Reissuance of Nationwide Permits

AGENCY: Army Corps of Engineers, DoD.

ACTION: Final notice; correction.

-----------------------------------------------------------------------

SUMMARY: The U.S. Army Corps of Engineers published a document in the 
Federal Register of February 21, 2012, a final notice concerning the 
reissuance of nationwide permits. On March 19, 2012, the U.S. Army 
Corps of Engineers published a correction to that final notice. This 
document contains additional corrections to the February 21, 2012, 
final notice.

ADDRESSES: U.S. Army Corps of Engineers, Attn: CECW-CO-R, 441 G Street 
NW., Washington, DC 20314-1000.

FOR FURTHER INFORMATION CONTACT: Mr. David Olson at 202-761-4922 or by 
email at david.b.olson@usace.army.mil or access the U.S. Army Corps of 
Engineers Regulatory Home Page at http://www.usace.army.mil/Missions/CivilWorks/RegulatoryProgramandPermits.aspx.

Corrections

    In the Federal Register of February 21, 2012, in FR Doc. 2012-3687, 
the following corrections are made:

[[Page 58533]]

    On page 10273, second column, correct the first sentence of NWP 15 
to read as follows to reflect the fact that the U.S. Coast Guard 
authorizes bridges over navigable waters through permits issued under 
other statutory authorities, such as the General Bridge Act of 1946 (33 
U.S.C. 525, 528, 530, and 533), instead of Section 9 of the Rivers and 
Harbors Act of 1899 (33 U.S.C. 401): ``Discharges of dredged or fill 
material incidental to the construction of a bridge across navigable 
waters of the United States, including cofferdams, abutments, 
foundation seals, piers, and temporary construction and access fills, 
provided the construction of the bridge structure has been authorized 
by the U.S. Coast Guard under Section 9 of the Rivers and Harbors Act 
of 1899 or other applicable laws.''
    On page 10287, second column, correct the first sentence of 
paragraph (d)(2) of general condition 31 to read as follows: ``For all 
NWP activities that require pre-construction notification and result in 
the loss of greater than \1/2\-acre of waters of the United States, for 
NWP 21, 29, 39, 40, 42, 43, 44, 50, 51, and 52 activities that require 
pre-construction notification and will result in the loss of greater 
than 300 linear feet of stream bed, and for all NWP 48 activities that 
require pre-construction notification, the district engineer will 
immediately provide (e.g., via email, facsimile transmission, overnight 
mail, or other expeditious manner) a copy of the complete PCN to the 
appropriate Federal or state offices (U.S. FWS, state natural resource 
or water quality agency, EPA, State Historic Preservation Officer 
(SHPO) or Tribal Historic Preservation Officer (THPO), and, if 
appropriate, the NMFS).''

    Dated: September 18, 2012.
James R. Hannon,
Chief, Operations and Regulatory Directorate of Civil Works.