[Federal Register Volume 81, Number 14 (Friday, January 22, 2016)]
[Notices]
[Pages 3789-3790]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-01234]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP15-513-000]


Texas Gas Transmission, LLC; Revised Notice of Schedule for 
Environmental Review of the Northern Supply Access Project

    This notice identifies the Federal Energy Regulatory Commission 
(Commission or FERC) staff's revised schedule for the completion of the 
environmental assessment (EA) for Texas Gas Transmission, LLC's 
Northern Supply Access Project. The previous notice of schedule, issued 
on December 23, 2015, identified February 4, 2016 as the issuance date.

Schedule for Environmental Review

Issuance of EA, January 26, 2016
90-day Federal Authorization Decision Deadline, April 25, 2016


[[Page 3790]]


    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. Go to 
www.ferc.gov/docs-filing/esubscription.asp.

    Dated: January 15, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-01234 Filed 1-21-16; 8:45 am]