[Federal Register Volume 78, Number 17 (Friday, January 25, 2013)]
[Rules and Regulations]
[Pages 5268-5276]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-01507]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
18 CFR Parts 2 and 35
[Docket Nos. AD12-9-000 and AD11-11-000]
Allocation of Capacity on New Merchant Transmission Projects and
New Cost-Based, Participant-Funded Transmission Projects; Priority
Rights to New Participant-Funded Transmission
AGENCY: Federal Energy Regulatory Commission, Energy.
ACTION: Final Policy Statement.
-----------------------------------------------------------------------
SUMMARY: The Commission issues this final policy statement to clarify
and refine its policies governing the allocation of capacity for new
merchant transmission projects and new nonincumbent, cost-based,
participant-funded transmission projects. Under this policy statement,
the Commission will allow developers of such projects to select a
subset of customers, based on not unduly discriminatory or preferential
criteria, and negotiate directly with those customers to reach
agreement on the key rates, terms, and conditions for procuring up to
the full amount of transmission capacity, when the developers broadly
solicit interest in the project from potential customers, and
demonstrate to the Commission that the developer has satisfied the
solicitation, selection and negotiation process criteria set forth
herein. The Commission is making these clarifications and refinements
to fulfill its statutory responsibility of preventing undue
discrimination and undue preference while providing developers the
ability to bilaterally negotiate rates, terms, and conditions for the
full amount of transmission capacity with potential customers. These
clarifications and refinements will be implemented within the
Commission's existing four-factor analysis used to evaluate requests
for negotiated rate authority for transmission service. The Commission
will apply this policy statement on a prospective basis to filings
received after this issuance.
DATES: These policies became effective January 17, 2013.
FOR FURTHER INFORMATION CONTACT:
Becky Robinson, Office of Energy Policy and Innovation, Federal Energy
Regulatory Commission, 888 First Street NE., Washington, DC 20426,
(202) 502-8868, becky.robinson@ferc.gov;
Andrew Weinstein, Office of General Counsel, Federal Energy Regulatory
Commission, 888 First Street NE., Washington, DC 20426, (202) 502-6230,
andrew.weinstein@ferc.gov;
Brian Bak, Office of Energy Policy and Innovation, Federal Energy
Regulatory Commission, 888 First Street NE., Washington, DC 20426,
(202) 502-6574, brian.bak@ferc.gov.
SUPPLEMENTARY INFORMATION:
Before Commissioners: Jon Wellinghoff, Chairman; Philip D. Moeller,
John R. Norris, Cheryl A. LaFleur, and Tony T. Clark.
Final Policy Statement
(Issued January 17, 2013)
I. Introduction
1. The Commission issues this final policy statement to clarify and
refine its policies governing the allocation of capacity for new
merchant transmission projects and new nonincumbent, cost-based,
participant-funded transmission projects. Under this policy statement,
the Commission will allow developers of such projects to select a
subset of customers, based on not unduly discriminatory or preferential
criteria, and negotiate directly with those customers to reach
agreement on the key rates, terms, and conditions for procuring up to
the full amount of transmission capacity, when the developers (1)
broadly solicit interest in the project from potential customers, and
(2) demonstrate to the Commission that the developer has satisfied the
solicitation, selection and negotiation process criteria set forth
herein. The Commission is making these clarifications and refinements
to fulfill its statutory responsibility of preventing undue
discrimination and undue preference while providing developers the
ability to bilaterally negotiate rates, terms, and conditions for the
full amount of transmission capacity with potential customers. These
clarifications and refinements will be implemented within the
Commission's existing four-factor analysis used to evaluate requests
for negotiated rate authority for transmission service.\1\ The
Commission will apply this policy statement on a prospective basis to
filings received after this issuance.
---------------------------------------------------------------------------
\1\ See infra note 6 and P 15.
---------------------------------------------------------------------------
II. Background
2. The Commission first granted negotiated rate authority to a
merchant transmission project developer over a decade ago, finding that
merchant transmission can play a useful role in expanding competitive
generation alternatives for customers.\2\ Unlike traditional utilities
recovering their costs-of-service from captive and wholesale customers,
investors in merchant transmission projects assume the full market risk
of development.\3\ Over the course of a number of early proceedings,
the Commission developed ten criteria to guide its analysis in making a
determination as to whether negotiated rate authority would be just and
reasonable for a given merchant transmission project.\4\ Two of these
criteria were that (1) an open season process should be employed to
initially allocate all transmission capacity and (2) the results of the
open season should be posted on an Open Access Same-Time Information
System (OASIS) and filed in a report with the Commission.\5\
---------------------------------------------------------------------------
\2\ TransEnergie U.S., Ltd., 91 FERC ] 61,230, at 61,838 (2000)
(TransEnergie).
\3\ Id. at 61,836.
\4\ Id.; Neptune Regional Transmission System, LLC, 96 FERC ]
61,147, at 61,633 (2001) (Neptune); Northeast Utilities Service Co.,
97 FERC ] 61,026, at 61,075 (2001) (Northeast Utilities I);
Northeast Utilities Service Co., 98 FERC ] 61,310, at 62,327 (2002)
(Northeast Utilities II).
\5\ The ten criteria were: (1) The merchant transmission
facility must assume full market risk; (2) the service should be
provided under the open access transmission tariff (OATT) of the
Independent System Operator (ISO) or Regional Transmission
Organization (RTO) that operates the merchant transmission facility
and that operational control be given to that ISO or RTO; (3) the
merchant transmission facility should create tradable firm secondary
transmission rights; (4) an open season process should be employed
to initially allocate transmission rights; (5) the results of the
open season should be posted on the OASIS and filed in a report to
the Commission; (6) affiliate concerns should be adequately
addressed; (7) the merchant transmission facility not preclude
access to essential facilities by competitors; (8) the merchant
transmission facilities should be subject to market monitoring for
market power abuse; (9) physical energy flows on merchant
transmission facilities should be coordinated with, and subject to,
reliability requirements of the relevant ISO or RTO; and (10)
merchant transmission facilities should not impair pre-existing
property rights to use the transmission grids of inter-connected
RTOs or utilities. E.g., Northeast Utilities I, 97 FERC ] 61,026 at
61,075.
---------------------------------------------------------------------------
3. In recent years, a number of merchant and nontraditional
transmission developers have sought guidance from the Commission
regarding application of open access principles to new transmission
facilities through petitions for declaratory orders. As the Commission
addressed these requests, its policies evolved over time to provide
potential customers adequate opportunities to obtain service while also
providing transmission developers adequate certainty to assist with
financing transmission projects. As a result of these evolving
policies,
[[Page 5269]]
different rules have been adopted regarding capacity allocation for
merchant transmission projects and nonincumbent, cost-based,
participant-funded transmission projects.
4. In Chinook, the Commission refined its approach to evaluating
merchant transmission by adopting a four-factor analysis.\6\ Under this
analysis, the Commission continues to rely upon an open season and a
post-open season report as a means to provide transparency in the
allocation of initial transmission capacity and ensure against undue
discrimination among potential customers in the award of transmission
capacity. Specifically, the Commission evaluates the terms and
conditions of the open season as part of ensuring no undue
discrimination (second factor),\7\ and uses the open season as an added
protection in overseeing any affiliate participation, to ensure no
undue preference or affiliate concerns (third factor).
---------------------------------------------------------------------------
\6\ The four factors are: (1) The justness and reasonableness of
rates; (2) the potential for undue discrimination; (3) the potential
for undue preference, including affiliate preference; and (4)
regional reliability and operational efficiency requirements. E.g.,
Chinook Power Transmission, LLC, 126 FERC ] 61,134, at P 37 (2009)
(Chinook).
\7\ Also, the Commission looks to a developer's own OATT
commitments or its commitment to turn operational control over to an
RTO or ISO. See id. P 40. Guidance given in this policy statement
with regards to satisfying the second factor is directed at the open
season requirement; the Commission will continue to require merchant
and other transmission developers either to file an OATT or to turn
over control to an RTO or ISO.
---------------------------------------------------------------------------
5. The Chinook order also marked a change in Commission policy on
capacity allocation, as in that order the Commission for the first time
authorized developers to allocate some portion of capacity through
anchor customer presubscription, while requiring that the remaining
portion be allocated in a subsequent open season. The Commission
implemented this policy to achieve the dual goals of requiring an open
season process that ensures capacity on a merchant transmission project
is allocated transparently in an open, fair, and not unduly
discriminatory manner, while permitting an anchor customer model that
enables developers of merchant transmission projects to meet the
financial challenges unique to merchant transmission development.\8\
Since the Chinook order, the Commission has issued orders on several
new merchant and other nontraditional transmission development
proposals, including granting requests to allocate up to 75 percent of
a transmission project's capacity to anchor customers.\9\
---------------------------------------------------------------------------
\8\ See id. P 46.
\9\ See, e.g., Champlain Hudson Power Express, Inc., 132 FERC ]
61,006 (2010); Rock Island Clean Line LLC, 139 FERC ] 61,142 (2012);
Southern Cross Transmission LLC, 137 FERC ] 61,207 (2011).
---------------------------------------------------------------------------
6. The Commission also has received proposals from transmission
developers regarding the allocation of capacity on cost-based,
participant-funded transmission projects. These proceedings involved
incumbent transmission developers,\10\ while one involved a
nonincumbent transmission developer.\11\ In NU/NSTAR, the Commission
approved the structure of a transaction whereby a customer was granted
usage rights to transmission capacity in exchange for funding the
transmission expansion, under the reasoning that any potential
transmission customer has the right to request transmission service
expansion from a transmission owning utility, and that utility is
obligated to make any necessary system expansions and offer service at
the higher of an incremental cost or an embedded cost rate to the
transmission customer. More recently, in National Grid, the Commission
found again that participant funding of transmission projects by
incumbent transmission providers is not inconsistent with the
Commission's open access requirements.\12\ Cost-based participant-
funded projects are similar to merchant projects in that both involve
willing customers assuming part of the risk of a transmission project
in return for defined capacity rights; i.e., there is no direct
assignment of costs to captive customers. Cost-based participant-funded
projects differ between incumbents and nonincumbents, in that incumbent
transmission providers have a clearly defined set of existing
obligations under their tariffs for the expansion of their existing
transmission facilities, whereas nonincumbents have no existing
obligation to build any transmission facilities.
---------------------------------------------------------------------------
\10\ See, e.g., Northeast Utilities Service Company, NSTAR
Electric Company, 127 FERC ] 61,179 (2009) (NU/NStar), order denying
reh'g and clarification, 129 FERC ] 61,279 (2009); National Grid
Transmission Services Corporation and Bangor Hydro Electric Company,
139 FERC ] 61,129 (2012) (National Grid).
\11\ See Grasslands Renewable Energy, LLC, 133 FERC ] 61,225
(2010).
\12\ National Grid, 139 FERC ] 61,129 at P 29.
---------------------------------------------------------------------------
A. Technical Conference and Workshop
7. To gain feedback regarding the Commission's capacity allocation
policies, the Commission held a technical conference in March 2011 to
discuss the extent to which nonincumbent developers of transmission
should be provided flexibility in the allocation of rights to use
transmission facilities developed on a cost-of-service or negotiated
rate basis.\13\ Participants at that conference and subsequent
commenters acknowledged the value in widely soliciting new customers,
but they also expressed the desire to be able to allocate 100 percent
of their projects' capacity through bilateral negotiations with
identified customers.\14\ Based on these comments, the Commission held
a follow up workshop in February 2012 to obtain input on potential
reforms to the Commission's capacity allocation policies.\15\ Many
participants at the 2012 workshop emphasized that a bilateral exchange
of information is necessary to address the unique needs of developers
and their potential customers, and that a rigid open season process
does not allow for bilateral exchanges. However, other commenters at
the 2012 workshop voiced concerns with the merchant transmission model
in general, and discouraged the Commission from pursuing policies that
enable anchor customers to exclude or burden generation competitors or
engage in other abusive practices the Commission sought to eradicate in
Order No. 888.
---------------------------------------------------------------------------
\13\ ``Priority Rights to New Participant-Funded Transmission,''
Docket No. AD11-11-000, March 15, 2011. This technical conference
also addressed generator lead lines, but those facilities are not
the subject of this proposed policy statement.
\14\ See, e.g., Clean Line Energy Partners May 5, 2011 Comments
at 7; LS Power Transmission, LLC May 5, 2011 Comments at 3-4;
Transmission Developers, Inc. May 5, 2011 Comments at 4-5; Western
Independent Transmission Group May 5, 2011 Comments at 6; and
Tonbridge Power Inc. April 19, 2011 Comments at 2.
\15\ ``Allocation of Capacity on New Merchant Transmission
Projects and New Cost-Based, Participant-Funded Transmission
Projects,'' Docket No. AD12-9-000 (February 28, 2012).
---------------------------------------------------------------------------
B. Proposed Policy Statement
8. Informed by the discussion at the workshop and technical
conference and by comments filed afterwards, the Commission in July
2012 issued a proposed policy statement on the allocation of capacity
on new merchant transmission projects and new cost-based, participant-
funded transmission projects. The Commission proposed to allow
developers of new merchant transmission projects and new nonincumbent
cost-based, participant-funded transmission projects to select a subset
of customers, based on not unduly discriminatory or preferential
criteria, and negotiate directly with those customers to reach
agreement on the rates, terms, and conditions for procuring capacity.
The proposed policy would allow such direct negotiations
[[Page 5270]]
when the developers (1) broadly solicit interest in the project from
potential customers, and (2) demonstrate to the Commission that the
developer has satisfied the solicitation, selection, and negotiation
process criteria set forth in the proposed policy statement. Such
proposed policy would also allow the developer to allocate up to 100
percent of the capacity on a transmission project to a single customer,
including an affiliate, if the developer has satisfied the obligations
set forth in the proposed policy statement.
9. The Commission received comments on the proposed policy
statement from 18 entities.\16\ As a general matter, the proposed
policy statement received broad support in the comments received,
albeit there were some comments in opposition. In addition, the
Commission received requests to clarify the policies articulated in the
proposed policy statement. We summarize here the general comments in
support and in opposition to the proposed policy statement, with
comments requesting clarification noted in the discussion of specific
elements of this final policy statement.
---------------------------------------------------------------------------
\16\ American Antitrust Institute (AAI); American Electric Power
Services Corporation (AEP); American Public Power Association
(APPA); American Wind Energy Association (AWEA); Clean Line Energy
Partners, LLC (Clean Line); Duke Energy Corporation (Duke); Edison
Electric Institute (EEI); LSP Transmission Holdings, LLC (LSP
Transmission); National Grid USA; National Rural Electric
Cooperative Association (NRECA); New Jersey Division of Rate Counsel
(NJ Rate Counsel); New York Transmission Owners (NYTO); Northeast
Utilities Service Company (Northeast Utilities); Pattern
Transmission, LP; Transmission Access Policy Study Group (TAPS);
Transmission Developers, Inc. (TDI); TransWest Express, LLC; and
Western Independent Transmission Group (WITG).
---------------------------------------------------------------------------
10. Many commenters broadly support the proposed policy
statement.\17\ WITG asserts that the proposed policy statement will
give new transmission development momentum by allowing transmission
developers to discuss contractual arrangements, technical
specifications and project timing with prospective customers.\18\ WITG
asserts that, under the proposed policy statement, a transmission
developer will be more able to ``right-size'' its project based on
market interest for the project.\19\ AWEA and NYTO similarly suggest
that the proposed policy statement will allow merchant transmission
developments to be tailored to the needs of the market.\20\ EEI asserts
that the proposed policy statement will allow transmission developers
to identify viable transmission customers early in the process, and
suggests that the flexibility allowed for in the proposed policy
statement will aid funding and enable construction on a timely
basis.\21\ Duke Energy also asserts that the bilateral negotiation
process allowed for in the proposed policy statement will provide the
most efficient and effective way of ensuring that commercial
transmission projects are successfully completed.\22\
---------------------------------------------------------------------------
\17\ AEP; AWEA; Clean Line; Duke; EEI; LSP Transmission; NYTO;
National Grid USA; Northeast Utilities; Pattern Transmission, LP;
TDI; TransWest Express, LLC; and WITG.
\18\ WITG at 3.
\19\ WITG at 4.
\20\ AWEA at 3; NYTO at 2.
\21\ EEI at 5.
\22\ Duke at 3.
---------------------------------------------------------------------------
11. AWEA emphasizes the importance of merchant transmission
development in removing barriers to the development of renewable
energy.\23\ AWEA notes that the proposed policy statement will allow
transmission developers to provide incentives to first-movers, which
should encourage potential transmission customers to negotiate with
developers early in the development process. In contrast, AWEA asserts
that, under current Commission policy, ``a prospective transmission
customer has no economic incentive to commit to a capacity allocation
early during the development process because that customer can obtain
the same terms, and conditions during the open season auction without
taking any development risk.'' \24\
---------------------------------------------------------------------------
\23\ AWEA at 6.
\24\ AWEA at 6.
---------------------------------------------------------------------------
12. However, APPA, NRECA, NJ Rate Counsel and TAPS argue that
changes to our capacity allocation policies are unnecessary, run
counter to our open access principles, and are inconsistent with our
obligations under the Federal Power Act (FPA). These commenters argue
that the Commission's proposal to allow allocation of 100 percent of a
merchant's capacity through bilateral negotiations is counter to the
Commission's core obligation under sections 205, 206, and 217(b)(4)
\25\ of the FPA, compromises the open access principles at the core of
Order Nos. 888,\26\ 890 \27\ and 1000,\28\ and will result in an
unjust, unreasonable, and unduly discriminatory paradigm.\29\ For
example, TAPS argues that the Commission should not relax its merchant
policies but should instead continue to require a substantial portion
of the capacity to be made available to other customers, through an
open season, on the same rates and terms as are applied to the anchor
customer(s).\30\
---------------------------------------------------------------------------
\25\ APPA and NRECA argue the Commission has ignored its
statutory obligation under FPA section 217(b)(4) that directs the
Commission to facilitate the planning and expansion of transmission
facilities to meet the reasonable needs of load-serving entities to
satisfy their service obligations. APPA at 12; NRECA at 11-12.
\26\ Promoting Wholesale Competition Through Open Access Non-
Discriminatory Transmission Services by Public Utilities; Recovery
of Stranded Costs by Public Utilities and Transmitting Utilities,
Order No. 888, FERC Stats. & Regs. ] 31,036 (1996), order on reh'g,
Order No. 888-A, FERC Stats. & Regs. ] 31,048, order on reh'g, Order
No. 888-B, 81 FERC ] 61,248 (1997), order on reh'g, Order No. 888-C,
82 FERC ] 61,046 (1998), aff'd in relevant part sub nom.
Transmission Access Policy Study Group v. FERC, 225 F.3d 667 (DC
Cir. 2000), aff'd sub nom. New York v. FERC, 535 U.S. 1 (2002).
\27\ Preventing Undue Discrimination and Preference in
Transmission Service, Order No. 890, FERC Stats. & Regs. ] 31,241,
order on reh'g, Order No. 890-A, FERC Stats. & Regs. ] 31,261
(2007), order on reh'g, Order No. 890-B, 123 FERC ] 61,299 (2008),
order on reh'g, Order No. 890-C, 126 FERC ] 61,228 (2009), order on
clarification, Order No. 890-D, 129 FERC ] 61,126 (2009).
\28\ Transmission Planning and Cost Allocation by Transmission
Owning and Operating Public Utilities, Order No. 1000, FERC Stats. &
Regs. ] 31,323 (2011), order on reh'g, Order No. 1000-A, 139 FERC ]
61,132, order on reh'g, Order No. 1000-B, 141 FERC ] 61,044 (2012).
\29\ APPA at 3; NJ Rate Counsel at 4-9; NRECA at 4-9, 12; and
TAPS at 10. TAPS argues that the Commission's proposed policy
statement will (1) result in undersized, single-purpose merchant
transmission facilities with restricted access, (2) undermine
regional transmission planning processes, (3) balkanize the grid and
impair competitive wholesale markets, and (4) hamstring access to
competitive generation and transmission development. TAPS at 1-5.
\30\ TAPS at 10.
---------------------------------------------------------------------------
13. APPA and NRECA assert that our existing policies already
provide substantial flexibility and have not prevented the development
of merchant transmission projects.\31\ They argue that the incentives
inherent in the Commission's proposed policy statement are poorly
aligned with the Commission's goals. TAPS similarly refutes the claim
that developers have an inherent incentive to widely solicit interest
in merchant transmission projects, arguing that once a developer takes
on an anchor customer, its opportunity and incentives align with that
customer.\32\
---------------------------------------------------------------------------
\31\ APPA at 4; NRECA at 5.
\32\ TAPS at 6-7, 9.
---------------------------------------------------------------------------
14. Further, NJ Rate Counsel argues that the proposed policy
statement may have the unintended consequence of reducing competition
in the long run and thus ultimately increasing the delivered cost of
electricity.\33\ NJ Rate Counsel and TAPS both argue that the
Commission has long recognized that
[[Page 5271]]
transmission is a natural monopoly and that ``the most likely route to
market power in today's electric utility industry lies through
ownership or control of transmission facilities.'' \34\ TAPS and NRECA
underscore concerns over transmission siting fatigue \35\ and right-of-
way limitations, arguing that a small wind developer excluded from a
merchant project is unlikely to be able to reach the market.\36\
---------------------------------------------------------------------------
\33\ NJ Rate Counsel at 4.
\34\ TAPS at 6 (citing Promoting Wholesale Competition Through
Open Access Non-Discriminatory Transmission Services by Public
Utilities; Recovery of Stranded Costs by Public Utilities and
Transmitting Utilities, Order No. 888, FERC Stats. & Regs. ] 31,036
at 31,643). NJ Rate Counsel additionally posits that, in private
negotiations, an anchor tenant that expects to gain market power by
excluding other generators from access to the new transmission
project could seek an allocation of 100 percent of project capacity
in return for an offer to split the anticompetitive gains with the
merchant developer. NJ Rate Counsel at 7.
\35\ Transmission siting fatigue is the idea that, after a
transmission line is sited and permitted in an area, it will be
significantly more difficult to get an additional transmission line
sited and permitted in that same area.
\36\ TAPS at 6; NRECA at 10-11.
---------------------------------------------------------------------------
III. Final Policy Statement
A. Need for Refined Policies Regarding Allocation of Capacity on
Transmission Projects
15. The fundamental concern underlying the second and third factor
of the Commission's four-factor analysis for negotiated rate authority
is that new transmission capacity should be allocated in a not unduly
discriminatory or preferential manner. Based on the Commission's
experience with new merchant transmission projects and on the comments
received in this proceeding, the Commission believes that it can
provide more flexibility in the capacity allocation process for
customers and transmission developers, while still ensuring that the
resulting allocation of new transmission capacity is not unduly
discriminatory or preferential. By adopting the policies herein, the
Commission seeks to encourage merchant transmission developers
intending to seek negotiated rate authority to utilize the guidelines
discussed herein. To the extent the Commission determines that a
merchant transmission developer complies with such policies, the
Commission will find that the developer has satisfied the second (undue
discrimination) and third (undue preference) factors of the four-factor
analysis.\37\
---------------------------------------------------------------------------
\37\ The remaining two Chinook factors, the justness and
reasonableness of rates and regional reliability and operational
efficiency requirements, remain elements of the Commission's
analysis of merchant applications for negotiated rate authority.
---------------------------------------------------------------------------
16. The Commission therefore refines its capacity allocation
policies to allow the developer of a new merchant transmission project
to select a subset of customers, based on not unduly discriminatory or
preferential criteria, and negotiate directly with those customers to
reach agreement on the key rates, terms, and conditions for procuring
up to the full amount of transmission capacity, when the developer (1)
broadly solicits interest in the project from potential customers and
(2) demonstrates to the Commission that the developer has satisfied the
solicitation, selection and negotiation process criteria set forth
herein. This capacity allocation process also will apply to the
developer of a new nonincumbent, cost-based, participant-funded
project.
17. With regard to concerns raised by commenters that the policies
described in the proposed policy statement may compromise open access,
balkanize the grid, or otherwise impair competition, these comments
were taken into account in our development of the capacity allocation
policies set forth herein. We believe that the allocation process
outlined herein will provide the same protections as a formal open
season process, i.e., that a broad notice at the early stages of
project development and rigorous demonstration after the selection of
transmission customers will mirror our earlier requirements. Therefore,
the Commission disagrees that the refinements to our capacity
allocation policies reflected herein are a departure from the
Commission's fundamental policies governing open access and encouraging
competition. Retaining and refining the process by which capacity is
allocated on such projects will increase, rather than impair,
opportunities for customers in need of new transmission service.
18. Specifically, under this final policy statement the Commission
will allow merchant transmission developers to allocate up to 100
percent of their projects' capacity through bilateral negotiations. The
Commission will also allow capacity allocation to affiliates, when done
in a transparent manner with the transparency protections adopted in
this final policy statement, so that other interested parties can voice
concern if they believe the affiliate was treated preferentially at the
expense of another party.
19. The flexibility we afford under the policy outlined below is
complemented by the emphasis on additional detail the Commission will
expect from transmission project developers concerning the process they
utilize to allocate project capacity. The Commission agrees with
commenters that each merchant transmission project has unique project-
specific characteristics that warrant providing such developers
flexibility in negotiating risk-sharing and other details. The
Commission likewise acknowledges that merchant transmission developers
have inherent incentives to solicit interest widely in a potential
project. However, the Commission also appreciates commenter concerns
that counter-incentives may exist that could motivate a developer to
unduly prefer one or more customers. To protect against undue
discrimination and undue preference, the Commission will expect
merchant transmission developers to engage in an open solicitation to
identify potential transmission customers, and to demonstrate to the
Commission that the processes leading to the identification of
customers and execution of relevant capacity arrangements are
consistent with our policies herein and our open access principles. The
Commission believes that this approach, when coupled with the existing
section 206 protections against undue discrimination and undue
preference, serves the interest of customers and developers alike.\38\
---------------------------------------------------------------------------
\38\ See Chinook, 126 FERC ] 61,134 at P 41.
---------------------------------------------------------------------------
20. We recognize that a developer's incentives may change once it
has contracted with a customer for a substantial portion of the
transmission developer's capacity. Indeed, several participants at the
February 2012 workshop noted that part of the reason developers need to
be able to negotiate more freely with potential customers is that there
are a number of details to coordinate between the generation and
transmission projects, recognizing that once a transmission developer
has secured customers, its business success depends on its customers'
success. In this way, the relationship between transmission developer
and transmission customer will inherently resemble that of a joint
venture. We believe the policies described herein ensure that there is
an open, transparent, and fair process to become a transmission
customer, and in particular we believe that the Commission's review of
the post-selection demonstration will help discipline the process. We
further believe the flexibility allowed through bilateral negotiations
is appropriate in light of the risk-sharing inherent in the
relationship between the transmission developer and its customers.
21. The Commission similarly appreciates concerns with respect to
transmission siting fatigue and right-of-way limitations. Under the
policies
[[Page 5272]]
adopted herein, the Commission will evaluate a developer's reasoning
for the sizing of new transmission facilities to ensure that the sizing
of such facilities was based on objective criteria, rather than the
result of undue preference or undue discrimination. In doing so, the
Commission will be cognizant of the potential for undersized
transmission facilities that show an undue preference for one customer
over another, involve undue discrimination against a potential
customer, and/or that, as a result of the anticompetitive nature of the
sizing, result in rates for transmission service that are not just and
reasonable. If the Commission finds that a transmission project is
undersized as the result of undue preference, undue discrimination or
other anticompetitive behavior, the Commission has the authority to
reject the proposed allocation of capacity on such project. Moreover,
entities that believe that such biases resulted in a discriminatory
allocation of capacity will have the opportunity to protest the
transmission developer's post-selection demonstration.\39\ The
Commission can, and has demonstrated that it will, reject unacceptable
proposals for transmission capacity allocation when appropriate.\40\
---------------------------------------------------------------------------
\39\ Such entities remain entitled to exercise their statutory
right to challenge such capacity allocations under section 206 of
the FPA.
\40\ See, e.g., Mountain States Transmission Intertie, LLC and
NorthWestern Corp., 127 FERC ] 61,270 (2009).
---------------------------------------------------------------------------
22. We reaffirm here that all merchant transmission developers and
nonincumbent cost-based, participant-funded transmission projects
become public utilities at the time their projects are energized (and,
depending on the circumstances, may become public utilities even
earlier). Public utility transmission providers are subject to the
Commission's OATT requirements, including the obligation to expand
their transmission systems, if necessary, to provide transmission
service.\41\ This should help to allay concerns about the potential for
undue discrimination and preference with respect to the sizing of these
types of projects.
---------------------------------------------------------------------------
\41\ See Pro Forma Open Access Transmission Tariff Sec.
15.4(a). See also Tres Amigas LLC, 130 FERC ] 61,207, at PP 18, 76,
80 (2010); SunZia Transmission LLC, 131 FERC ] 61,162, at P 43
(2010); SunZia Transmission LLC, 135 FERC ] 61,169, at PP 10-11, 22
(2011); Montana Alberta Tie, Ltd., 119 FERC ] 61,216, at P 7 (2007).
---------------------------------------------------------------------------
B. Merchant Projects
1. Open Solicitation Process
23. Based on the Commission's experience with prior cases and
information received from the technical conference, the workshop, and
in responses to the proposed policy statement, the Commission believes
that bilateral negotiations, if conducted in a transparent manner, may
serve the same purpose as an open season process to ensure against
undue discrimination or preference in the provision of transmission
service. Hence, under this final policy statement, merchant
transmission developers seeking negotiated rate authority may instead
engage in an open solicitation of interest in their projects from
potential transmission customers in lieu of the previous requirement of
a formal open season. Such open solicitation should include a broad
notice issued in a manner that ensures that all potential and
interested customers are informed of the proposed project. For example,
such notice may be placed in trade magazines or regional energy
publications, may include communications with regional transmission
planning groups such as through the Order No. 1000 regional planning
process,\42\ and may use email distribution lists addressing
transmission-related matters. In response to commenters that asked that
we clarify what constitutes broad notice,\43\ we note that these
examples of broad notice are not intended to be exhaustive or
prescriptive. A developer should make reasonable efforts to ensure that
all potential transmission customers would be made aware of the
intention to develop the project.
---------------------------------------------------------------------------
\42\ We note that NJ Rate Counsel suggested that a group's
participation in the Order No. 1000 process could bear on the open
solicitation requirements. NJ Rate Counsel at 12-13.
\43\ See, e.g., Pattern Transmission, LP at 10; WITG at 4.
---------------------------------------------------------------------------
24. Such notice should include transmission developer points of
contact and pertinent project dates, as well as sufficient technical
specifications and contract information to inform interested customers
of the nature of the project, including:
[ssquf] Project size/capacity: MW and/or kV rating (specific value
or range of values)
[ssquf] End points of line (as specific as possible such as points
of interconnection to existing lines and substations, although it may
be potentially broad, such as Montana to Nevada, if the project is very
early in development)
[ssquf] Projected construction and/or in-service dates
[ssquf] Type of line--for example, AC, DC, bi-directional
[ssquf] Precedent agreement (if developed)
[ssquf] Other capacity allocation arrangements (including how it
will address potential oversubscription of capacity)
25. The developer should also specify in the notice the criteria it
plans to use to select transmission customers, such as credit rating;
``first mover'' status (i.e., customers who respond early and take on
greater project risk); and customers' willingness to incorporate
project risk-sharing into their contracts. This will contribute to the
transparency of the process and will help interested entities know at
the outset the features of the project and how the merchant
transmission developer will consider bids. This list of criteria is not
prescriptive or exhaustive.
26. Developers may also adopt a specific set of objective criteria
that they will use to rank prospective customers, provided they can
justify why such criteria are appropriate. Clean Line suggests the
Commission should consider incorporating additional criteria as part of
the capacity allocation process, including: Willingness to pay, length
of term for transmission service, acceptance of proposed business
terms, and the state of advancement in generation project
development.\44\ The Commission believes that, while the additional
criteria suggested by Clean Line appear reasonable on their face, we
would need additional information to ensure the criteria proposed are
indeed uniformly appropriate and are not discriminatory. Thus, we
decline to incorporate at this time the additional criteria proposed by
Clean Line, though we could consider these types of criteria in a
specific case before the Commission.
---------------------------------------------------------------------------
\44\ Clean Line at 6.
---------------------------------------------------------------------------
27. Finally, the Commission expects the merchant transmission
developer to update its posting if there are any material changes to
the nature of the project or the status of the capacity allocation
process, in particular to ensure that interested entities are informed
of remaining available capacity. As proposed by WITG,\45\ time-stamped
updates on a developer's Web site is one reasonable approach for
alerting interested parties to periodic changes in project information,
provided that the developer's initial broad notice had alerted entities
to the developer's Web site, and to the possibility that changes might
occur and would be posted there.
---------------------------------------------------------------------------
\45\ WITG at 2, 5.
---------------------------------------------------------------------------
28. Under the final policy statement, once a subset of customers
has been identified by the developer through the open solicitation
process, the Commission will allow developers to engage in bilateral
negotiations with each potential customer on the specific rates, terms,
and conditions for
[[Page 5273]]
procuring transmission capacity, as the Commission recognizes that
developers and potential customers may need to negotiate individualized
terms that meet their unique project-specific needs.\46\ In these
negotiations, the Commission will allow for distinctions among
prospective customers based on transparent and not unduly
discriminatory or preferential criteria--so long as the differences in
negotiated terms recognize material differences and do not result in
undue discrimination or preference--with the potential result that a
single customer, including an affiliate, may be awarded up to 100
percent of capacity. For instance, developers might offer ``first
mover'' customers more favorable rates, terms, and conditions than
later customers. This represents a change from prior policy, under
which the Commission required that a developer offer their ``anchor
customer deal'' in the open season to any other customer willing to
make the same commitment as the anchor customer, such that all
customers had access to the same rates, terms, and conditions.\47\ For
reasons discussed above, including the need to negotiate individualized
terms and incent early movers, we conclude that this policy change is
appropriate.
---------------------------------------------------------------------------
\46\ While negotiations for the allocation of initial
transmission rights may address terms and conditions of the
transmission service to be ultimately taken once the facilities are
in service, the Commission will adhere to its policy, regardless of
any negotiated agreement, that any deviations from the Commission's
pro forma OATT must be justified as consistent with or superior to
the pro forma OATT when the transmission developer files its OATT
with the Commission. The Commission will evaluate any deviations on
that basis when they are submitted. See Chinook, 126 FERC ] 61,134
at PP 47, 63.
\47\ See Chinook, 126 FERC ] 61,134 at P 61.
---------------------------------------------------------------------------
2. Post-Selection Demonstration
29. In the past, the Commission required that developers file a
report, shortly after the close of the open season, on the results of
the open season and any anchor customer presubscription, including
information on the notice of the open season, the method used for
evaluating bids, the identity of the parties that purchased capacity,
and the amount, term, and price of that capacity.\48\ The Commission
required this report to provide transparency to the allocation of
initial transmission rights, and to enable unsuccessful bidders to
determine if they were treated in an unduly discriminatory manner so
that they may file a complaint if they believe they were.\49\ These
reports were not noticed, and did not receive Commission action.
---------------------------------------------------------------------------
\48\ Chinook, 126 FERC ] 61,134 at PP 41, 43.
\49\ See Chinook, 126 FERC ] 61,134 at P 41; Montana Alberta
Tie, Ltd., 116 FERC ] 61,071, at P 37 (2006).
---------------------------------------------------------------------------
30. The Commission will continue to require merchant transmission
developers to disclose the results of their capacity allocation
process, though this disclosure will be part of the Commission's
approval of such capacity allocation process, and thus noticed and
acted upon under section 205 of the FPA. Specifically, to provide
transparency, and to prevent against undue discrimination and undue
preference by merchant transmission developers, this final policy
statement expects developers to demonstrate that the processes that led
to the identification of transmission customers and the execution of
the relevant contractual arrangements are consistent with the policies
described herein, and consistent with our open access principles. The
merchant transmission developer should describe the criteria used to
select customers, any price terms, and any risk-sharing terms and
conditions that served as the basis for identifying transmission
customers selected versus those that were not. To this end, and in
response to comments suggesting additional transparency measures,\50\
the Commission will expect that the developer include, at a minimum,
the following information in the demonstration to provide sufficient
transparency to the Commission and interested parties:
---------------------------------------------------------------------------
\50\ AAI at 6-7; TAPS at 13-14.
---------------------------------------------------------------------------
(1) Steps the developer took to provide broad notice, including the
project information and customer evaluation criteria that were relayed
in the broad notice;
(2) Identity of the parties that expressed interest in the project,
placed bids for project capacity, and/or purchased capacity; and the
capacity amounts, terms, and prices involved in that interest, bid, or
purchase;
(3) Basis for the developer's decision to prorate, or not to
prorate, capacity, if a proposed project is oversubscribed;
(4) Basis for the developer's decision not to increase capacity for
a proposed project if it is oversubscribed (including the details of
the economic, technical, or financial infeasibility that is the basis
for declining to increase capacity);
(5) Justification for offering more favorable rates, terms, and
conditions to certain customers, such as ``first movers'' or those
willing to take on greater project risk-sharing;
(6) Criteria used for distinguishing customers and the method used
for evaluating bids. This should include the details of how each
potential transmission customer (including both those who were and
those who were not allocated capacity) was evaluated and compared to
other potential transmission customers, both at the early stage when
the developer chooses with whom to enter into bilateral negotiations
and subsequently when the developer chooses in the negotiation phase to
whom to award transmission capacity;
(7) Explanation of decisions used to select and reject specific
customers. In particular, the report should identify the facts,
including any rates, terms or conditions of agreements unique to
individual customers that led to their selection, and relevant
information about others that led to their rejection. If a selected
customer is an affiliate, the Commission will look more carefully at
the basis for reaching that determination.
31. In response to requests that the Commission clarify when a
transmission developer needs to request approval of its capacity
allocation process,\51\ we will allow a developer discretion in timing
its request that the Commission approve a capacity allocation process.
For example, developers can seek approval of their capacity allocation
approach after having completed the process of selecting customers in
accordance with our policies. Alternatively, a developer can first seek
approval of its capacity allocation approach, and then demonstrate in a
compliance filing to the Commission order approving that approach that
the developer's selection of customers was consistent with the approved
selection process. Under either procedural framework, the Commission
will notice the demonstration, allow protests, and reach a
determination regarding whether the developer's selection of customers
was consistent with our policies herein and our open access
principles.\52\ However, we agree with some commenters that protests
filed in response to the post-selection demonstration should be focused
on the
[[Page 5274]]
matters at issue in the Commission's review.\53\
---------------------------------------------------------------------------
\51\ See, e.g., Pattern Transmission, LP at 13.
\52\ Under this policy statement, the Commission's policies for
reviewing capacity allocation processes will apply equally to both
new merchant transmission developers and new nonincumbent cost-based
participant-funded transmission developers. With respect to new
merchant transmission developers, the Commission's consideration of
this capacity allocation process will be a part of the Commission's
evaluation of the applicant's request for negotiated rate authority.
\53\ See Pattern Transmission, LP at 14; WITG at 6.
---------------------------------------------------------------------------
32. We emphasize that the information in the post-selection
demonstration is an essential part of a merchant developer's request
for approval of a capacity allocation process, and that the developer
will have the burden to demonstrate that its process was in fact not
unduly discriminatory or preferential, and resulted in rates, terms,
and conditions that are just and reasonable. Thus, interested parties
will have the opportunity to submit protests on the demonstration to
ensure there is sufficient transparency. The Commission expects that
interested parties who believe that the process used to select
customers and allocate capacity on merchant transmission projects was
unjust or preferential would file comments or protests on the
demonstration. Interested parties also remain entitled to exercise
their statutory right to challenge the process under section 206 of the
FPA.
33. In response to commenters that request that we recognize the
commercially sensitive nature of the business arrangements associated
with capacity allocation, we clarify that we will address whether to
allow for protection of such information on a case-by-case basis.\54\
We believe transparency is essential to our allowing capacity to be
allocated through bilateral negotiations rather than a more formally
structured open season process. Thus, we do not agree that certain
types of commercial information should be generically protected. To the
extent developers believe they cannot file certain information
publicly, they may make their case for confidential treatment to the
Commission when they file their post-selection demonstrations.
---------------------------------------------------------------------------
\54\ See AEP at 4; AAI at 10-11; Duke at 4; EEI at 5; Pattern
Transmission, LP at 13; and WITG at 6.
---------------------------------------------------------------------------
34. With respect to potential affiliate participation in the
capacity allocation process, the Commission will continue to expect an
affirmative showing that the affiliate is not afforded an undue
preference.\55\ The developer will bear a high burden to demonstrate
that the assignment of capacity to its affiliate and the corresponding
treatment of non-affiliated potential customers is just, reasonable,
and not unduly preferential or discriminatory. While the Commission
will not require non-affiliates to receive the same rates, terms and
conditions as affiliates as suggested by some commenters,\56\ the
Commission will carefully scrutinize any differences in rates, terms
and conditions for affiliates versus non-affiliates to ensure those
differences are appropriately based on objective criteria.
---------------------------------------------------------------------------
\55\ See Chinook, 126 FERC ] 61,134 at PP 49-50.
\56\ See, e.g., TAPS at 26.
---------------------------------------------------------------------------
35. Commenters are concerned that the reporting obligations
described in the proposed policy statement provide inadequate
protections for potential transmission customers. NRECA argues that
discrimination can take place not only in the solicitation of a
project, but also in the design of a project, and that the proposed
reporting requirement would not remedy this flaw.\57\ APPA asserts that
this ``after-the-fact'' reporting requirement is of particular concern,
because the Commission will be under substantial pressure to
rubberstamp an after-the-fact filing because the applicants will have
already completed their contract negotiations and selected successful
customers.\58\ APPA cautions that, if the Commission adopts this
proposed policy despite commenters' concerns, it is critical that the
associated reporting requirements not be eroded over time.\59\
---------------------------------------------------------------------------
\57\ NRECA at 14.
\58\ APPA at 9.
\59\ APPA at 7.
---------------------------------------------------------------------------
36. The Commission believes that the reporting obligations set
forth in this final policy statement offer sufficient protections to
ensure that a capacity allocation process protects against undue
preference or discrimination. In response to commenters that questioned
if any consequences attach to the report or if it is just
informational,\60\ we reiterate that we will notice the demonstration
and consider any protests submitted in reaching our determination on
such demonstration.
---------------------------------------------------------------------------
\60\ See, e.g., TAPS at 17-20.
---------------------------------------------------------------------------
37. Certain commenters argue that the section 206 complaint process
is an insufficient deterrent to undue preference or discrimination in
the capacity allocation process, and that few section 206 complaints
are likely to be filed particularly due to inadequate resources or time
to mount effective section 206 challenges.\61\ In particular, NJ Rate
Counsel is concerned that the filing of section 206 challenges will
depend on the willingness of participants to assume a heavy burden
without attendant discovery rights, and on the need for an expedited
process with no assurance that the process will move quickly.\62\
Similarly, NRECA argues that complainants are unlikely to have access
to some or all of the required information, and NRECA notes that the
Commission has at times dismissed complaints alleging wrong-doing for
lack of specificity.\63\ The NJ Rate Counsel asserts that reliance on
the section 206 complaint process shifts the Commission's independent
regulatory responsibility to third-party complainants, and argues that
the Commission must exercise its independent responsibility to ensure
that rates remain just and reasonable and not unduly
discriminatory.\64\
---------------------------------------------------------------------------
\61\ APPA at 8; AAI at 6; NJ Rate Counsel at 3; NRECA at 14-15.
NRECA adds that the proposed Policy Statement is inconsistent with
the Commission's statement in Order No. 1000-A that, ``individual
complaints under section 206 of the FPA would not suffice to
overcome the free rider problem because litigating complaints
burdens and unduly delays the transmission planning process'' (or in
this case, unduly delay open access to transmission service). NRECA
at 15 (citing Transmission Planning and Cost Allocation by
Transmission Owning and Operating Public Utilities Order No. 1000-A,
139 FERC ] 61,132, at P 577 (2012)).
\62\ NJ Rate Counsel at 3.
\63\ NRECA at 14-15.
\64\ NJ Rate Counsel at 10.
---------------------------------------------------------------------------
38. In response to these comments, we clarify that, under the
processes adopted in this final policy statement, entities will be able
to protest a developer's proposed capacity allocation process (which we
expect to be described in detail as part of the developer's post-
selection demonstration pursuant to section 205 of the FPA). Under this
final policy statement, the Commission will evaluate the capacity
allocation process to ensure that the process was not unduly
discriminatory or preferential, and resulted in rates, terms, and
conditions that are just and reasonable. Entities also remain entitled
to challenge such capacity allocation processes by filing a complaint
under section 206 of the FPA.
C. Nonincumbent, Cost-Based, Participant-Funded Projects
39. The Commission will apply the policy clarifications and
refinements in this final policy statement not only to new merchant
transmission projects, but also to nonincumbent, cost-based,
participant-funded transmission projects. The Commission has similar
concerns regarding the capacity allocation process regardless of
whether the project is a new merchant transmission project, or a
nonincumbent, cost-based, participant-funded transmission project. That
is, the Commission is concerned that access not be unduly
discriminatory or preferential. We believe that the process outlined
herein will address such concerns, however. Commenters and workshop
participants, moreover, support the Commission's application of these
policy clarifications and refinements to both new merchant transmission
developers and
[[Page 5275]]
nonincumbent, cost-based, participant-funded transmission
developers.\65\ Petitions regarding capacity allocation on
nonincumbent, cost-based, participant-funded transmission projects will
be evaluated by the Commission in accordance with the Commission's
responsibilities under the FPA.
---------------------------------------------------------------------------
\65\ TAPS March 29, 2012 Comments at 24; Pathfinder Renewable
Wind Energy, LLC March 28, 2012 Comments at 3-4.
---------------------------------------------------------------------------
40. However, use of this common process does not eliminate the
distinction between these types of projects. In particular, although
the negotiations between developers and potential customers could
address a transmission rate, among other issues, the Commission's
approach to reviewing such a rate would be different for a new merchant
transmission project than for a new nonincumbent, cost-based,
participant-funded transmission project. For a nonincumbent, cost-
based, participant-funded transmission project, the Commission will
review the transmission rate, terms and conditions, including any
agreed upon return on equity, more closely to ensure that they satisfy
Commission precedent regarding cost-based transmission service.
D. Incumbent, Cost-Based, Participant-Funded Projects
41. The Commission is not changing its case-by-case evaluation of
requests for cost-based participant-funded transmission projects by
incumbent transmission providers.\66\ This final policy statement thus
does not affect incumbent transmission development for the purpose of
serving native load. Incumbents differ from nonincumbents in that the
former have a clearly defined set of existing obligations under their
OATTs with regard to new transmission development, including
participation in regional planning processes and the processing of
transmission service request queues. Nonincumbent transmission
developers do not yet own or operate transmission facilities in the
region that they propose to develop transmission; thus, they are not
yet subject to an OATT in that region.\67\ Thus, the Commission's final
policy statement establishes the Commission's process for evaluating,
going forward, the allocation of capacity only for merchant
transmission developers and nonincumbent, cost-based, participant-
funded projects for new transmission facilities.
---------------------------------------------------------------------------
\66\ See, e.g., NU/NSTAR, 127 FERC ] 61,179 (2009), order
denying reh'g and clarification, 129 FERC ] 61,279 (2009); National
Grid, 139 FERC ] 61,129 (2012).
\67\ We clarify, in response to Clean Line, that, for purposes
of this final policy statement, a nonincumbent transmission
developer will not become an incumbent within a transmission
planning region until such time as it energizes a transmission
facility within that region. See Order No. 1000-A, 139 FERC ] 61,132
at P 421.
---------------------------------------------------------------------------
42. In contrast, in most instances, we would expect that an
incumbent transmission provider will be able to use existing processes
set forth in its OATT to allocate capacity on a new transmission
facility. These existing OATT processes do not prohibit incumbent
transmission owners from identifying projects that could be constructed
on a participant-funded basis in conjunction with processing of
transmission service requests or in addition to meeting transmission
needs through participation in a regional transmission planning
process.\68\ Furthermore, the Commission will continue to entertain on
a case-by-case basis requests for waiver of any OATT requirements that
may be needed for the incumbent transmission owner to pursue innovative
transmission development that is just, reasonable, and not unduly
discriminatory. For example, an incumbent may seek waiver of serial
queue processing requirements so that it may cluster transmission
service requests,\69\ or it may seek to ``ring fence'' a transmission
project in order to ensure that new transmission facilities developed
for a particular customer or set of customers do not adversely affect
existing customers, including native load.\70\ Incumbent developers
should address capacity allocation issues in a manner that does not
constitute undue discrimination or preference and is consistent with
applicable Commission-accepted tariffs.\71\
---------------------------------------------------------------------------
\68\ See, e.g., Subscription Process for Proposed PacifiCorp
Transmission Expansion Projects, available at http://www.oasis.pacificorp.com/oasis/ppw/SUBSCRIPTION_PROCESS.PDF (noting
incumbent's solicitation of interest from third parties in the
development of a cost-based transmission project in advance of
receipt of transmission service requests from third parties under
the incumbent's OATT).
\69\ See, e.g., Portland General Electric Co., 139 FERC ] 61,133
(2012) (granting waiver of serial queue processing requirements,
allowing a general facilities study for a cluster of transmission
and interconnection service requests).
\70\ See, e.g., Mountain States Transmission Intertie, LLC and
NorthWestern Corp., 127 FERC ] 61,270, at PP 2, 5 (2009) (incumbent
developing an export-only transmission project through a separate
stand-alone company so that their existing transmission customers
will not be required to subsidize the cost of a new transmission
facility to serve off-system markets; the Commission presented the
option of this project proceeding on a cost-of-service basis).
\71\ See National Grid, 139 FERC ] 61,129 at P 33.
---------------------------------------------------------------------------
E. Miscellaneous
43. WITG requests that the Commission allow developers that have
already been granted negotiated rate authority the ability to allocate
any unsubscribed capacity according to the processes in this policy
statement. We clarify here that such developers, if they want to
utilize the capacity allocation process described in this final policy
statement for any unsubscribed capacity, must seek Commission approval
to deviate from their current capacity allocation process authority set
forth in the Commission order granting them negotiated rate authority.
This will ensure that all interested parties are fully aware of and
have an opportunity to comment on the proposed capacity allocation.
44. Several commenters raise concerns regarding the role of the
merchant transmission developer in the Order No. 1000 regional planning
processes. The policies set forth herein are intended only to be a
roadmap for the capacity allocation process for new merchant and
nonincumbent, cost-based, participant-funded transmission facilities.
Thus, we believe that comments addressing the Order No. 1000 regional
planning processes are outside the scope of this final policy
statement. However, we note that Order No. 1000 requires a merchant
transmission developer to provide adequate information and data to
allow public utility transmission providers in the transmission
planning region to assess the potential reliability and operational
impacts of the merchant transmission developer's proposed transmission
facilities on other systems in the region.\72\
---------------------------------------------------------------------------
\72\ See Order No. 1000, FERC Stats. & Regs. ] 31,323 at PP 163-
164; Order No. 1000-A, 139 FERC ] 61,132 at P 297.
---------------------------------------------------------------------------
45. Clean Line requests that the Commission ensure that all RTOs/
ISOs and transmission providers create interconnection queue processes
that do not hinder high voltage direct current (HVDC) transmission
development, and suggests that a standard interconnection procedure
specifically for HVDC lines would solve this issue.\73\ The Commission
believes that the matter of HVDC-specific interconnection procedures is
similarly outside the scope of this final policy statement.
---------------------------------------------------------------------------
\73\ Clean Line at 8.
---------------------------------------------------------------------------
IV. Document Availability
46. In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
Internet through the Commission's Home Page (http://www.ferc.gov) and
in the Commission's
[[Page 5276]]
Public Reference Room during normal business hours (8:30 a.m. to 5:00
p.m. Eastern time) at 888 First Street NE., Room 2A, Washington, DC
20426.
47. From Commission's Home Page on the Internet, this information
is available on eLibrary. The full text of this document is available
on eLibrary in PDF and Microsoft Word format for viewing, printing,
and/or downloading. To access this document in eLibrary, type the
docket number excluding the last three digits of this document in the
docket number field.
48. User assistance is available for eLibrary and the Commission's
Web site during normal business hours from FERC Online Support at (202)
502-6652 (toll free at 1-866-208-3676) or email at
ferconlinesupport@ferc.gov, or the Public Reference Room at (202) 502-
8371, TTY (202) 502-8659. Email the Public Reference Room at
public.referenceroom@ferc.gov.
By the Commission.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2013-01507 Filed 1-24-13; 8:45 am]