DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2355-018]


Exelon Generation Company, LLC; Notice of Application Tendered 
for Filing With the Commission and Deadline for Submission of Final 
Amendments

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: New Major License
    b. Project No.: 2355-018
    c. Date Filed: August 29, 2012
    d. Applicant: Exelon Generation Company, LLC
    e. Name of Project: Muddy Run Pumped Storage Project
    f. Location: On Muddy Run, a tributary to the Susquehanna River, in 
Lancaster and York Counties, Pennsylvania. The project does not occupy 
any federal lands.
    g. Filed Pursuant to: Federal Power Act, 16 USC 791 (a)-825(r)
    h. Applicant Contact: Colleen Hicks, Manager, Regulatory and 
Licensing, Hydro, Exelon Power, 300 Exelon Way, Kennett Square, PA 
19348, at (610) 765-6791 or email at [email protected] and 
Kathleen Barr[ograve]n, Vice President, Federal Regulatory Affairs and 
Wholesale Market Policy, Exelon Corporation, 101 Constitution Avenue, 
Washington, DC 20001, at (202) 347-7500 or email at 
[email protected].
    i. FERC Contact: Emily Carter, (202) 502-6512 or 
[email protected].
    j. This application is not ready for environmental analysis at this 
time.
    k. The Project Description: The Muddy Run Pumped Storage Project 
consists of four dams. The main dam is a rock-filled structure across 
the Muddy Run ravine with a central impervious core, a maximum height 
of approximately 260 feet and a total length of 4,800 feet. The east 
dike is a zoned-earth and rock-filled embankment with a maximum height 
of approximately 12 feet and a total length of 800 feet. The recreation 
pond dike is a zoned-earth and rock-filled embankment with a maximum 
height of approximately 90 feet and a total length of 750 feet. The 
canal embankment has a maximum height of approximately 35 feet. Total 
storage in the 900-acre Muddy Run reservoir (upper reservoir) is 
approximately 60,000 acre-feet and the total useable storage is 
approximately 35,500 acre-feet at the maximum pool elevation of 520 
feet. The maximum pool elevation is approximately 411 feet above the 
normal elevation of Conowingo pond. Conowingo pond (lower reservoir) 
has a surface area of 9,000 acres and design storage of approximately 
310,000 acre-feet at the normal full pool elevation of 109.2 feet.
    The main spillway is a non-gated concrete ogee-type structure that 
is 200 feet long, 20 feet high and with crest elevation of 521 feet, 
which is directed to a vegetated natural ravine. The recreation pond 
spillway is a rock-cut channel approximately 140 feet wide and with a 
crest elevation of 520 feet.
    The power intake facilities consist of four cylinder gates with 
trash racks in a cylindrical tower. Each intake supplies two units. 
Each intake leads to a 430-foot-deep vertical shaft then to a 
horizontal power tunnel, which divides into two sections. The power 
tunnel sections transition to a penstock that leads to one of the eight 
reversible pump-turbine units in the powerhouse. The power plant is 
constructed of concrete and is 133 feet wide and 600 feet long. It 
houses eight Francis turbines each equipped with a 100-MW generator. 
The powerhouse turbines each have a hydraulic capacity of 4,000 cfs, 
for a total discharge capacity from the powerhouse of 32,000 cfs. The 
pumping capacity of the pump turbines is 3,500 cfs each for a total 
powerhouse pumping capability of 28,000 cfs. Water flowing through the 
turbines is discharged via the draft tubes into the Susquehanna River 
adjacent to the powerhouse. The units are equipped with trash racks 
between the draft tube outlet and the river.
    Electricity generated at the project is transmitted by two 
individual 220-kV transmission lines extending from the project 
switching station approximately 4.25 miles to the Peach Bottom Atomic 
Power Station (PBAPS) North Substation located in York County.
    The Muddy Run Project has an authorized nameplate generating 
capacity of 800 MW and generates an average of 1,610,611 MWh annually. 
Exelon is not proposing any new or upgraded facilities or structural 
changes to the project at this time. Also, Exelon has engaged 
interested stakeholders to participate in the development of a 
comprehensive settlement agreement based on collaborative negotiation 
of specific terms and conditions for the new Muddy Run license.
    l. Locations of the Application: A copy of the application is 
available for review at the Commission in the Public Reference Room or 
may be viewed on the Commission's Web site at http://www.ferc.gov using 
the ``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. For 
assistance, contact FERC Online Support at [email protected] 
or toll-free at 1-866-208-3676, or for TTY, (202) 502-8659. A copy is 
also available for inspection and reproduction at the address in item 
(h) above.
    m. You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. Procedural Schedule: A preliminary Hydro Licensing Schedule will 
be provided in a subsequent notice.
    o. Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of the notice 
of ready for environmental analysis.

    Dated: September 12, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012-23024 Filed 9-18-12; 8:45 am]