[Federal Register Volume 80, Number 230 (Tuesday, December 1, 2015)]
[Notices]
[Page 75091]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-30389]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. EL16-16-000; Docket No. QF06-17-004 ]
P[aacute]Tu Wind Farm, LLC v. Portland General Electric Company,
P[aacute]Tu Wind Farm, LLC; Notice of Complaint
Take notice that on November 18, 2015, pursuant to sections 206 and
306 of the Federal Power Act (FPA),\1\ section 210(h)(1) of the Public
Utility Regulatory Policies Act (PURPA),\2\ and Rule 206 of the Federal
Energy Regulatory Commission's (Commission) Rules of Practice and
Procedure,\3\ P[aacute]Tu Wind Farm, LLC (P[aacute]Tu or Complainant)
filed a formal complaint against Portland General Electric Company
(Respondent) alleging that Respondent violated the Commission's orders
\4\ by refusing to permit Complainant to establish a dynamic scheduling
arrangement for delivery of power from the P[aacute]Tu wind farm to
Respondent's Balancing Authority Area, all as more fully explained in
the complaint.
---------------------------------------------------------------------------
\1\ 16 U.S.C. 824e & 825e.
\2\ 16 U.S.C. 824a-3(h)(1).
\3\ 18 CFR 385.206 (2014).
\4\ P[aacute]Tu Wind Farm, LLC v. Portland General Electric Co.,
150 FERC ] 61,032, reh'g denied, 151 FERC ] 61,223 (2015), petitions
for review pending sub nom., Portland General Electric Co. v. FERC,
D.C. Cir. Nos. 15-1237 et al.
---------------------------------------------------------------------------
The Complainant certifies that a copy of the complaint has been
served on the Respondents.
Any person desiring to intervene or to protest this filing must
file in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211, 385.214). Protests will be
considered by the Commission in determining the appropriate action to
be taken, but will not serve to make protestants parties to the
proceeding. Any person wishing to become a party must file a notice of
intervention or motion to intervene, as appropriate. The Respondent's
answer and all interventions, or protests must be filed on or before
the comment date. The Respondent's answer, motions to intervene, and
protests must be served on the Complainants.
The Commission encourages electronic submission of protests and
interventions in lieu of paper using the ``eFiling'' link at http://www.ferc.gov. Persons unable to file electronically should submit an
original and 5 copies of the protest or intervention to the Federal
Energy Regulatory Commission, 888 First Street NE., Washington, DC
20426.
This filing is accessible on-line at http://www.ferc.gov, using the
``eLibrary'' link and is available for electronic review in the
Commission's Public Reference Room in Washington, DC There is an
``eSubscription'' link on the Web site that enables subscribers to
receive email notification when a document is added to a subscribed
docket(s). For assistance with any FERC Online service, please email
[email protected], or call (866) 208-3676 (toll free). For
TTY, call (202) 502-8659.
Comment Date: 5:00 p.m. Eastern Time on December 8, 2015.
Dated: November 18, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015-30389 Filed 11-30-15; 8:45 am]