    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Amendment of Exemption.
    b. Project No.: 6952-008.
    c. Date filed: December 12, 2011, and supplemented on October 8, 
2012.
    d. Applicant: Water Wheel Ranch.
    e. Name of Project: Water Wheel Ranch Hydroelectric Project.
    f. Location: The Water Wheel Ranch Hydroelectric Project would be 
located on the North Fork Little Cow Creek in Shasta County, 
California. The land on which all the project structures are located is 
owned by the applicant.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791a--825r.
    h. Applicant Contact: Mr. Finley McMillan, P.O. Box 130, Round 
Mountain, CA 96084. Phone (530) 337-6581.
    i. FERC Contact: Robert Bell, (202) 502-6062, [email protected].
    j. Status of Environmental Analysis: This application is ready for 
environmental analysis at this time, and the Commission is requesting 
comments, reply comments, recommendations, terms and conditions, and 
prescriptions.
    k. Deadline for filing responsive documents: All comments, motions 
to intervene, protests, recommendations, terms and conditions, and 
prescriptions due within 30 days from the issuance date of this notice. 
All reply comments filed in response to comments submitted by any 
resource agency, Indian tribe, or person, must be filed with the 
Commission within 15 days from the issuance date of this notice.
    Comments, protests, and interventions may be filed electronically 
via the Internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and 
the instructions on the Commission's web site at http://www.ferc.gov/docs-filing/efiling.asp. The Commission strongly encourages electronic 
filings.
    The Commission's Rules of Practice and Procedure require all 
intervenors filing documents with the Commission to serve a copy of 
that document on each person in the official service list for the 
project. Further, if an intervenor files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency.
    l. Description of the project: The amended Water Wheel Ranch 
Hydroelectric Project would consist of: (1) Relocating powerhouse No. 
2, which was destroyed by a forest fire, 850 feet closer to the dam, up 
the existing penstock, (2) installing a new 100-foot-long tailrace 
which would discharge into Cedar Creek, 1,400 feet upstream of the 
current discharge location and (3) appurtenant facilities. The 
applicant states there would be no change in project capacity.
    m. This filing is available for review and reproduction at the 
Commission in the Public Reference Room, Room 2A, 888 First Street NE., 
Washington, DC 20426. The filing may also be viewed on the web at 
http://www.ferc.gov/docs-filing/elibrary.asp using the ``eLibrary'' 
link. Enter the docket number, P-6952, in the docket number field to 
access the document. For assistance, call toll-free 1-866-208-3676 or 
email [email protected]. For TTY, call (202) 502-8659. A copy 
is also available for review and reproduction at the address in item h 
above.
    n. Protests or Motions to Intervene--Anyone may submit a protest or 
a motion to intervene in accordance with the requirements of Rules of 
Practice and Procedure, 18 CFR 385.210, 385.211, and 385.214. In 
determining the appropriate action to take, the Commission will 
consider all protests filed, but only those who file a motion to 
intervene in accordance with the Commission's Rules may become a party 
to the proceeding. Any protests or motions to intervene must be 
received on or before the specified deadline date for the particular 
application.
    q. All filings must (1) bear in all capital letters the title 
``PROTEST'', ``MOTION TO INTERVENE'', ``COMMENTS'', ``REPLY COMMENTS,'' 
``RECOMMENDATIONS,'' ``TERMS AND CONDITIONS,'' or ``PRESCRIPTIONS;'' 
(2) set forth in the heading, the name of the applicant and the project 
number of the application to which the filing responds; (3) furnish the 
name, address, and telephone number of the person protesting or 
intervening; and (4) otherwise comply with the requirements of 18 CFR 
385.2001 through 385.2005. All comments, recommendations, terms and 
conditions or prescriptions must set forth their evidentiary basis and 
otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may 
obtain copies of the application directly from the applicant. Any of 
these documents must be filed by providing the original and seven 
copies to: The Secretary, Federal Energy Regulatory Commission, 888 
First Street NE., Washington, DC 20426. An additional copy must be sent 
to Director, Division of Hydropower Administration and Compliance, 
Office of Energy Projects, Federal Energy Regulatory Commission, at the 
above address. A copy of any protest or motion to intervene must be 
served upon each representative of the applicant specified in the 
particular application. A copy of all other filings in reference to 
this application must be accompanied by proof of service on all persons 
listed in the service list prepared by the Commission in this 
proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.

    Dated: November 8, 2012.
Kimberly D. Bose,
Secretary.