DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

18 CFR Parts 2 and 157

[Docket No. RM12-11-003; Order No. 790-B]


Revisions to Auxiliary Installations, Replacement Facilities, and 
Siting and Maintenance Regulations

AGENCY: Federal Energy Regulatory Commission.

ACTION: Final rule, order on clarification; correction.

-----------------------------------------------------------------------

SUMMARY: This document contains corrections to the final rule (RM12-11-
003) which was published in the Federal Register of Friday, July 24, 
2015 (80 FR 43944). The final rule amended regulations to: provide pre-
granted authority under a new paragraph to abandon or replace auxiliary 
facilities, subject to certain conditions; permit auxiliary facilities 
that cannot meet the conditions for the pre-granted abandonment 
authority in the new paragraph to be abandoned under the blanket 
certificate regulations, subject to those regulations' requirements; 
and permit replacement facilities constructed under the regulations to 
be abandoned under the blanket certificate regulations, subject to 
those regulations' requirements.

DATES: Effective October 7, 2015.

FOR FURTHER INFORMATION CONTACT:
Katherine Liberty, Office of the General Counsel, Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426, 
(202) 502-6491, [email protected].
Gordon Wagner, Office of the General Counsel, Federal Energy Regulatory 
Commission, 888 First Street NE., Washington, DC 20426, (202) 502-8947, 
[email protected].
Howard Wheeler, Office of Energy Projects, Federal Energy Regulatory 
Commission, 888 First Street NE., Washington, DC 20426, (202) 502-8688, 
[email protected].
Shannon Jones, Office of Energy Projects, Federal Energy Regulatory 
Commission, 888 First Street NE., Washington, DC 20426, (202) 502-6410, 
[email protected].

SUPPLEMENTARY INFORMATION:

Revisions to Auxiliary Installations, Replacement Facilities, and 
Siting and Maintenance Regulations Docket No. RM12-11-003

Errata Notice

    On July 16, 2015, the Commission issued a Final Rule in the above

[[Page 50559]]

captioned proceeding. Revisions to Auxiliary Installations, Replacement 
Facilities, and Siting and Maintenance Regulations, 152 FERC ] 61,049 
(2015). This errata notice makes a correction to the Final Rule as 
issued.
    In FR Doc. 2015-17919 appearing on page 43949 in the Federal 
Register of Friday, July 24, 2015, the following correction is made:
    1. On page 43949, in the second column, Sec.  157.216(b)(2)(i)(A) 
of the regulatory text is revised to read as follows:
    ``(A) Will not exceed the cost limit in Sec.  157.208(d) for 
activities under the prior notice provisions;''

    Dated: August 14, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-20538 Filed 8-19-15; 8:45 am]