DEPARTMENT OF HOMELAND SECURITY
Federal Emergency Management Agency
[Docket ID FEMA-2014-0009]
Simplified Procedures Project Thresholds for the Public
Assistance Program
AGENCY: Federal Emergency Management Agency, DHS.
ACTION: Notice.
-----------------------------------------------------------------------
SUMMARY: On February 26, 2014, the Federal Emergency Management Agency
(FEMA) published a final rule (79 FR 10685) revising the monetary
thresholds for when FEMA will process an application using simplified
procedures under its Public Assistance Program. FEMA based the revised
thresholds on an analysis it completed pursuant to the Sandy Recovery
Improvement Act of 2013. The findings of the analysis were submitted in
a Report to Congress on January 29, 2014. FEMA is seeking comment on
the findings in this Report to inform any future revisions to the
project thresholds.
DATES: Comments must be received by January 20, 2015.
ADDRESSES: Comments must be identified by docket ID FEMA-2014-0009 and
may be submitted by one of the following methods:
Federal eRulemaking Portal: http://www.regulations.gov. Follow the
instructions for submitting comments.
Mail: Regulatory Affairs Division, Office of Chief Counsel, Federal
Emergency Management Agency, Room 8NE, 500 C Street SW., Washington, DC
20472-3100.
FOR FURTHER INFORMATION CONTACT: Liza Davis, Associate Chief Counsel,
Regulatory Affairs, Office of Chief Counsel, Federal Emergency
Management Agency, 500 C Street SW., Washington, DC 20472, 202-646-
4046, [email protected].
SUPPLEMENTARY INFORMATION:
I. Public Participation
Instructions: All submissions received must include the agency name
and docket ID. Regardless of the method used for submitting comments or
material, all submissions will be posted, without change, to the
Federal eRulemaking Portal at http://www.regulations.gov, and will
include any personal information you provide. Therefore, submitting
this information makes it public. You may wish to read the Privacy Act
notice, which can be viewed by clicking on the ``Privacy Notice'' link
in the footer of www.regulations.gov.
You may submit your comments and material by the methods specified
in the ADDRESSES section of this Notice. Please submit your comments
and any supporting material by only one means to avoid the receipt and
review of duplicate submissions.
Docket: The Report to Congress and the final rule are available in
docket ID FEMA-2014-0009. For access to the docket to read background
documents or comments received, go to the Federal eRulemaking Portal at
http://www.regulations.gov and search for the docket ID. Submitted
comments may also be inspected at FEMA, Office of Chief Counsel, Room
8NE, 500 C Street SW., Washington, DC 20472.
II. Background
FEMA's Public Assistance program provides grants to State, Tribal,
and local governments, as well as eligible private nonprofit
organizations, for debris removal, emergency protective measures, and
the repair, replacement, or restoration of disaster-damaged facilities
after a Presidentially-declared emergency or major disaster.\1\ Each
grant award is categorized as either a large or small project, which is
determined by a monetary threshold set each year by FEMA pursuant to
statute.\2\ The Sandy Recovery Improvement Act of 2013 (SRIA) \3\
required FEMA to analyze the thresholds, and, based on its findings, to
implement new thresholds immediately. FEMA submitted a Report to
Congress, ``Determination of the Public Assistance Simplified
Procedures Thresholds,'' on January 29, 2014.\4\ The report included a
summary of FEMA's analysis and findings. FEMA implemented the new
thresholds based on those findings on February 26, 2014 via a final
rule.\5\ FEMA raised the maximum threshold from $68,500 to $120,000;
all projects below this amount are categorized as small projects, and
all projects at or above this amount are categorized as large projects.
FEMA raised the minimum threshold from $1,000 to $3,000.\6\ Both the
maximum and minimum threshold will be adjusted annually to reflect
changes in the Consumer Price Index for All Urban Consumers (CPI)
published by the U.S. Department of Labor.
---------------------------------------------------------------------------
\1\ The Public Assistance program is authorized by the Robert T.
Stafford Disaster Relief and Emergency Assistance Act, as amended,
42 U.S.C. 5170a, 5170b, 5172, 5173, 5192.
\2\ See 42 U.S.C. 5189; 44 CFR 206.203(c), 206.205. FEMA
obligates money for a small project based on an estimate of the
project cost; FEMA obligates money for a large project based on
actual project costs as the project progresses and cost
documentation is provided to FEMA. See 44 CFR 206.203(c); Public
Assistance Guide, FEMA 322 (June 2007), Chapter 3, ``Applying for
Public Assistance,'' ``Project Formulation'' available at http://www.fema.gov/public-assistance-local-state-tribal-and-non-profit/public-assistance-guide-3.
\3\ Public Law 113-2, section 1107, codified in relevant part at
42 U.S.C. 5189.
\4\ Both the Report to Congress and the Final Rule are included
in the docket for this Notice on www.regulations.gov under Docket ID
FEMA-2014-0009. A copy of the report is also available at http://www.fema.gov/media-library/assets/documents/90458.
\5\ See 79 FR 10685 (Feb. 26, 2014).
\6\ See id.
---------------------------------------------------------------------------
FEMA is seeking comment on the findings that are included in its
Report to Congress, ``Determination on the Public Assistance Simplified
Procedures Thresholds,'' to inform possible future revisions to the
maximum and minimum thresholds.
III. Public Comment
FEMA welcomes comments on all aspects of the report. In general,
FEMA expects that comments will be most useful if accompanied by
supportive data and a recommendation for future action. FEMA is
particularly interested in responses to the following questions:
1. How will the revised thresholds impact your State, Tribe,
jurisdiction, or community? For example, please consider how the
revised thresholds might impact the administrative costs of processing
grants, the timeliness of receiving recovery funds, and the ability to
ensure proper use of Public Assistance grant funding. Please provide
data to support your statement, if available.
If available please provide input on the following:
a. How does the process to administer and close out Public
Assistance grants vary between large and small projects in your State,
Tribe, and/or local jurisdiction? (i.e., for both large and small
projects, how does your State, Tribe, and/or local jurisdiction manage
grants, disburse funds, conduct final projects inspections, verify the
completion of the proposed scope of work, close out the projects, or
require any other procedures for closing out a project)?
b. For large projects, how much time is typically spent per request
for disbursement of additional funds based on completed work?
c. Since small project grants can be awarded based on the
estimates, will the increase in the maximum threshold save time for
subgrantees and grantees? If so, will this time be saved from:
i. Reducing requests for additional funds for large projects as
work progresses?
[[Page 68900]]
ii. The need to track and reconcile actual costs?
iii. Other savings?
d. Does your State, Tribe, or jurisdiction reconcile actual costs
for both small and large projects regardless of Federal requirements?
e. What is the average amount of time spent on reconciling (if
applicable and assuming the subgrantee is not requesting a net small
project overrun) and closing a project, considering project amounts
near the previous and current maximum thresholds, for example:
i. Between $40,000 and $68,500?
ii. Between $68,500 and $120,000?
iii. Between $120,000 and $200,000?
f. Will there be a reduction in the number of final site
inspections for projects between $68,500 and $120,000?
g. What is the average amount of time spent on a final site
inspection for a project between $68,500 and $120,000?
h. If the increased maximum threshold would decrease the number of
final site inspections, will that create grantee and/or subgrantees
cost savings on transportation, lodging, per diem, travel time and
other associated final inspection costs? If so, what are the estimated
savings?
i. Are there impacts to other processes and/or savings generated by
the change in the maximum threshold for the grantees and/or
subgrantees? If so, what are these impacts and savings?
j. Will the maximum threshold change cause challenges to the
grantees and subgrantees? If available, please provide any solutions to
the identified challenges.
k. What processes does your State, Tribe or jurisdiction have in
place to alleviate waste, fraud and abuse?
l. As a grantee, does your State, Tribe, or jurisdiction perform
audits on small projects? If so, can you estimate how much it costs to
complete the audit?
m. Does your State, Tribe, or jurisdiction foresee or plan to
change your policies, procedures, laws, or regulations in response to
the new maximum threshold? For example:
i. Grantee/subgrantee cost shares for large or small projects (if
so, can you estimate how much or by what percentage change)?
ii. Reconciliation for large or small projects?
iii. Audits for large or small projects?
iv. Additional consolidation of work on small projects?
2. How will the change to the minimum threshold impact your State,
Tribe, jurisdiction, or community? For example, please consider how it
might impact the administrative costs of processing grants, the
timeliness of receiving recovery funds, and the ability to ensure
proper use of Public Assistance grant funding. Please provide data to
support your statement, if available.
a. How many projects between $1,000 and $3,000 would be
consolidated into a single project worksheet over $3,000 based on a
logical grouping of work (which is the current standard)? If not many,
why?
b. Are there obstacles to project consolidation that FEMA needs to
consider? If so, please provide solutions to the identified obstacles.
c. Is there a way to track the number of projects that will be
consolidated? Would your State, Tribe, jurisdiction, or community be
willing to submit data to support an estimate of the number of
consolidated projects and/or participate in a survey to collect data?
d. Is there a way to track the number of projects that did not meet
the minimum threshold and will not be consolidated? Would your State,
Tribe, jurisdiction, or community be willing to submit data to support
an estimate of the number of consolidated project and/or participate in
a survey to collect data?
e. Will greater consolidation of projects based on a logical
grouping of work under the minimum threshold save time in the closeout
of a small project? For example, will closing one consolidated project
worksheet save time compared to closing three separate project
worksheets?
f. Does your State, Tribe, or jurisdiction foresee or plan to
change your policies, procedures, laws, or regulations in response to
the new minimum threshold? For example:
i. Training and policies for project consolidation and logical
grouping.
ii. Change to disaster assistance minimum thresholds in your State,
Tribe, or jurisdiction, if applicable.
3. Do you have other comments or recommendations related to this
subject that you would like to share for FEMA's consideration?
Authority: 42 U.S.C. 5189.
Dated: November 7, 2014.
W. Craig Fugate,
Administrator, Federal Emergency Management Agency.
[FR Doc. 2014-27470 Filed 11-18-14; 8:45 am]