[Federal Register Volume 63, Number 23 (Wednesday, February 4, 1998)] [Notices] [Page 5793] From the Federal Register Online via the Government Publishing Office [www.gpo.gov] [FR Doc No: 98-2651] ----------------------------------------------------------------------- DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP98-187-000] ANR Pipeline Company; Notice of Request Under Blanket Authorization January 29, 1998. Take notice that on January 15, 1998, ANR Pipeline Company (ANR), 500 Renaissance Center, Detroit, Michigan 48243, filed in Docket No. CP98-187-000 a request pursuant to Section 157.205 and 157.211 of the Commission's Regulations under the Natural Gas Act (18 CFR 157.205, 157.211) for authorization to construct and operate an interconnection between ANR and DePere Energy LLC (DePere) for delivery of natural gas to DePere's proposed power plant in DePere, Wisconsin, under ANR's blanket certificate pursuant to Section 7 of the Natural Gas Act, all as more fully set forth in the request that is on file with the Commission and open to public inspection. ANR's proposed interconnection facilities will consist of one 8- inch ultrasonic meter and approximately 0.88 miles of 10-inch pipeline extending from ANR's 16-inch Green Bay Lateral to DePere's proposed power plant. The total cost of the facilities will be approximately $1,125,000, which will be fully reimbursed by DePere. ANR will initially provide deliveries to DePere at the Interconnection pursuant to the provisions of its tariff. The proposed interconnection will accommodate up to 60 MMcf/d. ANR states that the construction of the proposed interconnection facilities will have no effect on its peak day and annual deliveries, that its existing tariff does not prohibit additional interconnections, that deliveries will be accomplished without detriment or disadvantage to its other customers and that the total volumes delivered will not exceed total volumes authorized prior to this request. Any person or the Commission's staff may, within 45 days after issuance of the instant notice by the Commission, file pursuant to Rule 214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to intervene or notice of intervention and pursuant to Section 157.205 of the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to the request. If no protest is filed within the time allowed therefor, the proposed activity shall be deemed to be authorized effective the day after the time allowed for filing a protest. If a protest is filed and not withdrawn within 30 days after the time allowed for filing a protest, the instant request shall be treated as an application for authorization pursuant to Section 7 of the Natural Gas Act. Linwood A. Watson, Jr., Acting Secretary. [FR Doc. 98-2651 Filed 2-3-98; 8:45 am] BILLING CODE 6717-01-M