Tennessee Gas Pipeline Company, L.L.C; Notice of Revised Schedule 
for Environmental Review of the Susquehanna West Project

    This notice identifies the Federal Energy Regulatory Commission 
staff's revised schedule for the completion of the environmental 
assessment (EA) for Tennessee Gas Pipeline Company, L.L.C.'s (TGP) 
proposed Susquehanna West Project. The first notice of schedule, issued 
on November 24, 2015, identified February 23, 2016 as the EA issuance 
date. However, TGP has recently filed supplemental information that 
warrants further review. As a result, staff has revised the schedule 
for issuance of the EA.

Schedule for Environmental Review

    Issuance of Notice of Availability of the EA, March 17, 2016.
    90-day Federal Authorization Decision Deadline, June 15, 2016.
    If a schedule change becomes necessary, an additional notice will 
be provided so that the relevant agencies are kept informed of the 
project's progress.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription (http://www.ferc.gov/docs-filing/esubscription.asp).

    Dated: February 5, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-02757 Filed 2-10-16; 8:45 am]
 BILLING CODE 6717-01-P