DEPARTMENT OF ENERGY
Western Area Power Administration
Final 2025 Salt Lake City Area Integrated Projects Power
Marketing Plan
AGENCY: Western Area Power Administration, Department of Energy (DOE).
ACTION: Notice of the Final 2025 Power Marketing Plan for the Salt Lake
City Area Integrated Projects.
-----------------------------------------------------------------------
SUMMARY: Western Area Power Administration (WAPA), Colorado River
Storage Project Management Center (CRSP MC), a Federal power marketing
agency of the Department of Energy, announces the Final 2025 Power
Marketing Plan (2025 Marketing Plan) for the Salt Lake City Area
Integrated Projects (SLCA/IP). The Post-1989 General Power Marketing
and Allocation Criteria (Post-1989 Plan), February 7, 1986, as extended
June 25, 1999, will expire on September 30, 2024. After consideration
of the public comments received, WAPA has decided to implement the
Proposed 2025 Marketing Plan with the exception that WAPA will not
create a new, 2-percent resource pool for potential new customers. This
Federal Register notice is published to announce WAPA's decision for
the Final 2025 Marketing Plan, respond to the comments received on the
Proposed 2025 Marketing Plan, and specify the terms and conditions
under which WAPA will market SLCA/IP firm hydroelectric resources
beginning October 1, 2024.
DATES: The 2025 Marketing Plan will become effective December 29, 2016.
FOR FURTHER INFORMATION CONTACT: Mr. Parker Wicks, Public Utilities
Specialist, or Mr. Steve Mullen, Public Utilities Specialist, Western
Area Power Administration, CRSP Management Center, 150 East Social Hall
Avenue, Suite 300, Salt Lake City, UT 84111-1580, telephone (801) 524-
5493, or email to [email protected]. Information can also be found
at https://www.wapa.gov/regions/CRSP/PowerMarketing/Pages/power-marketing.aspx.
SUPPLEMENTARY INFORMATION:
Brief descriptions of the projects included in the SLCA/IP are
provided below:
Colorado River Storage Project (CRSP)
Authorized by Congress in 1956, the CRSP and participating projects
initiated the comprehensive development and use of water resources of
the Upper Colorado River. The CRSP is comprised of the Glen Canyon,
Flaming Gorge, Blue Mesa, Crystal, and Morrow Point dams and
powerplants. CRSP storage units stabilize the erratic flows of the
Colorado River and its tributaries so annual water delivery commitments
to the Lower Colorado River Basin, as well as to farmers,
municipalities, and industries in the Upper Basin, can be met. Delivery
of this water to consumers is accomplished, in part, through the
participating projects discussed below, and additional project
development may occur in future years. Initial hydroelectric generation
began at the CRSP facilities in 1963. The maximum operating capacity of
the five original CRSP powerplants is currently approximately 1,760 MW.
The average annual generation from 1994 through 2014 was approximately
5,208,238 MWh.
Participating Projects
Seedskadee Project (Fontenelle Powerplant): The Seedskadee Project
is in the Upper Green River Basin in southwestern Wyoming. The
Fontenelle Dam, powerplant, and reservoir are the principal features of
the Seedskadee Project. The powerplant commenced operation in May 1968.
The maximum operating capacity of Fontenelle Powerplant is 10 MW. The
average annual generation from 1994-2014 was 53,477 MWh.
Dolores Project (McPhee Dam and Towaoc Canal Powerplants): The
Dolores Project was authorized by the Colorado River Basin Act of
September 30, 1968, as a participating project under the CRSP Act. The
maximum operating capacity of the two powerplants is 12.8 MW, and the
combined average annual output of McPhee Dam and Towaoc Canal
powerplants from 1994-2014 was 18,161 MWh.
Integrated Projects
WAPA consolidated and operationally integrated the Collbran and Rio
Grande projects with CRSP beginning on October 1, 1987. These
integrated projects have retained their separate financial obligations
for repayment; however, the SLCA/IP rate is set to recover revenues to
meet the repayment requirements of all projects. The maximum operating
capacity of the eleven SLCA/IP powerplants is 1,818.6 MW, and the
average annual generation from 1994-2014 was about 5,635,057 MWh. The
SLCA/IP resources are currently marketed to approximately 135 long-term
customers, and many more electric service providers benefit from this
power indirectly through parent organizations that are direct customers
of the SLCA/IP. Existing SLCA/IP contracts will terminate at the end of
the September 2024 billing period.
Collbran Project (Upper Molina and Lower Molina Powerplants): The
Colbran Project was authorized in 1952 and has been in service since
1962. The maximum operating capacity of the two powerplants is
presently 13.5 MW. The average annual generation from 1994-2014 was
41,915 MWh.
[[Page 85947]]
Rio Grande Project (Elephant Butte Powerplant): The Rio Grande
Project was authorized in 1905, and the powerplant went into service in
1940. The maximum operating capacity of the Elephant Butte Powerplant
is 27.0 MW. The average annual generation was 66,743 MWh from 1994-
2014.
Background Information
The Post-1989 Plan provided the power marketing principles used to
market what is now referred to as the SLCA/IP firm hydropower
resources. The Firm Electric Service (FES) contracts associated with
the Post-1989 Plan were initially set to expire October 1, 2004, and
were extended to September 30, 2024.
WAPA published its Proposed 2025 Marketing Plan, 80 FR 78222
(December 16, 2015), and held a Public Information Forum on January 14,
2016, in Salt Lake City, Utah, and a Public Comment Forum on February
17, 2016, in Salt Lake City, Utah, to provide the public an opportunity
to submit comments. During these meetings, the CRSP MC announced it
would complete and post a preliminary determination of the 2025 SLCA/IP
Marketable Resource, which would help determine if WAPA would offer a
2-percent New Customer Power Pool, as proposed. WAPA extended the
comment period, 81 FR 17163 (March 28, 2016), to May 31, 2016, to allow
customers the opportunity to comment on the analysis and to make
additional comments about the Proposed 2025 Marketing Plan. On May 10,
2016, the CRSP MC posted notice on its Web site that, based on its
Analysis of Potential Marketable Resource, insufficient sustainable
hydro power (SHP) energy existed to offer a New Customer Power Pool.
WAPA received oral comments at the public comment forum as well as
18 written comment letters during the comment period. WAPA's responses
to the comments received are included in this notice.
Response to Comments Received on the Proposed 2025 Marketing Plan
Right to Re-Evaluate Allocations and Contract Term
Comment: Commenters supported a 40-year contract term for FES
contracts. Several commenters did not support the concept of a
reopener, or re-evaluation, at a 20-year interval during the contract
period. Several commenters supported a 20-year contract term with an
automatic right of renewal for an additional 20 years, without resource
reduction considerations, if favorable hydrology exists.
Response: In 2017, WAPA will begin the process of offering new FES
contracts with a 40-year length of contract. However, depending on when
contracts are actually negotiated and offered for signature, the period
of performance may be less than 40 years. For example, a new contract
executed in January 2017 would be let for 40 years and terminate in
January 2057, while the period of performance and delivery of firm
electric service would be approximately 33 years--as the existing
contract remains in effect until September 30, 2024. This is due
entirely to the 40-year limit to both length of contract and period of
performance established by the Reclamation Project Act of 1939.
Moreover, WAPA agrees with commenters and will not offer allocations
for the first 20 years and then require a re-evaluation of the
allocations later. WAPA will work with its customers to ensure that the
FES contracts provide sufficient flexibility to address issues of
changing hydrology or resource availability.
New Resource Pool
Comment: Several commenters opposed the creation of a 2-percent
resource pool for new customers. Several commenters supported the
creation of a new resource pool only if power is available without
reduction to existing Post-1989 Plan customers and only for the benefit
of tribal customers not already receiving SLCA/IP power.
Response: Modeling of SLCA/IP resources by the CRSP MC indicates
there is no additional marketable capacity and energy available. WAPA
will not offer a new customer resource pool under the 2025 Marketing
Plan.
Hydropower Allocation to Tribe Served by SLCA/IP Customer
Comment: A Native American tribe stated that it did not receive an
allocation during WAPA's prior remarketing, but instead receives the
benefits of the hydropower allocation through its local electric
cooperative. The tribe stated that Indian self-determination must be
furthered and WAPA should recognize that the benefits of receiving
Federal preference power may potentially be greater for smaller tribes.
The tribe requested WAPA consider allocating directly to the tribe.
Response: WAPA does not have additional marketable capacity and
energy to create an allocation for new customers. However, WAPA will
work directly with the tribe to ensure Indian self-determination is
furthered at all levels through whatever means WAPA has available--such
as discussing arrangements made with the tribe's servicing utility.
Request for Additional Resources
Comment: A commenter requested an increase in the amount of energy
it receives to meet its growing loads and also stated that additional
energy should be provided to correct for load factor issues.
Response: WAPA is unable to provide additional energy because
modeling of SLCA/IP resources indicate there is no additional
marketable capacity and energy available. WAPA will extend the seasonal
firm capacity allocations, referenced in the FES contracts as the
Contract Rate of Delivery (CROD), along with the associated seasonal
energy allocations, to the existing SLCA/IP firm power customers.
Priority of Preference in Proposed 2025 Marketing Plan
Comment: Request for clarification on priority consideration for
entities satisfying the marketing criteria.
Response: WAPA will not offer a new customer resource pool under
the 2025 Marketing Plan; but to reiterate the clarification given
during the comment period, priority consideration for the 2-percent
resource pool for potential new customers under the Proposed Marketing
Plan would have been provided in the following order: (A) Federally
recognized Native American tribes; (B) Municipal corporations and
political subdivisions, including irrigation or other districts,
municipalities, and other governmental organizations, electric
cooperatives and public utilities, other than electric utilities, that
are recognized as utilities by their applicable legal authorities, are
nonprofit in nature, have electrical facilities, and are independently
governed and financed; (C) Other eligible applicants.
Distribution of Additional Resources
Comment: Should an increase in SLCA/IP resources ever occur,
several commenters supported a pro-rata distribution of any additional
resources to existing customers while several other commenters
supported prioritizing new tribal customers over new non-tribal
customers.
Response: If additional marketable resources become available, WAPA
will determine, through appropriate procedures and in consultation with
its customers, how to allocate those additional resources. Moreover,
WAPA will work with its customers to ensure that the FES contracts
provide sufficient flexibility to address issues with
[[Page 85948]]
changing hydrology or resource availability.
Marketing Area
Comment: Several commenters supported the Post-1989 Plan marketing
area and requested WAPA make no changes to the Northern and Southern
Division areas.
Response: WAPA concurs and will preserve the Post-1989 Plan
marketing area. No changes will be made to the Northern and Southern
Division areas in the 2025 Marketing Plan.
Adjustment of Contract Rate of Delivery
Comment: Several commenters do not support an overall reduction in
the contracted customer shares, at any time. Several commenters support
WAPA having the right to adjust the CROD and associated energy on 5
years written notice, provided WAPA collaborates and meets with
Preference Customers prior to giving any such notice.
Response: WAPA will reserve the right to adjust, through
appropriate procedures and in consultation with its customers, the CROD
on 5 years advance written notice in response to changes in hydrology
and river operations.
Service Seasons
Comment: Several commenters support using the SLCA/IP definition
currently implemented for the Winter Season (October-March) and Summer
Season (April-September). One commenter supports the flexibility to
determine monthly energy patterns within its seasonal allocation.
Response: WAPA will continue the use of existing summer and winter
seasons and work with its customers to determine if monthly energy
allocation patterns could be adjusted within a season to better match
customer needs and hydropower availability.
Replacement Power
Comment: Several commenters indicated support for the capacity
replacements programs currently in place through Customer Displacement
Power (CDP) and Western Replacement Power (WRP) programs.
Response: WAPA appreciates the commenters' support for the CDP and
WRP programs. The 2025 Marketing Plan FES contracts will continue to
include CDP and WRP programs.
Transmission Availability for Replacement Power
Comment: Several commenters support the sale of unused firm
transmission on a non-firm basis when that capacity is not used to
deliver customer allocations or customer CDP/WRP so long as any revenue
generated from such sales is applied in order to reduce the rate for
CRSP customers.
Response: WAPA will continue to include all projected revenues
during the rate calculation process. Unused transmission will be made
available per the Open Access Transmission Tariff (OATT) when that
capacity is not needed for delivery of WRP, CDP, or the customers'
allocations.
Use of Renewables
Comment: Has WAPA considered the use of renewable energy to make up
for the loss of hydropower to Post-2025 customers?
Response: WAPA has considered the use of renewable energy as
firming resources in the past and will in the future. If WAPA
experiences a projected decrease in marketable hydropower resources, it
will consider firming purchases from available resources, including
renewables, in accordance with its power marketing authority. However,
no such decrease is currently projected. WAPA has a long-term purchase
power policy, as set forth in 10 CFR part 905--subpart E, whereby WAPA
will develop criteria to consider long-term power purchases, which can
include renewable resources, to meet long-term resource needs. Any
long-term resource acquisition would be made in close consultation with
the customers.
Renewable Energy Credits
Comment: CRSP customers should receive Renewable Energy Credits
(REC) in manner consistent with the Loveland Area Projects (LAP) REC
program.
Response: Consistent with WAPA's REC policy, the SLCA/IP generating
units are registered with Western Renewable Energy Generation
Information System (WREGIS), and the CRSP MC uploads monthly generation
data. The monthly generation loaded into the WREGIS system creates one
REC for every megawatthour of energy produced. Based on the amount
generated from SLCA/IP hydropower facilities during the preceding
calendar year, REC are dispersed annually to each customer
proportionally based on its SLCA/IP allocation. Unlike the LAP, there
is no special consideration for the smaller hydro facilities versus the
large facilities. However, future changes to the REC distribution
policy can be discussed with the customers for possible implementation.
Extension of Existing Contracts
Comment: Several commenters support the extension of the customers'
existing CROD allocations for the contract term. Several commenters
suggested customers should be offered amended and restated contracts,
developed with appropriate diligence and expedience, to extend the
existing contracts at the existing CROD and associated energy
commitments.
Response: WAPA will offer new contracts that maintain the CROD
allocations, with associated energy, to the existing SLCA/IP FES
customers. WAPA will not offer amended and restated contracts, but will
work with existing FES customers to develop a new contract.
Contract Development and Implementation
Comment: Draft contracts should be developed with appropriate
diligence and expedience and with minimal changes from the existing
contract terms and conditions. Customer meetings to discuss the draft
contracts should be limited and follow a formal process that includes
notice and comment periods of reasonable duration and additional
agency/customer/applicant dialogue on an individualized basis unless
such topics advance to affect broader customer interests.
Response: WAPA will collaborate with the FES customers on contract
development while not impacting timely contract implementation. WAPA
will provide timely notice and allow for reasonable periods of informal
review and comments in order to facilitate customer participation.
General Power Contract Provisions
Comment: Several commenters support the continued use of the
current General Power Contract Provisions (GPCP), dated September 1,
2007, for the proposed contract.
Response: While specific contract provisions are outside of the
2025 Marketing Plan, WAPA intends to use the GPCP dated September 1,
2007.
Creditworthiness Procedures
Comment: The inclusion of ``creditworthiness'' provisions in new
FES contracts was not supported by commenters since the existing
customers have a demonstrated history of paying WAPA timely, and no
basis exists for WAPA to justify insertion of this type of provision.
Response: Specific contractual provisions such as creditworthiness
provisions are beyond the scope of the 2025 Marketing Plan. However,
existing WAPA policy requires creditworthiness provisions in FES
contracts and it is the intent of CRSP to include them in its FES
contracts.
[[Page 85949]]
Customer Profile Data
Comment: Only new customers should submit customer profile data;
existing customers should not be required to submit customer profile
data or applications for power.
Response: WAPA concurs and no customer load profile data or
applications will be required from existing customers. Furthermore,
there will be no new customers because modeling of SLCA/IP resources
indicate there is no additional marketable capacity and energy
available.
Methods Report
Comment: Commenters questioned some of the methodologies and
assumptions WAPA made in determining the availability of future
hydropower generation, as explained in the Methodology for SLCA/IP
Resource Analysis for Consideration in the Development of the 2025
Marketing Plan (Methods Report). These commenters questioned the use of
certain hydrologic traces, particular assumptions about weekend versus
weekday load patterns, and requested that only the current operating
criteria be used for modeling purposes.
Response: WAPA appreciates the interest and review of its Methods
Report. After reviewing the comments, WAPA does not believe the items
questioned would affect its decision to use the existing power and
energy commitments in the 2025 Marketing Plan because these would
result in only minimal changes to the modeling results.
Hydropower Production Scenarios
Comment: Several commenters support WAPA proposing a variety of
Marketing Plan approaches that address differing hydroelectric power
production scenarios. Several commenters noted WAPA's reliance on a
specific Department of the Interior (DOI) proposed Environmental Impact
Statement (EIS) methodology in WAPA's resource analysis and urged WAPA
to avoid reliance on any specific environmental-mitigation proposal in
advance of any final DOI decision on that matter.
Response: There are various impacts to hydropower availability such
as drought, maintenance issues, transmission availability, and water
delivery requirements in addition to operational changes made to
mitigate potential environmental impacts. WAPA will continue to work
with its customers to ensure that the FES contracts provide sufficient
flexibility to address issues with changing hydrology and resource
availability. For the Long-term Experimental and Management Plan
(LTEMP) EIS, DOI has identified a preferred alternative, and WAPA is
using this alternative for planning purposes only. If DOI implements a
Glen Canyon Dam operation that significantly differs from the preferred
alternative, WAPA will consider a change to its 2025 Marketing Plan.
Modeling of Marketable Resources
Comment: Several commenters requested information describing the
fundamental differences among GTMax, GTMax Lite, and GTMax Superlite v1
software platforms WAPA used to model hydropower.
Response: The GTMax model uses an older platform and architecture,
which can only model 1 year at a time--under a single hydrological
condition. GTMax Lite performs the same functions as GTMax but only
simulates hydropower operations at Glen Canyon Dam rather than all of
the CRSP facilities. This allows for various operational scenarios at
Glen Canyon Dam to be modeled quickly. The GTMax Superlite model used
by WAPA to model hydropower availability has all of the features and
capabilities of the full GTMax model. The advantage of using GTMax
Superlite for the 2025 Marketing Plan study is that it allows
simulation and optimization of decades of operations, under numerous
hydrological conditions, in a relatively short amount of time.
Final 2025 Power Marketing Plan and Marketing Criteria
WAPA's 2025 Marketing Plan will provide the existing CROD
commitments with associated energy to current SLCA/IP FES customers as
set forth in the existing FES contracts, which implemented the Post-
1989 General Power Marketing Criteria and Post-2004 PMI. The 2025
Marketing Plan principles are as follows:
Final 2025 Marketing Plan Principles
1. Contract Term: The maximum 40-year contract term, as provided
for in the Reclamation Project Act of 1939, will be used for FES
contracts.
2. Existing Marketable Resource: WAPA will extend the CROD
commitments with associated energy to the existing SLCA/IP FES
customers as set forth in the existing FES contracts, which implemented
the Post-1989 General Power Marketing Criteria and Post-2004 PMI.
3. New Resource Pool: Modeling of SLCA/IP resources by WAPA
indicates there is no additional marketable capacity and energy
available. WAPA will not establish a new customer resource pool under
the 2025 Marketing Plan.
4. Firm Electric Service Contract Provisions: Existing SLCA/IP FES
contracts will serve as the basis for new FES contracts. CDP and WRP
contract provisions will be included in the new FES contracts.
5. Benefit Crediting Contracts: For those Native American tribes
that do not operate their own electric utilities, Benefit Crediting
Contracts will be available to deliver the benefit of the Federal
hydropower allocation to those tribes.
6. Marketing Area: The SLCA/IP marketing area remains unchanged,
which is divided into Northern and Southern Divisions.
A. The Northern Division consists of the states of Colorado, New
Mexico, Utah, and Wyoming; the City of Page, Arizona; a portion of the
area in Arizona which lies in the drainage area of the Upper Colorado
River Basin to be served by the Navajo Tribal Utility Authority; and
White Pine County and portions of Elko and Eureka counties in Nevada.
B. The Southern Division consists of the remaining portion of the
state of Arizona and that part of the state of Nevada in Clark,
Lincoln, and Nye counties that comprise the southern portion of the
state.
7. Hydrology and River Operations Withdrawal Provision: WAPA will
continue to reserve the right to adjust, at its discretion and sole
determination, the CROD on 5 years advance written notice in response
to changes in hydrology and river operations. Any such adjustments
would occur after an appropriate public process.
8. Service Seasons: Summer and winter seasons remain unchanged.
A. Summer Season: The 6-month period from the first day of the
April billing period through the last day of the September billing
period in any calendar year.
B. Winter Season: The 6-month period from the first day of the
October billing period of any calendar year through the last day of the
March billing period of the next succeeding calendar year.
Availability of Information
Documents developed or retained by WAPA during this public process
will be available by appointment for inspection and copying at the CRSP
MC, located at 150 East Social Hall Avenue, Suite 300, Salt Lake City,
Utah. WAPA will post information concerning the Final 2025 Marketing
Plan on its Web site at: https://www.wapa.gov/regions/CRSP/PowerMarketing/Pages/power-marketing.aspx.
[[Page 85950]]
Procedural Requirements
Environmental Compliance
In compliance with the National Environmental Policy Act (NEPA) of
1969, 42 U.S.C. 4321, et seq., the Council on Environmental Quality
Regulations for implementing NEPA, 40 CFR parts 1500 through 1508, and
the Integrated DOE NEPA Implementing Procedures, 10 CFR part 1021, WAPA
has determined this action is categorically excluded from the
preparation of an environmental assessment or an EIS.
Determination Under Executive Order 12866
WAPA has an exemption from centralized regulatory review under
Executive Order 12866; accordingly, no clearance of this notice by the
Office of Management and Budget is required.
Regulatory Flexibility Analysis
The Regulatory Flexibility Act of 1980 (RFA), 5 U.S.C. 601, et
seq., requires a Federal agency to perform a regulatory flexibility
analysis whenever the agency is required by law to publish a general
notice of proposed rulemaking for any proposed rule, unless the agency
can certify that the rule will not have a significant economic impact
on a substantial number of small entities. In defining the term
``rule,'' the RFA specifies that a ``rule'' does not include ``a rule
of particular applicability relating to rates [and] services . . . or
to valuations, costs or accounting, or practices relating to such rates
[and] services . . . .'' 5 U.S.C. 601. WAPA has determined that this
action relates to rates or services offered by WAPA and, therefore, is
not a rule within the purview of the RFA.
Dated: November 18, 2016.
Mark A. Gabriel,
Administrator.
[FR Doc. 2016-28690 Filed 11-28-16; 8:45 am]