[Federal Register Volume 83, Number 129 (Thursday, July 5, 2018)]
[Notices]
[Pages 31386-31387]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-14345]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[ Project No. 14581-002; Project No. 2299-082]
Notice of Modification of Procedural Schedule; Turlock Irrigation
District, Modesto Irrigation District
Take notice that the schedule for processing the following
hydroelectric applications has been modified.
a. Type of Applications: Major Licenses.
b. Project Nos.: 14581-002 and 2299-082.
c. Date filed: October 11, 2017.
d. Applicant: Turlock Irrigation District and Modesto Irrigation
District (Districts).
e. Name of Projects: La Grange and Don Pedro Hydroelectric
Projects.
f. Location: The La Grange Project is located on the Tuolumne River
in
[[Page 31387]]
Stanislaus and Tuolumne Counties, California. The Don Pedro Project is
located on the Tuolumne River in Tuolumne County, California. Portions
of both projects occupy public lands managed by the Bureau of Land
Management.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contacts: Steve Boyd, Turlock Irrigation District, 333
East Canal Drive, Turlock, California 95381-0949, (209) 883-8300; and
Anna Brathwaite, Modesto Irrigation District, P.O. Box 4060, Modesto,
CA 95352, (209) 526-7384.
i. FERC Contact: Jim Hastreiter at (503) 552-2760 or
[email protected].
j. Procedural Schedule: The Commission's November 30, 2017, Notice
of Application Ready for Environmental Analysis for each of the
projects established July 2018 as the estimated date for issuing the
Draft Environmental Impact Statement (EIS). The revised estimate for
issuing the Draft EIS is now November 2018. As such, the applications
will be processed according to the following revised schedule.
Revisions to the schedule may be made as appropriate. If a due date
falls on a weekend or holiday, the due date will be the following
business day.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Commission issues Draft EIS............ November 2018.
Comments on Draft EIS.................. January 2019.
Modified Terms and Conditions.......... March 2019.
Commission issues Final EIS............ May 2019.
------------------------------------------------------------------------
Dated: June 27, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-14345 Filed 7-3-18; 8:45 am]