DEPARTMENT OF DEFENSE

Defense Acquisition Regulations System

48 CFR Parts 204, 215, 217, 219, 225, 239, 241, 242, and 252

RIN 0750-AH49


Defense Federal Acquisition Regulation Supplement: Definition of 
Cost or Pricing Data (DFARS Case 2011-D040)

AGENCY: Defense Acquisition Regulations System, Department of Defense 
(DoD).

ACTION: Final rule.

-----------------------------------------------------------------------

SUMMARY: DoD is issuing a final rule to amend the Defense Federal 
Acquisition Regulation Supplement (DFARS) to update the text to reflect 
the distinction between ``certified cost or pricing data'' and ``data 
other than certified cost or pricing data.'' The DFARS changes are 
necessary to ensure consistency with the Federal Acquisition Regulation 
(FAR) which had been amended to clarify the distinction between those 
terms, as well as the requirements for the submission of cost or 
pricing data.

DATES: December 31, 2012.

FOR FURTHER INFORMATION CONTACT: Mr. Mark Gomersall, telephone 571-372-
6099.

SUPPLEMENTARY INFORMATION: 

I. Background

    DoD published a proposed rule in the Federal Register at 77 FR 2680 
on January 19, 2012. The comment period closed on March 19, 2012. This 
final rule updates the DFARS for consistency with FAR changes 
addressing the definition of cost or pricing data which clarified the 
distinction between ``certified cost or pricing data'' and ``data other 
than certified cost or pricing data,'' as well as the requirements for 
the submission of cost or pricing data (75 FR 53135, August 30, 2010).

II. Discussion and Analysis

    Two respondents submitted comments. One respondent supported the 
rule without further comment, and the second respondent's comment was 
non-substantive. Therefore, the DFARS is revised as proposed.

III. Executive Orders 12866 and 13563

    Executive Orders (E.O.s) 12866 and 13563 direct agencies to assess 
all costs and benefits of available regulatory alternatives and, if 
regulation is necessary, to select regulatory approaches that maximize 
net benefits (including potential economic, environmental, public 
health and safety effects, distributive impacts, and equity). E.O. 
13563 emphasizes the importance of quantifying both costs and benefits, 
of reducing costs, of harmonizing rules, and of promoting flexibility. 
This is not a significant regulatory action and, therefore, was not 
subject to review under section 6(b) of E.O. 12866, Regulatory Planning 
and Review, dated September 30, 1993. This rule is not a major rule 
under 5 U.S.C. 804.

IV. Regulatory Flexibility Act

    DoD does not expect this rule to have a significant economic impact 
on a substantial number of small entities within the meaning of the 
Regulatory Flexibility Act, 5 U.S.C. 601, et seq., because the rule 
merely aligns the DFARS with the FAR. However, a final regulatory 
flexibility analysis has been performed consistent with 5 U.S.C. 604. 
This rule amends the DFARS to update the text addressing the definition 
of cost or pricing data by inserting the word ``certified'' in front of 
``cost or pricing data.'' The DFARS changes are necessary to ensure 
consistency with the FAR. The rule does not expand or diminish the 
existing rights of the contracting officer to obtain cost data or 
pricing data. Instead, this rule will benefit all entities, both large 
and small, by clarifying the requirements for the submission of 
``certified cost or pricing data'' and ``data other than certified cost 
or pricing data.'' No comments were received in response to the initial 
regulatory flexibility analysis published with the proposed rule on 
January 19, 2012. No comments were filed by the Chief Counsel for 
Advocacy of the Small Business Administration in response to the rule. 
The rule does not require any reporting, recordkeeping, or other 
compliances, or compel contractors to expend significant effort or 
cost. No known significant alternatives to the rule have been 
identified. A copy of the analysis may be obtained from the point of 
contact specified herein.

V. Paperwork Reduction Act

    The rule does not contain any information collection requirements 
that require the approval of the Office of Management and Budget under 
the Paperwork Reduction Act (44 U.S.C chapter 35).

List of Subjects in 48 CFR Parts 204, 215, 217, 219, 225, 239, 241, 
242, and 252

    Government procurement.

Manuel Quinones,
Editor, Defense Acquisition Regulations System.

    Therefore, DoD amends 48 CFR parts 204, 215, 217, 219, 225, 239, 
241, 242, 244, and 252 as follows:

0
1. The authority citation for 48 CFR parts 204, 215, 217, 219, 225, 
239, 241, 242, and 252 continues to read as follows:

    Authority: 41 U.S.C. 1303 and 48 CFR chapter 1.

PART 204--ADMINISTRATIVE MATTERS


204.805   [Amended]

0
2. Section 204.805 is amended in paragraph (5) by removing ``subject to 
cost or pricing data'' and adding ``subject to certified cost or 
pricing data'' in its place.

PART 215--CONTRACTING BY NEGOTIATION

0
3. Section 215.403 is amended by revising the section heading to read 
as follows:


215.403   Obtaining certified cost or pricing data.


215.403-1   [Amended]

0
4. Section 215.403-1 is amended by--
0
a. In paragraph (b) and the heading of paragraph (c) removing ``cost or 
pricing data requirements'' and adding ``certified cost or pricing data 
requirements'' in its place;
0
b. In paragraph (c)(4)(C) and the introductory text of paragraph 
(c)(4)(D) removing ``cost or pricing data'' and adding ``certified cost 
or pricing data'' in its place;
0
c. In paragraph (c)(4)(D)(1) removing ``information other than cost or 
pricing

[[Page 76940]]

data'' and adding ``data other than certified cost or pricing data'' in 
its place; and
0
d. In paragraph (c)(4)(D)(2) removing ``Cost or pricing data'' and 
adding ``Certified cost or pricing data'' in its place and removing 
``cost or pricing data threshold'' and adding ``certified cost or 
pricing data threshold'' in its place.

0
5. Section 215.403-3 is amended by revising the section heading to read 
as follows:


215.403-3   Requiring data other than certified cost or pricing data.

* * * * *


215.404-1   [Amended]

0
6. Section 215.404-1 is amended in paragraph (2)(i) by removing the 
word ``information'' and adding the word ``data'' in its place.


215.404-2   [Amended]

0
7. Section 215.404-2 is amended by revising the section heading to read 
as follows:


215.404-2   Data to support proposal analysis.

* * * * *


215.404-4   [Amended]

0
8. Section 215.404-4 is amended by--
0
a. In the introductory text of paragraph (b)(1) removing ``cost or 
pricing data'' and adding ``certified cost or pricing data'' in its 
place; and
0
b. In paragraph (c)(2)(C)(1)(i) removing ``cost or pricing data 
threshold'' and adding ``certified cost or pricing data threshold'' in 
its place.


215.407-5-70   [Amended]

0
9. Section 215.407-5-70 is amended in paragraphs (b)(2)(i) and (ii) by 
removing ``cost or pricing data'' and adding ``certified cost or 
pricing data'' in its place.


215.408   [Amended]

0
10. Section 215.408 is amended by--
0
a. In paragraphs (1)(i) through (iii) by removing ``Cost or Pricing 
Data'' and adding ``Certified Cost or Pricing Data'' in its place;
0
b. In paragraph (2) by removing ``cost or pricing data'' and adding 
``certified cost or pricing data'' in its place.

PART 217--SPECIAL CONTRACTING METHODS


217.7401   [Amended]

0
11. Section 217.7401 is amended by--
0
a. In the introductory text of paragraph (c) by removing the word 
``information'' and adding the word ``data'' in its place;
0
b. In paragraph (c)(1) by removing ``Information in the proposal'' and 
adding ``Data in the proposal'' in its place; and
0
c. In paragraph (c)(2) by removing the word ``information'' and adding 
the word ``data'' in its place.


217.7406  [Amended]

    12. Section 217.7406 is amended in paragraph (b)(3) by removing 
``of cost or pricing data'' and adding ``of certified cost or pricing 
data'' in its place and removing ``and cost or pricing data'' and 
adding ``and certified cost or pricing data'' in its place.

PART 219--SMALL BUSINESS PROGRAMS


219.806  [Amended]

0
13. Section 219.806 is amended in paragraph (1) by removing ``cost or 
pricing data'' and adding ``certified cost or pricing data'' in its 
place and removing ``FAR Subpart 15.4'' and adding ``FAR subpart 15.4'' 
in its place.

PART 225--FOREIGN ACQUISITION


225.7303  [Amended]

0
14. Section 225.7303 is amended in paragraph (b) by removing ``cost or 
pricing data'' and adding ``certified cost or pricing data'' in its 
place.


225.7304  [Amended]

0
15. Section 225.7304 is amended by--
0
a. In paragraph (c) by removing ``cost or pricing data'' and adding 
``certified cost or pricing data'' in its place,
0
b. In paragraph (e)(3) by removing ``cost or pricing data'' and adding 
``certified cost or pricing data'' in its place, and removing ``Subpart 
201.4'' and adding ``subpart 201.4'' in its place, and
0
c. In paragraph (h) by removing ``additional information concerning'' 
and adding ``additional data concerning'' in its place and removing 
``sufficient information to'' and adding ``sufficient data to 
demonstrate'' in its place and removing ``This information--'' and 
adding ``This data--'' in its place.

PART 239-- ACQUISITION OF INFORMATION TECHNOLOGY

0
16. Section 239.7406 is revised to read as follows:


239.7406  Certified cost or pricing data and data other than certified 
cost or pricing data.

    (a) Common carriers are not required to submit certified cost or 
pricing data before award of contracts for tariffed services. Rates or 
preliminary estimates quoted by a common carrier for tariffed 
telecommunications services are considered to be prices set by 
regulation within the provisions of 10 U.S.C. 2306a. This is true even 
if the tariff is set after execution of the contract.
    (b) Rates or preliminary estimates quoted by a common carrier for 
nontariffed telecommunications services or by a noncommon carrier for 
any telecommunications service are not considered prices set by law or 
regulation.
    (c) Contracting officers shall obtain sufficient data to determine 
that the prices are reasonable in accordance with FAR 15.403-3 or 
15.403-4. See PGI 239.7406 for examples of instances where additional 
data may be necessary to determine price reasonableness.

PART 241-- ACQUISITION OF UTILITY SERVICES


241.201  [Amended]

0
17. Section 241.201 is amended in paragraph (3)(ii) by removing ``cost 
or pricing data'' and adding ``certified cost or pricing data'' in its 
place and removing ``FAR Subpart 15.4'' and adding ``FAR subpart 15.4'' 
in its place.

PART 242-- CONTRACT ADMINISTRATION AND AUDIT SERVICES


242.7203  [Amended]

0
18. Section 242.7203 is amended in paragraph (b) by removing ``cost or 
pricing data'' and adding ``certified cost or pricing data'' in its 
place.


242.7301  [Amended]

0
19. Section 242.7301 is amended in paragraph (c) by removing the word 
``Subparts'' and adding the word ``subparts'' in its place.


242.7302  [Amended]

0
20. Section 242.7302 is amended by--
0
a. In paragraph (a)(2) by removing ``cost or pricing data'' and adding 
``certified cost or pricing data'' in its place.
0
b. In paragraph (b)(1) by removing ``Information reveals'' and adding 
``Data reveals'' in its place.


242.7502  [Amended]

0
21. Section 242.7502 is amended in paragraph (g)(3)(ii) by removing 
``cost or pricing data'' and adding ``certified cost or pricing data'' 
in its place.

PART 252--SOLICITATION PROVISIONS AND CONTRACT CLAUSES


252.209-7009  [Amended]

0
22. Section 252.209-7009 is amended by removing the clause date ``(DEC

[[Page 76941]]

2010)'' and adding ``(DEC 2012)'' in its place, redesignating 
paragraphs (a)(1) and (2) as (a)(i) and (ii), and in newly designated 
paragraph (a)(i) removing ``cost or pricing data'' and adding 
``certified cost or pricing data'' in its place.


252.215-7000  [Amended]

0
23. Section 252.215-7000 is amended by removing the clause date ``(DEC 
1991)'' and adding ``(DEC 2012)'' in its place and removing ``Cost or 
Pricing Data-Modifications'' and adding ``Certified Cost or Pricing 
Data-Modifications'' in its place wherever it appears.


252.215-7002  [Amended]

0
24. Section 252.215-7002 is amended by--
0
a. Removing the clause date ``(FEB 2012)'' and adding ``(DEC 2012)'' in 
its place;
0
b. In the definition of ``Significant Deficiency'' in paragraph (a), 
removing ``rely upon information'' and adding ``rely upon data and 
information'' in its place;
0
c. In paragraph (d)(1) removing ``protect the information as 
privileged'' and adding ``protect the data and information as 
privileged'' in its place;
0
d. In paragraph (d)(4)(ix) removing the word ``information'' and adding 
the word ``data'' in its place; and
0
e. In paragraph (d)(4)(xi) removing ``Integrate information available'' 
and adding ``Integrate data and information available'' in its place.


252.217-7027  [Amended]

0
25. Section 252.217-7027 is amended by removing the clause date ``(OCT 
1998)'' and adding ``(DEC 2012)'' in its place, in paragraph (a) 
removing ``cost or pricing data'' and adding ``certified cost or 
pricing data'' in its place, and in paragraph (b) removing ``cost or 
pricing data'' and adding ``certified cost or pricing data'' in its 
place.


252.243-7002  [Amended]

0
26. Section 252.243-7002 is amended by removing the clause date ``(MAR 
1998)'' and adding ``(DEC 2012)'' in its place, in paragraph (c)(1) 
removing ``Cost or pricing data'' and adding ``Certified cost or 
pricing data,'' in its place, and in paragraph (c)(2) removing 
``Information other than cost or pricing data'' and adding ``Data other 
than certified cost or pricing data'' in its place and removing ``cost 
or pricing data'' and adding ``certified cost or pricing data'' in its 
place.
[FR Doc. 2012-31088 Filed 12-28-12; 8:45 am]
BILLING CODE 5001-06-P