    This notice identifies the Federal Energy Regulatory Commission 
(FERC or Commission) staff's revised schedule for the completion of the 
environmental impact statement (EIS) for Transcontinental Gas Pipe Line 
Company, LLC's (Transco) Atlantic Sunrise Project. The first notice of 
schedule, issued on March 9, 2016, identified October 21, 2016 as the 
EIS issuance date. Based on additional information filed by Transco, 
however, we intend to issue a draft General Conformity Determination 
for the Atlantic Sunrise Project with a 30-day comment period. 
Commission staff has therefore revised the schedule for issuance of the 
final EIS.

Schedule for Environmental Review

    Issuance of Notice of Availability of the final EIS--December 30, 
2016.
    90-day Federal Authorization Decision Deadline--March 30, 2017.
    If a schedule change becomes necessary, an additional notice will 
be provided so that the relevant agencies are kept informed of the 
project's progress.

Additional Information

    In order to receive notification of the issuance of the EIS and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription (https://www.ferc.gov/docs-filing/esubscription.asp).

    Dated: October 20, 2016.
Kimberly D. Bose,
 Secretary.
[FR Doc. 2016-25834 Filed 10-25-16; 8:45 am]
 BILLING CODE 6717-01-P