DEPARTMENT OF TRANSPORTATION

Federal Aviation Administration


Notice of Intent To Prepare an Environmental Assessment (EA) for 
the Proposed Part 139 Operating Certificate and Related Actions at 
Paulding Northwest Atlanta Airport

AGENCY: Federal Aviation Administration (FAA), DOT.

ACTION: Notice of Intent to prepare an Environmental Assessment and 
notice of opportunity for public comment.

-----------------------------------------------------------------------

SUMMARY: The Federal Aviation Administration (FAA) is announcing its 
intent to prepare an Environmental Assessment (EA) pursuant to the 
National Environmental Policy Act (NEPA) of 1969 and its implementing 
regulations for the application by Paulding County Airport Authority 
(PCAA) for certification of Paulding Northwest Atlanta Airport (PUJ) 
under 14 Code of Federal Regulations Part 139. The EA will also address 
connected actions related to the introduction of scheduled commercial 
air carrier service at PUJ. The purpose of the EA is to consider and 
evaluate the potential environmental impacts of the proposed actions 
and alternatives, including the no-action alternative.

DATES: FAA invites comments on the contents of EA during a 30-day 
comment period that will be initiated upon publication of this Notice. 
Please submit any written comments you may have on the content of the 
EA May 21, 2014.

ADDRESSES: Please submit any written comments you may have on the 
content of the EA to Atlanta Airports District Office, Attn: Lisa 
Favors, Env. Program Manager, 1701 Columbia Ave., Suite 2-260, Atlanta, 
GA 30337-2747. Comments may also be submitted by email to 
[email protected].

FOR FURTHER INFORMATION CONTACT: Lisa Favors, Environmental Program 
Manager, Atlanta Airports District Office, 1701 Columbia Ave., Suite 2-
260, Atlanta, GA 30337-2747, (404) 305-7145, [email protected].

SUPPLEMENTARY INFORMATION: Paulding Northwest Atlanta Airport (PUJ or 
airport) is located outside Atlanta, Georgia in the town of Dallas, 
Georgia. It is owned by Paulding County and the PCAA and operated by 
PCAA. It is designated as a general aviation airport. In 2013, the PCAA 
submitted an application to the FAA requesting a Part 139 Operating 
Certificate. A Part 139 Operating Certificate allows the airport to 
accommodate scheduled passenger-carrying operations, frequently 
referred to as ``commercial service.'' The FAA plans to prepare an EA 
in accordance with FAA Order 1050.1E, Policies and Procedures for 
Considering Environmental Impacts and FAA Order 5050.4B, National 
Environmental Policy Act Implementing Instructions For Airport Actions.
    It is anticipated that the EA will consider the potential 
environmental impacts associated with the following

[[Page 22178]]

proposed actions, and alternatives including the no-action alternative, 
at PUJ: (1) Obtain an Airport Operating Certificate from FAA, as 
required for commercial service under 14 CFR Part 139; (2) Relocate the 
Runway 13 threshold 500 feet west, to the end of the existing concrete 
pavement, which would increase the usable runway length from 5,505 feet 
to 6,005 feet; (3) Relocate the Runway 13 Precision Approach Path 
Indicators (PAPIs) by approximately 500 feet from their current 
location, to accommodate the threshold relocation; (4) Re-mark the 
runway and modify the runway lighting and electrical system to coincide 
with the new threshold location; (5) Extend the parallel taxiway 500 
feet west, to connect with the end of the existing runway pavement; (6) 
Install approximately 19,000 linear feet of wildlife fencing around the 
perimeter of the Airport; (7) Construct an Aircraft Rescue and Fire 
Fighting (ARFF) facility adjacent to Airport Parkway, in conjunction 
with the construction by Paulding County of an Airport Fire Station/
Emergency 911 Call Center; (8) Provide a mobile Air Traffic Control 
Tower in the existing terminal area; (9) Obtain FAA redesignation of 
airspace (to Class D) during periods when mobile Air Traffic Control 
Tower is in operation; (10) Construct corporate hangars in the existing 
terminal area; (11) Construct a terminal area expansion to provide 
hangars and apron area; (12) Design and construct a 400-foot extension 
of the Runway Safety Area (RSA) at the Runway 31 End to provide a 1,000 
feet long by 500 feet wide RSA; (13) Design and install an approach 
lighting system consisting of a Medium-Intensity Approach Lighting 
System with Sequenced Flashers (MALSF) and towers; (14) Design paving 
and marking for a corporate hangar area expansion; (15) Design paving 
and marking for an itinerant parking area expansion; (16) Design paving 
and marking for a T-hangar tie-down area expansion; (17) Construct a 
blast pad on new pavement at the Runway 13 End; (18) Widen Runway 13-31 
from 100 feet to 150 feet; (19) Provide temporary vehicle parking; and 
(20) Acquire land interest for approximately two (2) acres of property 
within the future Runway Protection Zone (RPZ) located west of the 
Runway 13 End.
    In addition, the EA will consider the cumulative impacts of airport 
improvement projects recently completed at PUJ including a runway 
safety area expansion project and a taxiway widening and lighting 
project. The EA will also consider the environmental impacts of the 
introduction of scheduled commercial air carrier service to PUJ based 
on an air traffic forecast. In addition, or in the alternative to the 
forecast, the EA may consider a request by one or more commercial 
service air carrier(s) to amend its operating specifications to allow 
operation at PUJ. The EA will also consider the environmental impacts 
of similar actions not connected to the introduction of scheduled 
commercial air carrier service at PUJ but expected to occur at PUJ 
around the same time as the connected actions.
    If, during preparation of the EA, it is determined that the 
proposed project would result in significant environmental impacts that 
cannot be mitigated, the FAA will issue a revised Notice of Intent 
(NOI) to complete the NEPA process using an Environmental Impact 
Statement (EIS).
    The FAA is now inviting the public, agencies, tribal governments, 
and other interested parties to provide comments, suggestions, and 
input on the content of the EA. The FAA requests that comments be as 
specific as possible. The FAA will not provide responses to those 
submitting comments at this time, but all timely comments will be 
considered and included in the public record. Additional comments will 
be solicited on a draft EA, and at least one public meeting held in 
Paulding County, upon completion of the draft EA.

    Issued in Atlanta, Georgia, on April 15, 2014.
Larry F. Clark,
Manager, Atlanta Airports District Office, Southern Region.
[FR Doc. 2014-09027 Filed 4-18-14; 8:45 am]