[Federal Register Volume 63, Number 26 (Monday, February 9, 1998)] [Notices] [Page 6552] From the Federal Register Online via the Government Publishing Office [www.gpo.gov] [FR Doc No: 98-3140] ----------------------------------------------------------------------- DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP98-205-000] Texas Eastern Transmission Corporation; Notice of Request Under Blanket Authorization February 3, 1998. Take notice that on January 27, 1998, Texas Eastern Transmission Corporation (Texas Eastern), 5400 Westheimer Court, Houston, Texas 77056-5310, filed in Docket No. CP98-205-000 a request pursuant to Sections 157.205 and 157.211 of the regulations under the Natural Gas Act (18 CFR 157.205) for authorization to construct a delivery point on Texas Eastern's existing 24-inch Line No. 1 in Alexander County, Illinois, to make natural gas deliveries to the Village of East Cape Girardeau, Illinois (East Cape Girardeau), a municipal corporation. Texas Eastern requests the authorization pursuant to Texas Eastern's blanket certificate issued in Docket No. CP82-535-000 pursuant to Section 7 of the Natural Gas Act, all as more fully set forth in the request on file with the Commission and open to public inspection. Texas Eastern proposes to construct and install a 2-inch tap valve and 2-inch check valve (tap) on Texas Eastern's existing 24-inch Line No. 1 in Alexander County, Illinois. Texas Eastern states that East Cape Girardeau would install, or cause to be installed, dual 2-inch turbine meter runs (meter station), approximately 50 feet of 2-inch pipeline which would extend from the meter station to the tap (connecting pipe), and electronic gas measurement equipment (EMG). In addition it is stated that East Cape Girardeau is in the process of developing a natural gas distribution system in order to serve East Cape Girardeau and surrounding areas. Texas Eastern states that East Cape Girardeau would reimburse Texas Eastern for 100% of the cost and expenses that Texas Eastern would incur for installing the tap, and for reviewing and inspecting the installation of the meter station, connecting pipe, and EGM which costs and expenses are estimated to be approximately $20,118, including an allowance for federal income taxes. Texas Eastern proposes to deliver approximately 400 Mcf per day of natural gas to East Cape Girardeau. Texas Eastern further states that it would render the transportation service pursuant to Texas Eastern's Rate Schedule SCT included in Texas Eastern's F.E.R.C. Gas Tariff, Sixth Revised Volume No. 1 after Texas Eastern receives Commission approval to Waive Section 1 of Rate Schedule SCT to permit East Cape Girardeau to receive service under Texas Eastern's Rate Schedule SCT. It is stated that the transportation service rendered through the proposed delivery point would be performed using existing capacity on Texas Eastern's system and pursuant to East Cape Girardeau's existing service agreement and would have no effect on Texas Eastern's peak day and annual deliveries. Any person or the Commission's staff may, within 45 days after issuance of the instant notice by the Commission, file pursuant to Rule 214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to intervene or notice of intervention and pursuant to Sec. 157.205 of the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to the request. If no protest is filed within the time allowed therefor, the proposed activity shall be deemed to be authorized effective the day after the time allowed for filing a protest. If a protest is filed and not withdrawn within 30 days after the time allowed for filing a protest, the instant request shall be treated as an application for authorization pursuant to Section 7 of the Natural Gas Act. David P. Boergers, Acting Secretary. [FR Doc. 98-3140 Filed 2-6-98; 8:45 am] BILLING CODE 6717-01-M