DEPARTMENT OF ENERGY
[Docket No. RP94-259-000]

 

El Paso Natural Gas Co.; Tariff Filing

June 3, 1994.
    Take notice that on May 31, 1994, El Paso Natural Gas Company (El 
Paso), tendered for filing and acceptance pursuant to part 154 of the 
Federal Energy Regulatory Commission's (Commission) Regulations Under 
the Natural Gas Act and section 31 of the General Terms and Conditions 
of El Paso's Second Revised Volume No. 1-A Tariff, certain tariff 
sheets.
    El Paso states section 31.4(b) of its tariff provides the mechanism 
by which El Paso will adjust each Shipper's Monthly Amortized Amount 
for interest calculated on the unrecovered balance of its stranded 
investment cost in Washington Ranch. The tariff further provides that 
El Paso will adjust its rates for any differences resulting from the 
use of estimated interest versus actual interest and such differences 
shall be added to or deducted from the estimated interest for the 
upcoming six (6) month period.
    El Paso states that no adjustment for differences in the estimated 
interest rate for the period January 1, 1994 through June 30, 1994 is 
necessary since the interest rate did not change.
    El Paso states the Monthly Amortized Amount has been adjusted for 
estimated interest. The estimated interest has been calculated pursuant 
to Sec. 154.67(c)(2)(iii) of the Commission's Regulations, for the 
period July 1994 through December 1994, on the unrecovered balance of 
the stranded investment costs. El Paso states that the revised 
Washington Ranch Reservation Surcharges and resulting Monthly Billed 
Amounts are shown on the tendered tariff sheets.
    El Paso requests that the tendered tariff sheets be accepted for 
filing and permitted to become effective July 1, 1994.
    El Paso states that copies of the filing were served upon all of El 
Paso's interstate pipeline system transportation customers and 
interested state regulatory commissions.
    Any person desiring to be heard or to protest said filing should 
file a motion to intervene or protest with the Federal Energy 
Regulatory Commission, 825 North Capitol Street, NE., Washington, DC 
20426, in accordance with Secs. 385.214 and 385.211 of the Commission's 
Rules and Regulations. All such motions or protests should be filed on 
or before June 10, 1994.
    Protests will be considered by the Commission in determining the 
appropriate action to be taken, but will not serve to make protestants 
parties to the proceeding. Any person wishing to become a party must 
file a motion to intervene. Copies of this filing are on file with the 
Commission and are available for public inspection in the public 
reference room.
Lois D. Cashell,
Secretary.
[FR Doc. 94-13983 Filed 6-8-94; 8:45 am]
BILLING CODE 6717-01-M