[Federal Register Volume 82, Number 12 (Thursday, January 19, 2017)]
[Notices]
[Pages 6495-6496]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-01136]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket Nos. CP15-499-001; CP15-499-000]
Texas Eastern Transmission, LP; Notice of Amendment to
Application
Take notice that on December 30, 2016, Texas Eastern Transmission,
LP (Texas Eastern), 5400 Westheimer Court, Houston, Texas 77056, filed
an amendment to its application in Docket No. CP15-499-000, pursuant to
section 7(c) of the Natural Gas Act (NGA) and Part 157 of the
Commission's regulations for its proposed South Texas Expansion Project
(Project). Specifically, Texas Eastern requests, in addition to the
authorizations requested in the previous application, authorization to
(i) construct, install, own, operate, and maintain new gas release
measurement equipment and associated enclosures at its existing Vidor
and Mont Belvieu Compressor Stations in Orange and Chambers Counties,
Texas, respectively, and at its proposed Petronila Compressor Station
in Nueces County, Texas, new gas coolers at its existing Blessing
Compressor Station in Matagorda County, Texas, and a new tie-in to
Pomelo Connector at Texas Eastern's proposed Petronila Compressor
Station; (ii) acquire, by lease, 400,000 dekatherms per day (Dth/d) of
capacity on Pomelo Connector, LLC's proposed pipeline; (iii) change the
Project's targeted in-service date from May 1, 2017 to October 1, 2018;
(iv) change the Project's capacity from 400,000 Dth/d to 396,000 Dth/d;
and (v) remove from the Project's scope the meter and regulating
station at the proposed Petronila Compressor Station. Texas Eastern
further proposes to amend its incremental project recourse rate and to
modify its Exhibit K, all as more fully set forth in the application
which is on file with the Commission and open to public inspection. The
filing may be viewed on the web at http://www.ferc.gov using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For
assistance, contact FERC at [email protected] or call toll-
free, (886) 208-3676 or TYY, (202) 502-8659.
Any questions concerning these applications may be directed to Berk
Donaldson, General Manager, Rates & Certificates, Texas Eastern
Transmission, LP, P.O. Box 1642, Houston, Texas 77251-1642, by
telephone at (713) 627-4488, or by fax at (713) 627-5947.
Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9,
within 90 days of this Notice the Commission staff will either:
Complete its environmental analysis (EA) and place it into the
Commission's public record (eLibrary) for this proceeding, or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the EA for this proposal. The filing of the EA in the Commission's
public record for this proceeding or the issuance of a Notice of
Schedule will serve to notify federal and state agencies of the timing
for the completion of all necessary reviews, and the subsequent need to
complete all federal authorizations within 90 days of the date of
issuance of the Commission staff's EA.
There are two ways to become involved in the Commission's review of
this project. First, any person wishing to obtain legal status by
becoming a party to the proceedings for this project should, on or
before the comment date stated below, file with the Federal Energy
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a
motion to intervene in accordance with the requirements of the
Commission's Rules of Practice and Procedure (18 CFR 385.214 or
385.211) and the Regulations under the NGA (18 CFR 157.10). A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission and will receive copies of all
documents filed by the applicant and by all other parties. A party must
submit 5 copies of filings made with the Commission and must mail a
copy to the applicant and to every other party in the proceeding. Only
parties to the proceeding can ask for court review of Commission orders
in the proceeding.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commenters will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commenters will not be required to serve copies of filed
documents on all other parties. However, the non-party commenters will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right to seek court
review of the Commission's final order.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFiling'' link
at http://www.ferc.gov. Persons unable to file electronically should
submit an original and 7 copies of the protest or intervention to the
Federal Energy Regulatory Commission, 888 First Street NE., Washington,
DC 20426.
[[Page 6496]]
Comment Date: 5:00 p.m. Eastern Time on February 2, 2017.
Dated: January 12, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-01136 Filed 1-18-17; 8:45 am]
BILLING CODE 6717-01-P