[Federal Register Volume 77, Number 196 (Wednesday, October 10, 2012)]
[Notices]
[Page 61593]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2012-24908]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. EL13-10-000]
North American Natural Resources, Inc. Complainant v. PJM
Interconnection, L.L.C, American Electric Power Service Corporation,
Indiana Michigan Power Company, Respondents; Notice of Complaint
Take notice that on October 2, 2012, pursuant to section 206 of the
Federal Energy Regulatory Commission's (Commission) Rules of Practice
and Procedure, 18 CFR 385.206 and sections 206 of the Federal Power Act
(FPA), 16 U.S.C. 824(e), North American Natural Resource, Inc. (NSANR)
filed a formal complaint against PJM Interconnection, L.L.C, (PJM),
American Electric Power Service Corporation (AEP), and AEP's wholly
owned subsidiary Indiana Michigan Power Company (I & M) alleging, that
contrary to sections 1.7A.02, 1.3A, 1.17A, 1.26, 212.4, 217.3, 205, 206
and 217 of PJM's Open Access Transmission Tariff (OATT), the
Interconnection Construction Service Agreement (ICSA) between AEP and
NANR, the Interconnection Service Agreement (ISA) between AEP and NANR,
the Commission's Order No. 2003 \1\ and other applicable FERC
decisions, and the FPA, AEP and PJM have refused to properly categorize
$2,269,012 of the interconnection costs as Network Upgrades and
allocate those costs to AEP and its customers, failed to update AEP's
Regional Transmission System Expansion (RTEP) and wrongfully foisted
the costs of the Network Upgrades onto NANR by mischaracterizing them
as Attachment Facilities, and wrongfully utilized the interconnection
of Project T-111 as a means of upgrading its inadequate 69 kV line,
which had previously not included adequate re-closing or breaker
failure protection, and replacing obsolete relays and other equipment.
---------------------------------------------------------------------------
\1\ Standardization of Generator Interconnection Agreements and
Procedure, Order No. 2003, 104 FERC ] 61,103 (2003).
---------------------------------------------------------------------------
NANR certifies that copies of the complaint were served on the
contacts for PJM, AEP, and I & M as listed on the Commission's list of
Corporate Officials.
Any person desiring to intervene or to protest this filing must
file in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211, 385.214). Protests will be
considered by the Commission in determining the appropriate action to
be taken, but will not serve to make protestants parties to the
proceeding. Any person wishing to become a party must file a notice of
intervention or motion to intervene, as appropriate. The Respondent's
answer and all interventions, or protests must be filed on or before
the comment date. The Respondent's answer, motions to intervene, and
protests must be served on the Complainants.
The Commission encourages electronic submission of protests and
interventions in lieu of paper using the ``eFiling'' link at http://www.ferc.gov. Persons unable to file electronically should submit an
original and 14 copies of the protest or intervention to the Federal
Energy Regulatory Commission, 888 First Street NE., Washington, DC
20426.
This filing is accessible on-line at http://www.ferc.gov, using the
``eLibrary'' link and is available for review in the Commission's
Public Reference Room in Washington, DC. There is an ``eSubscription''
link on the Web site that enables subscribers to receive email
notification when a document is added to a subscribed docket(s). For
assistance with any FERC Online service, please email
[email protected], or call (866) 208-3676 (toll free). For
TTY, call (202) 502-8659.
Comment Date: 5 p.m. Eastern Time on October 22, 2012.
Dated: October 3, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012-24908 Filed 10-9-12; 8:45 am]
BILLING CODE 6717-01-P