[Federal Register Volume 81, Number 58 (Friday, March 25, 2016)]
[Notices]
[Pages 16147-16153]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-06695]
-----------------------------------------------------------------------
DEPARTMENT OF DEFENSE
Department of the Army, Corps of Engineers
One-Time Deauthorization of Water Resources Projects
AGENCY: Army Corps of Engineers, DoD.
ACTION: Notice of Final Deauthorization Report.
-----------------------------------------------------------------------
SUMMARY: The U.S. Army Corps of Engineers is publishing a Final
Deauthorization Report of water resources development projects and
separable elements that have been identified for deauthorization in
accordance with section 6001(d) of the Water Resources Reform and
Development Act of 2014, Public Law 113-121, 128 STAT. 1346-1347 (WRRDA
2014). The Assistant Secretary of the Army for Civil Works transmitted
the Final Deauthorization Report to Congress on February 26, 2016. An
electronic copy of the complete report is available at: http://www.usace.army.mil/Portals/2/docs/civilworks/budget/final_deauth_report_23feb2016.pdf.
For Further Information Contact or To Provide Comments: Mr. Joseph W.
Aldridge, Headquarters, U.S. Army Corps of Engineers, Attention: CECW-
IP, Washington, DC 20314-1000. Tel. (202) 761-4130 or
[email protected].
SUPPLEMENTARY INFORMATION: Final Deauthorization Report required by
Sec. 6001(d).
Section 6001(d) provides that the Secretary shall develop a Final
Deauthorization Report. This report includes a list of each water
resources
[[Page 16148]]
development project, or separable element of a project, described in
Section 6001(c) and the other provisions of Section 6001(d), as well as
an appendix (Appendix A) that lists any project, or separable element
of a project, included as part of the Interim Deauthorization List but
not included in the Final Deauthorization Report and the reasons why
they are not included in the report. Appendix B of the Final
Deauthorization Report (available on the U.S. Army Corps of Engineers
Web site referenced below) contains copies of the comments received
during the public comment period. The Final Deauthorization Report with
Appendix A follows below in Table 1. An electronic copy of the Final
Deauthorization Report with appendices can be found at: http://www.usace.army.mil/Portals/2/docs/civilworks/budget/final_deauth_report_23feb2016.pdf.
The Interim Deauthorization List was developed in accordance with
Section 6001(c) of WRRDA 2014 and was published for public comment in
the Federal Register on October 7, 2015. Per Section 6001(d), not later
than 120 days following the 90-day public comment period of the Interim
Deauthorization List, that ended on January 4, 2016, the Assistant
Secretary of the Army for Civil Works (ASA(CW)) will transmit the Final
Deauthorization Report to the Environment & Public Works Committee of
the Senate and the Transportation and Infrastructure Committee of the
House of Representatives. Additionally, the ASA(CW) will publish the
Final Deauthorization Report in the Federal Register. The ASA(CW)
transmitted the Final Deauthorization Report to the Committees on
February 26, 2016.
Section 6001(d)(2)(A) of WRRDA 2014 requires that the Secretary
shall include on the Final Deauthorization Report, projects and
separable elements of projects that have, in the aggregate, an
estimated Federal cost to complete that is at least $18 billion. The
ASA(CW) has strived to meet the requirements of Section 6001, but was
not able to identify projects that totaled $18 billion based upon the
criteria provided in Section 6001. The projects and elements on the
Final Deauthorization Report will be deauthorized automatically after
180 days following the date that the ASA(CW) submits the Final
Deauthorization List to the Committees, unless the Congress passes a
joint resolution disapproving the Final Deauthorization Report or the
non-Federal interest for the project or separable element of a project
provides sufficient funds to complete the construction of the project
or separable element. The amount shown as the Federal Balance to
complete is a working estimate generally based on the authorization and
as such any non-Federal interests considering providing sufficient
funds to complete a project or separable element should contact the
appropriate District Commander to discuss the process necessary to
develop a final cost to complete a project or separable element.
The Final Deauthorization Report identifies water resources
development projects, or separable elements of a project, that meet the
following criteria. Projects and separable elements eligible for
deauthorization are those uncompleted construction projects and
separable elements meeting all of the following criteria: (1) They were
authorized for construction before November 8, 2007, or their most
recent modification of the construction authorization predates November
8, 2007; (2) their construction has not been initiated, or, if
construction has been initiated, there have been no obligations of
Federal or non-Federal funds for construction in the current fiscal
year or any of the past 6 fiscal years; and, (3) there has been no
funding for a post-authorization study in the current fiscal year or
any of the past 6 fiscal years. As specifically provided in section
6001(f)(1)(B) of WRRDA 2014, water resources development projects
include environmental infrastructure assistance projects and programs
of the U.S. Army Corps of Engineers. In accordance with section 103(f)
of the Water Resources Development Act of 1986, separable elements is
defined as ``a portion of a project--
(1) which is physically separable from other portions of the
project; and
(2) which--
(A) achieves hydrologic effects, or
(B) produces physical or economic benefits, which are separately
identifiable from those produced by other portions of the project.''
The following elements of an authorized water resources development
project also qualify as separable elements: an element for which there
is an executed design agreement or project partnership agreement
specific to that element; an element that has received funding
specified for that element; an element that was authorized separately
from or as an amendment to the authorization for the remainder of the
water resources development project, that was separately identified in
the authorization for the water resources development project, or for
which a statute specifies an authorized cost, estimated cost, or amount
authorized to be appropriated; an element that has been placed in
service or for which the Government or the non-Federal partner has
assumed operation and maintenance; an element that has been
deauthorized; or the remaining portion of the water resources
development project apart from other separable elements.
Authority: This notice is required by Sec. 6001(d) of the
Water Resources Reform and Development Act of 2014, Public Law 113-
121, 128 STAT 1346-1347.
Jo-Ellen Darcy,
Assistant Secretary of the Army (Civil Works).
Table 1 (Final Deauthorization Report)
--------------------------------------------------------------------------------------------------------------------------------------------------------
Public law of Latest fiscal year of Federal balance to
authorization Section of Federal or non-Federal complete (subject to
State Project/Element name or latest public law obligations for section 902 where
amendment construction applicable) ($)
--------------------------------------------------------------------------------------------------------------------------------------------------------
AL..................................... ALABAMA-COOSA RIVER AND 99-662 813 1986...................... 3,781,921,691
TRIBUTARIES, AL (COOSA
RIVER BETWEEN MONTGOMERY
AND GADSDEN).
AL..................................... DUCK RIVER, AL............ 106-554 108a NO OBLIGATION FOR 5,000,000
CONSTRUCTION.
AR..................................... UNION COUNTY, AR.......... 106-554 108d 2008...................... 51,247,100
L'ANGUILLE RIVER BASIN, AR 99-662 103 2004...................... 19,466,768
ARKANSAS RIVER LEVEES, AR. 101-640 110(a1) NO OBLIGATION FOR 591,605
CONSTRUCTION.
BEAVER DAM, AR (TROUT 94-587 105 NO OBLIGATION FOR 5,990,000
PRODUCTION CENTER). CONSTRUCTION.
[[Page 16149]]
BEAVER LAKE, BENTON/WASH, 104-303 523 2002...................... 5,000,000
AR.
CA..................................... CALAVERAS COUNTY, CA...... 104-303 526 NO OBLIGATION FOR 1,500,000
CONSTRUCTION.
CLEAR LAKE BASIN, CA...... 106-554 108a NO OBLIGATION FOR 1,543,324
CONSTRUCTION.
COLUSA TROUGH DRAINAGE 99-662 830 NO OBLIGATION FOR 18,900,846
CANAL, SACRAMENTO RIVER CONSTRUCTION.
AND TRIBUTARIES, CA.
PINE FLAT DAM, CA......... 106-541 101b(7) NO OBLIGATION FOR 41,502,918
CONSTRUCTION.
CHINO HILLS, CA........... 106-554 108a NO OBLIGATION FOR 1,543,324
CONSTRUCTION.
EASTERN MUNICIPAL WATER 106-554 108a NO OBLIGATION FOR 1,543,324
DISTRICT, CA. CONSTRUCTION.
GOLETA & VICINITY, CA..... 102-580 102b 1984...................... 1,233,626
LOS ANGELES HARBOR/ 106-554 108d NO OBLIGATION FOR 6,500,000
TERMINAL ISLAND, CA. CONSTRUCTION.
LOWER MISSION CREEK, CA... 100-676 3a NO OBLIGATION FOR 14,625,971
CONSTRUCTION.
SAN DIEGO AREA WATER REUSE 102-580 217c(2) NO OBLIGATION FOR 5,000,000
DEMOSTRATION FACILITIES, CONSTRUCTION.
CA.
SAN DIEGO COUNTY, CA 106-554 108d NO OBLIGATION FOR 10,000,000
(CORONADO TRANSBAY CONSTRUCTION.
WASTEWATER PIPELINE).
SOUTHERN CALIFORNIA 102-580 217c(1) NO OBLIGATION FOR 5,000,000
COMPREHENSIVE WATER REUSE CONSTRUCTION.
SYSTEM, CA.
CT..................................... BRIDGEPORT COMBINED SEWER 106-53 502b NO OBLIGATION FOR 10,000,000
OVERFLOW PTOJECT, CT. CONSTRUCTION.
CT, ME, MA, NH, RI & VT................ NEW ENGLAND WATER 106-541 507 NO OBLIGATION FOR 0
RESOURCES AND ECOSYSTEM CONSTRUCTION.
RESTORATION, CT, ME, MA,
NH, RI & VT.
DC & MD................................ WASHINGTON, DC AND 106-554 108d 1998...................... 14,807,000
MARYLAND, DC & MD.
FL..................................... COMPREHENSIVE EVERGLADES 106-541 601b2bii 2005...................... 17,000,000
RESTORATION PLAN, FL
(LAKE BELT IN-GROUND
RESERVOIR TECHNOLOGY).
COMPREHENSIVE EVERGLADES 106-541 601b2cix NO OBLIGATION FOR 67,150,000
RESTORATION PLAN, FL CONSTRUCTION.
(NORTH NEW RIVER
IMPROVEMENTS).
COMPREHENSIVE EVERGLADES 106-541 601b2cviii NO OBLIGATION FOR 21,500,000
RESTORATION PLAN, FL CONSTRUCTION.
(RAISE AND BRIDGE EAST
PORTION OF TAMIAMI TRAIL
AND FILL MIAMI CANAL
WITHIN WATER)
(CONSEVATION AREA 3).
COMPREHENSIVE EVERGLADES 106-541 601b2cvii NO OBLIGATION FOR 67,800,000
RESTORATION PLAN, FL CONSTRUCTION.
(TAYLOR CREEK/NUBBIN
SLOUGH STORAGE AND
TREATMENT AREA).
COMPREHENSIVE EVERGLADES 106-541 601b2biv 2005...................... 20,500,000
RESTORATION PLAN, FL
(WASTEWATER REUSE
TECHNOLOGY).
HUDSON RIVER, FL.......... 81-516 101 NO OBLIGATION FOR 3,650,000
CONSTRUCTION.
KEY BISCAYNE, FL.......... 106-554 108a NO OBLIGATION FOR 1,543,324
CONSTRUCTION.
LITTLE TALBOT ISLAND, FL.. 106-53 101(b)(7) 2000...................... 6,786,030
SOUTH TAMPA, FL........... 106-554 108a NO OBLIGATION FOR 1,543,324
CONSTRUCTION.
TAMPA HARBOR, ALAFIA 106-554 107 2006...................... 64,771,847
RIVER, FL.
TAMPA HARBOR, FL ((PORT 99-662 858 NO OBLIGATION FOR 8,434,881
SUTTON TURNING BASIN) CONSTRUCTION.
WIDENING TO AN ADDITIONAL
105 FEET TO THE FENDER
LINE ALONG PENDOLA POINT).
[[Page 16150]]
HI..................................... WAIKIKI EROSION CONTROL, 89-298 301 NO OBLIGATION FOR 16,584,000
HI. CONSTRUCTION.
ID..................................... SNAKE RIVER INTERPRETIVE 108-137 124 2004...................... 3,750,044
CENTER, CLARKSTON, WA.
IL..................................... AURORA, IL................ 106-554 108d NO OBLIGATION FOR 8,000,000
CONSTRUCTION.
DES PLAINES RIVER, IL 106-53 101b(10) NO OBLIGATION FOR 5,795,400
(NORTH FORK MILL CREEK CONSTRUCTION.
DAM MODIFICATION).
IN..................................... FORT WAYNE, IN............ 106-554 108a NO OBLIGATION FOR 1,529,324
CONSTRUCTION.
INDIANAPOLIS, IN.......... 106-554 108a NO OBLIGATION FOR 1,543,324
CONSTRUCTION.
KY..................................... BEAVER CREEK BASIN, KY.... 89-298 204 NO OBLIGATION FOR 20,873,500
CONSTRUCTION.
KY & TN................................ REELFOOT LAKE, TN & KY.... 106-53 101b(11) NO OBLIGATION FOR 33,072,769
CONSTRUCTION.
LA..................................... PEARL RIVER, SLIDELL, 99-662 401b 2002...................... 29,311,000
SAINT TAMMANY PARISH, LA.
BAYOU COCODRIE AND 93-251 87 1987...................... 345,472,000
TRIBUTARIES, LA.
GULF INTRACOASTAL 87-874 101 NO OBLIGATION FOR 201,422,000
WATERWAY, LA & TX (LA-TX CONSTRUCTION.
SECTION--UNCONSTRUCTED
FEATURES).
KENNER, LA................ 106-554 108 NO OBLIGATION FOR 5,000,000
CONSTRUCTION.
ST. CHARLES, ST. BERNARD, 106-554 108a NO OBLIGATION FOR 1,543,324
AND PLAQUEMINES PARISHES, CONSTRUCTION.
LA.
ST. JOHN THE BAPTIST AND 106-554 108a NO OBLIGATION FOR 1,543,324
ST. JAMES PARISHES, LA. CONSTRUCTION.
TANGIPAHOA, TCHEFUNCTE, 99-662 401 NO OBLIGATION FOR 21,723,000
AND TICKFAW RIVERS, LA. CONSTRUCTION.
MA..................................... MUDDY RIVER, BROOKLINE AND 106-541 522 NO OBLIGATION FOR 24,050,000
BOSTON, MA (AQUATIC CONSTRUCTION.
ECOSYSTEM RESTORATION
FEATURES).
MI..................................... ALPENA HARBOR, MI (25-FOOT 104-303 363d NO OBLIGATION FOR 4,063,120
CHANNEL). CONSTRUCTION.
BAY CITY, MI.............. 101-640 105 NO OBLIGATION FOR 8,466,275
CONSTRUCTION.
BENTON HARBOR, ST JOSEPH 106-554 108d NO OBLIGATION FOR 1,500,000
WASTEWATER TREATMENT CONSTRUCTION.
PLANT, ST JOSEPH, MI.
CHARLEVOIX, MI (REVETMENT 106-53 373 NO OBLIGATION FOR 52,500
CONNECTION). CONSTRUCTION.
ONTONAGON HARBOR, 104-303 363e NO OBLIGATION FOR 37,134,623
ONTONAGON COUNTY MI. CONSTRUCTION.
SAGINAW RIVER AND 106-53 364(3) NO OBLIGATION FOR 13,909,394
TRIBUTARIES, MI (CASS CONSTRUCTION.
RIVER AT VASSAR).
SAGINAW RIVER AND 99-662 845 NO OBLIGATION FOR 720,653
TRIBUTARIES, MI (CURTIS CONSTRUCTION.
ROAD BRIDGE).
SAGINAW RIVER AND 104-303 329 NO OBLIGATION FOR 571,781
TRIBUTARIES, MI (FLINT CONSTRUCTION.
RIVER AT FLINT).
SAGINAW RIVER AND 106-53 364(4) NO OBLIGATION FOR 106,825,583
TRIBUTARIES, MI CONSTRUCTION.
(SHIAWASSEE FLATS).
MI, MN & WI............................ GREAT LAKES CONNECTING 101-640 101a15 NO OBLIGATION FOR 17,938,174
CHANNELS & HARBORS, MN, CONSTRUCTION.
MI & WI.
MN..................................... DULUTH, MN (ALTERNATIVE 104-303 541a/b NO OBLIGATION FOR 1,000,000
TECHNOLOGY PROJECT). CONSTRUCTION.
LAKE SUPERIOR CENTER, MN.. 104-303 542 NO OBLIGATION FOR 10,000,000
CONSTRUCTION.
MISSISSIPPI PLACE, MN..... 106-53 577 2006...................... 2,968,178
MN & WI................................ DULUTH-SUPERIOR CHANNEL 99-662 201a 1995...................... 14,064,481
EXTENSION, MN & WI.
[[Page 16151]]
MO..................................... KANSAS CITY, MO........... 106-53 502b NO OBLIGATION FOR 15,000,000
CONSTRUCTION.
MO & IL................................ ST LOUIS HARBOR, MO & IL.. 99-662 601a NO OBLIGATION FOR 43,253,100
CONSTRUCTION.
MS..................................... YAZOO BASIN, TRIBUTARIES, 89-298 204 2007...................... 233,490,728
MS (UNCONSTRUCTED
FEATURES).
YAZOO RIVER, MS 99-662 822 NO OBLIGATION FOR 2,011,094
(SHEPARDSTOWN BRIDGE). CONSTRUCTION.
MS & LA................................ MISSISSIPPI AND LOUISIANA 100-676 3(a)8 2003...................... 70,668,540
ESTUARINE AREAS, MS & LA.
NC..................................... LUMBERTON, NC............. 106-53 502b NO OBLIGATION FOR 1,700,000
CONSTRUCTION.
UNION COUNTY, NC.......... 106-554 108a NO OBLIGATION FOR 1,543,324
CONSTRUCTION.
NC & SC................................ SUGAR CREEK BASIN, NC & SC 99-662 401a NO OBLIGATION FOR 54,523,100
CONSTRUCTION.
NH..................................... NASHUA, NH (COMBINED SEWER 106-53 502(b) NO OBLIGATION FOR 19,853,000
OVERFLOW). CONSTRUCTION.
ROCHESTER, NH............. 104-303 504(e)(4) NO OBLIGATION FOR 10,897,120
CONSTRUCTION.
NJ..................................... ELIZABETH, NJ............. 106-53 502(f) NO OBLIGATION FOR 20,000,000
CONSTRUCTION.
NORTH HUDSON, NJ.......... 106-53 502(f) NO OBLIGATION FOR 20,000,000
CONSTRUCTION.
PATTERSON AND PASSAIC 106-554 108c NO OBLIGATION FOR 30,000,000
COUNTY, NJ. CONSTRUCTION.
STATE OF NEW JERSEY AND 102-580 219c(10) NO OBLIGATION FOR 1,543,324
NEW JERSEY WASTEWATER CONSTRUCTION.
TREATMENT TRUST, NJ.
TOWN OF NEWTON, NJ........ 106-554 108d NO OBLIGATION FOR 7,000,000
CONSTRUCTION.
NV..................................... LAS VEGAS WASH AND 102-580 101(13) NO OBLIGATION FOR 3,360,938
TRIBUTARIES, NV. CONSTRUCTION.
LAS VEGAS, NV............. 109-103 115 NO OBLIGATION FOR 20,000,000
CONSTRUCTION.
ERIE COUNTY, BUFFALO 102-580 221 NO OBLIGATION FOR 7,000,000
AMHERST, NY. CONSTRUCTION.
NY..................................... ERIE COUNTY, NY (SLUDGE 102-580 219c(12) NO OBLIGATION FOR 1,543,324
DISPOSAL). CONSTRUCTION.
ERIE COUNTY, NY (WATER 102-580 219c(11) NO OBLIGATION FOR 1,543,324
QUALITY TUNNEL). CONSTRUCTION.
LEWISTON STORMWATER, NY... 102-580 222 NO OBLIGATION FOR 200,000
CONSTRUCTION.
LIVERPOOL, NY............. 106-554 108d NO OBLIGATION FOR 2,000,000
CONSTRUCTION.
INNER HARBOR PROJECT, NEW 106-53 502(f) NO OBLIGATION FOR 15,000,000
YORK, NY. CONSTRUCTION.
LOWER HUDSON RIVER & 106-53 212e NO OBLIGATION FOR 30,000,000
TRIBUTARIES, NY. CONSTRUCTION.
OUTER HARBOR PROJECT, NEW 106-53 502(f) NO OBLIGATION FOR 15,000,000
YORK, NY. CONSTRUCTION.
NY/NJ.................................. NEW YORK HARBOR COLLECTION 101-640 102 2005...................... 201,549,768
AND REMOVAL OF DRIFT, NY
& NJ.
OH..................................... OTTAWA RIVER HARBOR, OH... 101-640 107a(7) 2006...................... 13,218,200
HOCKING RIVER, LOGAN, OH.. 99-662 401a NO OBLIGATION FOR 16,282,709
CONSTRUCTION.
MIAMI RIVER BASIN, 99-662 401(a) NO OBLIGATION FOR 18,041,480
PLEASANT RUN, VICINITY CONSTRUCTION.
FAIRFIELD, OH.
OK..................................... FORT GIBSON LAKE, OK 99-662 601a NO OBLIGATION FOR 45,485,000
(POWER UNITS 5 & 6). CONSTRUCTION.
OR..................................... ASTORIA, OR............... 106-53 502b NO OBLIGATION FOR 5,000,000
CONSTRUCTION.
HOOD RIVER, OR............ 106-554 108a(36) NO OBLIGATION FOR 1,543,324
CONSTRUCTION.
MEDFORD, OR............... 106-554 108a(37) NO OBLIGATION FOR 1,543,324
CONSTRUCTION.
PORTLAND, OR.............. 106-554 108a(38) NO OBLIGATION FOR 1,543,324
CONSTRUCTION.
[[Page 16152]]
PA..................................... COUDERSPORT, PA........... 106-554 108 NO OBLIGATION FOR 1,543,324
CONSTRUCTION.
FINDLAY TOWNSHIP, PA...... 106-53 502 NO OBLIGATION FOR 11,000,000
CONSTRUCTION.
GREENSBORO AND GLASSWORKS, 102-580 219c(15) NO OBLIGATION FOR 1,543,324
PA. CONSTRUCTION.
JEFFERSON TOWNSHIP, GREENE 106-53 502 NO OBLIGATION FOR 1,000,000
COUNTY, PA. CONSTRUCTION.
NORTH FAYETTE TOWNSHIP, 106-53 502 NO OBLIGATION FOR 500,000
ALLEGHENY COUNTY, PA. CONSTRUCTION.
ROBINSON TOWNSHIP, PA..... 106-53 502 NO OBLIGATION FOR 1,200,000
CONSTRUCTION.
SPRINGDALE BOROUGH, PA.... 106-53 502 NO OBLIGATION FOR 500,000
CONSTRUCTION.
TITUSVILLE, PA............ 106-554 108 NO OBLIGATION FOR 7,300,000
CONSTRUCTION.
WASHINGTON, GREENE, 106-554 108 NO OBLIGATION FOR 8,000,000
WESTMORELAND, AND FAYETTE CONSTRUCTION.
COUNTIES, PA.
BRADFORD AND SULLIVAN 106-53 548 NO OBLIGATION FOR 13,000,000
COUNTIES, PA. CONSTRUCTION.
DAUPHIN COUNTY, PA........ 106-53 502b NO OBLIGATION FOR 2,000,000
CONSTRUCTION.
DILLSBURG BOROUGH 106-53 502b NO OBLIGATION FOR 2,000,000
AUTHORITY, PA. CONSTRUCTION.
HAMPDEN TOWNSHIP, PA...... 106-53 502b NO OBLIGATION FOR 3,000,000
CONSTRUCTION.
MOUNT JOY TOWNSHIP AND 106-554 108d NO OBLIGATION FOR 8,300,000
CONEWAGO TOWNSHIP, PA. CONSTRUCTION.
PATTON TOWNSHIP, PA....... 106-53 502b NO OBLIGATION FOR 1,400,000
CONSTRUCTION.
UPPER ALLEN TOWNSHIP, PA.. 106-53 502b NO OBLIGATION FOR 3,400,000
CONSTRUCTION.
DELAWARE RIVER BASIN-- 93-251 2 1993...................... 13,194,000
WABASH CREEK, BOROUGH OF
TAMAQUA, PA.
PHILADELPHIA, PA 104-303 564e NO OBLIGATION FOR 900,000
(FRANKFORD DAM). CONSTRUCTION.
PHILADELPHIA, PA 104-303 564d NO OBLIGATION FOR 15,000,000
(PENNYPACK PARK). CONSTRUCTION.
PHILADELPHIA, PA (WATER 104-303 564a NO OBLIGATION FOR 1,000,000
WORKS RESTORATION). CONSTRUCTION.
PHOENIXVILLE BOROUGH, 106-554 108d NO OBLIGATION FOR 2,400,000
CHESTER COUNTY, PA. CONSTRUCTION.
TOWAMENCIN TOWNSHIP, PA... 106-53 502b 2005...................... 1,462,000
PR..................................... GUANAJIBO RIVER, PR....... 106-53 101 NO OBLIGATION FOR 3,495,941
CONSTRUCTION.
RIO NIGUA AT SALINAS, PR.. 106-53 101 NO OBLIGATION FOR 12,145,000
CONSTRUCTION.
RI..................................... CRANSTON, RI.............. 101-640 54 NO OBLIGATION FOR 6,000,000
CONSTRUCTION.
DREDGING OF SALT PONDS IN 106-53 578 NO OBLIGATION FOR 1,100,000
THE STATE OF RHODE CONSTRUCTION.
ISLAND, RI.
SC..................................... CHARLESTON, SC............ 108-137 127 NO OBLIGATION FOR 10,000,000
CONSTRUCTION.
TN..................................... MEMPHIS HARBOR, MEMPHIS, 106-53 364 NO OBLIGATION FOR 110,044,000
TN. CONSTRUCTION.
NONCONNAH CREEK, TN & MS 106-541 334 2004...................... 36,188,000
(EXTENSION).
TX..................................... NAVASOTA RIVER BASIN, TX 90-483 203 1983...................... 778,421,000
(MILLICAN LAKE, TX).
TRINITY RIVER AND 108-447 116 1981...................... 19,985,000
TRIBUTARIES, TX (LIBERTY
LOCAL PROTECTION PROJECT).
TRINITY RIVER AND 108-447 116 1981...................... 5,412,060,000
TRIBUTARIES, TX
(NAVIGATION CHANNEL ABOVE
LIBERTY).
TRINITY RIVER AND 108-447 116 1981...................... 119,408,000
TRIBUTARIES, TX (WEST
FORK FLOODWAY).
[[Page 16153]]
BUFFALO BAYOU AND 101-640 101(21) NO OBLIGATION FOR 112,536,000
TRIBUTARIES, TX (HALLS CONSTRUCTION.
BAYOU).
LOWER RIO GRANDE BASIN, 99-662 401(a) 2005...................... 207,183,000
TEXAS (SOUTH MAIN
CHANNEL), TX.
TX & OK................................ RED RIVER WATERWAY (BANK 90-483 101 2004...................... 685,324,228
STABILIZATION FEATURES).
UT..................................... CACHE COUNTY, UT.......... 106-53 502(b) NO OBLIGATION FOR 5,000,000
CONSTRUCTION.
UT..................................... UPPER JORDAN RIVER, UT.... 106-53 357 2004...................... 11,087,268
VA..................................... LEVISA AND TUG FORKS AND 104-303 353 1989...................... 185,915,319
UPPER CUMBERLAND RIVER
VA, WV, KY (HAYSI LAKE,
VA).
NORFOLK HARBOR ANCHORAGES, 101-640 107(a)(13) NO OBLIGATION FOR 63,130,000
VA. CONSTRUCTION.
WALLOPS ISLAND, VA........ 106-53 567 NO OBLIGATION FOR 8,000,000
CONSTRUCTION.
WA..................................... STILLAGUMAISH RIVER BASIN, 106-541 101b(27) NO OBLIGATION FOR 26,047,966
WA. CONSTRUCTION.
WV..................................... CABIN CREEK LPP, WV....... 99-662 601a NO OBLIGATION FOR 10,409,900
CONSTRUCTION.
ISLAND CREEK BASIN, 99-662 401a NO OBLIGATION FOR 107,707,600
VICINITY OF LOGAN, WV CONSTRUCTION.
(NON-STRUCTURAL FEATURES).
WEST VIRGINIA PORT 106-53 557(3) NO OBLIGATION FOR 24,144,000
DEVELOPMENT, WV. CONSTRUCTION.
WEIRTON PORT, WV.......... 106-53 557(2) NO OBLIGATION FOR 15,274,778
CONSTRUCTION.
----------------------------------------------------
TOTAL..................... 14,255,612,373
--------------------------------------------------------------------------------------------------------------------------------------------------------
Final Deauthorization Report WRRDA 2014, Section 6001(d)(3)(B)
Appendix A--Projects Removed From the Interim Deauthorization List
------------------------------------------------------------------------
Reason project removed
State Project/Element from interim
name deauthorization list
------------------------------------------------------------------------
Louisiana.................... Amite River and Technical Correction:
Tributaries. The Amite River and
Tributaries project is
identified in later
authorizations as the
Comite River Diversion
project, which is under
construction.
Connecticut.................. Hartford Technical Correction:
Environmental Project Previously
Infrastructure. Deauthorized (Federal
Register 74.126).
Connecticut.................. New Haven Technical Correction:
Environmental Project Previously
Infrastructure. Deauthorized (Federal
Register 74.126).
Maine........................ Fall River and Technical Correction:
New Bedford Project Previously
Environmental Deauthorized (Federal
Infrastructure. Register 74.126).
------------------------------------------------------------------------
[FR Doc. 2016-06695 Filed 3-24-16; 8:45 am]
BILLING CODE 3720-58-P