[Federal Register Volume 80, Number 95 (Monday, May 18, 2015)]
[Notices]
[Pages 28261-28262]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-11918]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP15-348-000]


Southern Star Central Gas Pipeline, Inc.; Notice of Request Under 
Blanket Authorization

    Take notice that on April 30, 2015, Southern Star Central Gas 
Pipeline, Inc. (Southern Star), 4700 State Highway 56, Owensboro, 
Kentucky 42301, filed a prior notice application pursuant to sections 
157.205, 157.208, 157.211, and 157.216 of the Federal Energy Regulatory 
Commission's (Commission)

[[Page 28262]]

regulations under the Natural Gas Act (NGA), and Southern Star's 
blanket certificate issued in Docket No. CP82-479-000. Southern Star 
seeks authorization to relocate approximately 6,600 feet of 16-inch 
Pipeline EX-001 by means of horizontal directional drills in order to 
relocate the pipeline off the Platte Purchase Bridge that spans the 
Missouri River between Platte County, Missouri and Wyandotte County, 
Kansas, all as more fully set forth in the application, which is open 
to the public for inspection. The filing may also be viewed on the web 
at http://www.ferc.gov using the ``eLibrary'' link. Enter the docket 
number excluding the last three digits in the docket number field to 
access the document. For assistance, contact FERC at 
[email protected] or call toll-free, (866) 208-3676 or TTY, 
(202) 502-8659.
    Any questions regarding this application should Phyllis K. Medley, 
Senior Analyst, Regulatory Compliance, Southern Star Central Gas 
Pipeline, Inc., 4700 State Highway 56, Owensboro, Kentucky 42301, or 
phone (270) 852-4653, or by email [email protected].
    Relocation of Southern Star's 6,600 foot section of 16-inch 
Pipeline EX-00 is needed since the Kansas Department of Transportation 
and Missouri Department of Transportation are working to demolish the 
Platte Purchase Bridge and replace it with a new bridge system in the 
pipeline's location by December 1, 2016.
    Any person or the Commission's staff may, within 60 days after 
issuance of the instant notice by the Commission, file pursuant to Rule 
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
intervene or notice of intervention and pursuant to section 157.205 of 
the regulations under the NGA (18 CFR 157.205), a protest to the 
request. If no protest is filed within the time allowed therefore, the 
proposed activity shall be deemed to be authorized effective the day 
after the time allowed for filing a protest. If a protest is filed and 
not withdrawn within 30 days after the allowed time for filing a 
protest, the instant request shall be treated as an application for 
authorization pursuant to section 7 of the NGA.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding, or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenters will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commenters will not be required to serve copies of filed 
documents on all other parties. However, the non-party commenter will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at http://www.ferc.gov. Persons unable to file electronically should 
submit an original and 5 copies of the protest or intervention to the 
Federal Energy Regulatory Commission, 888 First Street NE., Washington, 
DC 20426.

    Dated: May 12, 2015.
 Kimberly D. Bose,
 Secretary.
[FR Doc. 2015-11918 Filed 5-15-15; 8:45 am]
 BILLING CODE 6717-01P