Midwest Generation, LLC; Notice of Institution of Section 206 
Proceeding and Refund Effective Date

    On June 21, 2016, the Commission issued an order in Docket No. 
EL16-66-000, pursuant to section 206 of the Federal Power Act (FPA), 16 
U.S.C. 824e (2012), instituting an investigation into the justness and 
reasonableness of Midwest Generation, LLC's Reactive Supply tariff 
rate. Midwest Generation, LLC, 155 FERC ] 61,289 (2016).
    The refund effective date in Docket No. EL16-66-000, established 
pursuant to section 206(b) of the FPA, will be the date of publication 
of this notice in the Federal Register.

    Dated: June 22, 2016.
Kimberly D. Bose,
Secretary.