[Federal Register Volume 81, Number 173 (Wednesday, September 7, 2016)]
[Rules and Regulations]
[Pages 61615-61616]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-21448]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF HOMELAND SECURITY
Coast Guard
33 CFR Part 117
[Docket No. USCG-2016-0847]
Drawbridge Operation Regulation; Lake Washington Ship Canal,
Seattle, WA
AGENCY: Coast Guard, DHS.
ACTION: Notice of deviation from drawbridge regulation.
-----------------------------------------------------------------------
SUMMARY: The Coast Guard has issued a temporary deviation from the
operating schedule that governs the Montlake Bridge across the Lake
Washington Ship Canal, mile 5.2, at Seattle, WA. The Montlake Bridge is
a double leaf bascule bridge. The deviation is necessary to allow work
crews to replace bridge decking. This deviation allows a single leaf
opening with a one hour advance notice during the day, and remains in
the closed-to-navigation position at night.
DATES: This deviation is effective from 6 a.m. on September 24, 2016 to
6 a.m. on September 26, 2016.
ADDRESSES: The docket for this deviation, [USCG-2016-0847] is available
at http://www.regulations.gov. Type the docket number in the ``SEARCH''
box and click ``SEARCH.'' Click on Open Docket Folder on the line
associated with this deviation.
FOR FURTHER INFORMATION CONTACT: If you have questions on this
temporary deviation, call or email Mr. Steven Fischer, Bridge
Administrator, Thirteenth Coast Guard District; telephone 206-220-7282,
email [email protected].
SUPPLEMENTARY INFORMATION: Washington Department of Transportation has
requested a temporary deviation from the operating schedule for the
Montlake Bridge across the Lake Washington Ship Canal, at mile 5.2, at
Seattle, WA. The deviation is necessary to accommodate work crews to
conduct timely bridge deck
[[Page 61616]]
repairs. The Montlake Bridge in the closed position provides 30 feet of
vertical clearance throughout the navigation channel, and 46 feet of
vertical clearance throughout the center 60 feet of the bridge;
vertical clearance references to the Mean Water Level of Lake
Washington. When half the span is open, single leaf, 46 feet of
vertical clearance will be reduced throughout the center to 30 feet of
the bridge. To facilitate this event, the north half of the bridge span
will open with at least a one hour advance notice provided to the
bridge operator from 6 a.m. to 6 p.m. From 6 p.m. to 6 a.m., the
Montlake Bridge span will remain in the closed-to-navigation position,
or full closure.
The deviation period is from 6 a.m. until 6 p.m. on September 24,
2016 (north single leaf opening if a one hour notice is given); from 6
p.m. on September 24, 2016 until 6 a.m. on September 25, 2016 (span
remain in the closed-to-navigation position); from 6 a.m. until 6 p.m.
on September 25, 2016 (north single leaf opening if a one hour notice
is given); from 6 p.m. on September 25, 2016 until 6 a.m. on September
26, 2016 (span remain in the closed-to-navigation position). The normal
operating schedule for the Montlake Bridge operates in accordance with
33 CFR 117.1051(e).
Waterway usage on the Lake Washington Ship Canal ranges from
commercial tug and barge to small pleasure craft. Vessels able to pass
through the bridge in the closed-to-navigation position may do so at
any time. The bridge will be able to open for emergency vessels in
route to a call when an hour notice is given to the bridge operator,
and a single leaf opening will be provided. The Lake Washington Ship
Canal has no immediate alternate route for vessels to pass. The Coast
Guard will also inform the users of the waterways through our Local and
Broadcast Notices to Mariners of the change in operating schedule for
the bridge so that vessels can arrange their transits to minimize any
impact caused by the temporary deviation.
In accordance with 33 CFR 117.35(e), the drawbridge must return to
its regular operating schedule immediately at the end of the designated
time period. This deviation from the operating regulations is
authorized under 33 CFR 117.35.
Dated: August 25, 2016.
Steven M. Fischer,
Bridge Administrator, Thirteenth Coast Guard District.
[FR Doc. 2016-21448 Filed 9-6-16; 8:45 am]
BILLING CODE 9110-04-P