U.S. GOVERNMENT PRINTING OFFICE
BOARD OF CONTRACT APPEALS
The Appeal of THE PRINTERY, INC.
Docket No. GPO BCA 14-87
July 7, 1989
MICHAEL F. DiMARIO
Administrative Law Judge
SUMMARY OPINION
BACKGROUND
This appeal, timely filed by The Printery, Inc., 5323
West Reno, Oklahoma City, OK 73127, by letter dated June
30, 1987, is from the June 19, 1987, final decision of
R.W. Wildbrett, Contracting Officer (CO), Dallas Regional
Printing Procurement Office (DRPPO), United States
Government Printing Office (Respondent), directing
Appellant to repair or reprint as necessary and at no
additional expense to the Government, the entire order of
some 3,000 saddle-stitched 76 page, plus cover, 8-1/2 x
11" 4-color publications requisitioned by the Department
of the Air Force (Req. No. 7-00083) because the
publications were purportedly "not printed in the 4-color
process colors. It appears the blue negative was not
used. Instead, it appears the yellow negative was
duplicated and used in lieu of the blue negative." (Rule
4 File, hereinafter "R4 File," Tab A.)
The Appellant denies the allegation made by the CO and
asserts that:
We made a color key proof using the negatives provided us
by the Regional Office and determined that the proof did
not look right. I then telephoned the Dallas office and
talked with Mr. Casey and he advised me in a rather curt
manner that they had furnished those same negatives to many
other printers and they had never had a problem producing
the job. The attitude was that we were not really capable
of doing the job. I was then advised that those negatives
were to be used.
We ran four (4) process colors of ink. We provided a color
key proof to Dallas as soon as they rejected the job. It
seems that they can not [sic] see that four (4) colors were
run. Anyone with a magnifier can see that all four colors
were run.
The problem is that the negatives furnished were not good
negatives. We were told to use them as other printers had.
We did not duplicate any negatives. We stripped up what was
sent to us.
We do not feel we should have to print this job over due
to the Dallas Office furnishing bad negatives and then
instructions to go ahead and use them even though I told
them on the phone the job did not look right.
Official File, Tab 1.
Appellant enclosed a color key proof it purportedly had
submitted to the DRPPO together with a sample of the
rejected booklet it had printed. (Official File, Tab 1.)
By memorandum to this Board dated July 30, 1987, the CO
stated:
The contractor was advised of the problem with the cover on
June 12, 1987 and was directed to return negatives and
camera copy to the DRPPO. We received negatives and color
keys for the cover from the contractor on June 19, 1987.
Examination of the negatives revealed the following:
The negatives for the Red and Yellow plates were intact and
suitable for their intended purpose.
The negative for the Black plate had been cut into two
pieces and restripped to conform to the configuration of a
black line border on the furnished camera copy, rather than
being used as furnished.
The negative for the Blue plate was not the negative
furnished by the Government, but rather, appeared to be a
contractor duplicated negative of the furnished yellow
negative that had been cut into three pieces and restripped
with a "blue" key line.
The contractor was advised of our findings, and was
informed that we would require him to reprint the covers
and repair the publications. He refused to reprint the
order and on June 19, 1987, the Contracting Officer made
a final decision and directed the contractor to repair or
reprint as necessary. On July 1, 1987, we received a
copy of a letter sent by the contractor appealing that
final decision. We contacted the department on July 15,
1987, to determine if the publications had been picked up
by the contractor. We were told the publications were
still there. The contractor was again called regarding
the reprint and told us no action had been taken because
they were waiting for a response to their appeal. The
contractor was referred to the disputes clause in U.S.
GPO Contract Terms No. 1 and the requirement for him to
"proceed diligently with the performance of the contract
and in accordance with the Contracting Officers [sic]
decision." At that time the contractor said he would
make arrangements to pick up the publications. As of
July 17, 1987, the publications were still at the
Department.
Official File, Tab 4.
DECISION
The question presented by this appeal is whether or not
the product manufactured by Appellant was done in 4-color
process as required by the specifications. The question
is purely technical in nature and, pursuant to the terms
of the contract concerning rights of inspection, is
reserved to the Government to determine. The exercise of
such authority by the Government is usually made by the
CO, as here, and will not be overturned by the Board
except upon clear and convincing evidence that it was
fraudulently made or that the discretion was clearly
erroneous or exercised in an arbitrary and capricious
way. No such evidence having been presented by
Appellant, it is the decision of this Board that the
appeal be denied and the decision of the CO affirmed.