Florida Gas Transmission Company, L.L.C.; Notice of Revised 
Schedule for Environmental Review of the Wekiva Parkway Relocation 
Project

    This notice identifies the Federal Energy Regulatory Commission 
staff's revised schedule for the completion of the environmental 
assessment (EA) for the Florida Gas Transmission Company, L.L.C. 
(Florida Gas) Wekiva Parkway Relocation Project. The first notice of 
schedule, issued on June 7, 2017, identified July 28, 2017 as the EA 
issuance date. However, due to additional environmental information to 
be filed by Florida Gas since issuance of the June 7, 2017 Scheduling 
Notice, the Commission staff requires more time to complete our review. 
As a result, staff has revised the schedule for issuance of the EA, to 
allow for time to incorporate supplemental information into the final 
document.

[[Page 37206]]

Schedule for Environmental Review

    Issuance of Notice of Availability of EA: September 14, 2017.
    90-day Federal Authorization Decision Deadline: December 13, 2017.
    If a schedule change becomes necessary, an additional notice will 
be provided so that the relevant agencies are kept informed of the 
project's progress.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription 
(www.ferc.gov/docs-filing/esubscription.asp).

    Dated: July 27, 2017.
Kimberly D. Bose,