Black Canyon Hydro, LLC; Notice of Preliminary Permit Application
Accepted for Filing and Soliciting Comments, Motions To Intervene, and
Competing Applications
On June 13, 2016, the Black Canyon Hydro, LLC filed an application
for a preliminary permit, pursuant to section 4(f) of the Federal Power
Act (FPA), proposing to study the feasibility of the Seminoe Pumped
Storage Project (project) to be located at the U.S. Bureau of
Reclamation's (Reclamation) Seminoe Reservoir on the North Platte
River, near Rawlins, Carbon County, Wyoming. The project would occupy
lands managed by the U.S. Bureau of Reclamation and the U.S. Bureau of
Land Management. The sole purpose of a preliminary permit, if issued,
is to grant the permit holder priority to file a license application
during the permit term. A preliminary permit does not authorize the
permit holder to perform any land-disturbing activities or otherwise
enter upon lands or waters owned by others without the owners' express
permission.
The proposed project would consist of the following: (1) Two new
intake structures located in Reclamation's 20,291-acre Seminoe
Reservoir; (2) two new concrete-faced, rock-fill upper reservoirs--one
85 acres and one 63 acres--located on either side of, and about 1,000
feet above, Seminoe Reservoir; (3) a 3,000-foot-long, 18.8-foot
diameter, low pressure tunnel and 1,250-foot-long, 18.8-foot-diameter,
pressure shaft leading to a 250-foot-long, 65-foot-wide, 170-foot-high
powerhouse located 1,300 feet east of Seminoe Reservoir in an
underground cavern with a 2,800-foot-long access tunnel and a 1,300-
foot-long, 22.6-foot wide tailrace; (5) a 1,300-foot-long, 22.6-foot-
diameter, low pressure tunnel and 1,800-foot-long, 16.1-foot-diameter
pressure shaft leading to a 220-foot-long, 55-foot-wide, 120-foot-high
powerhouse located 2,800 feet north-northwest of Seminoe reservoir in
an underground cavern with a 800-foot-long access tunnel and a 2,800-
foot-long, 19.3-foot-diameter tailrace; (6) three 133.3-megawatt (MW)
adjustable-speed, reversible pump turbines in the east powerhouse; and
(7) three 100-MW adjustable-speed reversible pump-turbines in the west
powerhouse. The project would also include a double-circuit, 230-
kilovolt (kV) transmission line connecting either at PacifiCorp's
planned Aeolus Substation located northwest of Medicine Bow, Wyoming,
or the planned northern terminal for the TransWest Express DC Line near
Sinclair, Wyoming. If the Aeolus interconnection alternative is built,
the line would parallel the existing Western Area Power
Administration's (WAPA) Miracle Mile-Cheyenne-Ault 230-kV transmission
line. If the TransWest interconnection alternative is built, the line
would parallel or consist of a rebuild of the existing WAPA Miracle
Mile-Sinclair, 115 kV transmission line. The estimated annual
generation would be 1,839,600 MW-hours.
Applicant Contact: Mr. Matthew Shapiro, Chief Executive Officer,
Gridflex Energy, LLC, 1210 W. Franklin Street, Suite 2, Boise, ID
83702, phone: (208) 246-9925.
FERC Contact: Suzanne Novak; phone: (202) 502-6665.
Deadline for filing comments, motions to intervene, competing
applications (without notices of intent), or notices of intent to file
competing applications: 60 days from the issuance of this notice.
Competing applications and notices of intent must meet the requirements
of 18 CFR 4.36.
The Commission strongly encourages electronic filing. Please file
comments, motions to intervene, notices of intent, and competing
applications using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief
comments up to 6,000 characters, without prior registration, using the
eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You
must include your name and contact information at the end of your
comments. For assistance, please contact FERC Online Support at
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to:
Secretary, Federal Energy Regulatory Commission, 888 First Street NE.,
Washington, DC 20426. The first page of any filing should include
docket number P-14787-000.
More information about this project, including a copy of the
application, can be viewed or printed on the ``eLibrary'' link of
Commission's Web site at http://www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P-14787) in the docket number field to access
the document. For assistance, contact FERC Online Support.
Dated: June 30, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-16167 Filed 7-7-16; 8:45 am]
BILLING CODE 6717-01-P