DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP13-3-000]
Tennessee Gas Pipeline Company, L.L.C.; Notice of Intent To
Prepare an Environmental Assessment for the Proposed Rose Lake
Expansion Project and Request for Comments on Environmental Issues
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Rose Lake Expansion Project
involving the modification of compression facilities by Tennessee Gas
Pipeline Company, L.L.C. (TGP) in Bradford and Tioga Counties,
Pennsylvania. The Commission will use this EA in its decision-making
process to determine whether the project is in the public convenience
and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the project. Your input will help the Commission staff
determine what issues they need to evaluate in the EA. Please note that
the scoping period will close on December 10, 2012.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this proposed
project and encourage them to comment on their areas of concern.
TGP provided landowners with a fact sheet prepared by the FERC
entitled ``An Interstate Natural Gas Facility On My Land? What Do I
Need To Know?''. This fact sheet addresses a number of typically-asked
questions, including the use of eminent domain and how to participate
in the Commission's proceedings. It is also available for viewing on
the FERC Web site (www.ferc.gov).
Summary of the Proposed Project
TGP proposes to construct, abandon, and replace certain compression
facilities at three existing compressor stations on its 300 Line in
northeastern Pennsylvania. The proposed Rose Lake Expansion Project
includes the following:
Installation of a new 12,630 horsepower (hp) compressor
unit, ancillary equipment, and station piping modifications at Station
315 in Tioga County, Pennsylvania;
Abandonment in place of two 4,500 hp compressor units and
replacing these with the installation of a new 12,661 hp compressor
unit, ancillary equipment, and station piping modifications at Station
319 in Bradford County, Pennsylvania; and
Abandonment by removal of an existing gear box and
compressor unit and replacement with a new gear box and compressor
unit, ancillary equipment, and station piping modifications at Station
317 in Bradford County, Pennsylvania.
Construction of the project would disturb about 70 acres of land,
of which approximately 5.4 acres would be permanently impacted. All
land disturbance would occur on land owned by TGP adjacent to its
existing facilities. The general location of the project facilities is
shown in appendix 1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of appendices were sent to all those
receiving this notice in the mail and are available at www.ferc.gov
using the link called ``eLibrary'' or from the Commission's Public
Reference Room, 888 First Street NE., Washington, DC 20426, or call
(202) 502-8371. For instructions on connecting to eLibrary, refer to
the last page of this notice.
---------------------------------------------------------------------------
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
\2\ to discover and address concerns the public may have about
proposals. This process is referred to as ``scoping.'' The main goal of
the scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EA. We will
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------
\2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the proposed project under these
general headings:
Geology and soils;
Land use;
Water resources, fisheries, and wetlands;
Cultural resources;
Vegetation and wildlife;
Air quality and noise;
Endangered and threatened species; and
Public safety.
We will also evaluate reasonable alternatives to the proposed
project or portions of the project, and make recommendations on how to
lessen or avoid impacts on the various resource areas.
The EA will present our independent analysis of the issues. The EA
will be available in the public record through eLibrary. Depending on
the comments received during the scoping process, we may also publish
and distribute the EA to the public for an allotted comment period. We
will consider all comments on the EA before making our recommendations
to the Commission. To ensure we have the opportunity to consider and
address your comments, please carefully follow the instructions in the
Public Participation section beginning on page 4.
With this notice, we are asking agencies with jurisdiction by law
and/or special expertise with respect to the environmental issues of
this project to formally cooperate with us in the preparation of the
EA.\3\ Agencies that would like to request cooperating agency status
should follow the instructions for filing comments provided under the
Public Participation section of this notice.
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Sec. 1501.6.
---------------------------------------------------------------------------
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultation
with the Pennsylvania State Historic Preservation Office (SHPO), and to
solicit their views and those of other government agencies, interested
Indian tribes, and the public on the project's potential effects on
historic properties.\4\ We will define the project-specific Area of
Potential Effects (APE) in consultation with the SHPO as the project
develops. On natural gas facility projects, the APE at a minimum
encompasses all areas subject to ground disturbance (examples include
construction right-of-way, contractor/pipe storage yards, compressor
stations, and access roads). Our EA for this project will document our
findings on the impacts on historic properties and summarize the status
of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register for Historic
Places.
---------------------------------------------------------------------------
[[Page 68764]]
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the project. Your comments should focus on
the potential environmental effects, reasonable alternatives, and
measures to avoid or lessen environmental impacts. The more specific
your comments, the more useful they will be. To ensure that your
comments are timely and properly recorded, please send your comments so
that the Commission receives them in Washington, DC on or before
December 10, 2012.
For your convenience, there are three methods which you can use to
submit your comments to the Commission. In all instances please
reference the project docket number (CP13-3-000) with your submission.
The Commission encourages electronic filing of comments and has expert
staff available to assist you at (202) 502-8258 or efiling@ferc.gov.
(1) You can file your comments electronically using the eComment
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. This is an easy method for interested persons to
submit brief, text-only comments on a project;
(2) You can file your comments electronically using the eFiling
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. With eFiling, you can provide comments in a
variety of formats by attaching them as a file with your submission.
New eFiling users must first create an account by clicking on
``eRegister.'' You must select the type of filing you are making. If
you are filing a comment on a particular project, please select
``Comment on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the following address: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC
20426.
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials; Native
American Tribes; other interested parties; and local libraries and
newspapers. This list also includes all affected landowners (as defined
in the Commission's regulations) who are current right-of-way grantors,
whose property may be used temporarily for project purposes, or who own
homes within certain distances of aboveground facilities, and anyone
who submits comments on the project. We will update the environmental
mailing list as the analysis proceeds to ensure that we send the
information related to this environmental review to all individuals,
organizations, and government entities interested in and/or potentially
affected by the proposed project.
If we publish and distribute the EA, copies will be sent to the
environmental mailing list for public review and comment. If you would
prefer to receive a paper copy of the document instead of the CD
version or would like to remove your name from the mailing list, please
return the attached Information Request (appendix 2).
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an ``intervenor'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
An intervenor formally participates in the proceeding by filing a
request to intervene. Instructions for becoming an intervenor are in
the User's Guide under the ``e-filing'' link on the Commission's Web
site.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number,
excluding the last three digits in the Docket Number field (i.e., CP13-
3). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: November 9, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012-27958 Filed 11-15-12; 8:45 am]
BILLING CODE 6717-01-P