Texas Gas Transmission, LLC; Notice of Schedule for Environmental 
Review of the Morgan City and Youngsville Compression Station 
Abandoment Project

    On April 26, 2017, Texas Gas Transmission, LLC (Texas Gas) filed an 
application in Docket No. CP17-256-000 requesting authorization 
pursuant to Section 7(b) of the Natural Gas Act, to abandon in-place 
certain compression facilities. The proposed project is known as the 
Morgan City and Youngsville Compressor Station Abandonment Project 
(Project), and would consist of abandoning in-place certain facilities 
at the Morgan City Compressor Station in Assumption Parish, Louisiana, 
and the Lafayette (referred to as ``Youngsville'') Compressor Station 
in Lafayette Parish, Louisiana. In addition, Texas Gas would relinquish 
the firm design capacity associated with the Project facilities.
    On May 9, 2017, revised on May 19, 2017, the Federal Energy 
Regulatory Commission (Commission or FERC) issued its Notice of 
Application for the Project. Among other things, that notice alerted 
agencies issuing federal authorizations of the requirement to complete 
all necessary reviews and to reach a final decision on a request for a 
federal authorization within 90 days of the date of issuance of the 
Commission staff's Environmental Assessment (EA) for the Project. This 
instant notice identifies the FERC staff's planned schedule for the 
completion of the EA for the Project.

Schedule for Environmental Review

Issuance of EA, September 25, 2017
90-day Federal Authorization Decision Deadline, December 24, 2017

    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    Texas Gas proposes to abandon in-place the Morgan City Compressor 
Station consisting of one 9,100 horsepower gas-fired turbine compressor 
unit, a compressor building, yard and station piping, and appurtenant 
auxiliary facilities located in Assumption Parish, Louisiana, and 
abandon in-place one 9,100 horsepower gas-fired turbine compressor unit 
and its compressor building at the Lafayette (Youngsville) Compressor 
Station located in Lafayette Parish, Louisiana.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC Web site (www.ferc.gov). Using the eLibrary link, select General 
Search from the eLibrary menu, enter the selected date range and 
``Docket Number'' excluding the last three digits (i.e., CP17-256), and 
follow the instructions. For assistance with access to eLibrary, the 
helpline can be reached at (866) 208-3676, TTY (202) 502-8659, or at 
[email protected]. The eLibrary link on the FERC Web site also 
provides access to the texts of formal documents issued by the 
Commission, such as orders, notices, and rule makings.