DEPARTMENT OF DEFENSE
Department of the Navy
Record of Decision for the U.S. Marine Corps Basewide Water
Infrastructure Project at Marine Corps Base Camp Pendleton, California
AGENCY: Department of the Navy, DoD.
ACTION: Notice of record of decision.
-----------------------------------------------------------------------
SUMMARY: Pursuant to Section 102(2)(c) of the National Environmental
Policy Act (NEPA) of 1969, 42 United States Code (U.S.C.) Section
4332(2)(c), the regulations of the Council on Environmental Quality for
Implementing the Procedural Provisions of NEPA (40 Code of Federal
Regulations [CFR] parts 1500-1508), the Department of the Navy (DoN)
NEPA regulations (32 CFR part 775), and the Marine Corps Environmental
Compliance and Protection Manual (Marine Corps Order P5090.2A, Change
2), the DoN announces its decision to upgrade and improve the Basewide
water infrastructure at Marine Corps Base Camp Pendleton, California
(MCBCP). More specifically, the DoN has decided to implement
Alternative 5, the Preferred Alternative of the Basewide Water
Infrastructure Improvements Final Environmental
[[Page 60688]]
Impact Statement (EIS), which entails two separate projects to
construct, operate, and maintain water infrastructure upgrades,
expansions, and improvements at MCBCP. These potable water
infrastructure improvements will include construction, operation, and
maintenance of a new Northern Advanced Water Treatment plant and
associated facilities, an effluent discharge system, and connection of
the MCBCP northern and southern water systems. All practical means to
avoid or minimize environmental impacts resulting from implementation
of the Preferred Alternative have been adopted.
SUPPLEMENTARY INFORMATION: The complete text of the Record of Decision
is available for public viewing on the project Web site at http://www.marines.mil/unit/basecamppendleton/Pages/BaseStaffandAgencies/Environmental/EAEIS/Home.aspx along with the Final Environmental Impact
Statement (EIS). For further information, contact Mr. Jesse Martinez,
EIS Project Manager, 1220 Pacific Highway, San Diego, California 92132-
5190, 619-532-3844 or [email protected].
Dated: September 25, 2012.
D.G. Zimmerman,
Lieutenant Commander, Office of the Judge Advocate General, U.S. Navy,
Federal Register Liaison Officer.
[FR Doc. 2012-24481 Filed 10-3-12; 8:45 am]