[Federal Register Volume 62, Number 112 (Wednesday, June 11, 1997)] [Notices] [Pages 31811-31813] From the Federal Register Online via the Government Publishing Office [www.gpo.gov] [FR Doc No: 97-15248] ----------------------------------------------------------------------- DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. EG97-56-000, et al.] American Ref-Fuel Company of Delaware County, L.P., et al.; Electric Rate and Corporate Regulation Filings June 4, 1997. Take notice that the following filings have been made with the Commission: 1. American Ref-Fuel Company of Delaware County, L.P. [Docket No. EG97-56-000] On May 30, 1997, American Ref-Fuel Company of Delaware County, L.P. (ARC), a Delaware limited partnership, with its principal place of business at c/o American Ref-Fuel Company, 770 North Eldridge, Houston, TX 77079, filed with the Federal Energy Regulatory Commission an amendment to its application for determination of exempt wholesale generator status pursuant to Part 365 of the Commission's Regulations. ARC is engaged directly and exclusively in the business of operating a municipal solid waste-fired small power production facility with a maximum net power production capacity of 79.5 MW which is an eligible facility. All of the facility's electric power net of the facility's operating electric power is and will be purchased at wholesale by Atlantic City Electric Company and PECO Energy Company. Comment date: June 30, 1997, in accordance with Standard Paragraph E at the end of this notice. The commission will limit its consideration of comments to those that concern the adequacy or accuracy of the application. 2. Sky River Partnership [Docket No. EG97-66-000] On May 23, 1997, Sky River Partnership, 13000 Jameson Road, Tehachapi, California 93561 (Sky River), filed with the Federal Energy Regulatory Commission an application for determination of exempt wholesale generator status pursuant to Part 365 of the Commission's Regulations. Sky River owns a wind-powered eligible facility with a capacity of approximately 77 megawatts (along with certain appurtenant interconnected transmission facilities), located in Tehachapi, California. Comment date: June 24, 1997, in accordance with Standard Paragraph E at the end of this notice. The Commission will limit its consideration [[Page 31812]] of comments to those that concern the adequacy or accuracy of the application. 3. Zond Windsystems Holding Company [Docket No. EG97-67-000] On May 23, 1997, Zond Windsystems Holding Company, 13000 Jameson Road, Tehachapi, California 93561 (ZWHC), filed with the Federal Energy Regulatory Commission an application for determination of exempt wholesale generator status pursuant to Part 365 of the Commission's Regulations. ZWHC owns a wind-powered eligible facility with a capacity of approximately 20 megawatts (along with certain appurtenant interconnected transmission facilities), located in Tehachapi, California. Comment date: June 24, 1997, in accordance with Standard Paragraph E at the end of this notice. The Commission will limit its consideration of comments to those that concern the adequacy or accuracy of the application. 4. Victory Garden Phase IV Partnership [Docket No. EG97-68-000] On May 23, 1997, Victory Garden Phase IV Partnership, 13000 Jameson Road, Tehachapi, California 93561 (Victory Garden IV), filed with the Federal Energy Regulatory Commission an application for determination of exempt wholesale generator status pursuant to Part 365 of the Commission's Regulations. Victory Garden IV owns a wind-powered eligible facility with a capacity of approximately 22.05 megawatts (along with certain appurtenant interconnected transmission facilities), located in Tehachapi, California. Comment date: June 24, 1997, in accordance with Standard Paragraph E at the end of this notice. The Commission will limit its consideration of comments to those that concern the adequacy or accuracy of the application. 5. Sachsen Holding B.V. [Docket No. EG97-69-000] On May 28, 1997, Sachsen Holding B.V. (Applicant) applied for a determination that it will be an ``exempt wholesale generator'' within the meaning of Section 32(a)(1) of PUHCA. Applicant will own 45 percent of the equity capital of PT Dayalistrik Pratama (PTDP). PTDP is a special purpose company incorporated under the laws of Indonesia to develop, construct and own a power plant to be built in West Java, Indonesia (the ``Facility''). Indirectly through PTDP, Applicant will be an owner of the Facility. The Facility will be a single unit, coal- fired steam generating boiler and a single unit steam turbine generator with a 100 percent nominal load of 420 megawatts and a net output capacity of 400 megawatts. All of the output of the Facility will be sold to PT Perusahaan Listrik Negara (Persero) (PLN), the state-owned electric utility of Indonesia, pursuant to a 30-year Power Purchase Agreement. Comment date: June 24, 1997, in accordance with Standard Paragraph E at the end of this notice. The commission will limit its consideration of comments to those that concern the adequacy or accuracy of the application. 6. Pennsylvania Power Company [Docket No. ER96-749-001] Take notice that on April 24, 1997, Pennsylvania Power Company tendered for filing its refund report in the above-referenced docket. Comment date: June 18, 1997, in accordance with Standard Paragraph E at the end of this notice. 7. Sunoco Power Marketing L.L.C. [Docket No. ER97-870-000] Take notice that on May 22, 1997, Sunoco Power Marketing L.L.C. (Sunoco), tendered for filing an amended application in the above- captioned docket seeking the additional authority to buy power from, and sell power to, all willing buyers and sellers--including, but not limited to, Sunoco's affiliates--at market based rates under Sunoco's FERC Electric Rate Schedule No. 1. Sunoco requested that it be granted this additional authority without prejudice to the blanket authorizations and waivers previously granted in this docket by order of the Director of the Division of Applications of the Commission's Electric Power Regulation Office on April 11, 1997. Sunoco also submitted a revised FERC Electric Rate Schedule No. 1 which it requested become effective within sixty (60) days from the date of its filing. Comment date: June 18, 1997, in accordance with Standard Paragraph E at the end of this notice. 8. Nevada Power Company [Docket No. ER97-1655-000] Take notice that on May 21, 1997, Nevada Power Company (Nevada Power) tendered for filing an Amendment to its Electric Service Coordination Tariff (Amended Coordination Tariff) having a proposed effective date of March 1, 1997. The amendment is being made to comply with FERC's Order No. 888 unbundling requirements. Comment date: June 18, 1997, in accordance with Standard Paragraph E at the end of this notice. 9. Valero Power Services Company [Docket No. ER97-1847-000] Take notice that on May 14, 1997, Valero Power Services Company (Valero Power) filed an amendment to the notification of a change in its status which was previously filed on February 26, 1997. The Amendment adopts the Standards of Conduct applicable to the relationship between Valero Power and Pacific Gas and Electric Company, a wholly-owned subsidiary of PG&E Corporation, pending and after approval of the proposed merger between PG&E Corporation and Valero Energy Corporation. The Standards of Conduct submitted are the same as Pacific Gas and Electric Company has adopted to govern its conduct with other power marketing affiliates and which the Commission has previously approved. Comment date: June 18, 1997, in accordance with Standard Paragraph E at the end of this notice. 10. Energis Resources Incorporated [Docket No. ER97-2176-001] Take notice that on May 30, 1997, Energis Resources Incorporated tendered for filing copies of its compliance filing in the above referenced docket in response to Ordering Paragraph (A) of the Commission's Order Conditionally Accepting For Filing Proposed Market- Based Rates, Energis Resources Incorporated, 79 FERC para. 61,170 (1997). Comment date: June 18, 1997, in accordance with Standard Paragraph E at the end of this notice. 11. Hartford Power Sales, L.L.C. [Docket No. ER97-2227-000] Take notice that on May 22, 1997, Hartford Power Sales, L.L.C. filed a notice of withdrawal of its filing in this docket. Comment date: June 18, 1997, in accordance with Standard Paragraph E at the end of this notice. 12. Wisconsin Electric Power Company [Docket No. ER97-2309-001] Take notice that Wisconsin Electric Power Company (Wisconsin Electric) on May 27, 1997, tendered for filing its refund report in the above referenced proceeding. The submittal was made in compliance with the letter order issued by the Director, Division of Applications on May 13, 1997. Copies of the filing have been served on Madison Gas and Electric Company, Sonat Power Marketing, L.P., and the Public Service Commission of Wisconsin. [[Page 31813]] Comment date: June 18, 1997, in accordance with Standard Paragraph E at the end of this notice. 13. Houston Lighting & Power Company [Docket No. ER97-2524-000] Take notice that on May 23, 1997, Houston Lighting & Power Company (HL&P) tendered for filing an amendment to its filing in the referenced docket. HL&P states that copies of the amendment have been served on the parties to Docket No. ER97-2524 and on the Public Utility Commission of Texas. Comment date: June 18, 1997, in accordance with Standard Paragraph E at the end of this notice. 14. Keystone Energy Services [Docket No. ER97-3053-000] Take notice that on May 23, 1997, Keystone Energy Services, Inc. (Keystone) petitioned the Commission for acceptance of Keystone Rate Schedule FERC No. 1; the granting of certain blanket approvals, including the authority to sell electricity at market-based rates; and the waiver of certain Commission Regulations. Keystone intends to engage in wholesale electric power and energy purchases and sales as a marketer. Neither Keystone nor any affiliate of Keystone is in the business of generating or transmitting electric power. Comment date: June 18, 1997, in accordance with Standard Paragraph E at the end of this notice. 15. Otter Tail Power Company [Docket No. OA96-192-002] Take notice that on May 12, 1997, Otter Tail Power Company tendered for filing its refund report in the above-referenced docket. Comment date: June 18, 1997, in accordance with Standard Paragraph E at the end of this notice. Standard Paragraph E. Any person desiring to be heard or to protest said filing should file a motion to intervene or protest with the Federal Energy Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426, in accordance with Rules 211 and 214 of the Commission's Rules of Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such motions or protests should be filed on or before the comment date. Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a motion to intervene. Copies of this filing are on file with the Commission and are available for public inspection. Lois D. Cashell, Secretary. [FR Doc. 97-15248 Filed 6-10-97; 8:45 am] BILLING CODE 6717-01-P