[Federal Register Volume 62, Number 112 (Wednesday, June 11, 1997)]
[Notices]
[Pages 31811-31813]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 97-15248]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission
[Docket No. EG97-56-000, et al.]


American Ref-Fuel Company of Delaware County, L.P., et al.; 
Electric Rate and Corporate Regulation Filings

June 4, 1997.
    Take notice that the following filings have been made with the 
Commission:

1. American Ref-Fuel Company of Delaware County, L.P.

[Docket No. EG97-56-000]

    On May 30, 1997, American Ref-Fuel Company of Delaware County, L.P. 
(ARC), a Delaware limited partnership, with its principal place of 
business at
c/o American Ref-Fuel Company, 770 North Eldridge, Houston, TX 77079, 
filed with the Federal Energy Regulatory Commission an amendment to its 
application for determination of exempt wholesale generator status 
pursuant to Part 365 of the Commission's Regulations.
    ARC is engaged directly and exclusively in the business of 
operating a municipal solid waste-fired small power production facility 
with a maximum net power production capacity of 79.5 MW which is an 
eligible facility. All of the facility's electric power net of the 
facility's operating electric power is and will be purchased at 
wholesale by Atlantic City Electric Company and PECO Energy Company.
    Comment date: June 30, 1997, in accordance with Standard Paragraph 
E at the end of this notice. The commission will limit its 
consideration of comments to those that concern the adequacy or 
accuracy of the application.

2. Sky River Partnership

[Docket No. EG97-66-000]

    On May 23, 1997, Sky River Partnership, 13000 Jameson Road, 
Tehachapi, California 93561 (Sky River), filed with the Federal Energy 
Regulatory Commission an application for determination of exempt 
wholesale generator status pursuant to Part 365 of the Commission's 
Regulations.
    Sky River owns a wind-powered eligible facility with a capacity of 
approximately 77 megawatts (along with certain appurtenant 
interconnected transmission facilities), located in Tehachapi, 
California.
    Comment date: June 24, 1997, in accordance with Standard Paragraph 
E at the end of this notice. The Commission will limit its 
consideration

[[Page 31812]]

of comments to those that concern the adequacy or accuracy of the 
application.

3. Zond Windsystems Holding Company

[Docket No. EG97-67-000]

    On May 23, 1997, Zond Windsystems Holding Company, 13000 Jameson 
Road, Tehachapi, California 93561 (ZWHC), filed with the Federal Energy 
Regulatory Commission an application for determination of exempt 
wholesale generator status pursuant to Part 365 of the Commission's 
Regulations.
    ZWHC owns a wind-powered eligible facility with a capacity of 
approximately 20 megawatts (along with certain appurtenant 
interconnected transmission facilities), located in Tehachapi, 
California.
    Comment date: June 24, 1997, in accordance with Standard Paragraph 
E at the end of this notice. The Commission will limit its 
consideration of comments to those that concern the adequacy or 
accuracy of the application.

4. Victory Garden Phase IV Partnership

[Docket No. EG97-68-000]

    On May 23, 1997, Victory Garden Phase IV Partnership, 13000 Jameson 
Road, Tehachapi, California 93561 (Victory Garden IV), filed with the 
Federal Energy Regulatory Commission an application for determination 
of exempt wholesale generator status pursuant to Part 365 of the 
Commission's Regulations.
    Victory Garden IV owns a wind-powered eligible facility with a 
capacity of approximately 22.05 megawatts (along with certain 
appurtenant interconnected transmission facilities), located in 
Tehachapi, California.
    Comment date: June 24, 1997, in accordance with Standard Paragraph 
E at the end of this notice. The Commission will limit its 
consideration of comments to those that concern the adequacy or 
accuracy of the application.

5. Sachsen Holding B.V.

[Docket No. EG97-69-000]

    On May 28, 1997, Sachsen Holding B.V. (Applicant) applied for a 
determination that it will be an ``exempt wholesale generator'' within 
the meaning of Section 32(a)(1) of PUHCA. Applicant will own 45 percent 
of the equity capital of PT Dayalistrik Pratama (PTDP). PTDP is a 
special purpose company incorporated under the laws of Indonesia to 
develop, construct and own a power plant to be built in West Java, 
Indonesia (the ``Facility''). Indirectly through PTDP, Applicant will 
be an owner of the Facility. The Facility will be a single unit, coal-
fired steam generating boiler and a single unit steam turbine generator 
with a 100 percent nominal load of 420 megawatts and a net output 
capacity of 400 megawatts. All of the output of the Facility will be 
sold to PT Perusahaan Listrik Negara (Persero) (PLN), the state-owned 
electric utility of Indonesia, pursuant to a 30-year Power Purchase 
Agreement.
    Comment date: June 24, 1997, in accordance with Standard Paragraph 
E at the end of this notice. The commission will limit its 
consideration of comments to those that concern the adequacy or 
accuracy of the application.

6. Pennsylvania Power Company

[Docket No. ER96-749-001]

    Take notice that on April 24, 1997, Pennsylvania Power Company 
tendered for filing its refund report in the above-referenced docket.
    Comment date: June 18, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

7. Sunoco Power Marketing L.L.C.

[Docket No. ER97-870-000]

    Take notice that on May 22, 1997, Sunoco Power Marketing L.L.C. 
(Sunoco), tendered for filing an amended application in the above-
captioned docket seeking the additional authority to buy power from, 
and sell power to, all willing buyers and sellers--including, but not 
limited to, Sunoco's affiliates--at market based rates under Sunoco's 
FERC Electric Rate Schedule No. 1. Sunoco requested that it be granted 
this additional authority without prejudice to the blanket 
authorizations and waivers previously granted in this docket by order 
of the Director of the Division of Applications of the Commission's 
Electric Power Regulation Office on April 11, 1997. Sunoco also 
submitted a revised FERC Electric Rate Schedule No. 1 which it 
requested become effective within sixty (60) days from the date of its 
filing.
    Comment date: June 18, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

8. Nevada Power Company

[Docket No. ER97-1655-000]

    Take notice that on May 21, 1997, Nevada Power Company (Nevada 
Power) tendered for filing an Amendment to its Electric Service 
Coordination Tariff (Amended Coordination Tariff) having a proposed 
effective date of March 1, 1997. The amendment is being made to comply 
with FERC's Order No. 888 unbundling requirements.
    Comment date: June 18, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

9. Valero Power Services Company

[Docket No. ER97-1847-000]

    Take notice that on May 14, 1997, Valero Power Services Company 
(Valero Power) filed an amendment to the notification of a change in 
its status which was previously filed on February 26, 1997. The 
Amendment adopts the Standards of Conduct applicable to the 
relationship between Valero Power and Pacific Gas and Electric Company, 
a wholly-owned subsidiary of PG&E Corporation, pending and after 
approval of the proposed merger between PG&E Corporation and Valero 
Energy Corporation. The Standards of Conduct submitted are the same as 
Pacific Gas and Electric Company has adopted to govern its conduct with 
other power marketing affiliates and which the Commission has 
previously approved.
    Comment date: June 18, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

10. Energis Resources Incorporated

[Docket No. ER97-2176-001]

    Take notice that on May 30, 1997, Energis Resources Incorporated 
tendered for filing copies of its compliance filing in the above 
referenced docket in response to Ordering Paragraph (A) of the 
Commission's Order Conditionally Accepting For Filing Proposed Market-
Based Rates, Energis Resources Incorporated, 79 FERC para. 61,170 
(1997).
    Comment date: June 18, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

11. Hartford Power Sales, L.L.C.

[Docket No. ER97-2227-000]

    Take notice that on May 22, 1997, Hartford Power Sales, L.L.C. 
filed a notice of withdrawal of its filing in this docket.
    Comment date: June 18, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

12. Wisconsin Electric Power Company

[Docket No. ER97-2309-001]

    Take notice that Wisconsin Electric Power Company (Wisconsin 
Electric) on May 27, 1997, tendered for filing its refund report in the 
above referenced proceeding. The submittal was made in compliance with 
the letter order issued by the Director, Division of Applications on 
May 13, 1997.
    Copies of the filing have been served on Madison Gas and Electric 
Company, Sonat Power Marketing, L.P., and the Public Service Commission 
of Wisconsin.

[[Page 31813]]

    Comment date: June 18, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

13. Houston Lighting & Power Company

[Docket No. ER97-2524-000]

    Take notice that on May 23, 1997, Houston Lighting & Power Company 
(HL&P) tendered for filing an amendment to its filing in the referenced 
docket.
    HL&P states that copies of the amendment have been served on the 
parties to Docket No. ER97-2524 and on the Public Utility Commission of 
Texas.
    Comment date: June 18, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

14. Keystone Energy Services

[Docket No. ER97-3053-000]

    Take notice that on May 23, 1997, Keystone Energy Services, Inc. 
(Keystone) petitioned the Commission for acceptance of Keystone Rate 
Schedule FERC No. 1; the granting of certain blanket approvals, 
including the authority to sell electricity at market-based rates; and 
the waiver of certain Commission Regulations.
    Keystone intends to engage in wholesale electric power and energy 
purchases and sales as a marketer. Neither Keystone nor any affiliate 
of Keystone is in the business of generating or transmitting electric 
power.
    Comment date: June 18, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

15. Otter Tail Power Company

[Docket No. OA96-192-002]

    Take notice that on May 12, 1997, Otter Tail Power Company tendered 
for filing its refund report in the above-referenced docket.
    Comment date: June 18, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

Standard Paragraph

    E. Any person desiring to be heard or to protest said filing should 
file a motion to intervene or protest with the Federal Energy 
Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426, 
in accordance with Rules 211 and 214 of the Commission's Rules of 
Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such 
motions or protests should be filed on or before the comment date. 
Protests will be considered by the Commission in determining the 
appropriate action to be taken, but will not serve to make protestants 
parties to the proceeding. Any person wishing to become a party must 
file a motion to intervene. Copies of this filing are on file with the 
Commission and are available for public inspection.
Lois D. Cashell,
Secretary.
[FR Doc. 97-15248 Filed 6-10-97; 8:45 am]