[Federal Register Volume 78, Number 112 (Tuesday, June 11, 2013)]
[Notices]
[Page 35019]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2013-13803]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14485-000; Project No. 14485-000]


FFP Project 58, LLC; Notice of Preliminary Permit Application 
Accepted for Filing and Soliciting Comments, Motions To Intervene, and 
Competing Applications

    On February 1, 2013, FFP Project 58, LLC filed an application for a 
preliminary permit, pursuant to section 4(f) of the Federal Power Act 
(FPA), proposing to study the feasibility of a hydropower project at 
the Kentucky River Lock and Dam 6 located on the Kentucky 
River near the town of Salvisa in Mercer and Woodford Counties, 
Kentucky. The sole purpose of a preliminary permit, if issued, is to 
grant the permit holder priority to file a license application during 
the permit term. A preliminary permit does not authorize the permit 
holder to perform any land-disturbing activities or otherwise enter 
upon lands or waters owned by others without the owners' express 
permission.
    The proposed project would consist of the following: (1) A 465-
foot-long, 34-foot-high timber crib dam; (2) a reservoir with a surface 
area of 940 acres and a storage capacity of 16,310 acre-feet; (3) a 
300-foot-long, 160-foot-wide intake channel with a 70-foot-long 
retaining wall; (4) a 140-foot-long, 70-foot-wide powerhouse containing 
two generating units with a total capacity of 6.0 megawatts; (5) a 180-
foot-long, 130-foot-wide tailrace with a 70-foot-long retaining wall; 
(6) a 4.16/34.5 kilo-Volt (kV) substation; (7) a 4.3-mile-long, 34.5 kV 
transmission line. The project would have an average annual generation 
of 23,700 megawatt-hours.
    Applicant Contact: Ms. Ramya Swaminathan, Free Flow Power 
Corporation, 239 Causeway Street, Suite 300, Boston, MA 02114. (978) 
283-2822.
    FERC Contact: Chris Casey, [email protected], (202) 502-
8577.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36. Comments, motions to intervene, notices of intent, and 
competing applications may be filed electronically via the Internet. 
See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's 
Web site http://www.ferc.gov/docs-filing/efiling.asp. Commenters can 
submit brief comments up to 6,000 characters, without prior 
registration, using the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information 
at the end of your comments. For assistance, please contact FERC Online 
Support at [email protected] or toll free at 1-866-208-3676, 
or for TTY, (202) 502-8659. Although the Commission strongly encourages 
electronic filing, documents may also be paper-filed. To paper-file, 
mail an original and five copies to: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE., Washington, 
DC 20426.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of 
Commission's Web site at http://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-14485) in the docket number field to access 
the document. For assistance, contact FERC Online Support.

    Dated: June 5, 2013.
 Kimberly D. Bose,
 Secretary.
[FR Doc. 2013-13803 Filed 6-10-13; 8:45 am]
BILLING CODE 6717-01-P