    On February 28, 2014 Woodland Pulp, LLC, licensee for the Vanceboro 
Dam Storage Project, filed an Application for a New License pursuant to 
the Federal Power Act (FPA) and the Commission's regulations 
thereunder. The Vanceboro Dam Storage Project is located on the East 
Branch of the St. Croix River in Washington County, Maine.
    The license for Project No. 2492 was issued for a period ending 
February 29, 2016. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), 
requires the Commission, at the expiration of a license term, to issue 
from year-to-year an annual license to the then licensee under the 
terms and conditions of the prior license until a new license is 
issued, or the project is otherwise disposed of as provided in section 
15 or any other applicable section of the FPA. If the project's prior 
license waived the applicability of section 15 of the FPA, then, based 
on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c), 
and as set forth at 18 CFR 16.21(a), if the licensee of such project 
has filed an application for a subsequent license, the licensee may 
continue to operate the project in accordance with the terms and 
conditions of the license after the minor or minor part license 
expires, until the Commission acts on its application. If the licensee 
of such a project has not filed an application for a subsequent 
license, then it may be required, pursuant to 18 CFR 16.21(b), to 
continue project operations until the Commission issues someone else a 
license for the project or otherwise orders disposition of the project.
    If the project is subject to section 15 of the FPA, notice is 
hereby given that an annual license for Project No. 2492 is issued to 
the licensee for a period effective March 1, 2016 through February 28, 
2017 or until the issuance of a new license for the project or other 
disposition under the FPA, whichever comes first. If issuance of a new 
license (or other disposition) does not take place on or before 
February 28, 2017, notice is hereby given that, pursuant to 18 CFR 
16.18(c), an annual license under section 15(a)(1) of the FPA is 
renewed automatically without further order or notice by the 
Commission, unless the Commission orders otherwise.
    If the project is not subject to section 15 of the FPA, notice is 
hereby given that the licensee, Woodland Pulp LLC., is authorized to 
continue operation of the Vanceboro Dam Storage Project, until such 
time as the Commission acts on its application for a subsequent 
license.

    Dated: March 17, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-06504 Filed 3-22-16; 8:45 am]