Drawbridge Operation Regulation; Upper Mississippi River, Sabula,
IA
AGENCY: Coast Guard, DHS.
ACTION: Notice of deviation from drawbridge regulations.
-----------------------------------------------------------------------
SUMMARY: The Coast Guard has issued a temporary deviation from the
operating schedule that governs the Sabula Railroad Drawbridge across
the Upper Mississippi River, mile 535.0, at Sabula, Iowa. The deviation
is necessary to allow the bridge owner time to perform repairs and
maintenance that is essential to the continued safe operation of the
drawbridge. This deviation allows the bridge to remain in the closed-
to-navigation position while a damaged gear assembly is replaced and
structural steel repairs are completed.
DATES: This deviation is effective from 7 a.m., January 6, 2014 to 7
a.m., March 4, 2014.
ADDRESSES: The docket for this deviation, USCG-2013-1039 is available
at http://www.regulations.gov. Type the docket number in the ``SEARCH''
box and click ``SEARCH''. Click on Open Docket Folder on the line
associated with this deviation. You may also visit the Docket
Management Facility in Room W12-140 on the ground floor of the
Department of Transportation West Building, 1200 New Jersey Avenue SE.,
Washington, DC 20590, between 9 a.m. and 5 p.m., Monday through Friday,
except Federal holidays.
FOR FURTHER INFORMATION CONTACT: If you have questions on this
temporary deviation, call or email Eric A. Washburn, Bridge
Administrator, Western Rivers, Coast Guard; telephone 314-269-2378,
email [email protected]. If you have questions on viewing the
docket, call Cheryl Collins, Program Manager, Docket Operations,
telephone 202-366-9826.
SUPPLEMENTARY INFORMATION: The Canadian Pacific Railway requested a
temporary deviation for the Sabula Railroad Drawbridge, across the
Upper Mississippi River, mile 535.0, at Sabula, Iowa to remain in the
closed-to-navigation position while a damaged gear assembly is replaced
and structural steel repairs are completed. The closure period will
start at 7 a.m., January 6, 2014 to 7 a.m., March 4, 2014. Work is
scheduled in the winter and when there is less impact on navigation;
instead of scheduling work in the summer, when river traffic increases.
Once the gear assembly is removed and structural steel repairs have
commenced, the swing span will not be able to open, even for
emergencies, until repairs are complete and gear assembly is installed.
The Sabula Railroad Drawbridge currently operates in accordance
with 33 CFR 117.5, which states the general requirement that
drawbridges shall open promptly and fully for the passage of vessels
when a request to open is given in accordance with the subpart. In
order to facilitate the needed bridge work, the drawbridge must be kept
in the closed-to-navigation position.
There are no alternate routes for vessels transiting this section
of the Upper Mississippi River.
The Sabula Railroad Drawbridge, in the closed-to-navigation
position, provides a vertical clearance of 18.1 feet above normal pool.
Navigation on the waterway consists primarily of commercial tows and
recreational watercraft. This temporary deviation has been coordinated
with the waterway users. No objections were received.
In accordance with 33 CFR 117.35(e), the drawbridge must return to
its regular operating schedule immediately at the end of the effective
period of this temporary deviation. This deviation from the operating
regulations is authorized under 33 CFR 117.35.