[Federal Register Volume 62, Number 218 (Wednesday, November 12, 1997)]
[Notices]
[Page 60696]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 97-29679]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission
[Docket No. CP98-53-000]


ANR Pipeline Company; Notice of Request Under Blanket 
Authorization

November 5, 1997.
    Take notice that on October 29, 1997, ANR Pipeline Company (ANR), 
500 Renaissance Center, Detroit, Michigan 48243, filed in Docket No. 
CP98-53-000 a request pursuant to Secs. 157.205 and 157.211 of the 
Commission's Regulations under the Natural Gas Act (18 CFR 157.205, 
157.211) for authorization to construct and operate an interconnection 
between ANR and Louisiana Intrastate Gas Company L.L.C. (LIG) for 
delivery of natural gas to LIG in St. Mary Parish, Louisiana, under 
ANR's blanket certificate issued in Docket No. CP88-532 pursuant to 
Section 7 of the Natural Gas Act, all as more fully set forth in the 
request that is on file with the Commission and open to public 
inspection.
    ANR proposes to install on its above grade facilities a 16-inch 
tee, a 16-inch valve, an electronic measurement system, and 
approximately fifteen (15) feet of tie-in piping. The total cost of the 
facilities will be approximately $168,000 which will be fully 
reimbursed by LIG. The maximum capacity of the proposed interconnection 
will be 300 Mmcf/d.
    ANR states that the construction of the proposed interconnection 
will have no effect on its peak day and annual deliveries, that its 
existing tariff does not prohibit additional interconnections, that 
deliveries will be accomplished without detriment or disadvantage to 
its other customers and that the total volumes delivered will not 
exceed total volumes authorized prior to this request.
    Any person or the Commission's staff may, within 45 days after 
issuance of the instant notice by the Commission, file pursuant to Rule 
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
intervene or notice of intervention and pursuant to Sec. 157.205 of the 
Regulations under the Natural Gas Act (18 CFR 157.205) a protest to the 
request. If not protest is filed within the time allowed therefor, the 
proposed activity shall be deemed to be authorized effective the day 
after the time allowed for filing a protest. If a protest is filed and 
not withdrawn within 30 days after the time allowed for filing a 
protest, the instant request shall be treated as an application for 
authorization pursuant to Section 7 of the Natural Gas Act.
Lois D. Cashell,
Secretary.
[FR Doc. 97-29679 Filed 11-10-97; 8:45 am]
BILLING CODE 6717-01-M