[Federal Register Volume 83, Number 20 (Tuesday, January 30, 2018)]
[Notices]
[Pages 4196-4197]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-01789]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket Nos. CP18-45-000]
Dominion Energy Transmission, Inc.; Notice of Application
Take notice that on January 10, 2018, Dominion Energy Transmission,
Inc. (Dominion), 120 Tredegar Street, Richmond, Virginia 23219, filed
in Docket No. CP18-45-000 an application pursuant to section 7(c) of
the Natural Gas Act (NGA), and Part 157 of the Commission's regulations
requesting authorization to construct and operate the Sweden Valley
Project (Project), all as more fully set forth in the application which
is on file with the Commission and open to public inspection. The
filing is available for review at the Commission in the Public
Reference Room or may be viewed on the Commission's website at http://www.ferc.gov using the ``eLibrary'' link. Enter the docket number
excluding the last three digits in the docket number field to access
the document. For assistance, contact FERC at
[email protected] or call toll-free, (866) 208-3676 or TYY,
(202) 502-8659.
Any questions concerning this application may be directed to Kenan
W. Carioti, Regulatory & Certificates Analyst III, Dominion Energy
Transmission, Inc., 707 East Main Street, Richmond, VA 23219 at (804)
771-4018.
Specifically, the Project will enable Dominion to provide 120,000
dekatherms per day of firm transportation service from Pennsylvania to
Ohio for delivery to Tennessee Gas Pipeline Company, L.L.C. The Project
will include construction of: Approximately 1.7 miles 20-inch-diameter
pipeline lateral to the new Port Washington Metering and Regulation
(M&R) delivery point in Tuscarawas County, OH; approximately 3.2 miles
of 24-inch-diameter pipeline looping in Greene County, PA; the re-wheel
of compressors on three existing centrifugal compression sets at
Dominion's existing Newark Compressor Station in Licking County, OH;
the installation of regulation equipment at Dominion existing South
Bend Compressor Station in Armstrong County, PA and Leidy M&R Station
in Clinton County, PA; and the construction of related appurtenant
facilities. Dominion is proposing incremental rates for transportation
service on the facilities proposed for construction herein. The cost of
the project will be $49,876,709 million.
Pursuant to section 157.9 of the Commission's rules (18 CFR 157.9),
within 90 days of this Notice, the Commission staff will either:
Complete its environmental assessment (EA) and place it into the
Commission's public record (eLibrary) for this proceeding; or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final environmental impact statement (FEIS) or EA for this
proposal. The filing of the EA in the Commission's public record for
this proceeding or the issuance of a Notice of Schedule for
Environmental Review will serve to notify federal and state agencies of
the timing for the completion of all necessary reviews, and the
subsequent need to complete all federal authorizations within 90 days
of the date of issuance of the Commission staff's FEIS or EA.
There are two ways to become involved in the Commission's review of
this project. First, any person wishing to obtain legal status by
becoming a party to the proceedings for this project should, on or
before the comment date stated below file with the Federal Energy
Regulatory Commission, 888 First Street NE, Washington, DC 20426, a
motion to intervene in accordance with the requirements of the
Commission's Rules of Practice and Procedure (18 CFR 385.214 or
385.211) and the Regulations under the NGA (18 CFR 157.10). A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission and will receive copies of all
documents filed by the applicant and by all other parties. A party must
submit seven copies of filings made in the proceeding with the
Commission and must mail a copy to the applicant and to every other
party. Only parties to the proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commentors will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commentors will not be required to serve copies of filed
documents on all other parties.
[[Page 4197]]
However, the non-party commentors will not receive copies of all
documents filed by other parties or issued by the Commission (except
for the mailing of environmental documents issued by the Commission)
and will not have the right to seek court review of the Commission's
final order.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the eFiling link at
http://www.ferc.gov. Persons unable to file electronically should
submit an original and 7 copies of the protest or intervention to the
Federal Energy regulatory Commission, 888 First Street NE, Washington,
DC 20426.
Comment Date: 5:00 p.m. Eastern time on February 14, 2018.
Dated: January 24, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-01789 Filed 1-29-18; 8:45 am]
BILLING CODE 6717-01-P