[Federal Register Volume 80, Number 237 (Thursday, December 10, 2015)]
[Notices]
[Pages 76683-76684]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-31124]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Commission Staff Attendance
The Federal Energy Regulatory Commission (Commission) hereby gives
notice that members of the Commission's staff may attend the following
meeting related to the transmission planning activities of the New York
Independent System Operator, Inc.
The New York Independent System Operator, Inc. Electric System Planning
Working Group Meeting
December 8, 2015, 10:00 a.m.-4:30 p.m. (EST)
The above-referenced meeting will be via web conference and
teleconference.
[[Page 76684]]
The above-referenced meeting is open to stakeholders.
Further information may be found at: http://www.nyiso.com/public/markets_operations/services/planning/index.jsp.
The New York Independent System Operator, Inc. Business Issues
Committee Meeting
December 9, 2015, 10:00 a.m.-4:00 p.m. (EST)
The above-referenced meeting will be via web conference and
teleconference.
The above-referenced meeting is open to stakeholders.
Further information may be found at: http://www.nyiso.com/public/markets_operations/committees/meeting_materials/index.jsp?com=bic.
The New York Independent System Operator, Inc. Operating Committee
Meeting
December 10, 2015, 10:00 a.m.-4:00 p.m. (EST)
The above-referenced meeting will be via web conference and
teleconference.
The above-referenced meeting is open to stakeholders.
Further information may be found at: http://www.nyiso.com/public/markets_operations/committees/meeting_materials/index.jsp?com=oc.
The New York Independent System Operator, Inc. Inter-Regional Planning
Stakeholder Advisory Committee Teleconference
December 14, 2015, 10:00 a.m.-4:00 p.m. (EST)
The above-referenced meeting will be via web conference and
teleconference.
The above-referenced meeting is open to stakeholders.
Further information may be found at: http://www.pjm.com/committees-and-groups/meeting-center.aspx.
The New York Independent System Operator, Inc. Electric System Planning
Working Group Meeting
January 6, 2016, 10:00 a.m.-4:00 p.m. (EST)
The above-referenced meeting will be via web conference and
teleconference.
The above-referenced meeting is open to stakeholders.
Further information may be found at: http://www.nyiso.com/public/markets_operations/services/planning/index.jsp.
The New York Independent System Operator, Inc. Electric System Planning
Working Group Meeting
January 21, 2016, 10:00 a.m.-4:00 p.m. (EST)
The above-referenced meeting will be via web conference and
teleconference.
The above-referenced meeting is open to stakeholders.
Further information may be found at: http://www.nyiso.com/public/markets_operations/services/planning/index.jsp.
The discussions at the meeting described above may address matters
at issue in the following proceedings:
New York Independent System Operator, Inc., Docket No. ER13-102.
ISO New England Inc., et al., Docket Nos. ER13-1957, et al.
ISO New England Inc., Docket Nos. ER13-193 and ER13-196.
New York Independent System Operator, Inc., Docket No. ER15-2059.
New York Power Authority, Docket No. ER15-2102.
New York Transco, LLC, Docket No. ER15-572.
For more information, contact James Eason, Office of Energy Market
Regulation, Federal Energy Regulatory Commission at (202) 502-8622 or
[email protected].
Dated: December 4, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015-31124 Filed 12-9-15; 8:45 am]
BILLING CODE 6717-01-P