[Federal Register Volume 80, Number 39 (Friday, February 27, 2015)]
[Rules and Regulations]
[Pages 10596-10608]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-04171]


-----------------------------------------------------------------------

ENVIRONMENTAL PROTECTION AGENCY

40 CFR Parts 60, 61, and 63

[EPA-R07-OAR-2015-0016; FRL-9923-69-Region-7]


Delegation of Authority to the States of Iowa; Kansas; Missouri; 
Nebraska; Lincoln-Lancaster County, NE; and City of Omaha, NE., for New 
Source Performance Standards (NSPS), National Emission Standards for 
Hazardous Air Pollutants (NESHAP) Including Maximum Achievable Control 
Technology (MACT) Standards

AGENCY: Environmental Protection Agency (EPA).

ACTION: Delegation of authority.

-----------------------------------------------------------------------

SUMMARY: The States of Iowa, Kansas, Missouri, and Nebraska and the 
local agencies of Lincoln-Lancaster County, Nebraska, and the city of 
Omaha, Nebraska, have submitted updated regulations for delegation of 
EPA authority for implementation and enforcement of NSPS, NESHAP, and 
MACT standards. The submissions cover new EPA standards and, in some 
instances, revisions to standards previously delegated. EPA's review of 
the pertinent regulations shows that they contain adequate and 
effective procedures for the implementation and enforcement of these 
Federal standards. This action informs the public of delegations to the 
above-mentioned agencies.

DATES: This document is effective on February 27, 2015. The dates of 
delegation can be found in the SUPPLEMENTARY INFORMATION section of 
this document.

ADDRESSES: Copies of documents relative to this action are available 
for public inspection during normal business hours at the Environmental

[[Page 10597]]

Protection Agency, Air Planning and Development Branch, 11201 Renner 
Road, Lenexa, Kansas 66219. The interested persons wanting to examine 
these documents should make an appointment with the office at least 24 
hours in advance.
    Effective immediately, all notifications, applications, reports, 
and other correspondence required pursuant to the newly delegated 
standards and revisions identified in this document must be submitted 
with respect to sources located in the jurisdictions identified in this 
document, to the following addresses:
    Iowa Department of Natural Resources, Air Quality Bureau, 7900 
Hickman Road, Suite 1, Windsor Heights, Iowa 50324.
    Kansas Department of Health and the Environment, Bureau of Air, 
1000 SW Jackson Street, Suite 310, Topeka, Kansas 66612-1367.
    Missouri Department of Natural Resources, Air Pollution Control 
Program, PO Box 176, Jefferson City, Missouri 65102-0176.
    Nebraska Department of Environmental Quality, Air Quality Division, 
1200 ``N'' Street, Suite 400, P.O. Box 98922, Lincoln, Nebraska 68509.
    Lincoln-Lancaster County Health Department, Division of 
Environmental Public Health, Air Quality Section, 3140 ``N'' Street, 
Lincoln, Nebraska 68510.
    City of Omaha, Public Works Department, Air Quality Control 
Division, 5600 South 10th Street, Omaha, Nebraska 68107.
    Duplicates of required documents must also continue to be submitted 
to the EPA Regional Office at the above address.

FOR FURTHER INFORMATION CONTACT: Ms. Paula Higbee at (913) 551-7028, or 
by email at [email protected].

SUPPLEMENTARY INFORMATION: The supplementary information is organized 
in the following order:

I. What does this action do?
II. What is the authority for delegation?
III. What does delegation accomplish?
IV. What has been delegated?
V. What has not been delegated?

List of Delegation Tables

Table I--NSPS, 40 CFR part 60
Table II--NESHAP, 40 CFR part 61
Table III--NESHAP, 40 CFR part 63

I. What does this action do?

    EPA is providing notice of an update to its delegable authority for 
implementation and enforcement of the Federal standards shown in the 
tables below to the states of Iowa, Kansas, Missouri, and Nebraska. 
This action updates the delegation tables previously published at 78 FR 
71510 (November 29, 2013). EPA has established procedures by which 
these agencies are automatically delegated the authority to implement 
the standards when they adopt regulations which are identical to the 
Federal standards. We then periodically provide notice of the new and 
revised standards for which delegation has been given. This document 
does not affect or alter the status of the listed standards under state 
or Federal law.

II. What is the authority for delegation?

    1. Section 111(c)(1) of the Clean Air Act (CAA) authorizes EPA to 
delegate authority to any state agency which submits adequate 
regulatory procedures for implementation and enforcement of the NSPS 
program. The NSPS are codified at 40 CFR part 60.
    2. Section 112(l) of the CAA and 40 CFR part 63, subpart E, 
authorizes EPA to delegate authority to any state or local agency which 
submits adequate regulatory procedures for implementation and 
enforcement of emission standards for hazardous air pollutants. The 
hazardous air pollutant standards are codified at 40 CFR parts 61 and 
63, respectively.

III. What does delegation accomplish?

    Delegation confers primary responsibility for implementation and 
enforcement of the listed standards to the respective state and local 
air agencies. However, EPA also retains the concurrent authority to 
enforce the standards.

IV. What has been delegated?

    Tables I, II, and III below list the delegated standards. Each item 
listed in the Subpart column has two relevant dates listed in each 
column for each state. The first date in each block is the reference 
date to the CFR contained in the state rule. In general, the state or 
local agency has adopted the applicable standard through the date as 
noted in the table. The second date is the most recent effective date 
of the state agency rule for which the EPA has granted the delegation. 
This document specifically addresses revisions to the columns for Iowa, 
Kansas, Missouri, and Nebraska and the local agencies of Lincoln-
Lancaster County, Nebraska, and the city of Omaha, Nebraska. If there 
are no dates listed in the delegation table, the state has not accepted 
delegation of the standard and implementation of those standards reside 
with EPA.

V. What has not been delegated?

    1. The EPA regulations effective after the first date specified in 
each block have not been delegated, and authority for implementation of 
these regulations is retained solely by EPA.
    2. In some cases, the standards themselves specify that specific 
provisions cannot be delegated. In such cases, a specific section of 
the standard details what authorities can and cannot be delegated. You 
should review the applicable standard in the CFR for this information.
    3. In some cases, the state rules do not adopt the Federal standard 
in its entirety. Each state rule (available from the respective agency) 
should be consulted for specific information.
    4. In some cases, existing delegation agreements between the EPA 
and the agencies limit the scope of the delegated standards. Copies of 
delegation agreements are available from the state agencies, or from 
this office.
    5. With respect to 40 CFR part 63, subpart A, General Provisions 
(see Table III), EPA has determined that sections 63.6(g), 63.6(h)(9), 
63.7(e)(2)(ii) and (f), 63.8(f), and 63.10(f) cannot be delegated. 
Additional information is contained in an EPA memorandum titled 
``Delegation of 40 CFR part 63 General Provisions Authorities to State 
and Local Air Pollution Control Agencies'' from John Seitz, Director, 
Office of Air Quality Planning and Standards, dated July 10, 1998.

List of Delegation Tables

                            Table I--Delegation of Authority--Part 60 NSPS--Region 7
----------------------------------------------------------------------------------------------------------------
                                                                                                    State of
   Sub[dash]Part     Source category     State of Iowa     State of Kansas   State of Missouri      Nebraska
----------------------------------------------------------------------------------------------------------------
A.................  General            06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Provisions.       10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                                                          Except 60.4;       Except 60.4;
                                                           60.9; 60.10;       60.9; and 60.10..
                                                           60.16..

[[Page 10598]]

 
D.................  Fossil-Fuel Fired  06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Steam Generators  10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     for Which
                     Construction is
                     Commenced After
                     August 17, 1971.
Da................  Electric Utility   06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Steam Generating  10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Units for Which
                     Construction is
                     Commenced After
                     September 18,
                     1978.
Db................  Industrial-        06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Commercial-       10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Institutional
                     Steam Generating
                     Units.
Dc................  Small Industrial-  06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Commercial-       10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Institutional
                     Steam Generating
                     Units.
E.................  Incinerators.....  06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                                       10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
Ea................  Municipal Waste    06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Combustors for    10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Which
                     Construction is
                     Commenced After
                     December 20,
                     1989, and on or
                     before September
                     20 1994.
Eb................  Large Municipal    06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Waste Combustors  10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     for Which
                     Construction is
                     Commenced after
                     September 20,
                     1994, or for
                     Which
                     Modification or
                     Reconstruction
                     is Commenced
                     After June 19,
                     1996.
Ec................  Hospital/Medical/  06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Infectious Waste  10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Incinerators for
                     Which
                     Construction
                     Commenced after
                     June 20, 1996.
F.................  Portland Cement    10/17/00.........  07/01/08.........  6/30/12..........  07/01/13.
                     Plants.           10/21/12.........  11/05/10.........  12/30/13.........  05/13/14.
G.................  Nitric Acid        06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Plants.           10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
Ga................  Nitric Acid        .................  .................  6/30/12..........  07/01/13.
                     Plants for Which                                        12/30/13.........  05/13/14.
                     Construction,
                     Reconstruction,
                     or Modification
                     Commenced After
                     October 14, 2011.
H.................  Sulfuric Acid      06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Plants.           10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
I.................  Hot Mix Asphalt    06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Facilities.       10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
J.................  Petroleum          06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Refineries.       10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                                                          Except provisions
                                                           in Ja:
                                                           60.100a(c); in
                                                           60.101a, the
                                                           definition of
                                                           ``flare'';
                                                           60.102a(g); and
                                                           60.107a(d) and
                                                           (e)..
Ja................  Standards of       .................  .................  6/30/12..........  07/01/13.
                     Performance for                                         12/30/13.........  05/13/14.
                     Petroleum
                     Refineries for
                     Which
                     Construction,
                     Reconstruction,
                     or Modification
                     Commenced After
                     May 14, 2007.

[[Page 10599]]

 
K.................  Storage Vessels    06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     for Petroleum     10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Liquids for
                     Which
                     Construction,
                     Reconstruction,
                     or Modification
                     Commenced After
                     June 11, 1973,
                     and Prior to May
                     19, 1978.
Ka................  Storage Vessels    06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     for Petroleum     10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Liquids for
                     Which
                     Construction,
                     Reconstruction,
                     or Modification
                     Commenced After
                     May 18, 1978,
                     and Prior to
                     July 23, 1984.
Kb................  Volatile Organic   06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Liquid Storage    10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Vessels
                     (including
                     Petroleum Liquid
                     Storage Vessels)
                     for Which
                     Construction,
                     Reconstruction,
                     or Modification
                     Commenced After
                     July 23, 1984.
L.................  Secondary Lead     06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Smelters.         10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
M.................  Secondary Brass    06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     and Bronze        10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Production
                     Plants.
N.................  Basic Oxygen       06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Process Furnaces  10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     for Which
                     Construction is
                     Commenced After
                     June 11, 1973.
Na................  Basic Oxygen       06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Process           10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Steelmaking
                     Facilities for
                     Which
                     Construction is
                     Commenced After
                     January 20, 1983.
O.................  Sewage Treatment   06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Plants.           10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
P.................  Primary Copper     06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Smelters.         10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
Q.................  Primary Zinc       06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Smelters.         10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
R.................  Primary Lead       06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Smelters.         10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
S.................  Primary Aluminum   06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Reduction Plants. 10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
T.................  Phosphate          06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Fertilizer        10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Industry: Wet
                     Process
                     Phosphoric Acid
                     Plants.
U.................  Phosphate          06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Fertilizer        10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Industry:
                     Superphosphoric
                     Acid Plants.
V.................  Phosphate          06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Fertilizer        10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Industry:
                     Diammonium
                     Phosphate Plants.
W.................  Phosphate          06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Fertilizer        10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Industry: Triple
                     Superphosphate
                     Plants.
X.................  Phosphate          06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Fertilizer        10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Industry:
                     Granular Triple
                     Superphosphate
                     Storage
                     Facilities.
Y.................  Coal Preparation   06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Plants.           10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.

[[Page 10600]]

 
Z.................  Ferroalloy         06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Production        10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Facilities.
AA................  Steel Plants:      06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Electric Arc      10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Furnaces
                     Constructed
                     After October
                     21, 1974, and on
                     or Before August
                     17, 1983.
AAa...............  Steel Plants:      06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Electric Arc      10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Furnaces and
                     Argon-Oxygen
                     Decarburization
                     Vessels
                     Constructed
                     After August 17,
                     1983.
BB................  Kraft Pulp Mills.  06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                                       10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
CC................  Glass              06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Manufacturing     10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Plants.
DD................  Grain Elevators..  06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                                       10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
EE................  Surface Coating    06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     of Metal          10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Furniture.
GG................  Stationary Gas     06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Turbines.         10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
HH................  Lime               06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Manufacturing     10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Plants.
KK................  Lead-Acid Battery  06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Manufacturing     10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Plants.
LL................  Metallic Mineral   06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Processing        10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Plants.
MM................  Automobile and     06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Light Duty Truck  10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Surface Coating
                     Operations.
NN................  Phosphate Rock     06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Plants.           10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
PP................  Ammonium Sulfate   06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Manufacture.      10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
QQ................  Graphic Arts       06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Industry:         10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Publication
                     Rotogravure
                     Printing.
RR................  Pressure           06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Sensitive Tape    10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     and Label
                     Surface Coating
                     Operations.
SS................  Industrial         06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Surface Coating:  10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Large Appliances.
TT................  Metal Coil         06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Surface Coating.  10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
UU................  Asphalt            06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Processing and    10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Asphalt Roofing
                     Manufacture.
VV................  Equipment Leaks    06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     of VOC in the     10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Synthetic
                     Organic
                     Chemicals
                     Manufacturing
                     Industry.
VVa...............  Equipment Leaks    .................  .................  6/30/12..........  07/01/13.
                     of VOC in the                                           12/30/13.........  05/13/14.
                     Synthetic
                     Organic
                     Chemicals
                     Manufacturing
                     Industry for
                     Which
                     Construction,
                     Reconstruction,
                     or Modification
                     Commenced After
                     November 7, 2006.
WW................  Beverage Can       06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Surface Coating   10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Industry.
XX................  Bulk Gasoline      06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Terminals.        10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
AAA...............  New Residential    .................  07/01/08.........  6/30/12..........  07/01/13.
                     Wood Heaters.                        11/05/10.........  12/30/13.........  05/13/14.

[[Page 10601]]

 
BBB...............  Rubber Tire        06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Manufacturing     10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Industry.
DDD...............  Volatile Organic   06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Compound (VOC)    10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Emissions from
                     the Polymer
                     Manufacturing
                     Industry.
FFF...............  Flexible Vinyl     06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     and Urethane      10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Coating and
                     Printing.
GGG...............  Equipment Leaks    06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     of VOC in         10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Petroleum
                     Refineries.
GGGa..............  Equipment Leaks    .................  .................  6/30/12..........  07/01/13.
                     of VOC in                                               12/30/13.........  05/13/14.
                     Petroleum
                     Refineries for
                     Which
                     Construction,
                     Reconstruction,
                     or Modification
                     Commenced After
                     November 7, 2006.
HHH...............  Synthetic Fiber    06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Production        10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Facilities.
III...............  Volatile Organic   06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Compound (VOC)    10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Emissions From
                     the Synthetic
                     Organic Chemical
                     Manufacturing
                     Industry (SOCMI)
                     AIR Oxidation
                     Unit Processes.
JJJ...............  Petroleum Dry      06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Cleaners.         10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
KKK...............  Equipment Leaks    06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     of VOC from       10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Onshore Natural
                     Gas Processing
                     Plants.
LLL...............  Onshore Natural    06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Gas Processing:   10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     SO2 Emissions.
NNN...............  Volatile Organic   06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Compound (VOC)    10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Emissions from
                     Synthetic
                     Organic Chemical
                     Manufacturing
                     Industry (SOCMI)
                     Distillation
                     Operations.
OOO...............  Nonmetallic        06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Mineral           10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Processing
                     Plants.
PPP...............  Wool Fiberglass    06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Insulation        10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Manufacturing
                     Plants.
QQQ...............  VOC Emissions      06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     from Petroleum    10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Refinery
                     Wastewater
                     Systems.
RRR...............  Volatile Organic   06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Compound          10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Emissions from
                     Synthetic
                     Organic Chemical
                     Manufacturing
                     Industry (SOCMI)
                     Reactor
                     Processes.
SSS...............  Magnetic Tape      06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Coating           10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Facilities.
TTT...............  Industrial         06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Surface Coating:  10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Surface Coating
                     of Plastic Parts
                     for Business
                     Machines.
UUU...............  Calciners and      06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Dryers in         10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Mineral
                     Industries.

[[Page 10602]]

 
VVV...............  Polymeric Coating  06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     of Supporting     10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Substrates
                     Facilities.
WWW...............  Municipal Solid    06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Waste Landfills.  10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
AAAA..............  Small Municipal    06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Waste Combustion  10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Units for Which
                     Construction is
                     Commenced After
                     August 30, 1999
                     or for Which
                     Modification or
                     Reconstruction
                     is Commenced
                     After June 6,
                     2001.
CCCC..............  Commercial and     06/28/11.........  07/01/05.........  6/30/12..........  07/01/13.
                     Industrial Solid  10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Waste
                     Incineration
                     Units for Which
                     Construction is
                     Commenced After
                     November 30,
                     1999 or for
                     Which
                     Modification or
                     Reconstruction
                     is Commenced on
                     or After June 1,
                     2001.
DDDD..............  Commercial and     .................  07/01/05.........  Not delegated....  07/01/13.
                     Industrial Solid                     11/05/10.........                     05/13/14.
                     Waste
                     Incineration
                     Units that
                     Commenced
                     Construction On
                     or Before
                     November 30,
                     1999.
EEEE..............  Other Solid Waste  06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Incineration      10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Units for Which
                     Construction
                     Commenced After
                     December 9, 2004
                     or Modification
                     or
                     Reconstruction
                     Commenced On or
                     After June 16,
                     2006.
FFFF..............  Other Solid Waste  .................  07/01/08.........  Not delegated....  07/01/13.
                     Incineration                         11/05/10.........                     05/13/14.
                     Units that
                     Commenced
                     Construction On
                     or Before
                     December 9, 2004.
IIII..............  Stationary         06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Compression       10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Ignition
                     Internal
                     Combustion
                     Engines.
JJJJ..............  Stationary Spark   06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Ignition          10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Internal
                     Combustion
                     Engines.
KKKK..............  Stationary         06/28/11.........  07/01/08.........  6/30/12..........  07/01/13.
                     Combustion        10/24/12.........  11/05/10.........  12/30/13.........  05/13/14.
                     Turbines.
LLLL..............  New Sewage Sludge  .................  .................  6/30/12..........  07/01/13.
                     Incinerator                                             12/30/13.........  05/13/14.
                     Units.
MMMM..............  Emission           .................  .................  .................  07/01/13.
                     Guidelines and                                                             05/13/14.
                     Compliance Times
                     for Existing
                     Sewage Sludge
                     Incineration
                     Units.
OOOO..............  Crude Oil and      .................  .................  6/30/12..........  07/01/13.
                     Natural Gas                                             12/30/13.........  05/13/14.
                     Production,
                     Transmission and
                     Distribution.
----------------------------------------------------------------------------------------------------------------


[[Page 10603]]


                                               Table II--Delegation of Authority--Part 61 NESHAP--Region 7
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                                                                      Lincoln[dash]
   Sub[dash]Part      Source category     State of Iowa     State of Kansas   State of Missouri  State of Nebraska   Lancaster County    City of Omaha
--------------------------------------------------------------------------------------------------------------------------------------------------------
A..................  General            9/19/11..........  07/01/10.........  6/30/12..........  07/01/01.........  07/01/13.........  07/01/09.
                      Provisions.       10/24/12.........  12/28/12.........  12/30/13.........  07/21/10.........  12/10/13.........  12/22/12.
                                                           Except 61.04,      Except 61.04,
                                                            61.16 and 61.17..  61.16 and 61.17..
B..................  Radon Emissions    Not delegated....  Not delegated....  Not delegated....  Not delegated....  Not delegated....  Not delegated.
                      from Underground
                      Uranium Mines.
C..................  Beryllium........  9/19/11..........  07/01/10.........  6/30/12..........  07/01/01.........  07/01/13.........  07/01/09.
                                        10/24/12.........  12/28/12.........  12/30/13.........  07/21/10.........  12/10/13.........  12/22/12.
D..................  Beryllium Rocket   9/19/11..........  07/01/10.........  6/30/12..........  07/01/01.........  07/01/13.........  07/01/09.
                      Motor Firing.     10/24/12.........  12/28/12.........  12/30/13.........  07/21/10.........  12/10/13.........  12/22/12.
E..................  Mercury..........  9/19/11..........  07/01/10.........  6/30/12..........  07/01/01.........  07/01/13.........  07/01/09.
                                        10/24/12.........  12/28/12.........  12/30/13.........  07/21/10.........  12/10/13.........  12/22/12.
F..................  Vinyl Chloride...  9/19/11..........  07/01/10.........  6/30/12..........  07/01/01.........  07/01/13.........  07/01/09.
                                        10/24/12.........  12/28/12.........  12/30/13.........  07/21/10.........  12/10/13.........  12/22/12.
J..................  Equipment Leaks    9/19/11..........  07/01/10.........  6/30/12..........  07/01/01.........  07/01/13.........  07/01/09.
                      (Fugitive         10/24/12.........  12/28/12.........  12/30/13.........  07/21/10.........  12/10/13.........  12/22/12.
                      Emission
                      Sources) of
                      Benzene.
L..................  Benzene Emissions  9/19/11..........  07/01/10.........  6/30/12..........  07/01/01.........  07/01/13.........  07/01/09.
                      from Coke By-     10/24/12.........  12/28/12.........  12/30/13.........  07/21/10.........  12/10/13.........  12/22/12.
                      Product Recovery
                      Plants.
M..................  Asbestos.........  9/19/11..........  07/01/10.........  6/30/12..........  07/01/01.........  07/01/13.........  07/01/09.
                                        10/24/12.........  12/28/12.........  12/30/13.........  07/21/10.........  12/10/13.........  12/22/12.
N..................  Inorganic Arsenic  9/19/11..........  07/01/10.........  6/30/12..........  07/01/01.........  07/01/13.........  07/01/09.
                      Emissions from    10/24/12.........  12/28/12.........  12/30/13.........  07/21/10.........  12/10/13.........  12/22/12.
                      Glass
                      Manufacturing
                      Plants.
O..................  Inorganic Arsenic  9/19/11..........  07/01/10.........  6/30/12..........  07/01/01.........  07/01/13.........  07/01/09.
                      Emissions From    10/24/12.........  12/28/12.........  12/30/13.........  07/21/10.........  12/10/13.........  12/22/12.
                      Primary Copper
                      Smelters.
P..................  Inorganic Arsenic  9/19/11..........  07/01/10.........  6/30/12..........  07/01/01.........  07/01/13.........  07/01/09.
                      Emissions From    10/24/12.........  12/28/12.........  12/30/13.........  07/21/10.........  12/10/13.........  12/22/12.
                      Arsenic Trioxide
                      and Metallic
                      Arsenic
                      Production
                      Facilities.
Q..................  Radon Emissions    Not delegated....  Not delegated....  Not delegated....  Not delegated....  Not delegated....  Not delegated.
                      From Department
                      of Energy
                      Facilities.
R..................  Radon Emissions    Not delegated....  Not delegated....  Not delegated....  Not delegated....  Not delegated....  Not delegated.
                      From
                      Phosphogypsum
                      Stacks.
T..................  Radon Emissions    Not delegated....  Not delegated....  Not delegated....  Not delegated....  Not delegated....  Not delegated.
                      From the
                      Disposal of
                      Uranium Mill
                      Tailings.
V..................  Equipment Leaks    9/19/11..........  07/01/10.........  6/30/12..........  07/01/01.........  07/01/13.........  07/01/09.
                      (Fugitive         10/24/12.........  12/28/12.........  12/30/13.........  07/21/10.........  12/10/13.........  12/22/12.
                      Emission
                      Sources).
W..................  Radon Emissions    Not delegated....  Not delegated....  Not delegated....  Not delegated....  Not delegated....  Not delegated.
                      From Operating
                      Mill Tailings.
Y..................  Benzene Emissions  9/19/11..........  07/01/10.........  6/30/12..........  07/01/01.........  07/01/13.........  07/01/09.
                      From Benzene      10/24/12.........  12/28/12.........  12/30/13.........  07/21/10.........  12/10/13.........  12/22/12.
                      Storage Vessels.
BB.................  Benzene Emissions  9/19/11..........  07/01/10.........  6/30/12..........  07/01/01.........  07/01/13.........  07/01/09.
                      From Benzene      10/24/12.........  12/28/12.........  12/30/13.........  07/21/10.........  12/10/13.........  12/22/12.
                      Transfer
                      Operations.
FF.................  Benzene Waste      9/19/11..........  07/01/10.........  6/30/12..........  07/01/01.........  07/01/13.........  07/01/09.
                      Operations.       10/24/12.........  12/28/12.........  12/30/13.........  07/21/10.........  12/10/13.........  12/22/12.
--------------------------------------------------------------------------------------------------------------------------------------------------------


                                              Table III--Delegation of Authority--Part 63 NESHAP--Region 7
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                                   State of           State of        Lincoln[dash]
   Sub[dash]Part      Source category     State of Iowa     State of Kansas        Missouri           Nebraska       Lancaster County    City of Omaha
--------------------------------------------------------------------------------------------------------------------------------------------------------
A..................  General            9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Provisions.       10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                                                           Except             Except 63.13 &
                                                            63.6(f)(1), (g),   63.15(a)(2)..
                                                            (h)(1) and
                                                            (h)(9);
                                                            63.7(e)(2)(ii)
                                                            and (f);
                                                            63.8(f);
                                                            63.10(f); 63.12;
                                                            63.13;
                                                            63.14(b)(27) and
                                                            phrase ``and
                                                            table 5 to
                                                            subpart DDDDD of
                                                            this part'';
                                                            63.14(b)(35),
                                                            (39) through
                                                            (53), and (55)
                                                            through (62); in
                                                            63.14(i)(1), the
                                                            phrase ``table 5
                                                            to subpart DDDDD
                                                            of this part'';
                                                            and 63.15..
F..................  Organic Hazardous  9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Air Pollutants    10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      From the
                      Synthetic
                      Organic Chemical
                      Manufacturing
                      Industry.

[[Page 10604]]

 
G..................  Organic Hazardous  9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Air Pollutants    10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      From the
                      Synthetic
                      Organic Chemical
                      Manufacturing
                      Industry for
                      Process Vents,
                      Storage Vessels,
                      Transfer
                      Operations, and
                      Wastewater.
H..................  Organic Hazardous  9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Air Pollutants    10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      for Equipment
                      Leaks.
I..................  Organic Hazardous  9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Air Pollutants    10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      for Certain
                      Processes
                      Subject to the
                      Negotiated
                      Regulation for
                      Equipment Leaks.
J..................  Polyvinyl          9/19/11..........  07/01/10.........  Not delegated....  Not delegated....  07/01/13.........  Not delegated.
                      Chloride and      10/24/12.........  12/28/12.........                                        12/10/13.........
                      Copolymers
                      Production.
L..................  Coke Oven          9/19/11..........  07/01/10.........  6/30/12..........  Not delegated....  07/01/13.........  Not delegated.
                      Batteries.        10/24/12.........  12/28/12.........  12/30/13.........                     12/10/13.........
M..................  National           9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Perchloroethylen  10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      e Air Emission
                      Standards for
                      Dry Cleaning
                      Facilities.
N..................  Chromium           9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Emissions From    10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Hard and
                      Decorative
                      Chromium
                      Electroplating
                      and Chromium
                      Anodizing Tanks.
O..................  Ethylene Oxide     9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Emissions         10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Standards for
                      Sterilization
                      Facilities.
Q..................  Industrial         9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Process Cooling   10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Towers.
R..................  Gasoline           9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Distribution      10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Facilities (Bulk
                      Gasoline
                      Terminals and
                      Pipeline
                      Breakout
                      Stations).
S..................  Pulp and Paper     9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Industry.         10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
T..................  Halogenated        9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Solvent Cleaning. 10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
U..................  Polymers and       9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Resins Group I.   10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
W..................  Epoxy Resins       9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Production and    10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Non-Nylon
                      Polyamides
                      Production.
X..................  Secondary Lead     9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Smelting.         10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
Y..................  Marine Tank        9/19/11..........  07/01/10.........  6/30/12..........  Not delegated....  Not delegated....  Not delegated.
                      Vessel Loading    10/24/12.........  12/28/12.........  12/30/13.........
                      Operations.
AA/BB..............  Phosphoric Acid    9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Manufacturing     10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Plants/Phosphate
                      Fertilizers
                      Production
                      Plants.
CC.................  Petroleum          9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Refineries.       10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
DD.................  Off-Site Waste     9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      and Recovery      10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Operations.
EE.................  Magnetic Tape      9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Manufacturing     10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Operations.
GG.................  Aerospace          9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Industry Surface  10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Coating
                      Manufacturing
                      and Rework
                      Facilities.
HH.................  Oil and Natural    9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Gas Production    10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Facilities.
II.................  Shipbuilding and   9/19/11..........  07/01/10.........  6/30/12..........  Not delegated....  Not delegated....  Not delegated.
                      Ship Repair       10/24/12.........  12/28/12.........  12/30/13.........
                      (Surface
                      Coating).
JJ.................  Wood Furniture     9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Manufacturing     10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Operations.
KK.................  Printing and       9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Publishing        10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Industry.
LL.................  Primary Aluminum   9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Reduction Plants. 10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
MM.................  Chemical Recovery  9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Combustion        10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Sources at
                      Kraft, Soda,
                      Sulfite, and
                      Stand-Along
                      Semichemical
                      Pulp Mills.
OO.................  Tanks-Level 1....  9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                                        10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.

[[Page 10605]]

 
PP.................  Containers.......  9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                                        10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
QQ.................  Surface            9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Impoundments.     10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
RR.................  Individual Drain   9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Systems.          10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
SS.................  Closed Vent        9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Systems, Control  10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Devices,
                      Recovery Devices
                      and Routing to a
                      Fuel Gas System
                      or a Process.
TT.................  Equipment Leaks--  9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Control Level 1   10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Standards.
UU.................  Equipment Leaks--  9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Control Level 2   10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Standards.
VV.................  Oil-Water          9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Separators and    10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Organic-Water
                      Separators.
WW.................  Storage Vessel     9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      (Tanks)--Control  10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Level 2.
XX.................  Ethylene           9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Manufacturing     10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Process Units:
                      Heat Exchange
                      Systems and
                      Waste Operations.
YY.................  Generic Maximum    9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Achievable        10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Control
                      Technology
                      Standards.
CCC................  Steel Pickling-    9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      HCL Process       10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Facilities and
                      Hydrochloric
                      Acid
                      Regeneration
                      Plants.
DDD................  Mineral Wool       9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Production.       10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
EEE................  Hazardous Waste    9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Combustors.       10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
GGG................  Pharmaceutical     9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Production.       10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
HHH................  Natural Gas        9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Transmission and  10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Storage
                      Facilities.
III................  Flexible           9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Polyurethane      10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Foam Production.
JJJ................  Polymers and       9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Resins Group IV.  10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
LLL................  Portland Cement    12/20/06.........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Manufacturing     10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Industry.
MMM................  Pesticide Active   9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Ingredient        10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Production.
NNN................  Wool Fiberglass    9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Manufacturing.    10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
OOO................  Manufacture of     9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Amino/Phenolic    10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Resins.
PPP................  Polyether Polyols  9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Production.       10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
QQQ................  Primary Copper     9/19/11..........  07/01/10.........  6/30/12..........  Not delegated....  07/01/13.........  Not delegated.
                      Smelting.         10/24/12.........  12/28/12.........  12/30/13.........                     12/10/13.........
RRR................  Secondary          9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Aluminum          10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Production.
TTT................  Primary Lead       9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Smelting.         10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
UUU................  Petroleum          9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Refineries.       10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
VVV................  Publicly Owned     9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Treatment Works.  10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
XXX................  Ferroalloys        9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Production.       10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
AAAA...............  Municipal Solid    9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Waste Landfills.  10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
CCCC...............  Manufacturing of   9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Nutritional       10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Yeast.
DDDD...............  Plywood and        9/19/11..........  07/01/10.........  6/30/12..........  Not delegated....  07/01/13.........  Not delegated.
                      Composite Wood    10/24/12.........  12/28/12.........  12/30/13.........                     12/10/13.........
                      Products.
EEEE...............  Organic Liquids    9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Distribution      10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      (Non-Gasoline).
FFFF...............  Misc. Organic      9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Chemical          10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Manufacturing.
GGGG...............  Solvent            9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Extraction for    10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Vegetable Oil
                      Production.
HHHH...............  Wet Formed         9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Fiberglass Mat    10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Production.

[[Page 10606]]

 
IIII...............  Surface Coating    9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      of Automobiles    10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      and Light-Duty
                      Trucks.
JJJJ...............  Paper and Other    9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Web Coating.      10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
KKKK...............  Surface Coating    9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      of Metal Cans.    10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
MMMM...............  Surface Coating    9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      of Misc. Metal    10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Parts and
                      Products.
NNNN...............  Surface Coating    9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      of Large          10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Appliances.
OOOO...............  Printing, Coating  9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      and Dyeing of     10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Fabrics and
                      Other Textiles.
PPPP...............  Surface Coating    9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      of Plastic Parts  10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      and Products.
QQQQ...............  Surface Coating    9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      of Wood Building  10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Products.
RRRR...............  Surface Coating    9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      of Metal          10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Furniture.
SSSS...............  Surface Coating    9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      of Metal Coil.    10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
TTTT...............  Leather Finishing  9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Operations.       10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
UUUU...............  Cellulose          9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Products          10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Manufacturing.
VVVV...............  Boat               9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Manufacturing.    10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
WWWW...............  Reinforced         9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Plastic           10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Composites
                      Production.
XXXX...............  Rubber Tire        9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Manufacturing.    10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
YYYY...............  Stationary         9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Combustion        10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Turbines.
ZZZZ...............  Stationary         01/30/13.........  7/1/09...........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Reciprocating     10/23/13.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Internal
                      Combustion
                      Engines.
AAAAA..............  Lime               9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Manufacturing     10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Plants.
BBBBB..............  Semiconductor      9/19/11..........  07/01/10.........  6/30/12..........  Not delegated....  07/01/13.........  Not delegated.
                      Manufacturing.    10/24/12.........  12/28/12.........  12/30/13.........                     12/10/13.........
CCCCC..............  Coke Ovens:        9/19/11..........  07/01/10.........  6/30/12..........  Not delegated....  07/01/13.........  Not delegated.
                      Pushing,          10/24/12.........  12/28/12.........  12/30/13.........                     12/10/13.........
                      Quenching, and
                      Battery Stacks.
DDDDD..............  Industrial,        Not delegated....  Not delegated....  6/30/12..........  07/01/13.........  07/01/13.........  Not delegated.
                      Commercial and                                          12/30/13.........  05/13/14.........  12/10/13.........
                      Institutional
                      Boilers and
                      Process Heaters.
EEEEE..............  Iron and Steel     9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Foundries.        10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
FFFFF..............  Integrated Iron    9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      and Steel         10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Manufacturing
                      Facilities.
GGGGG..............  Site Remediation.  9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                                        10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
HHHHH..............  Misc. Coating      9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Manufacturing.    10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
IIIII..............  Mercury Cell       9/19/11..........  07/01/10.........  6/30/12..........  Not delegated....  07/01/13.........  Not delegated.
                      Chlor-Alkali      10/24/12.........  12/28/12.........  12/30/13.........                     12/10/13.........
                      Plants.
JJJJJ..............  Brick and          Not delegated....  Not delegated....  Not delegated....  Not delegated....  07/01/13.........  Not delegated.
                      Structural Clay                                                                               12/10/13.........
                      Products
                      Manufacturing.
KKKKK..............  Clay Ceramics      9/19/11..........  Not delegated....  Not delegated....  Not delegated....  07/01/13.........  Not delegated.
                      Manufacturing.    10/24/12.........                                                           12/10/13.........
LLLLL..............  Asphalt            9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Processing and    10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Asphalt Roofing
                      Manufacturing.
MMMMM..............  Flexible Poly-     9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      urethane Foam     10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Fabrication
                      Operation.
NNNNN..............  Hydrochloric Acid  9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Production.       10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
PPPPP..............  Engine Test Cells/ 9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Stands.           10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
QQQQQ..............  Friction           9/19/11..........  07/01/10.........  6/30/12..........  Not delegated....  07/01/13.........  Not delegated.
                      Materials         10/24/12.........  12/28/12.........  12/30/13.........                     12/10/13.........
                      Manufacturing
                      Facilities.
RRRRR..............  Taconite Iron Ore  9/19/11..........  07/01/10.........  6/30/12..........  Not delegated....  07/01/13.........  Not delegated.
                      Processing.       10/24/12.........  12/28/12.........  12/30/13.........                     12/10/13.........
SSSSS..............  Refractory         9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Products          10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Manufacturing.
TTTTT..............  Primary Magnesium  9/19/11..........  07/01/10.........  6/30/12..........  Not delegated....  07/01/13.........  Not delegated.
                      Refining.         10/24/12.........  12/28/12.........  12/30/13.........                     12/10/13.........

[[Page 10607]]

 
UUUUU..............  Coal and Oil-      Not delegated....  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  Not delegated.
                      fired Electric                       12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........
                      Utility Steam
                      Generating Units.
WWWWW..............  Hospital Ethylene  9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Oxide Sterilizer. 10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
YYYYY..............  Electric Arc       9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Furnace           10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Steelmaking
                      Facilities or
                      Stainless and
                      Non-stainless
                      Steel
                      Manufacturing
                      (EAFs).
ZZZZZ..............  Iron and Steel     9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Foundries Area    10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Sources.
BBBBBB.............  Gasoline           9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Distribution      10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Bulk Terminal,
                      Bulk Plant and
                      Pipeline
                      Facilities.
CCCCCC.............  Gasoline           1/24/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Distribution,     10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Gasoline
                      Dispensing
                      Facilities.
DDDDDD.............  PVC & Copolymer    Not delegated....  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Production.                          12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
EEEEEE.............  Primary Copper     Not delegated....  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Smelting.                            12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
FFFFFF.............  Secondary Copper   Not delegated....  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Smelting.                            12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
GGGGGG.............  Primary            Not delegated....  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Nonferrous Metal.                    12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
HHHHHH.............  Paint Stripping    9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Operations,       10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Misc. Surface
                      Coating,
                      Autobody
                      Refinishing.
JJJJJJ.............  Industrial,        Not delegated....  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  Not delegated.
                      Commercial, and                      12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........
                      Institutional
                      Boilers.
LLLLLL.............  Acrylic/           9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  Not delegated.
                      Modacrylic        10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........
                      Fibers
                      Production.
MMMMMM.............  Carbon Black       9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  Not delegated.
                      Production.       10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........
NNNNNN.............  Chromium           9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  Not delegated.
                      Compounds.        10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13,........
OOOOOO.............  Flexible           9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  Not delegated.
                      Polyurethane      10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........
                      Foam Fabrication
                      and Production.
PPPPPP.............  Lead Acid Battery  9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  Not delegated.
                      Manufacturing.    10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........
QQQQQQ.............  Wood Preserving..  9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  Not delegated.
                                        10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........
RRRRRR.............  Clay Ceramics      9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Manufacturing.    10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
SSSSSS.............  Pressed & Blown    9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Glass             10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
                      Manufacturing.
TTTTTT.............  Secondary Non-     9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  07/01/11.
                      Ferrous Metals.   10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........  12/22/12.
VVVVVV.............  Chemical           12/21/12.........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  Not delegated.
                      Manufacturing     09/10/14.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........
                      Area Sources.
WWWWWW.............  Plating and        9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  Not delegated.
                      Polishing.        10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........
XXXXXX.............  Metal Fabrication  9/19/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  Not delegated.
                      and Finishing.    10/24/12.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........
YYYYYY.............  Ferroalloys        Not delegated....  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  Not delegated.
                      Production.                          12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........
ZZZZZZ.............  Area Source        6/28/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  Not delegated.
                      Standards for     1/24/11..........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........
                      Aluminum, Copper
                      and Other
                      Nonferrous
                      Foundries.
AAAAAAA............  Asphalt            Not delegated....  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  Not delegated.
                      Processing and                       12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........
                      Asphalt Roofing
                      Manufacturing.
BBBBBBB............  Chemical           Not delegated....  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  Not delegated.
                      Preparations                         12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........
                      Industry.
CCCCCCC............  Paints and Allied  6/28/11..........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  Not delegated.
                      Products          1/24/11..........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........
                      Manufacturing.
DDDDDDD............  Prepared Foods     12/23/11.........  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  Not delegated.
                      Manufacturing.    09/10/14.........  12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........
EEEEEEE............  Gold Mine Ore      Not delegated....  07/01/10.........  6/30/12..........  07/01/13.........  07/01/13.........  Not delegated.
                      Processing and                       12/28/12.........  12/30/13.........  05/13/14.........  12/10/13.........
                      Production Area
                      Source Category.
HHHHHHH............  Polyvinyl          Not delegated....  .................  6/30/12..........  07/01/13.........  07/01/13.........  Not delegated.
                      Chloride and                                            12/30/13.........  05/13/14.........  12/10/13.........
                      Copolymers
                      Production.
--------------------------------------------------------------------------------------------------------------------------------------------------------


[[Page 10608]]

    Note: At this time, Missouri is temporarily not accepting 
delegation for area source NESHAP requirements (40 CFR part 63, 
subparts 5W-7H) within the State of Missouri as described in an August 
24, 2010 letter from MDNR to the U.S. EPA, Region 7.

Summary of This Action

    All sources subject to the requirements of 40 CFR parts 60, 61, and 
63 are also subject to the equivalent requirements of the above-
mentioned state or local agencies.
    This document informs the public of delegations to the above-
mentioned agencies of the above-referenced Federal regulations.

Authority

    This document is issued under the authority of sections 101, 110, 
112, and 301 of the CAA, as amended (42 U.S.C. 7401, 7410, 7412, and 
7601).

    Dated: February 13, 2015.
Karl Brooks,
Regional Administrator, Region 7.
[FR Doc. 2015-04171 Filed 2-26-15; 8:45 am]
BILLING CODE 6560-50-P