
PRC-023-1 requires transmission owners, generation owners, and
distribution providers to each have evidence to show that each of its
transmission relays are set according to one of the criteria in
criteria R1.1 through R1.13. Similarly, revised Reliability Standard
PRC-023-2 requires transmission owners, generation owners, and
distribution providers to have evidence that each of its transmission
relays is set according to one of the 13 criteria in Requirement R1 but
adds that each such entity shall also have evidence that relays set
according to criterion 10 do not expose the transformer to fault levels
and durations beyond those indicated in the Standard. Thus, the
recordkeeping obligations for some Requirements are more specific but
not necessarily more expansive than those of currently effective
Reliability Standard PRC-023-1. However, revised PRC-023-2 does add new
Requirements, each of which has new recordkeeping obligations.
86. Requirement R2 requires each transmission owner, generator
owner, and distribution provider to have evidence that its out-of-step
blocking elements are set in accordance with the Standard, and
Requirements R4 and R5 require those same entities to maintain evidence
that they have informed the appropriate parties of their updated lists
of certain circuits. Under Requirement R6, planning coordinators are
required to execute a test for applicability of the Standard as set
forth in Attachment B and retain analyses, calculation summaries, or
study reports to evidence execution of the test, whereas under the
currently effective PRC-023-1, a test was required but only the results
needed to be retained. Because an unspecified test is currently
required to be carried out on facilities operated at between 100 kV and
200 kV under currently effective Reliability Standard PRC-023-1, for
purposes of this analysis, we assume that there is little additional
cost for planning coordinators to implement and document that portion
of the test. However, the Requirement R6 of the revised Standard
imposes the new burdens of performing the test on sub-100 kV
facilities, maintaining appropriate records, and distributing the list
of circuits identified by the test to Regional Entities.
87. Public Reporting Burden: Our estimate below regarding the
number of respondents is based on the NERC compliance registry as of
January 26, 2012. According to the NERC compliance registry, there are
337 transmission owners, 858 generation owners, 554 distribution
providers, and 81 planning coordinators. However, under NERC's
compliance registration program, entities may be registered for
multiple functions, so these numbers incorporate some double counting.
The net number of entities responding will be approximately 660
entities registered as a transmission owner, a distribution provider,
or a generation owner that is also a transmission owner and/or a
distribution owner, and 81 planning coordinators.\93\ The estimated
burden for the requirements in this Order follow:
---------------------------------------------------------------------------
\93\ Under its applicability provisions, proposed Reliability
Standard applies to specified circuits such that very few, if any,
generator owners that are not also a transmission owner and/or a
distribution provider will be subject to the Standard.
\94\ The burden hours are based on estimates that the Commission
has used for similar reporting requirements.
\95\ This applies to the portion of R6 that deals with testing
for sub-100 kV facilities as described in the text. In addition it
includes burden hours associated with adding Regional Entities to
the list of entities to receive a list of circuits from the planning
coordinator.
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
Changes to FERC-725G data Number of Number of Average burden hours per Total annual
collection respondents responses per response \94\ hours
annually respondent
(1) (2) (3) (1 x 2 x 3)
----------------------------------------------------------------------------------------------------------------
R1 criterion 1.10: TOs, GOs, 660 1 Analysis for 8 5,280
and DPs must analyze and compliance
document criterion 1.10 documents.
compliance.
-------------------------------------------------
.............. .............. Record Retention 2 1,320
----------------------------------------------------------------------------------------------------------------
R2: TOs, GOs, and DPs must 660 1 Analysis for 8 5,280
perform analysis and retain compliance
evidence of compliance. documents.
-------------------------------------------------
.............. .............. Record Retention 2 1,320
----------------------------------------------------------------------------------------------------------------
R4 and R5: TOs, GOs, and DPs 660 1 Reporting (dist. 10 6,600
must distribute updated lists of list).
and retain evidence that
lists were distributed.
-------------------------------------------------
.............. .............. Record Retention 10 6,600
----------------------------------------------------------------------------------------------------------------
R6: PC must perform 81 1 Reporting 20 1,620
assessment, distribute list (assessment and
of circuits and retain dist. of list).
evidence of testing and
distribution \95\.
-------------------------------------------------
.............. .............. Record Retention 10 810
----------------------------------------------------------------------------------------------------------------
Total..................... .............. .............. ................ .............. 28,830
----------------------------------------------------------------------------------------------------------------
[[Page 16446]]
Information Collection Costs: The Commission seeks comments on the
costs to comply with these requirements and recordkeeping burden
associated with Reliability Standard PRC-023-2.
Total Annual Hours for Collection: (Reporting and Record
Retention) = 28,830 hours.
Total Estimated Reporting/Analysis Cost = 18,780 hours @
$120/hour = $2,253,600.
Total Estimated Record Retention Cost = 10,050 hours @
$28/hour = $281,400.
Total Estimated Annual Cost (Reporting + Record Retention)
\96\ = $2,535,000.
---------------------------------------------------------------------------
\96\ The hourly reporting cost is based on the estimated cost of
an engineer to implement the requirements of the rule. The record
retention cost comes from Commission staff research on record
retention requirements.
---------------------------------------------------------------------------
Title: Mandatory Reliability Standards for the Bulk-Power
System
Action: FERC 725G, Proposed Modification to FERC-725G.
OMB Control No: 1902-0252.
Respondents: Business or other for profit, and/or not for
profit institutions.
Frequency of Responses: On occasion.
Necessity of the Information: This Final Rule approves a
revised Reliability Standard that modifies an existing requirement
regarding setting protective relays according to specific criteria in
order to ensure that the relays reliably detect and protect the
electric network from all fault conditions, but do not limit
transmission loadability or interfere with system operators' ability to
protect system reliability. Reliability Standard PRC-023-2 requires
entities to set transmission relays according to specified criteria and
to retain evidence of compliance. It also requires planning
coordinators to implement a test to determine which sub-200 kV
facilities are critical to the reliability of the power system and
subjects such facilities to the requirements of the Standard. The
revised Reliability Standard requires entities to maintain records
subject to review by the Commission and NERC to ensure compliance with
the Reliability Standard.
Internal review: The Commission has reviewed the
requirements pertaining to the revised Reliability Standard for the
Bulk-Power System and determined that the requirements are necessary to
meet the statutory provisions of the Energy Policy Act of 2005. These
requirements conform to the Commission's plan for efficient information
collection, communication and management within the energy industry.
The Commission has assured itself, by means of internal review, that
there is specific objective support for the burden estimates associated
with the information requirements.
88. Interested persons may obtain information on the reporting
requirements by contacting: Federal Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426 [Attention: Ellen Brown, Office
of the Executive Director, email: DataClearance@ferc.gove, Phone: (202)
502-8663, fax: (202) 273-0873]. Comments on the requirements of this
order may also be sent to the Office of Information and Regulatory
Affairs, Office of Management and Budget, Washington, DC 20503
[Attention: Desk Officer for the Federal Energy Regulatory Commission].
For security reasons, comments should be sent by email to OMB at oira_submission@omb.eop.gov. Please reference OMB Control Number 1902-0252
and the docket number of this Order in your submission.
VI. Environmental Analysis
89. The Commission is required to prepare an Environmental
Assessment or an Environmental Impact Statement for any action that may
have a significant adverse effect on the human environment.\97\ The
actions proposed here fall within the categorical exclusion in the
Commission's regulations for rules that are clarifying, corrective or
procedural, for information gathering, analysis, and dissemination.\98\
Accordingly, neither an environmental impact statement nor
environmental assessment is required.
---------------------------------------------------------------------------
\97\ Regulations Implementing the National Environmental Policy
Act, Order No. 486, 52 FR 47897 (Dec. 17, 1987), FERC Stats. & Regs.
Regulations Preambles 1986-1990 ] 30,783 (1987).
\98\ 18 CFR 380.4(a)(5).
---------------------------------------------------------------------------
VII. Regulatory Flexibility Act Analysis
90. The Regulatory Flexibility Act of 1980 (RFA) \99\ generally
requires a description and analysis of proposed and final rules that
will have significant economic impact on a substantial number of small
entities. The RFA mandates consideration of regulatory alternatives
that accomplish the stated objectives of a proposed order and that
minimize any significant economic impact on a substantial number of
small entities. The Small Business Administration's (SBA) Office of
Size Standards develops the numerical definition of a small
business.\100\ The SBA has established a size standard for electric
utilities, stating that a firm is small if, including its affiliates,
it is primarily engaged in the transmission, generation and/or
distribution of electric energy for sale and its total electric output
for the preceding twelve months did not exceed four million megawatt-
hours.\101\
---------------------------------------------------------------------------
\99\ 5 U.S.C. 601-612.
\100\ 13 CFR 121.101.
\101\ 13 CFR 121.201, Sector 22, Utilities & n.1.
---------------------------------------------------------------------------
91. Reliability Standard PRC-023-2 modifies currently existing
Reliability Standard PRC-023-1 which requires applicable entities to
set protective relays according to specific criteria, to communicate
about such settings with specified entities, and to conduct assessments
to determine the applicability of the Standard to 100-200 kV
facilities. The revised Standard modifies PRC-023-1 by (1) increasing
communication and documentation requirements, (2) extending the
applicability of the Standard to formerly excluded relays, and (3)
standardizing the terms of the assessment whose terms were formerly not
specified. In addition, PRC-023-2 extends the current requirement that
planning coordinators annually assess which 100-200 kV circuits must be
brought into compliance with the Standard and will require planning
coordinators to carry out the assessment with respect to some sub-100
kV facilities.
92. Comparison of the NERC compliance registry with data submitted
to the Energy Information Administration on Form EIA-861 indicates that
perhaps as many as 108 transmission owners, 327 distribution providers,
52 generation owners, and 14 planning coordinators qualify as small
entities. However, under NERC's compliance registration program,
entities may be registered for multiple functions, so these numbers
incorporate some double counting. The net number of registered entities
that qualify as small entities responding to this rule will be
approximately 339 entities registered as a transmission owner, a
distribution provider, or a generation owner that is also a
transmission owner and/or a distribution provider, and 8 planning
coordinators. The Final Rule directly affects each of the small
entities. Therefore, FERC has determined that this Final Rule will have
an impact on a substantial number of small entities. However, the
Commission has determined that the impact on entities affected by the
Final Rule will not be significant. The Commission estimates that in
order to comply with the Standard's modification of existing
requirements each of the small entities registered as planning
coordinators will face a cost of $2,680 and each of the remaining small
entities (transmission owners, distribution providers, or generation
[[Page 16447]]
owners that are also transmission owners and/or distribution providers)
will face a cost of $3,512. Accordingly, the Commission determines that
the incremental cost of Reliability Standard PRC-023-2 (going from PRC-
023-1 to PRC-023-2) is minimal, and should not present a significant
operating cost to any of the small entities.
93. Based on this understanding, the Commission certifies that this
Reliability Standard will not have a significant economic impact on a
substantial number of small entities. Accordingly, no regulatory
flexibility analysis is required.
VIII. Document Availability
94. In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
Internet through FERC's Home Page (http://www.ferc.gov) and in FERC's
Public Reference Room during normal business hours (8:30 a.m. to 5 p.m.
Eastern time) at 888 First Street NE., Room 2A, Washington, DC 20426.
95. From FERC's Home Page on the Internet, this information is
available on eLibrary. The full text of this document is available on
eLibrary in PDF and Microsoft Word format for viewing, printing, and/or
downloading. To access this document in eLibrary, type the docket
number excluding the last three digits of this document in the docket
number field.
96. User assistance is available for eLibrary and the FERC's Web
site during normal business hours from FERC Online Support at (202)-
502-6652 (toll free at 1-(866) 208-3676) or email at
ferconlinesupport@ferc.gov, or the Public Reference Room at (202) 502-
8371, TTY (202) 502-8659. Email the Public Reference Room at
public.referenceroom@ferc.gov.
By the Commission.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2012-6758 Filed 3-20-12; 8:45 am]
BILLING CODE 6717-01-P