DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 13005-003]


Oliver Hydro LLC; Notice Soliciting Scoping Comments

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Original Major License.
    b. Project No.: P-13005-003.
    c. Date filed: December 14, 2011.
    d. Applicant: Oliver Hydro LLC.
    e. Name of Project: William Bacon Oliver Lock and Dam Hydroelectric 
Project
    f. Location: At the U.S. Army Corps of Engineers' (Corps) William 
Bacon Oliver Lock and Dam on the Black Warrior River, in Tuscaloosa 
County, Alabama. The project would occupy 8.7 acres of United States 
lands administered by the Corps' Mobile District.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
    h. Applicant Contact: Brent Smith, Symbiotics LLC, 371 Upper 
Terrace, Suite 2, Bend, OR 97702; (541) 330-8779; or email at 
[email protected].
    i. FERC Contact: Allan Creamer at (202) 502-8365, or via email at 
[email protected].
    j. Deadline for filing scoping comments: October 4, 2012.
    All documents may be filed electronically via the Internet. See 18 
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web 
site http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at [email protected], or toll free at 1-866-208-3676, 
or for TTY, (202) 502-8659. Although the Commission strongly encourages 
electronic filing, documents may also be

[[Page 55469]]

paper-filed. To paper-file, mail an original and seven copies to: 
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First Street NE., Washington, DC 20426.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. This application is not ready for environmental analysis at this 
time.
    l. The proposed project would utilize the Corps' existing William 
Bacon Oliver Lock and Dam, and would consist of the following new 
facilities: (1) A forebay; (2) an intake structure; (3) a powerhouse 
containing two generating units with a total capacity of 11.72 
megawatts (MW); (4) a 150-foot-long, 68-foot-wide tailrace; (5) a 
proposed 1.7-mile-long, 25 kilovolt (kV) transmission line; (6) a 
switchyard; and (7) appurtenant facilities. The proposed project would 
have an average annual generation of 42.6 GWh, and operate in a run-of-
river mode utilizing surplus water from the William Bacon Oliver Lock 
and Dam, as directed by the Corps.
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at http://www.ferc.gov, using the ``eLibrary'' 
link. Enter the docket number, excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    n. You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    o. Scoping Process
    The Commission staff intends to prepare a single Environmental 
Assessment (EA) for the William Oliver Bacon Lock and Dam Hydroelectric 
Project in accordance with the National Environmental Policy Act. The 
EA will consider both site-specific and cumulative environmental 
impacts and reasonable alternatives to the proposed action.
    Commission staff does not propose to conduct any on-site scoping 
meetings at this time. Instead, we are soliciting comments, 
recommendations, and information, on the Scoping Document (SD) issued 
on August 31, 2012.
    Copies of the SD outlining the subject areas to be addressed in the 
EA were distributed to the parties on the Commission's mailing list and 
the applicant's distribution list. Copies of the SD may be viewed on 
the web at http://www.ferc.gov using the ``eLibrary'' link. Enter the 
docket number, excluding the last three digits in the docket number 
field to access the document. For assistance, call 1-866-208-3676 or 
for TTY, (202) 502-8659.

    Dated: September 4, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012-22184 Filed 9-7-12; 8:45 am]