TITLE: Cascade General, Inc., B-283872, January 18, 2000
BNUMBER: B-283872
DATE: January 18, 2000
**********************************************************************
Cascade General, Inc., B-283872, January 18, 2000
Decision
Matter of: Cascade General, Inc.
File: B-283872
Date: January 18, 2000
John T. Jozwick, Esq., for the protester.
William W. Goodrich, Esq., Arent Fox Kintner Plotkin & Kahn, for Ship
Dismantling and Recycling Joint Venture, and Katherine S. Nucci, Esq.,
Adduci, Mastriani & Schaumberg, for International Shipbreaking Limited,
intervenors.
John B. Dale, Esq., Susan S. Grooms, Esq., and Keith M. Dunn, Esq., Naval
Sea Systems Command, for the agency.
Andrew T. Pogany, Esq., and John M. Melody, Esq., Office of the General
Counsel, GAO, participated in the preparation of the decision.
DIGEST
1. Contracting agency properly did not downgrade or reject proposal based on
awardee's proposed exclusive use of a subcontractor's facility for
performance of contract, where solicitation did not restrict use of
subcontractors in performing the contract, and record demonstrates that
subcontractor's facility was fully available by lease with the government
during entire duration of the contract.
2. Contracting agency reasonably determined that awardee's price was not
unrealistically low where the cost difference between protester's and
awardee's proposals was driven by differences in proposed labor hours and
rates, with awardee proposing rudimentary, but satisfactory, technical
approach requiring significantly fewer hours, and lower labor rates as
confirmed by Defense Contract Audit Agency audit.
DECISION
Cascade General, Inc. protests contract awards to Ship Dismantling and
Recycling Joint Venture (SDR) and International Shipbreaking Limited (ISL),
under request for proposals (RFP) No. N00024-98-R-2219, issued by the
Department of the Navy to dismantle and dispose of ex-Naval vessels. Cascade
contends that the Navy did not reasonably or consistently evaluate
proposals.
We deny the protest.
BACKGROUND
The Ship Disposal Project (SDP)
This procurement, known as SDP, for the first time would pay a contractor to
dismantle ex-Naval vessels, thereby allowing the agency to administer and
oversee performance. Agency Report (AR) at 3-4. Previously, the Navy had
sold scrapping rights for its ex-Naval vessels to the highest bidder. This
method was deemed ineffective because the Navy was unable to ensure that
only the most technically qualified scrapping contractors would obtain the
scrapping rights. The Navy then tried the approach of awarding the rights on
a best value, rather than a highest bid, basis. However, even with this and
other changes, the selling of ships for scrapping had proven problematic in
two respects. First, it was not reducing the growing backlog of ships
awaiting scrapping; scrappers were unwilling to bid on the ships because the
price of scrap metal on the open market had fallen precipitously, while
environmental and safety regulations had increased. Second, ship scrapping,
which is an inherently dangerous and dirty process, had been criticized in
the media for its environmental, health and safety problems. AR at 3-4. The
SDP--under which contractors would be paid for scrapping ex-Naval vessels
and the Navy would oversee performance--was intended to resolve these
issues. AR at 4.
The RFP
On January 28, 1999, the Navy issued the RFP here, which contemplated the
award of up to two indefinite-delivery/indefinite-quantity contracts for
each of two lots (east and west coasts). Contract line items (CLINs) 0001
through 0008 of the west coast lot designated dismantlement of particular
classes of vessels, such as destroyers, frigates and cruisers. A task order
for CLIN 0001, which required dismantlement of a frigate-class ship, would
be placed on a cost-plus-incentive-fee (CPIF) basis at the time of contract
award. [1] Task orders under the other CLINs, if issued, would be placed on
either a CPIF basis, a fixed-price-incentive (successive targets) basis, or
a fixed-price basis, depending on a risk assessment at the time of issuance
of the task orders. AR, encl. 1, at 7.
The RFP stated that the proposals offering the best value to the government
would be selected for award, considering cost and technical factors. AR,
encl. 1, at 127. The RFP contained the following technical evaluation
factors (and subfactors): [2] (1) program and engineering management
(operational plan, ship dismantling capability and approach, approach to
cost control, and schedule); (2) environmental and hazardous waste and
worker safety management and capability (environmental management plan and
safety and health management plan); and (3) past performance. The technical
factors, when combined, were significantly more important than the
cost/price factor. Id. at 126-27.
The cost/price factor would be evaluated on the basis of whether the costs
in an offeror's proposal were realistic for the work to be performed,
reflected a clear understanding of the requirements, and were consistent
with the various elements of the offeror's technical proposal; the RFP
stated that the government may reject unrealistically low proposals
regardless of technical merit. AR, encl. 1, at 127. In order to arrive at a
total evaluated cost, the agency would evaluate offerors' proposed cost for
CLIN 0001 and then, using offerors' estimated mix of hours for dismantling
each ship and projected labor rates, overhead/burden rates and other costs,
adjusted for realism, also would calculate a total projected cost for all
CLINs based on the expected number of ships (tonnage) to be scrapped during
the period of performance. Id. at 127-28.
Proposal Evaluation
On March 30, six proposals were received for the west coast lot. The
technical evaluation review panel (TERP) conducted its initial evaluation
from April 5 until May 7. The TERP, with all members concurring, assigned
the following adjectival ratings to the proposals:
Factor 1: Program & Factor 2: Factor 3: Past
Engineering Environmental & Performance
Management Hazardous Waste &
Worker Safety
Management and
Capability
SDR Good (Low) Satisfactory (Middle) Satisfactory
(High)
Cascade Satisfactory (Middle) Satisfactory (Middle) Satisfactory
(Middle)
ISL Satisfactory (Low) Satisfactory (Middle) Satisfactory
(Low)
Offeror A Satisfactory (Low) Satisfactory (Low) Satisfactory
(Middle)
Offeror B Unsatisfactory Unsatisfactory Neutral (No
rating)
Offeror C Unsatisfactory Unsatisfactory Unsatisfactory
The cost analysis panel (CAP) began its evaluation of the offerors'
cost/price proposals on April 6. AR, encl. 4, at 4. In evaluating each
offeror's estimated cost for CLIN 0001, the CAP obtained input from the TERP
chairman regarding the reasonableness of the labor hours proposed. The CAP
also obtained current labor rates and indirect rates from the Defense
Contract Audit Agency (DCAA) for each offeror. The initial cost/price
evaluation results were as follows:
CLIN 0001 Total projected cost
ISL $1.9 million $28.8 million
[deleted] [deleted] [deleted]
[deleted] [deleted] [deleted]
SDR 3.7 million 60.3 million
Cascade [deleted] [deleted]
[deleted] [deleted] [deleted]
The Contract Award Review Panel (CARP) reviewed the TERP and CAP reports and
was briefed by the TERP and CAP chairmen. In its report dated July 2, the
CARP concurred with the findings of the TERP and CAP. AR, encl. 5. The CARP
recommended to the source selection authority (SSA) that four proposals be
included in the competitive range, those of SDR, ISL, Cascade and Offeror A.
The SSA concurred, and discussion questions and requests for final proposal
revisions (FPR) were sent to each of the four offerors. After receipt of the
offerors' responses, the TERP and CAP reconvened. The TERP issued a TERP
Report Addendum. AR, encl. 13. The TERP did not change its technical
proposal ratings for ISL, Offeror A or Cascade as a result of discussions
and FPRs. However, it raised SDR's ratings under factor 1 from Good (Low) to
Good (High), and under factor 2 from Satisfactory (Middle) to Good (Low),
based on the resolution of most weaknesses and the resulting reduction of
SDR's performance risk.
During the course of the CARP's review of the TERP Report Addendum, the CARP
became aware that the Maritime Administration (MARAD) had issued a
termination notice to ISL on August 20, 1999, partially terminating for
default ISL's scrapping rights contract for eight MARAD vessels. AR, encl.
15, at 1-2. (The matter was unresolved, and litigation was pending.) Since
the CARP considered this default as potentially affecting the past
performance rating assigned ISL by the TERP, the contracting officer
exchanged letters with ISL. According to ISL, MARAD and ISL were in a
dispute concerning the presence of barite on certain of the MARAD vessels.
According to ISL, MARAD was aware of the presence of the barite but failed
to advise ISL of this fact. ISL sought to be reimbursed for removing the
barite from one vessel, but MARAD believed that under a scrapping rights
sales contract such reimbursement was not appropriate or legal. AR, encl.
16, at 1-2, and encl. 17, at 1-2.
In the meantime, the CARP continued its review of the findings of the TERP
and CAP, and issued a CARP Report on September 8. The CARP agreed with all
ratings except ISL's. The CARP noted that the TERP had concluded that ISL's
backlog of MARAD and other ships would have a negative impact on ISL's
ability to handle the SDP contract; this was a significant concern that
contributed to the Satisfactory (Low) rating the TERP assigned ISL's
proposal under factor 1. The CARP found that the elimination of the
remaining MARAD ships from ISL's current backlog, albeit resulting from the
MARAD default, alleviated many of the factor 1 concerns the TERP had noted,
and "substantially reduced the risk of non-performance under the SDP
contract due to fewer resource demands and less interference from other
contracted work." AR, encl. 18, at 17. As a result of this assessment, the
CARP increased ISL's proposal rating under factor 1 to Satisfactory
(Middle). In the area of Past Performance, the CARP also noted that, while
ISL had experienced fatal accidents at its facility, and while fatal
accidents are always a serious concern, the fatal accidents at ISL's
facility had occurred in 1995 and 1996, and none had taken place since then
due to specific steps and corrective action taken by ISL. Id. The CARP
concluded that ISL's past performance rating should be increased to
Satisfactory (Middle). Id. at 18.
Following these adjustments, SDR was the technically superior offeror, and
ISL and Cascade were tied at Satisfactory (Middle) for all three factors.
The final evaluated cost/price for these three offerors were as follows:
ISL, $2.5 million ($35.5 million total); SDR, $3.7 million ($64.7 million);
and Cascade [deleted]. AR, encl. 18, at 10. The CARP conducted a best value
determination and ranked SDR's proposal first, ISL's second, and Cascade's
third. With respect to the latter two proposals, the CARP determined that
"either [Cascade] or ISL West could meet the Government's technical
requirements, but [Cascade's] significantly higher total projected cost
[deleted] did not represent best value." Id. at 21. On September 15, the SSA
concurred with the CARP's recommendation to award two contracts for the west
coast lot, one to SDR and one to ISL. AR, encl. 19, at 4. The awards were
made; these protests followed.
Cascade challenges the awards on several grounds. We have reviewed all of
Cascade's arguments and, based on our assessment of the record, find that
they are without merit. We address Cascade's principal arguments below.
SDR'S PROPOSAL TO USE SUBCONTRACTOR
Cascade contends that the agency lacked a reasonable basis for evaluating
SDR'S proposal under factor 1, program and engineering management, as Good
(low). Specifically, Cascade challenges SDR's proposed use of a
subcontractor, Astoria Metals Corporation (AMC), to provide the necessary
shipbreaking facility, and also questions the availability of the shipyard
and dry dock facilities identified in SDR's technical proposal, in view of
unspecified "other business activities" which it implies will interfere with
AMC's ability to support this contract. Protest at 2.
The evaluation of proposals is a matter within the discretion of the
contracting activity, since it is responsible for defining its needs and for
deciding on the best methods of accommodating them. See Abt Assocs. Inc.,
B-237060.2, Feb. 26, 1990, 90-1 CPD para. 223 at 3-4. In reviewing an agency's
evaluation, we will not reevaluate the technical proposals; rather, our
review is limited to examining the evaluation to ensure that it was
reasonable and in accordance with the RFP criteria as well as applicable
statutes and regulations. Id. at 4.
The evaluation in this area was reasonable. First, the RFP contains no
restrictions on subcontracting for facilities. Rather, the RFP states only
as follows:
Section 1.1--Operational Plan
The Operational Plan shall provide a description of the technical approach
planned which shows capability to accomplish towing, demilitarization, ship
dismantling, scrapping, scrap metal handling . . .
. . . . .
Describe how the offeror proposes to monitor the work of all subcontractors
to include subcontractors performing hazardous material removal, disposal,
and shipbreaking.
AR, encl. 1, at 111 (emphasis added). Since the RFP does not prohibit
subcontracting for facilities, and contemplates using subcontractors for the
various aspects of shipbreaking, there was no basis for downgrading SDR's
offer for proposing to use a subcontractor's facility.
In its proposal, SDR stated that its subcontractor, AMC, would provide its
facility at the ex-Hunter Point Naval Shipyard, California, for the
dismantling operation. SDR included a commitment letter from the
subcontractor and stated that in July 1999, AMC would exercise the first
option under its lease with the Navy for an additional 5-year lease of the
Hunter's Point facility. AR at 16-17. During discussions, the agency
notified SDR that it had provided insufficient documentary evidence that
facilities would be available for the duration of the contract, due to the
uncertainty as to whether AMC would exercise the option. AR, encl. 13, at 5.
In response, SDR stated that the option exercise no longer was an issue
because AMC exercised the renewal option early, on April 14. SDR's answer
provided copies of the actual option exercise document and a new commitment
letter from AMC's president indicating that the entire facility would be
dedicated to supporting SDP. AR, encl. 10, at W-32; AR, at 17-18. Moreover,
the record shows that there is no substance to Cascade's allegation about
AMC's "other business activities." In its FPR, SDR stated that AMC has
minimal production work currently under contract with no sizeable work in
the foreseeable future. AR, encl. 12, at 1.1-35C. SDR also advised the
agency that, due to AMC's recent award of the Ship Repair Facility contract
at the former Long Beach Naval Shipyard, AMC would be performing all new
ship repair activities at its new Long Beach facility. AR, encl. 12, at
1.2-22A. This development made feasible the exclusive dedication of the
Hunters Point facility to the ship dismantling effort. The agency was
satisfied that this information eliminated its concern. The TERP Report
Addendum stated that "[SDR's] response satisfactorily resolved the weakness.
The offeror provided proof of [AMC's] renewal of the lease option for the
[facility until October 11, 2004]." AR, encl. 13.
The protester does not attempt to refute the agency's findings,
determinations, or conclusions as set forth in the agency report concerning
SDR's use of AMC's facility or the availability of the shipyard and dry dock
facilities, and we find nothing unreasonable in the agency's conclusion; the
information submitted by SDR addressed the agency's expressed concerns by
showing that the facility in fact would be available for the entire duration
of the contract. We conclude that nothing in the RFP precluded SDR from
subcontracting for shipyard facilities, and that the evaluation of SDR's
proposal in this area was reasonable. [3]
REALISM OF ISL'S PROPOSED COST
Cascade alleges that the agency did not properly evaluate ISL's cost
proposal; specifically, Cascade asserts that ISL's proposed cost for CLIN
0001 was unrealistically low when compared to SDR's and Cascade's proposed
costs for this line item. Protest at 3.
When an agency evaluates proposals for the award of a cost-reimbursement
contract, an offeror's proposed estimated costs of contract performance and
proposed fees are not considered controlling, since the offeror's estimated
costs may not provide valid indications of the final actual costs that the
government is required, within certain limits, to pay. See ManTech Envtl.
Tech., Inc., B-271002 et al., June 3, 1996, 96-1 CPD para. 272 at 8.
Accordingly, a cost realism analysis must be performed whenever a
cost-reimbursement contract is contemplated. Federal Acquisition Regulation
(FAR) sect. 15.404-1(d)(2). A cost realism analysis is the process of
independently reviewing and evaluating specific elements of each offeror's
proposed cost estimate to determine whether the estimated proposed cost
elements are realistic for the work to be performed, reflect a clear
understanding of the requirements, and are consistent with the unique
methods of performance and materials described in the offeror's technical
proposal. FAR sect. 15.404-1(d)(1). The requirement to conduct a cost realism
analysis of proposals for a cost-reimbursement contract does not require the
agency to conduct an in-depth cost analysis, see FAR sect. 15.404-1(c), or to
verify each and every item in the proposals. Rather, the analysis of cost
realism calls for the exercise of informed judgment by the contracting
agency involved, since it is in the best position to assess the realism of
proposed costs and it must bear the difficulties or additional expenses
resulting from a defective cost realism analysis. Our review is limited to
determining whether the agency's cost realism analysis was reasonable. The
Warner/Osborn/G&T Joint Venture, B-256641.2, Aug. 23, 1994, 94-2 CPD para. 76 at
5.
The realism analysis of ISL's proposal was reasonable. The record shows that
the cost difference among the proposals was driven by proposed labor hours
and labor rates. ISL proposed [deleted] labor hours to accomplish CLIN 0001,
while Cascade proposed [deleted] hours (SDR proposed [deleted] hours). These
labor hour differences reflected what the agency found to be very different
technical approaches to performing the ship dismantling. According to the
agency, Cascade is a full service ship repair company with a fully outfitted
facility, while ISL is only in the business of scrapping ships and has
minimal facilities, management, or overhead. AR at 38-39. This fundamental
difference in the two companies was reflected in how each proposed to
dismantle the vessels--notably, Cascade proposed [deleted], while ISL would
use an [deleted]. [4] The agency determined that ISL's performance approach
was satisfactory, and Cascade does not challenge this determination.
As for labor rates, ISL's proposed rates were lower than Cascade's for every
labor category. However, the ISL rates as evaluated still were higher than
those recommended by DCAA based on other ISL contracts; ISL insisted during
discussions that its proposed labor rates, even though higher than the DCAA
recommended rates, were correct, so the agency used ISL's proposed rates in
the evaluation. The record shows that the CAP and the CARP reviewed every
element of ISL's costs and found them to be reasonable. Moreover, ISL was
the offeror most knowledgeable about the type of effort needed to scrap a
vessel, and was the only offeror that had successfully scrapped a ship. [5]
Given ISL's more rudimentary--but satisfactory--technical approach and lower
labor rates, we find that the Navy reasonably determined that ISL's proposed
CLIN 0001 cost was realistic for the scope of work to be performed. The
protester does not dispute the agency's conclusion in this regard.
EVALUATION OF SAFETY AND ENVIRONMENTAL VIOLATIONS
Cascade contends that the agency improperly considered
information--regarding federal, state or local regulatory agency violations
and evidence of corrective actions taken--under an evaluation factor for
which it was not furnished. Specifically, Cascade notes that, although the
information was requested in RFP section L-3, section 2.1 under the heading
"Environmental Management Plan," which was specified in section M as a
subfactor only under factor 2 (environmental and hazardous waste and worker
safety management and capability), the Navy used the information in the
factor 3 (past performance) evaluation.
This argument is without merit. While the protester is correct that the
agency considered the information under the past performance factor, the
agency explains its reason for doing so as follows:
Although information pertaining to violations and citations was requested
under Section L.2.1., it was actually considered under Factor 3, Past
Performance, rather than Factor 2, . . . in order to evaluate this aspect of
an offeror's proposal only once. Factor 2 was meant to assess from a
prospective basis how an offeror's safety and environmental management
[plans] met the [RFP requirements]. An offeror's safety and environmental
record seemed more relevant to Factor 3, which uses prior conduct and
performance to assess how well an offeror would be expected to perform under
the instant contract.
AR at 22 (emphasis added.).
Information requirements provided for in section L of an RFP are not the
same as evaluation criteria established in section M; rather than
establishing minimum evaluation standards, the instructions of section L
generally provide guidance intended to assist offerors in preparing and
organizing proposals. See generally JW Assocs. Inc., B-275209.3, July 22,
1997, 97-2 CPD para. 27 at 3. The information required by section L does not
necessarily have to correspond to the evaluation criteria in section M. Id.
at 3. Thus, the mere fact that information was requested under a certain
heading in section L did not preclude the agency from using that information
under an evaluation factor that does not correspond to the section L
heading. So long as the information reasonably related to the factor under
which it was evaluated, and the agency evaluated all proposals in the same
manner--the agency's explanation persuades us that both conditions were met
here, and the protester does not assert otherwise--there is no basis for us
to object to the agency's approach. We conclude that the evaluation was
reasonable.
ISL'S TERMINATION FOR DEFAULT
Cascade argues that the agency unreasonably increased ISL's factor 1
adjectival rating (from Satisfactory (Low) to Satisfactory (Middle)) as a
result of the MARAD default, [6] and, more specifically, that the agency
unreasonably failed to evaluate the "potential negative impact" on ISL's
financial position resulting from the default, such as the potential
assessment of liquidated damages [deleted], and excess costs. Protester's
Comments at 7-8.
This argument is without merit. As discussed previously, the CARP noted that
the TERP had concluded that ISL's backlog of MARAD and other ships would
have a negative impact on ISL's ability to handle the SDP contract. The CARP
further found that the elimination of the remaining MARAD ships from ISL's
current backlog, albeit resulting from the MARAD default, alleviated many of
the factor 1 concerns the TERP had noted and reduced the risk of
non-performance due to fewer resource demands and less interference from
other contracted work. As a result of this assessment, the CARP increased
ISL's proposal rating under factor 1. The CARP further determined that the
performance risk resulting from the default was minimized by the fact that
the Navy's objective under the SDP Pilot Phase is significantly different
from that under MARAD's scrap sales contracts. While the SDP contract is a
cost-reimbursement contract, the MARAD contract was a scrap sales contract
under which the contractor actually purchased the scrapping rights, and
under which the contractor's ability to make a profit thus depended
substantially on its ability to sell scrap and the strength of the scrap
metal market. That linkage between the scrap metal market and a contractor's
financial risk will not be present under the SDP contracts. In addition, if
an SDP contractor encounters barite or other substances of which it was
unaware, the contractor will be reimbursed for its actual cost for the
removal. As for the potential financial impact, we simply are not persuaded
that the agency was required to find that a contractor just awarded a
$35.5 million contract would be significantly affected from an overall
financial standpoint by [deleted], associated litigation costs or excess
costs. We conclude that the agency reasonably raised ISL's factor 1 rating.
The protest is denied.
Comptroller General
of the United States
Notes
1. The RFP was structured to provide for a pilot phase--the initial task
order under CLIN 0001 contemplated scrapping one ship on a
cost-reimbursement basis and gathering data. The RFP then contemplated a
second phase under which subsequent task orders would be issued for the
remaining CLINs using the data and lessons learned from the pilot phase.
2. The technical factors were to be rated at the factor level only;
technical subfactors were approximately equivalent in value and would not be
individually rated. The technical factors were to receive adjectival ratings
of outstanding, good, satisfactory or unsatisfactory, and a further
designation of high, middle or low would be assigned to each adjectival
rating. AR, encl. 1, at 127.
3. Cascade also asserts that SDR's subcontractor, AMC, and ISL failed to
provide information to the Navy about Occupational Safety and Health
Administration (OSHA) violations, including the employee fatalities
previously experienced by ISL, and that the agency therefore could not have
evaluated these violations. This allegation is factually erroneous. The
record shows that AMC and ISL in fact furnished the agency all relevant
information concerning OSHA and other violations. For example, concerning
ISL, the CARP stated as follows:
As a result of discussions with ISL, the TERP determined that ISL had
identified specific positive steps it had taken following fatal accidents in
1995 and 1996 and that it had not had a shipcutter accident or fatality
since the changes were implemented. . . . [W]hile any history of serious
accidents is a concern, ISL had resolved the weakness by the subsequent
actions it had taken and because there was no evidence of a continuing trend
of accidents.
AR at 25. Cascade does not dispute in its comments the agency's explanation
that the OSHA violations were in fact evaluated.
4. [deleted].
5. As the TERP noted in its deliberations:
ISL has extensive ship dismantling experience, having scrapped the most
tonnage of any shipbreaking company in the U.S. since 1996. Six former
[Navy] and MARAD ships and one commercial barge have been completely
scrapped within the past three years.
AR, encl. 3, at 32.
6. Cascade also asserts that ISL's factor 3 rating was unreasonably
increased as a result of the default. The CARP did, in fact, increase ISL's
factor 3 rating from Satisfactory (Low) to Satisfactory (Middle), but not
for any reason related to the default. Rather, the rating was raised "due to
resolution of the weakness involving a prior pattern of safety violations,
[and] the corrective action taken by ISL." See AR at 12-13, and encl. 18, at
18.