MILLENNIUM CHALLENGE CORPORATION

[MCC FR 14-01]


Notice of Quarterly Report (July 1, 2013-September 30, 2013)

AGENCY: Millennium Challenge Corporation.

SUMMARY: The Millennium Challenge Corporation (MCC) is reporting for 
the quarter July 1, 2013 to September 30, 2013, on assistance provided 
under section 605 of the Millennium Challenge Act of 2003 (22 U.S.C. 
7701 et seq.), as amended (the Act), and on transfers or allocations of 
funds to other federal agencies under section 619(b) of the Act. The 
following report will be made available to the public by publication in 
the Federal Register and on the Internet Web site of the MCC 
(www.mcc.gov) in accordance with section 612(b) of the Act.

    Dated: February 26, 2014.
Paul C. Weinberger,
Vice President, Congressional and Public Affairs,
    Millennium Challenge Corporation.

----------------------------------------------------------------------------------------------------------------
                                                                           Cumulative
            Projects                 Obligated          Objective        disbursements         Measures \3\
----------------------------------------------------------------------------------------------------------------
                  Country: Burkina Faso Year: 2013 Quarter 4 Total Obligation \1\: $478,954,470
   Entity to which the assistance is provided: MCA Burkina Faso Total Quarterly Disbursements \2\: $36,078,911
----------------------------------------------------------------------------------------------------------------
Roads Project..................       $194,130,681  Enhance access to        $77,726,203  Roughness: Sabou-
                                                     markets through                       Koudougou-Perkoa-
                                                     investments in                        Didyr.
                                                     the road network.                    Roughness: Dedougou-
                                                                                           Nouna-Bomborukuy-
                                                                                           Nouna Border.
                                                                                          Roughness: Banfora-
                                                                                           Sindou.
                                                                                          Kilometers of road
                                                                                           under works contract
                                                                                           (primary roads).
                                                                                          Access time (in
                                                                                           minutes) to the
                                                                                           nearest market in the
                                                                                           Sourou and Comoe.
                                 .................                     .................  Kilometers of road
                                                                                           under works contract
                                                                                           (rural roads).
                                 .................                     .................  Personnel trained.
                                 .................                     .................  Periodic road
                                                                                           maintenance coverage
                                                                                           rate (for all funds)
                                                                                           (percent).
----------------------------------------------------------------------------------------------------------------
Rural Land Governance Project..        $59,934,615  Increase                 $27,499,131  Trend in incidence of
                                                     investment in                         conflict over land
                                                     land and rural                        rights reported in
                                                     productivity                          the 17 pilot communes
                                                     through improved                      (annual rate of
                                                     land tenure                           change in the
                                                     security and                          occurrence of
                                                     land management.                      conflicts over land
                                                                                           rights).
                                                                                          Legal and regulatory
                                                                                           reforms adopted.
                                                                                          Stakeholders trained.
                                                                                          Rural land service
                                                                                           offices installed and
                                                                                           functioning.
                                 .................                     .................  Rural hectares
                                                                                           formalized.
                                 .................                     .................  Extent of confidence
                                                                                           in land tenure
                                                                                           security (percent).
                                 .................                     .................  New perimeter
                                                                                           development in Di
                                                                                           (Hectares).
----------------------------------------------------------------------------------------------------------------
Agriculture Development Project       $141,910,059  Expand the               $92,104,838  Value of contracts for
                                                     productive use                        irrigation systems
                                                     of land in order                      works disbursed.
                                                     to increase the                      Responsible members of
                                                     volume and value                      Water Users
                                                     of agricultural                       Association trained
                                                     production in                         in the Sourou.
                                                     project zones.                       Farmers trained.
                                                                                          Farmers who have
                                                                                           applied improved
                                                                                           practices as a result
                                                                                           of training,
                                 .................                     .................  Loan borrowers.
                                 .................                     .................  Volume of agricultural
                                                                                           and rural loans
                                                                                           (millions of U.S.
                                                                                           dollars).
                                 .................                     .................  Girls and boys
                                                                                           graduating from
                                                                                           BRIGHT II primary
                                                                                           schools.
----------------------------------------------------------------------------------------------------------------
Bright II Schools Project......        $26,840,570  Increase primary         $26,840,570  Ninety percent of
                                                     school                                girls regularly
                                                     completion rates.                     attending BRIGHT II
                                                                                           schools.
                                 .................                     .................  Girls enrolled in the
                                                                                           MCC/USAID-supported
                                                                                           BRIGHT II schools.
                                 .................                     .................  Boys enrolled in the
                                                                                           MCC/USAID-supported
                                                                                           BRIGHT II schools.
                                 .................                     .................  Educational facilities
                                                                                           constructed or
                                                                                           rehabilitated.
                                 .................                     .................  Teachers trained
                                                                                           through 10 provincial
                                                                                           workshops.
----------------------------------------------------------------------------------------------------------------
Program Administration \4\ and         $56,138,545  .................        $40,821,651
 Control, Monitoring and
 Evaluation.
Pending Subsequent Reports \5\.  .................  .................           $867,206
----------------------------------------------------------------------------------------------------------------


[[Page 12228]]


 
                                                                           Cumulative
            Projects                 Obligated          Objective        disbursements           Measures
----------------------------------------------------------------------------------------------------------------
                    Country: Cape Verde II Year: 2013 Quarter 4 Total Obligation: $66,230,000
     Entity to which the assistance is provided: MCA Cape Verde II Total Quarterly Disbursements: $1,086,045
----------------------------------------------------------------------------------------------------------------
Land Management for Investment         $17,260,000  Increased                 $1,009,742  Legal and regulatory
 Projects.                                           investments in                        reforms adopted.
                                                     and value of                         Stakeholders receiving
                                                     property;                             formal on-the-job
                                                     improved ease of                      training or technical
                                                     doing business;                       assistance regarding
                                                     increased                             roles,
                                                     investments and                       responsibilities or
                                                     value added in                        new technologies.
                                                     tourism;                             Field test of
                                                     increased                             ``Fieldwork
                                                     employment.                           Operations Manual''
                                                                                           and methodology
                                                                                           completed on Sal.
----------------------------------------------------------------------------------------------------------------
Water, Sanitation, and Hygiene         $41,030,000  Increased access            $503,800  Value of implicit
 Project.                                            to improved                           subsidy reduction
                                                     water and                             (U.S. dollars).
                                                     sanitation;                          Service coverage by
                                                     reduced                               corporatized
                                                     household costs                       utilities (percent).
                                                     for water;                           Operating cost
                                                     reduced                               coverage (percent)
                                                     incidence of                          (operational revenue/
                                                     waterborne                            annual operating
                                                     disease;                              costs).
                                                     improved capital                     Continuity of service
                                                     accumulation;                         (average hours of
                                                     increase                              service per day for
                                                     productive                            water supply).
                                                     government                           Objective measure of
                                                     spending.                             water quality
                                                                                           (randomized water
                                                                                           samples, fecal
                                                                                           coliform counts,
                                                                                           number per 100 mL).
                                                                                          Non-revenue water for
                                                                                           multiple municipal
                                                                                           utility/utilities.
                                 .................                     .................  Individuals adopting
                                                                                           improved water,
                                                                                           sanitation, and
                                                                                           hygiene behaviors and
                                                                                           practices (percent)
                                 .................                     .................  Value of signed water
                                                                                           and sanitation
                                                                                           construction
                                                                                           contracts
                                 .................                     .................  Percent disbursed of
                                                                                           water and sanitation
                                                                                           construction
                                                                                           contracts.
----------------------------------------------------------------------------------------------------------------
Program Administration and              $7,940,000  .................         $1,305,099
 Control, Monitoring and
 Evaluation.
----------------------------------------------------------------------------------------------------------------


 
                                                                           Cumulative
            Projects                 Obligated          Objective        disbursements           Measures
----------------------------------------------------------------------------------------------------------------
                    Country: El Salvador Year: 2013 Quarter 4 Total Obligation: $449,566,762
       Entity to which the assistance is provided: MCA El Salvador Total Quarterly Disbursements: $194,700
----------------------------------------------------------------------------------------------------------------
Human Development Project......        $84,210,866  Increase human           $84,210,865  Non-formal trained
                                                     and physical                          students that
                                                     capital of                            complete the
                                                     residents of the                      training.
                                                     Northern Zone to                     Students participating
                                                     take advantage                        in MCC-supported
                                                     of employment                         education activities.
                                                     and business                         Additional school
                                                     opportunities..                       female students
                                                                                           enrolled in MCC-
                                                                                           supported activities.
                                                                                          Instructors trained or
                                                                                           certified through MCC-
                                                                                           supported activities.
                                                                                          Educational facilities
                                                                                           constructed/
                                                                                           rehabilitated and/or
                                                                                           equipped through MCC-
                                                                                           supported activities.
                                                                                          Households with access
                                                                                           to improved water
                                                                                           supply.
                                 .................                     .................  Households with access
                                                                                           to improved
                                                                                           sanitation.
                                 .................                     .................  Persons trained in
                                                                                           hygiene and sanitary
                                                                                           best practices.
                                 .................                     .................  Households benefiting
                                                                                           from a connection to
                                                                                           the electricity
                                                                                           network.
                                 .................                     .................  Households benefiting
                                                                                           from the installation
                                                                                           of isolated solar
                                                                                           systems.
                                 .................                     .................  Kilometers of new
                                                                                           electrical lines with
                                                                                           construction
                                                                                           contracts signed.
                                 .................                     .................  Population benefiting
                                                                                           from strategic
                                                                                           infrastructure
                                                                                           (number of people).
----------------------------------------------------------------------------------------------------------------
Connectivity Project...........       $270,051,380  Reduce travel           $270,051,380  Average annual daily
                                                     cost and time                         traffic on the
                                                     within the                            Northern
                                                     Northern Zone,                        Transnational
                                                     with the rest of                      Highway.
                                                     the country, and                     Travel time from
                                                     within the                            Guatemala to Honduras
                                                     region..                              through the Northern
                                                                                           Zone (hours and
                                                                                           minutes).
                                                                                          Kilometers of roads
                                                                                           completed.
----------------------------------------------------------------------------------------------------------------

[[Page 12229]]

 
Productive Development Project.        $65,973,922  Increase                 $65,973,922  Employment created
                                                     production and                        (number of jobs).
                                                     employment in                        Investment in
                                                     the Northern                          productive chains by
                                                     Zone..                                selected
                                                                                           beneficiaries (U.S.
                                                                                           dollars).
                                                                                          Hectares under
                                                                                           production with MCC
                                                                                           support.
                                                                                          Beneficiaries of
                                                                                           technical assistance
                                                                                           and training.
                                                                                          Amount of Investment
                                                                                           Support Fund
                                                                                           (FIDENORTE) approved.
                                 .................                     .................  Value of agricultural
                                                                                           loans to farmers/
                                                                                           agribusiness.
                                 .................                     .................  Value of loans
                                                                                           guaranteed.
                                 .................                     .................  Guarantees granted.
----------------------------------------------------------------------------------------------------------------
Program Administration and             $29,330,595  .................        $29,330,595
 Control, Monitoring and
 Evaluation.
----------------------------------------------------------------------------------------------------------------


 
                                                                           Cumulative
            Projects                 Obligated          Objective         expenditures           Measures
----------------------------------------------------------------------------------------------------------------
                    Country: Georgia \6\ Year: 2013 Quarter 4 Total Obligation: $387,178,520
            Entity to which the assistance is provided: MCA Georgia Total Quarterly Expenditures: $0
----------------------------------------------------------------------------------------------------------------
Regional Infrastructure               $309,899,714  Key Regional            $309,899,714  Savings in vehicle
 Rehabilitation Project.                             Infrastructure                        operating costs.
                                                     Rehabilitated.                       International
                                                                                           roughness index.
                                                                                          Annual average daily
                                                                                           traffic.
                                 .................                     .................  Amount of travel time.
                                 .................                     .................  Kilometers of road
                                                                                           completed.
                                 .................                     .................  Sites rehabilitated
                                                                                           (phases I, II, III)--
                                                                                           pipeline.
                                 .................                     .................  Construction works
                                                                                           completed (phase II)--
                                                                                           pipeline.
                                 .................                     .................  Savings in household
                                                                                           expenditures for all
                                                                                           Regional
                                                                                           Infrastructure
                                                                                           Development (RID)
                                                                                           subprojects.
                                 .................                     .................  Population served by
                                                                                           all RID subprojects.
                                 .................                     .................  RID subprojects
                                                                                           completed.
                                 .................                     .................  Value of grant
                                                                                           agreements signed.
                                 .................                     .................  Subprojects with works
                                                                                           initiated.
Regional Enterprise Development        $52,040,800  Enterprises in           $52,040,800  Jobs created by
 Project.                                            Regions                               Agribusiness
                                                     Developed.                            Development Activity
                                                                                           (ADA) and by Georgia
                                                                                           Regional Development
                                                                                           Fund (GRDF).
                                                                                          Household net income--
                                                                                           ADA and GRDF.
                                                                                          Enterprises assisted.
                                 .................                     .................  Jobs created--ADA
                                 .................                     .................  Firm income--ADA
                                 .................                     .................  Household net income--
                                                                                           ADA
                                 .................                     .................  Direct beneficiaries
                                 .................                     .................  Indirect beneficiaries
                                 .................                     .................  Grant agreements
                                                                                           signed--ADA
                                 .................                     .................  Increase in gross
                                                                                           revenues of portfolio
                                                                                           companies
                                 .................                     .................  Increase in portfolio
                                                                                           company employees
                                 .................                     .................  Increase in wages paid
                                                                                           to the portfolio
                                                                                           company employees
                                 .................                     .................  Portfolio companies.
                                 .................                     .................  Amount of grant funds
                                                                                           disbursed.
                                 .................                     .................  Funds disbursed to the
                                                                                           portfolio companies.
Program Administration, Due            $25,238,005  .................        $25,238,005
 Diligence, Monitoring and
 Evaluation.
----------------------------------------------------------------------------------------------------------------
Pending Subsequent Reports.....  .................  .................               $101
----------------------------------------------------------------------------------------------------------------


[[Page 12230]]


 
                                                                           Cumulative
            Projects                 Obligated          Objective        disbursements           Measures
----------------------------------------------------------------------------------------------------------------
                       Country: Ghana Year: 2013 Quarter 4 Total Obligation: $536,288,969
             Entity to which the assistance is provided: MCA Ghana Total Quarterly Disbursements: $0
----------------------------------------------------------------------------------------------------------------
Agriculture Project............       $188,731,530  Enhance                 $188,911,823  Farmers trained in
                                                     profitability of                      commercial
                                                     cultivation,                          agriculture.
                                                     services to                          Additional hectares
                                                     agriculture and                       irrigated with MCC
                                                     product handling                      support.
                                                     in support of                        Hectares under
                                                     the expansion of                      production with MCC
                                                     commercial                            support.
                                                     agriculture                          Kilometers of feeder
                                                     among groups of                       road completed.
                                                     smallholder                          Percent of contracted
                                                     farms.                                road works disbursed:
                                                                                           feeder roads.
                                                                                          Value of loans
                                                                                           disbursed to clients
                                                                                           from agriculture loan
                                                                                           fund.
                                                                                          Portfolio-at-risk of
                                                                                           Agriculture Loan Fund
                                                                                           (percent).
                                 .................                     .................  Cooling facilities
                                                                                           installed.
                                 .................                     .................  Percent of value of
                                                                                           contracted irrigation
                                                                                           works disbursed.
                                 .................                     .................  Parcels surveyed in
                                                                                           the Pilot Land
                                                                                           Registration.
                                 .................                     .................  Land parcels
                                                                                           registered in the
                                                                                           Pilot Land
                                                                                           Registration Areas.
                                 .................                     .................  Volume of products
                                                                                           passing through post-
                                                                                           harvest treatment
                                                                                           (metric tons).
----------------------------------------------------------------------------------------------------------------
Rural Development Project......        $76,030,565  Strengthen the           $75,903,274  Students enrolled in
                                                     rural                                 schools affected by
                                                     institutions                          Education Facilities
                                                     that provide                          Sub-Activity.
                                                     services                             Agricultural
                                                     complementary                         facilities in target
                                                     to, and                               districts with
                                                     supportive of,                        electricity due to
                                                     agricultural and                      Rural Electrification
                                                     agriculture                           Activity.
                                                     business                             Additional female
                                                     development.                          students enrolled in
                                                                                           schools affected by
                                                                                           Education Facilities
                                                                                           Sub-Activity
Individuals completing
 internships at ministries,
 departments and agencies and
 metropolitan, municipal and
 district assemblies..
                                 .................                     .................  School blocks
                                                                                           rehabilitated and
                                                                                           constructed.
                                 .................                     .................  Distance to collect
                                                                                           water (meters).
                                 .................                     .................  Households with access
                                                                                           to improved water
                                                                                           supply.
                                 .................                     .................  Water points
                                                                                           constructed.
                                 .................                     .................  Electricity lines
                                                                                           identified and
                                                                                           diligence
                                                                                           (kilometers).
                                 .................                     .................  Inter-bank
                                                                                           transactions.
                                 .................                     .................  Rural banks automated
                                                                                           under the Automation/
                                                                                           Computerization and
                                                                                           Interconnectivity of
                                                                                           Rural Banks activity.
                                 .................                     .................  Rural banks connected
                                                                                           to the wide area
                                                                                           network.
Transportation Project.........       $227,710,512  Reduce the              $227,657,512  N1 Highway: annualized
                                                     transportation                        average daily
                                                     costs affecting                       traffic.
                                                     agriculture                          N1 Highway: kilometers
                                                     commerce at sub-                      of road completed.
                                                     regional levels.                     N1 Highway: Travel
                                                                                           time at peak hours
                                                                                           (minutes).
                                                                                          N1 Highway: Vehicles
                                                                                           per hour at peak
                                                                                           hours.
                                                                                          Trunk roads kilometers
                                                                                           of roads completed
Percent disbursed of contracted
 trunk road works..
                                 .................                     .................  Ferry activity:
                                                                                           annualized average
                                                                                           daily traffic
                                                                                           vehicles
                                 .................                     .................  Ferry activity: annual
                                                                                           average daily traffic
                                                                                           (passengers)
                                 .................                     .................  Percent of contracted
                                                                                           road works disbursed:
                                                                                           N1
                                 .................                     .................  Percent of contracted
                                                                                           work disbursed: ferry
                                                                                           and floating dock
                                 .................                     .................  Percent of contracted
                                                                                           work disbursed:
                                                                                           landings and
                                                                                           terminals.
----------------------------------------------------------------------------------------------------------------
Program Administration, Due            $43,816,362  .................        $43,816,360
 Diligence, Monitoring and
 Evaluation.
----------------------------------------------------------------------------------------------------------------


[[Page 12231]]


 
                                                                           Cumulative
            Projects                 Obligated          Objective        disbursements           Measures
----------------------------------------------------------------------------------------------------------------
                     Country: Indonesia Year: 2013 Quarter 4 Total Obligation: $600,000,000
       Entity to which the assistance is provided: MCA Indonesia Total Quarterly Disbursements: $1,356,847
----------------------------------------------------------------------------------------------------------------
Community Nutrition Project....       $131,500,000  .................        $22,458,673
Procurement Modernization              $50,000,000  .................            103,608
 Project.
Green Prosperity Project.......       $332,500,000  .................            $99,480
Program Administration and             $86,000,000  .................         $3,905,233
 Control, Monitoring and
 Evaluation.
----------------------------------------------------------------------------------------------------------------


 
                                                                           Cumulative
            Projects                 Obligated          Objective        disbursements           Measures
----------------------------------------------------------------------------------------------------------------
                       Country: Jordan Year: 2013 Quarter 4 Total Obligation: $275,100,000
        Entity to which the assistance is provided: MCA Jordan Total Quarterly Disbursements: $15,710,623
----------------------------------------------------------------------------------------------------------------
Water Network Project..........       $102,570,034  Reduce water              $4,416,060  Network water
                                                     losses, improve                       consumption per
                                                     continuity of                         capita (residential
                                                     water service                         and non-residential);
                                                     and improve                           liters/capita/day.
                                                     overall                              Operating cost
                                                     efficiency and                        coverage--Water
                                                     use of network                        Authority Jordan
                                                     water delivery                        Zarqa.
                                                     leading to                           Non-revenue water
                                                     households                            (percent).
                                                     substituting                         Continuity of supply
                                                     network water                         time; hours per week.
                                                     for costly                           Restructure and
                                                     alternatives.                         rehabilitate primary
                                                                                           and secondary
                                                                                           pipelines
                                                                                           (kilometers).
                                                                                          Restructure and
                                                                                           rehabilitate tertiary
                                                                                           pipelines
                                                                                           (kilometers).
                                 .................                     .................  Value of disbursed
                                                                                           water construction
                                                                                           contracts--Infrastruc
                                                                                           ture Activity and
                                                                                           Water Smart Homes
                                                                                           Activity (U.S.
                                                                                           dollars).
                                 .................                     .................  National Aid Fund
                                                                                           households with
                                                                                           improved water and
                                                                                           wastewater network.
                                 .................                     .................  National Aid Fund
                                                                                           households connected
                                                                                           to the wastewater
                                                                                           network as a result
                                                                                           of the Water Smart
                                                                                           Homes Activity.
Wastewater Network Project.....        $54,274,261  Increase access          $12,538,064  Sewer blockage events
                                                     to the                                (annual).
                                                     wastewater                           Volume of wastewater
                                                     network,                              collected; cubic
                                                     increase the                          meters/year/million.
                                                     volume of                            Residential population
                                                     wastewater                            connected to the
                                                     collected and                         sewer system.
                                                     reduce the                           Expand network
                                                     incidents of                          (kilometers).
                                                     sewage overflow.                     Value disbursed of
                                                                                           sanitation
                                                                                           construction
                                                                                           contracts.
As Samra Wastewater Treatment          $98,703,598  Increase the             $37,748,348  Treated wastewater
 Plant Expansion Project.                            volume of                             used in agriculture
                                                     treated waste                         (as a percent of all
                                                     water available                       water used for
                                                     as a substitute                       irrigation in
                                                     for fresh water                       Northern and Middle
                                                     in agriculture                        Jordan Valley).
                                                     use.                                 Value of disbursed
                                                                                           construction
                                                                                           contracts; MCC
                                                                                           contribution (U.S.
                                                                                           dollars).
                                                                                          Total engineering,
                                                                                           procurement and
                                                                                           construction cost of
                                                                                           As-Samra expansion
                                                                                           (U.S. dollars).
----------------------------------------------------------------------------------------------------------------
Program Administration and             $19,552,107  .................         $2,040,286
 Control, Monitoring and
 Evaluation.
----------------------------------------------------------------------------------------------------------------
Pending Subsequent Reports.....  .................  .................            $44,546
----------------------------------------------------------------------------------------------------------------


 
                                                                           Cumulative
            Projects                 Obligated          Objective        disbursements           Measures
----------------------------------------------------------------------------------------------------------------
                      Country: Lesotho Year: 2013 Quarter 4 Total Obligation: $362,551,000
       Entity to which the assistance is provided: MCA Lesotho Total Quarterly Disbursements: $65,987,603
----------------------------------------------------------------------------------------------------------------
Water Project..................       $155,187,239  Improve the water       $135,808,735  Physical completion of
                                                     supply for                            Metolong water
                                                     industrial and                        treatment works
                                                     domestic needs,                       contract (percent).
                                                     and enhance                          Physical completion of
                                                     rural                                 urban water supply
                                                     livelihoods                           works contracts
                                                     through improved                      (percent).
                                                     watershed                            People with access to
                                                     management..                          rural water supply.
                                                                                          Ventilated improved
                                                                                           pit latrines built.
                                 .................                     .................  Households with
                                                                                           provisions to connect
                                                                                           to water networks

[[Page 12232]]

 
                                 .................                     .................  Non-revenue water
                                                                                           (percent)
                                 .................                     .................  Knowledge of good
                                                                                           hygiene practices
                                                                                           (percent)
                                 .................                     .................  Water points
                                                                                           constructed.
----------------------------------------------------------------------------------------------------------------
Health Project.................       $138,511,863  Increase access         $128,460,579  People with HIV still
                                                     to life-                              alive 12 months after
                                                     extending                             initiation of
                                                     antiretroviral                        treatment.
                                                     therapy and                          Health centers with
                                                     essential health                      required staff
                                                     services by                           complement (full-time
                                                     providing a                           employees).
                                                     sustainable                          Tuberculosis
                                                     delivery                              notification (per
                                                     platform..                            100,000 people).
                                                                                          Health centers
                                                                                           equipped.
                                 .................                     .................  Deliveries conducted
                                                                                           in the health
                                                                                           facilities
                                 .................                     .................  Physical completion of
                                                                                           health center
                                                                                           facilities (percent)
                                 .................                     .................  Physical completion of
                                                                                           outpatient
                                                                                           departments (percent)
                                 .................                     .................  Physical completion of
                                                                                           the Botsabelo
                                                                                           facilities (percent)
Private Sector Development             $25,225,369  Stimulate                $22,176,405  Time required to
 Project.                                            investment by                         resolve commercial
                                                     improving access                      disputes (number of
                                                     to credit,                            days).
                                                     reducing                             Cases filed at the
                                                     transaction                           commercial court.
                                                     costs and                            Debit/smart cards
                                                     increasing the                        issued.
                                                     participation of                     Bonds registered.
                                                     women in the
                                                     economy..
                                 .................                     .................  Urban land parcels
                                                                                           regularized and
                                                                                           registered
                                 .................                     .................  People trained on
                                                                                           gender equality and
                                                                                           economic rights
                                 .................                     .................  Stakeholders trained
                                 .................                     .................  Change in time for
                                                                                           property transactions
                                                                                           (percent)
                                 .................                     .................  Women holding titles
                                                                                           to land.
----------------------------------------------------------------------------------------------------------------
Program Administration and             $43,626,528  .................        $37,702,451
 Control, Monitoring and
 Evaluation.
----------------------------------------------------------------------------------------------------------------
Pending Subsequent Reports.....  .................  .................           $212,441
----------------------------------------------------------------------------------------------------------------


 
                                                                           Cumulative
            Projects                 Obligated          Objective        disbursements           Measures
----------------------------------------------------------------------------------------------------------------
                       Country: Malawi Year: 2013 Quarter 4 Total Obligation: $350,700,000
         Entity to which the assistance is provided: MCA Malawi Total Quarterly Disbursements: $655,998
----------------------------------------------------------------------------------------------------------------
Gender Integration Project.....           $203,000
----------------------------------------------------------------------------------------------------------------
Power Project..................       $257,115,000
----------------------------------------------------------------------------------------------------------------
Natural Resource Management            $27,739,000
 Project.
----------------------------------------------------------------------------------------------------------------
Power Sector Reform Project....        $24,229,800  .................           $223,042
----------------------------------------------------------------------------------------------------------------
Program Administration and             $41,616,200  .................         $1,328,666
 Control, Monitoring and
 Evaluation.
----------------------------------------------------------------------------------------------------------------
Pending Subsequent Reports.....  .................  .................           $155,088
----------------------------------------------------------------------------------------------------------------


 
                                                                           Cumulative
            Projects                 Obligated          Objective        disbursements           Measures
----------------------------------------------------------------------------------------------------------------
                      Country: Moldova Year: 2013 Quarter 4 Total Obligation: $262,000,000
       Entity to which the assistance is provided: MCA Moldova Total Quarterly Disbursements: $14,279,187
----------------------------------------------------------------------------------------------------------------
Road Rehabilitation Project....       $132,840,000  Enhance                  $30,508,729  Reduced cost for road
                                                     transportation                        users.
                                                     conditions.                          Average annual daily
                                                                                           traffic.
                                                                                          Road maintenance
                                                                                           expenditure.
                                                                                          Kilometers of roads
                                                                                           completed.

[[Page 12233]]

 
                                 .................                     .................  Percent of contracted
                                                                                           roads works disbursed
                                 .................                     .................  Children participants
                                                                                           in the road safety
                                                                                           trainings
                                 .................                     .................  Resettlement action
                                                                                           plans implemented
                                 .................                     .................  Final design (date
                                                                                           received)
                                 .................                     .................  Trafficking in persons
                                                                                           training
                                                                                           participants.
----------------------------------------------------------------------------------------------------------------
Transition to High Value              $120,773,402  Increase incomes         $20,530,031  Hectares under
 Agriculture Project.                                in the                                improved or new
                                                     agricultural                          irrigation.
                                                     sector; create                       Centralized irrigation
                                                     models for                            systems
                                                     transition to                         rehabilitated.
                                                     high value                           Percent of contracted
                                                     agriculture in                        irrigation
                                                     centralized                           feasibility and/or
                                                     irrigation                            design studies
                                                     system areas and                      disbursed.
                                                     an enabling                          Value of irrigation
                                                     environment                           feasibility and/or
                                                     (legal,                               detailed design
                                                     financial and                         contracts signed.
                                                     market) for
                                                     replication.
                                 .................                     .................  Water user
                                                                                           associations
                                                                                           achieving financial
                                                                                           sustainability
                                 .................                     .................  Management transfer
                                                                                           agreements signed
                                 .................                     .................  Revised water
                                                                                           management policy
                                                                                           framework--with long-
                                                                                           term water rights
                                                                                           defined--established
                                 .................                     .................  Contracts of
                                                                                           association signed
                                 .................                     .................  New high value
                                                                                           agriculture
                                                                                           infrastructure in
                                                                                           place (metric tons of
                                                                                           cold storage
                                                                                           capacity)
                                 .................                     .................  Loans past due
                                 .................                     .................  Value of agricultural
                                                                                           and rural loans
                                 .................                     .................  Loan borrowers
                                 .................                     .................  Loan borrowers
                                                                                           (female)
                                 .................                     .................  Value of sales
                                                                                           facilitated
                                 .................                     .................  Farmers that have
                                                                                           applied improved
                                                                                           techniques (Growing
                                                                                           High Value
                                                                                           Agriculture Sales
                                                                                           [GHS])
                                 .................                     .................  Farmers that have
                                                                                           applied improved
                                                                                           techniques (GHS)
                                                                                           (female)
                                 .................                     .................  Farmers trained
                                 .................                     .................  Farmers trained
                                                                                           (female)
                                 .................                     .................  Enterprises assisted
                                 .................                     .................  Enterprises assisted
                                                                                           (female)
----------------------------------------------------------------------------------------------------------------
Program Administration and             $27,386,598  .................         $9,807,687
 Monitoring and Evaluation.
----------------------------------------------------------------------------------------------------------------
Pending Subsequent Reports.....  .................  .................           $130,626
----------------------------------------------------------------------------------------------------------------


 
                                                                           Cumulative
            Projects                 Obligated          Objective        disbursements           Measures
----------------------------------------------------------------------------------------------------------------
                      Country: Mongolia Year: 2013 Quarter 4 Total Obligation: $284,911,363
       Entity to which the assistance is provided: MCA Mongolia Total Quarterly Disbursements: $40,901,282
----------------------------------------------------------------------------------------------------------------
Property Rights Project........        $28,970,417  Increase security        $28,205,493  Wells completed.
                                                     and                                  Stakeholders trained
                                                     capitalization                        (Peri-Urban).
                                                     of land assets                       Leases awarded.
                                                     held by lower-                       Project herder groups
                                                     income                                limiting their
                                                     Mongolians, and                       livestock population
                                                     increased peri-                       to the carrying
                                                     urban herder                          capacity of their
                                                     productivity and                      leases on farms in 3
                                                     incomes.                              central aimags
                                                                                           (Ulaanbataar, Darkhan
                                                                                           and Erdenet)
                                                                                           (percent).
                                 .................                     .................  Official cost
                                                                                           prescribed for
                                                                                           property transactions
                                                                                           (first-time)
                                 .................                     .................  Household land rights
                                                                                           formalized
                                 .................                     .................  Legal and regulatory
                                                                                           reforms adopted
                                 .................                     .................  Stakeholders trained
                                                                                           (Ger Area Land
                                                                                           Plots).
----------------------------------------------------------------------------------------------------------------
Vocational Education Project...        $50,215,035  Increase                 $49,193,742  Students participating
                                                     employment and                        in MCC-supported
                                                     income among                          educational
                                                     unemployed and                        activities.
                                                     underemployed                        Public-Private
                                                     Mongolians.                           Partnership (PPP)
                                                                                           funding contributed
                                                                                           to Technical
                                                                                           Vocational Education
                                                                                           and Training (TVET)
                                                                                           schools (percent).
                                 .................                     .................  Instructors trained.
                                 .................                     .................  Educational facilities
                                                                                           constructed or
                                                                                           rehabilitated.
----------------------------------------------------------------------------------------------------------------

[[Page 12234]]

 
Health Project.................        $42,045,259  Increase the             $38,594,085  Amount of civil
                                                     adoption of                           society grants (USD).
                                                     behaviors that                       Cervical cancer cases
                                                     reduce                                detected early
                                                     noncommunicable                       (percent).
                                                     diseases and                         Screening for
                                                     injuries (NCDIs)                      hypertension
                                                     among target                          (percent).
                                                     populations and                      Health staff trained.
                                                     improved medical                     School teachers
                                                     treatment and                         trained.
                                                     control of NCDIs.
                                 .................                     .................  Primary healthcare
                                                                                           facilities with
                                                                                           noncommunicable
                                                                                           disease services
                                                                                           (percent).
----------------------------------------------------------------------------------------------------------------
Roads Project..................        $84,768,788  More efficient           $68,624,172  Kilometers of roads
                                                     transport for                         completed.
                                                     trade and access                     Kilometers of roads
                                                     to services.                          under design.
                                 .................                     .................  Percent disbursed of
                                                                                           road construction
                                                                                           contracts.
Energy and Environmental               $41,518,019  Increased wealth         $40,113,989  Power dispatched from
 Project.                                            and productivity                      substation (million
                                                     through greater                       kilowatt hours).
                                                     fuel use                             Heat only boilers
                                                     efficiency and                        sites upgraded.
                                                     decreasing                           Subsidized stoves
                                                     health costs                          sold.
                                                     from air.
----------------------------------------------------------------------------------------------------------------
Rail Project...................           $369,560  Terminated.......           $369,560  Terminated.
----------------------------------------------------------------------------------------------------------------
Program Administration and             $37,024,286  .................        $31,237,501
 Control, Monitoring and
 Evaluation.
----------------------------------------------------------------------------------------------------------------
Pending Subsequent Reports.....  .................  .................           $673,773
----------------------------------------------------------------------------------------------------------------


 
                                                                           Cumulative
            Projects                 Obligated          Objective        disbursements           Measures
----------------------------------------------------------------------------------------------------------------
                      Country: Morocco Year: 2013 Quarter 4 Total Obligation: $697,257,930
       Entity to which the assistance is provided: MCA Morocco Total Quarterly Disbursements: $68,770,191
----------------------------------------------------------------------------------------------------------------
Fruit Tree Productivity Project       $339,987,321  Stimulate growth        $292,981,583  Farmers trained.
                                                     in the                               Catalyst Fund
                                                     agricultural                          proposals approved.
                                                     sector and                           Disbursements under
                                                     reduce the                            the Catalyst Fund
                                                     volatility of                         (U.S. dollars).
                                                     agricultural                         Area planted and
                                                     production by                         delivered to farmers
                                                     restructuring                         (hectares).
                                                     farming from
                                                     grains towards
                                                     fruit tree
                                                     cultivation.
                                 .................                     .................  Area in expansion
                                                                                           perimeters for which
                                                                                           water and soil
                                                                                           conservation measures
                                                                                           have been implemented
                                                                                           (hectares)
                                 .................                     .................  Yield of rehabilitated
                                                                                           olive trees in rain-
                                                                                           fed areas (metric
                                                                                           tons per hectare) (mt/
                                                                                           ha)
                                 .................                     .................  ......................
                                 .................                     .................  Cumulative area of
                                                                                           irrigated perimeters
                                                                                           rehabilitated
                                                                                           (hectares)
                                 .................                     .................  Yield of rehabilitated
                                                                                           olive trees in
                                                                                           irrigated areas (mt/
                                                                                           ha)
                                 .................                     .................  Average agricultural
                                                                                           revenue per farm in
                                                                                           oasis areas
                                 .................                     .................  Hectares under
                                                                                           improved irrigation
                                 .................                     .................  Yield of rehabilitated
                                                                                           date palms in oasis
                                                                                           areas (mt/ha)
                                 .................                     .................  In-vitro seedlings
                                                                                           successfully planted.

[[Page 12235]]

 
Small Scale Fisheries Project..       $122,246,589  Supported by             $92,772,499  Boats benefitting from
                                                     modern landing-                       landing sites and
                                                     site                                  ports.
                                                     infrastructure,                      Artisan fishers who
                                                     equipment and                         received a training
                                                     storage                               certificate.
                                                     facilities,                          Work days created for
                                                     develop value-                        construction jobs in
                                                     chain activities                      fish landing sites,
                                                     related to the                        ports, and wholesale
                                                     fishing industry                      market sites.
                                                     encouraging                          Per capita fish
                                                     greater access                        consumption in areas
                                                     to national and                       of new market
                                                     international                         construction (kg/
                                                     markets, while                        year).
                                                     improving the
                                                     fish quality and
                                                     preserving
                                                     resources.
                                 .................                     .................  Active mobile fish
                                                                                           vendors trained and
                                                                                           equipped by the
                                                                                           project.
                                 .................                     .................  Average price of fish
                                                                                           at auction markets.
                                 .................                     .................  Net annual income of
                                                                                           mobile fish vendors
                                                                                           (U.S. dollars).
Artisan and Fez Medina Project.        $96,006,515  Increase revenue         $68,286,067  Total receiving
                                                     from cultural                         literacy training.
                                                     and artisan                          Graduates of MCC-
                                                     activities, and                       supported functional
                                                     improve                               literacy program
                                                     educational and                       (female).
                                                     professional                         Graduates of MCC-
                                                     qualifications                        supported functional
                                                     of compact                            literacy program
                                                     beneficiaries.                        (male).
                                                                                          Total receiving
                                                                                           professional
                                                                                           training.
                                 .................                     .................  Females receiving
                                                                                           professional
                                                                                           training.
                                 .................                     .................  Graduates vocational
                                                                                           training program
                                                                                           (residential,
                                                                                           apprenticeship and
                                                                                           continuing
                                                                                           education).
                                 .................                     .................  Drop-out rates of
                                                                                           participants of
                                                                                           residential and
                                                                                           apprenticeship
                                                                                           programs.
                                 .................                     .................  Potters trained.
                                 .................                     .................  MCC-subsidized gas
                                                                                           kilns bought by
                                                                                           artisans.
                                 .................                     .................  Adoption rate of
                                                                                           improved production
                                                                                           practices promoted by
                                                                                           the project
                                                                                           (percent).
                                 .................                     .................  Tourist circuits
                                                                                           improved or created.
                                 .................                     .................  Small and medium
                                                                                           enterprises (SMEs)
                                                                                           that append the label
                                                                                           on their products.
                                 .................                     .................  SMEs participating in
                                                                                           promotion events.
                                 .................                     .................  Sites constructed or
                                                                                           rehabilitated
                                                                                          (4 Fondouks, Place
                                                                                           Lalla Ydouna, Ain
                                                                                           Nokbi).
                                 .................                     .................  Beneficiaries of Ain
                                                                                           Nokbi construction
                                                                                           and artisan
                                                                                           resettlement program.
----------------------------------------------------------------------------------------------------------------
Enterprise Support Project.....        $15,185,642  Improved survival        $15,123,258  Reduction in SME
                                                     rate of new                           mortality (treatment
                                                     small and medium                      firms with respect to
                                                     enterprises                           control firms) one
                                                     (SMEs) and                            year after support
                                                     National                              completion (percent).
                                                     Initiative for                       Days of individual
                                                     Human                                 coaching (total
                                                     Development                           days).
                                                     (INDH)-funded                        Beneficiaries trained.
                                                     income
                                                     generating
                                                     activities;
                                                     increased
                                                     revenue for new
                                                     SMEs and INDH-
                                                     funded income
                                                     generating
                                                     activities.
Financial Services Project.....        $44,175,252  To be determined.        $40,888,926  Microfinance
                                                                                           institutions'
                                                                                           portfolio at risk at
                                                                                           30 days (percent).
                                 .................                     .................  Value of loans granted
                                                                                           through mobile
                                                                                           branches (U.S.
                                                                                           dollars).
                                 .................                     .................  Clients of microcredit
                                                                                           associations reached
                                                                                           through mobile
                                                                                           branches.
                                 .................                     .................  Value of loan
                                                                                           agreements between
                                                                                           micro credit
                                                                                           associations and
                                                                                           Jaida (millions of
                                                                                           dirhams).
                                 .................                     .................  Value of loan
                                                                                           disbursements to
                                                                                           Jaida.
----------------------------------------------------------------------------------------------------------------
Program Administration and             $79,656,611  .................        $66,048,833
 Control, Monitoring and
 Evaluation.
----------------------------------------------------------------------------------------------------------------
Pending Subsequent Reports.....  .................  .................         $1,236,649
----------------------------------------------------------------------------------------------------------------


[[Page 12236]]


 
                                                                           Cumulative
            Projects                 Obligated          Objective        disbursements           Measures
----------------------------------------------------------------------------------------------------------------
                     Country: Mozambique Year: 2013 Quarter 4 Total Obligation: $506,924,053
      Entity to which the assistance is provided: MCA Mozambique Total Quarterly Disbursements: $63,068,311
----------------------------------------------------------------------------------------------------------------
Water Supply and Sanitation           $207,385,393  Increase access         $174,770,895  Value of municipal
 Project.                                            to reliable and                       sanitation and
                                                     quality water                         drainage systems
                                                     and sanitation                        construction
                                                     facilities.                           contracts signed.
                                                                                          Amount disbursed for
                                                                                           municipal sanitation
                                                                                           and drainage
                                                                                           construction
                                                                                           contracts.
                                 .................                     .................  Volume of water
                                                                                           produced.
                                 .................                     .................  Value of contracts
                                                                                           signed for
                                                                                           construction of water
                                                                                           systems.
                                 .................                     .................  Percent of
                                                                                           construction contract
                                                                                           disbursed for water
                                                                                           systems.
                                 .................                     .................  Rural water points
                                                                                           constructed.
                                 .................                     .................  Percent of rural
                                                                                           population of the six
                                                                                           intervention
                                                                                           districts with access
                                                                                           to improved water
                                                                                           sources.
                                 .................                     .................  Amount disbursed for
                                                                                           rural water points
                                                                                           construction
                                                                                           contracts.
                                 .................                     .................  Persons trained in
                                                                                           hygiene and sanitary
                                                                                           best practices.
----------------------------------------------------------------------------------------------------------------
Road Rehabilitation Project....       $176,307,480  Increase access         $118,862,274  Percent of roads works
                                                     to productive                         contracts disbursed.
                                                     resources and                        Kilometers of roads
                                                     markets..                             issued ``Take-over
                                                                                           Certificates''
----------------------------------------------------------------------------------------------------------------
Land Tenure Project............        $40,068,307  Establish                $35,830,188  People trained
                                                     efficient,                            (paralegal courses at
                                                     secure land                           Centre for Juridical
                                                     access for                            and Judicial
                                                     households and                        Training, general
                                                     investors..                           training at National
                                                                                           Directorate of Land
                                                                                           and Forest, etc.).
                                 .................                     .................  Land administration
                                                                                           offices established
                                                                                           or upgraded.
                                 .................                     .................  Land tenure
                                                                                           regularization (LTR)
                                                                                           urban parcels mapped.
                                 .................                     .................  LTR DUATs (Direito de
                                                                                           Use e Aproveitamento--
                                                                                           Portuguese for land
                                                                                           lease) delivered to
                                                                                           the urban
                                                                                           beneficiaries.
                                 .................                     .................  LTR rural hectares
                                                                                           mapped.
                                 .................                     .................  LTR DUATs delivered to
                                                                                           the rural
                                                                                           beneficiaries.
                                 .................                     .................  Community Land Fund
                                                                                           (ITC) rural hectares
                                                                                           formalized.
                                 .................                     .................  ITC communities land
                                                                                           areas mapped.
Farmer Income Support Project..        $19,250,117  Improve coconut          $16,982,021  Coconut seedlings
                                                     productivity and                      planted.
                                                     diversification                      Survival rate of
                                                     into cash crop..                      coconut seedlings
                                                                                           (percent).
                                                                                          Hectares of alternate
                                                                                           crops under
                                                                                           production.
                                 .................                     .................  Farmers trained in
                                                                                           surveillance and pest
                                                                                           and disease control
                                                                                           for coconuts.
                                 .................                     .................  Farmers trained in
                                                                                           alternative crop
                                                                                           production and
                                                                                           productivity
                                                                                           enhancing strategies.
                                 .................                     .................  Farmers trained in
                                                                                           planting and post-
                                                                                           planting management
                                                                                           of coconuts.
                                 .................                     .................  Farmers using
                                                                                           alternative crop
                                                                                           production and
                                                                                           productivity
                                                                                           enhancing strategies.
                                 .................                     .................  Businesses receiving
                                                                                           Business Development
                                                                                           Fund grants.
----------------------------------------------------------------------------------------------------------------
Program Administration and             $63,912,756  .................        $42,872,175
 Control, Monitoring and
 Evaluation.
----------------------------------------------------------------------------------------------------------------
Pending Subsequent Reports.....  .................  .................         $5,999,607
----------------------------------------------------------------------------------------------------------------


 
                                                                           Cumulative
            Projects                 Obligated          Objective        disbursements           Measures
----------------------------------------------------------------------------------------------------------------
                      Country: Namibia Year: 2013 Quarter 4 Total Obligation: $304,477,815
       Entity to which the assistance is provided: MCA Namibia Total Quarterly Disbursements: $27,794,245
----------------------------------------------------------------------------------------------------------------
Education Project..............       $141,455,296  Improve the              $88,788,480  Learners (any level)
                                                     quality of the                        participating in the
                                                     workforce in                          47 schools sub-
                                                     Namibia by                            activity.
                                                     enhancing the                        Educational facilities
                                                     equity and                            constructed,
                                                     effectiveness of                      rehabilitated,
                                                     basic.                                equipped in the 47
                                                                                           schools
                                                                                           sub[hyphen]activity.

[[Page 12237]]

 
                                 .................                     .................  Percent of contracted
                                                                                           construction works
                                                                                           disbursed for 47
                                                                                           schools.
                                 .................                     .................  Textbooks delivered.
                                 .................                     .................  Educators trained to
                                                                                           be textbook
                                                                                           management trainers.
                                 .................                     .................  Educators trained to
                                                                                           be textbook
                                                                                           utilization trainers.
                                 .................                     .................  Percent disbursed
                                                                                           against works
                                                                                           contracts for
                                                                                           Regional Study
                                                                                           Resource Centers
                                                                                           Activity.
                                 .................                     .................  Visits to MCA Namibia
                                                                                           assisted Regional
                                                                                           Study and Resource
                                                                                           Centres.
                                 .................                     .................  Compliance rate for
                                                                                           National Training
                                                                                           Fund levy.
                                 .................                     .................  Graduates from MCC-
                                                                                           supported education
                                                                                           activities.
                                 .................                     .................  Percent disbursed
                                                                                           against construction,
                                                                                           rehabilitation, and
                                                                                           equipment contracts
                                                                                           for Community Skills
                                                                                           and Development
                                                                                           Centres.
                                 .................                     .................  Namibia Student
                                                                                           Financial Assistance
                                                                                           Fund Policy in place
                                                                                           (date).
Tourism Project................        $68,678,683  Grow the Namibian        $27,106,799  Tourists to Etosha
                                                     tourism industry                      National Park (ENP).
                                                     with a focus on                      Galton Gate Plan
                                                     increasing                            implemented
                                                     income to                             (percent).
                                                     households in                        Percent disbursed
                                                     communal.                             against construction,
                                                                                           rehabilitation and
                                                                                           equipment contracts
                                                                                           for ENP housing units/
                                                                                           management
                                                                                           structures.
                                 .................                     .................  Game translocated with
                                                                                           MCA Namibia support.
                                 .................                     .................  Unique visits on
                                                                                           Namibia Tourism Board
                                                                                           website.
                                 .................                     .................  Leisure tourist
                                                                                           arrivals.
                                 .................                     .................  North American tourism
                                                                                           businesses (travel
                                                                                           agencies and tour
                                                                                           operators) that offer
                                                                                           Namibian tours or
                                                                                           tour packages.
                                 .................                     .................  Value of grants issued
                                                                                           by the Conservancy
                                                                                           Development Support
                                                                                           Grant Fund (Namibian
                                                                                           dollars).
                                 .................                     .................  Amount of new private
                                                                                           sector investment
                                                                                           secured by MCA
                                                                                           Namibia assisted
                                                                                           conservancies
                                                                                           (Namibian dollars).
                                 .................                     .................  Annual gross revenue
                                                                                           to conservancies
                                                                                           receiving MCA Namibia
                                                                                           assistance.
Agriculture Project............        $51,386,344  Enhance the              $34,474,814  Participating
                                                     health and                            households registered
                                                     marketing                             in the Community-
                                                     efficiency of                         Based Rangeland and
                                                     livestock in the                      Livestock Management
                                                     NCAs of Namibia                       sub-activity.
                                                     and to increase                      Grazing areas with
                                                     income.                               documented combined
                                                                                           management plans.
                                 .................                     .................  Parcels corrected or
                                                                                           incorporated in land
                                                                                           system.
                                 .................                     .................  Stakeholders trained.
                                 .................                     .................  Cattle tagged with
                                                                                           radio frequency
                                                                                           identification tags.
                                 .................                     .................  Percent disbursed
                                                                                           against works
                                                                                           contracts for State
                                                                                           Veterinary Offices.
                                 .................                     .................  Value of grant
                                                                                           agreements signed
                                                                                           under Livestock
                                                                                           Market Efficiency
                                                                                           Fund.
                                 .................                     .................  Farmers trained.
                                 .................                     .................  Value of grant
                                                                                           agreements signed
                                                                                           under Indigenous
                                                                                           Natural Product
                                                                                           Innovation Fund.
----------------------------------------------------------------------------------------------------------------
Program Administration and             $42,957,491  .................        $27,409,907
 Control, Monitoring and
 Evaluation.
Pending Subsequent Reports.....  .................  .................         $8,867,273
----------------------------------------------------------------------------------------------------------------


 
                                                                           Cumulative
            Projects                 Obligated          Objective         expenditures           Measures
----------------------------------------------------------------------------------------------------------------
                   Country: Nicaragua \6\ Year: 2013 Quarter 4 Total Obligation: $112,703,083
        Entity to which the assistance is provided: MCA Nicaragua Total Quarterly Expenditures: $-28,532
----------------------------------------------------------------------------------------------------------------
Property Regularization Project         $7,158,799  Increase                  $7,158,799  Additional parcels
                                                     Investment by                         with a registered
                                                     strengthening                         title, urban.
                                                     property rights.                     Additional parcels
                                                                                           with a registered
                                                                                           title, rural.
                                 .................                     .................  Area covered by
                                                                                           cadastral mapping

[[Page 12238]]

 
                                 .................                     .................  Automated database of
                                                                                           registry and cadastre
                                                                                           installed in the 10
                                                                                           municipalities of
                                                                                           Leon
                                 .................                     .................  Protected Areas with
                                                                                           formulated Management
                                                                                           Plans.
----------------------------------------------------------------------------------------------------------------
Transportation Project.........        $57,884,159  Reduce                   $57,884,159  Annual Average daily
                                                     transportation                        traffic volume:
                                                     costs between                         Villanueva--Guasaule.
                                                     Leon and                             Average daily traffic
                                                     Chinandega and                        volume: Somotillo-
                                                     national,                             Cinco Pines (S1).
                                                     regional and                         Annual average daily
                                                     global markets.                       traffic volume:
                                                                                           Le[oacute]n-Poneloya-
                                                                                           Las Pe[ntilde]itas.
                                 .................                     .................  International
                                                                                           roughness index:
                                                                                           Villanueva--Guasaule.
                                 .................                     .................  International
                                                                                           roughness index:
                                                                                           Somotillo-Cinco
                                                                                           Pines.
                                 .................                     .................  International
                                                                                           roughness index:
                                                                                           Le[oacute]n-Poneloya-
                                                                                           Las Pe[ntilde]itas.
                                 .................                     .................  Kilometers of NI
                                                                                           [highway?] upgraded:
                                                                                           Villanueva--Guasaule.
                                 .................                     .................  Kilometers of S1 road
                                                                                           upgraded.
                                 .................                     .................  Kilometers of S9 road
                                                                                           upgraded.
                                 .................                     .................  Kilometers of NI
                                                                                           upgraded: R1 and R2
                                                                                           and S13.
----------------------------------------------------------------------------------------------------------------
Rural Development Project......        $32,709,497  Increase the             $32,709,497  Beneficiaries with
                                                     value added of                        business plans.
                                                     farms and                            Manzanas (1 manzana =
                                                     enterprises in                        1.7 hectares), by
                                                     the region.                           sector, harvesting
                                                                                           higher-value crops.
                                 .................                     .................  Beneficiaries
                                                                                           implementing forestry
                                                                                           business plans under
                                                                                           Improvement of Water
                                                                                           Supplies Activity.
                                 .................                     .................  Manzanas reforested.
                                 .................                     .................  Manzanas with trees
                                                                                           planted.
----------------------------------------------------------------------------------------------------------------
Program Administration, Due            $14,950,629  .................        $14,950,629
 Diligence, Monitoring and
 Evaluation.
----------------------------------------------------------------------------------------------------------------


 
                                                                           Cumulative
            Projects                 Obligated          Objective        disbursements           Measures
----------------------------------------------------------------------------------------------------------------
                    Country: Philippines Year: 2013 Quarter 4 Total Obligation: $433,910,000
     Entity to which the assistance is provided: MCA Philippines Total Quarterly Disbursements: $22,333,933
----------------------------------------------------------------------------------------------------------------
Kalahi-CIDSS Project...........       $120,000,000  Improve the              $42,045,588  Percent of Municipal
                                                     responsiveness                        Local Government
                                                     of local                              Units that provide
                                                     governments to                        funding support for
                                                     community needs,                      Kalahi-CIDSS (KC)
                                                     encourage                             subproject operations
                                                     communities to                        and maintenance.
                                                     engage in                            Completed KC
                                                     development                           subprojects
                                                     activities..                          implemented in
                                                                                           compliance with
                                                                                           technical plans and
                                                                                           within schedule and
                                                                                           budget.
                                 .................                     .................  Barangays that have
                                                                                           completed specific
                                                                                           training on
                                                                                           subproject management
                                                                                           and implementation.
Secondary National Roads              $214,493,000  Reduce                   $48,409,627  Kilometers of road
 Development Project.                                transportation                        sections completed.
                                                     costs and                            Bridges replaced.
                                                     improve access                       Bridges rehabilitated.
                                                     to markets and                       Value of road
                                                     social services..                     construction
                                                                                           contracts signed.
                                 .................                     .................  Value of road
                                                                                           construction
                                                                                           contracts disbursed.
Revenue Administration Reform          $54,300,000  Increase tax              $5,847,271  Number of Audits.
 Project.                                            revenues over                        Revenue District
                                                     time and support                      Offices using the
                                                     the Department                        electronic tax
                                                     of Finance's                          information system.
                                                     initiatives to                       Percent of audit
                                                     detect and deter                      completed in
                                                     corruption                            compliance with
                                                     within its                            prescribed period of
                                                     revenue                               120 days.
                                                     agencies..                           Percent of audit cases
                                                                                           performed using
                                                                                           automated audit tool.
                                 .................                     .................  Successful case
                                                                                           resolutions.
                                 .................                     .................  Personnel charged with
                                                                                           graft, corruption,
                                                                                           lifestyle and/or
                                                                                           criminal cases.
                                 .................                     .................  Time taken to complete
                                                                                           investigation
                                                                                           (average).
----------------------------------------------------------------------------------------------------------------

[[Page 12239]]

 
Program Administration and             $45,117,000  .................         $9,877,470
 Control, Monitoring and
 Evaluation.
----------------------------------------------------------------------------------------------------------------
Pending Subsequent Reports.....  .................  .................         $4,723,962
----------------------------------------------------------------------------------------------------------------


 
                                                                           Cumulative
            Projects                 Obligated          Objective        disbursements           Measures
----------------------------------------------------------------------------------------------------------------
                      Country: Senegal Year: 2013 Quarter 4 Total Obligation: $540,000,000
       Entity to which the assistance is provided: MCA Senegal Total Quarterly Disbursements: $12,912,694
----------------------------------------------------------------------------------------------------------------
Road Rehabilitation Project....       $324,712,499  Expand access to         $40,689,656  Value of contracts
                                                     markets and                           signed for the
                                                     services.                             feasibility, design,
                                                                                           supervision and
                                                                                           program management of
                                                                                           the RN2 and RN6
                                                                                           National Roads.
                                 .................                     .................  Percent of
                                                                                           disbursements for the
                                                                                           contract signed for
                                                                                           the constructions of
                                                                                           the RN 2 and RN6.
                                 .................                     .................  Kilometers of roads
                                                                                           rehabilitated on the
                                                                                           RN2.
                                 .................                     .................  Annual average daily
                                                                                           traffic Richard-Toll--
                                                                                           Ndioum.
                                 .................                     .................  Percent change in
                                                                                           travel time on the
                                                                                           RN2.
                                 .................                     .................  International
                                                                                           Roughness Index on
                                                                                           the RN2 (lower number
                                                                                           = smoother road).
                                 .................                     .................  Kilometers of roads
                                                                                           covered by the
                                                                                           contract for the
                                                                                           studies, the
                                                                                           supervision and
                                                                                           management of the
                                                                                           RN2.
                                 .................                     .................  Kilometers of roads
                                                                                           rehabilitated on the
                                                                                           RN6.
                                 .................                     .................  Annual average daily
                                                                                           traffic Ziguinchor--
                                                                                           Tanaff.
                                 .................                     .................  Annual average daily
                                                                                           traffic Tanaff--
                                                                                           Kolda.
                                 .................                     .................  Annual average daily
                                                                                           traffic Kolda--
                                                                                           Kounkan[eacute].
                                 .................                     .................  Percent change in
                                                                                           travel time on the
                                                                                           RN6.
                                 .................                     .................  International
                                                                                           roughness index on
                                                                                           the RN6 (lower number
                                                                                           = smoother road).
                                 .................                     .................  Kilometers of roads
                                                                                           covered by the
                                                                                           contract for the
                                                                                           studies, the
                                                                                           supervision and
                                                                                           management of the
                                                                                           RN6.
----------------------------------------------------------------------------------------------------------------
Irrigation and Water Resources        $170,008,860  Improve                  $29,484,039  Tons of irrigated rice
 Management Project.                                 productivity of                       production.
                                                     the agricultural                     Potentially irrigable
                                                     sector.                               lands area (Delta and
                                                                                           Ngallenka).
                                 .................                     .................  Hectares under
                                                                                           production.
                                 .................                     .................  Percent of the
                                                                                           disbursements on the
                                                                                           contracts signed for
                                                                                           the studies in the
                                                                                           Delta and the
                                                                                           Ngallenka.
                                 .................                     .................  Value of the
                                                                                           construction
                                                                                           contracts signed for
                                                                                           the irrigation
                                                                                           infrastructure in the
                                                                                           Delta and the
                                                                                           Ngallenka.
                                 .................                     .................  Cropping intensity
                                                                                           (hectares under
                                                                                           production per year/
                                                                                           cultivable hectares)
                                                                                           (Delta and
                                                                                           Ngallenka).
                                 .................                     .................  Hectares mapped.
                                 .................                     .................  New conflicts resolved
                                                                                           (percent).
                                 .................                     .................  People trained on land
                                                                                           security tools.
                                 .................                     .................  Women trained on land
                                                                                           security tools.
----------------------------------------------------------------------------------------------------------------
Program Administration and             $45,278,641  .................        $14,079,655
 Monitoring and Evaluation.
----------------------------------------------------------------------------------------------------------------
Pending Subsequent Reports.....  .................  .................         $1,385,021
----------------------------------------------------------------------------------------------------------------


 
                                                                           Cumulative
            Projects                 Obligated          Objective        disbursements           Measures
----------------------------------------------------------------------------------------------------------------
                      Country: Tanzania Year: 2013 Quarter 4 Total Obligation: $698,136,000
      Entity to which the assistance is provided: MCA Tanzania Total Quarterly Disbursements: $119,230,113
----------------------------------------------------------------------------------------------------------------
Energy Sector Project..........       $202,082,375  Increase value          $176,848,342  Number of current
                                                     added to                              power customers
                                                     businesses.                           (Zanzibar).
                                                                                          Transmission and
                                                                                           distribution
                                                                                           substations capacity
                                                                                           (megawatt-peak)
                                                                                           (Zanzibar).
                                 .................                     .................  Technical and non-
                                                                                           technical losses
                                                                                           (Zanzibar) (percent).

[[Page 12240]]

 
                                 .................                     .................  Kilometers of 132
                                                                                           kilovolt (KV) lines
                                                                                           constructed
                                                                                           (Zanzibar).
                                 .................                     .................  Percent disbursed on
                                                                                           overhead lines
                                                                                           contract (Zanzibar).
                                 .................                     .................  Current power
                                                                                           customers (Malagarasi/
                                                                                           Kigoma).
                                 .................                     .................  Capacity of
                                                                                           photovoltaic systems
                                                                                           installed (kilowatt-
                                                                                           peak) (Malagarasi/
                                                                                           Kigoma).
                                 .................                     .................  Current power
                                                                                           customers (all six
                                                                                           project regions)
                                                                                           (Mainland).
                                 .................                     .................  ......................
                                 .................                     .................  Kilometers of 33/11KV
                                                                                           lines constructed
                                                                                           (Mainland).
                                 .................                     .................  Transmission and
                                                                                           distribution
                                                                                           substations capacity
                                                                                           (megavolt ampere)
                                                                                           (all six project
                                                                                           regions) (Mainland).
                                 .................                     .................  Technical and
                                                                                           nontechnical losses
                                                                                           (Mainland and Kigoma)
                                                                                           (percent).
                                 .................                     .................  Cost recovery ratio
                                                                                           (Mainland).
----------------------------------------------------------------------------------------------------------------
Transport Sector Project.......       $396,138,379  Increase cash           $360,646,735  Percent disbursed on
                                                     crop revenue and                      construction
                                                     aggregate                             contracts.
                                                     visitor spending.                    Surfacing complete:
                                                                                           Tunduma--Sumbawanga
                                                                                           (percent).
                                 .................                     .................  Surfacing complete:
                                                                                           Tanga--Horohoro
                                                                                           (percent).
                                 .................                     .................  Surfacing complete:
                                                                                           Namtumba--Songea
                                                                                           (percent).
                                 .................                     .................  Surfacing complete:
                                                                                           Peramiho--Mbinga
                                                                                           (percent).
                                 .................                     .................  Kilometers of roads
                                                                                           completed (taken
                                                                                           over).
                                 .................                     .................  Pemba: Percent
                                                                                           disbursed on
                                                                                           construction
                                                                                           contract.
                                 .................                     .................  Surfacing complete:
                                                                                           Pemba (percent).
                                 .................                     .................  Kilometers of roads
                                                                                           completed (taken
                                                                                           over): Zanzibar.
                                 .................                     .................  Road maintenance
                                                                                           expenditures:
                                                                                           Mainland trunk roads
                                                                                           (percent).
                                 .................                     .................  Road maintenance
                                                                                           expenditures:
                                                                                           Zanzibar rural roads
                                                                                           (percent).
                                 .................                     .................  Runway surfacing
                                                                                           complete (percent).
----------------------------------------------------------------------------------------------------------------
Water Sector Project...........        $60,533,101  Increase                 $49,475,588  Volume of water
                                                     investment in                         produced--Lower Ruvu
                                                     human and                             (millions of liters
                                                     physical capital                      per day).
                                                     and to reduce                        Operations and
                                                     the prevalence                        maintenance cost
                                                     of water-related                      recovery--Lower Ruvu
                                                     disease.                              (percent).
                                 .................                     .................  Volume of water
                                                                                           produced--Morogoro
                                                                                           (millions of liters
                                                                                           per day).
                                 .................                     .................  Operations and
                                                                                           maintenance cost
                                                                                           recovery--Morogoro
                                                                                           (percent).
----------------------------------------------------------------------------------------------------------------
Program Administration and             $39,382,145  .................        $33,083,449
 Control, Monitoring and
 Evaluation.
----------------------------------------------------------------------------------------------------------------
\1\ ``Total Obligation'' for listed Compacts includes both ``Compact Implementation Funding'' under section
  609(g) of the Act as well as funding under section 605 of the Act.
\2\ ``Disbursements'' are cash outlays rather than expenditures.
\3\ ``Measures'' are the same Key Performance Indicators that MCC reports each quarter. The Key Performance
  Indicators may change over time to more accurately reflect compact implementation progress. The unit for these
  measures is ``a number of'' unless otherwise indicated.
\4\ Program administration funds are used to pay items such as salaries, rent, and the cost of office equipment.
\5\ Amounts listed as ``Pending Subsequent Reports'' represent disbursements made that will be allocated to
  individual projects in the subsequent quarter(s) and reported as such in subsequent quarterly report(s).
\6\ These compacts are closed; however, deobligations took place during the reporting period.
The following MCC compacts are closed and, therefore, do not have any quarterly disbursements: Armenia, Benin,
  Cape Verde I, Honduras, Madagascar, Mali and Vanuatu.


 
                 619(b) Transfer or Allocation of Funds
-------------------------------------------------------------------------
   United States agency to
which funds were transferred         Amount            Description of
        or allocated                                 program or project
------------------------------------------------------------------------
None........................  None................  None.
------------------------------------------------------------------------


[[Page 12241]]

[FR Doc. 2014-04658 Filed 3-3-14; 8:45 am]